GDM-03 2016
GDM-03 2016
GDM-03 2016
3
Field Investigation
3.1 Introduction
For any transportation project that has components supported on or in the earth, there is a need for
subsurface information and geotechnical data during its planning, design, and construction phases.
Any geologic feature that affects the design and construction phase of a project, or has a bearing on
site or corridor selection in terms of hazards and/or economics must be investigated and analyzed.
Of equal importance is the clear and accurate portrayal of these conditions in a format that is
accessible and understandable by all users.
Consider the following during field investigation:
• Subsurface investigation: The objectives of a subsurface investigation are the provision of
general information on the subsurface conditions of soil, rock, and water, and specific
information concerning the soil and rock properties that are necessary for the project
geotechnical design and construction.
• Scale of investigation: For transportation projects in Oregon, the appropriate scale of
investigation must be carefully considered. Because of Oregon’s geology and geography,
subsurface conditions are complex and may vary widely over short distances. A more
thorough investigation will provide additional information that will generally decrease the
probability of encountering unforeseen conditions during construction, and increase the
quality and economy of the geotechnical design of a project.
• Balance of investigation: Time and fiscal considerations will constrain the scale and
resolution of the field investigation. Therefore, the geotechnical designer must balance the
exploration costs with the information required and the acceptable risks.
The technical decisions and details required for site investigations require the input of trained and
experienced professionals. Every site has its own particular circumstances, and diverse geologic
conditions, professional experience, available equipment, and the previously described time and
budgetary restraints all contribute to the most cost-effective site investigations. The implications of
site-specific geologic conditions for the type of proposed facility must be investigated for each project.
The remainder of this chapter describes established ODOT criteria to be used in field investigations
as well as information on any areas where ODOT’s criteria differs from the FHWA and AASHTO
guidelines. More information can also be found in the Federal Highway Administration Subsurface
Investigations - Geotechnical Site Characterization Reference Manual (FHWA NHI-01-031).
3.2.1.1 P ha s e 1
For the Field Survey and/or Alternative Design phases (Usually described as “Phase 1”) of a project,
the information gathered from the office study is usually sufficient for preliminary
geologic/geotechnical input to the project team and for completion of the Soils and Geology chapter
of the Environmental Impact Statement (EIS). In the case of a large and/or complex project, or if
geologic conditions will have a major impact on the design and construction of a project, then some
amount of subsurface investigation will be warranted to determine the exact location and extent of the
problems and to devise some preliminary cost estimates and alternatives. Ideally, when performing a
subsurface investigation during Phase 1, the exploration would be situated at the location of a major
project feature that would be investigated later during project design. However, as this occurs early in
the project, or certain other alternatives are under consideration, the precise locations of bridge bents
and final alignments may not be known.
3.2.1.2 P ha s e 2
The project design phase (Field Survey up to Preliminary Plans, usually referred to as “Phase 2”) is
where the most intense and focused subsurface investigation occurs for specific project features.
Wherever possible, the project design or Phase 2 investigation should capitalize on any previous
explorations in the project area. Personnel responsible for the field investigation and geotechnical
design should determine the utility of this information.
The project design phase subsurface exploration and testing program provides the geotechnical data
specifically required by the project’s geotechnical design team. The investigation provides the
aforementioned informational needs for the foundation and earthworks design as well as:
• Additional information applicable to other related project elements such as the chemical
properties of soil with respect to corrosion of structural elements, and issues associated with
environmental protection and erosion control.
• The project geotechnical design analyses, decisions, and recommendations for construction
will be based on the information gathered during the Phase 2 investigations.
For these reasons, the information gathered during this phase of investigation should achieve a
degree of accuracy, thoroughness of coverage, and relevancy to support the project design decisions
and to allow for realistically accurate estimates of geotechnical bid items.
3.2.1.3 O t h e r P ha s e s
There will be some instances where additional subsurface investigation is necessary during
Advanced Plans, Final Plans, or even during the construction phase of a project. This is not
necessarily due to an incomplete investigation during the project design phase, but rather the result
of unforeseeable problems that arise during construction, or late design changes following the main
investigational effort and/or geotechnical design. Subsurface investigation is conducted to provide
Oregon Department of Transportation 3-3
Geotechnical Design Manual
December 2016
design information and is usually adequate, in most cases, for contractor’s estimates for construction
and bidding. Explorations conducted during construction are uncommon, and are usually carried out
to resolve problems or answer questions that arise while the project is being built.
Occasionally, explorations will occur as part of the construction activity to install and monitor needed
instrumentation. When design changes occur late in a project, additional subsurface investigation can
be necessary to confirm the geotechnical design assumptions or to develop additional information.
3.3.1.1 M i ni m u m R e q ui r e m e nt s f or S u b s ur f a c e
I n ve s t i ga t i o ns
The considerations of section 3.3.1 do not preclude the necessity of established minimum
requirements for subsurface investigations. The base level of investigation has value as an initial
approach to a subsurface investigation and for preliminary cost estimation of exploration activities as
well as assuring that some uniform amount of exploration is accomplished for all geotechnical design.
The minimum standards for subsurface investigations are well defined in the 1988 AASHTO Manual
on Subsurface Investigations and are broadly accepted in the practice.
Where ODOT Differs from the AASHTO Manual
Where ODOT practice differs from the AASHTO Manual is in the divergence from the minimum
amount of investigation. AASHTO allows for a reduction from the minimal amount of exploration in
areas of predictable geologic conditions and the absence of any geologic hazards. Such conditions
generally do not exist in Oregon and as a rule, prohibit any reduction of the exploration program.
Rather, explorations are added to the program due to the unpredictable nature of the state’s geology.
Much of the work performed during the preliminary office studies will assist in determining the overall
scale of the subsurface investigation program.
3.3.1.2 R i s k T ol e r a n c e
Further consideration in the development of the Exploration Plan should be given to developing an
assessment of the risk tolerance of the project to unforeseen subsurface conditions. In this regard, an
assessment of the risks assumed by the constructability and function of the design feature without
the benefit of site-specific subsurface information should be conducted with respect to the potential
for cost overruns during construction and to potential for long-term maintenance or increased lifecycle
costs. The cost of an over conservative design resulting from a hedge against unknown subsurface
conditions is another aspect of risk that should also be evaluated. This is where a design is forced to
be based on the worst possible condition known to be present or perceived at a site in order to
prevent failure because the lack of information precludes the assessment of other alternatives.
Generally, an evaluation of the potential risks at a project site occurs as exploration progresses and
the variability of the subsurface is discovered.
3.3.1.3 S t r u c t ur e S e ns i t i vi t y
The sensitivity of a structure or other facility in terms of performance to subsurface variability also
influences the scale of the subsurface investigation. Consider the following in relation to structure
sensitivity:
• Where settlement is concerned, structures are much more sensitive whereas embankments
overall are able to tolerate more post-construction deflection not withstanding those sections
adjacent to bridges.
• Existing structures adjacent to transportation projects also increase the sensitivity of projects
in the built-up or urban environment. Where construction is to occur adjacent to existing
structures or private buildings, the tolerance for settlement or deflection and even vibration is
essentially eliminated, and correspondingly, the need for subsurface information increases.
• Such sensitivity can also extend to environmental, cultural, and archaeological sites where
great efforts will be made to mitigate impacts during construction. For these circumstances,
significant efforts in pre through post-construction monitoring are often required with
instrumentation installed far in advance of contract letting.
• Certain types of construction may also be more sensitive to unanticipated subsurface
conditions such as drilled shaft installation where relatively small changes can result in a
sizeable cost increase.
Despite the best efforts and most detailed subsurface investigations, every significant subsurface
condition may not be discovered or fully examined. The objective here is to reduce the risks accepted
to the barest minimum, and to have some understanding of the risks that will remain.
3.3.1.4 S u bs ur f a c e I n ve s t i ga t i o n S t r a t e g y
An important strategy when conducting the subsurface investigation is to complete the most
important explorations first with the idea that the project schedule may change, funding may be
terminated, or some other decisions made that preclude the completion of all the planned borings.
From this standpoint, the important borings are those that:
1. Provide information about geologic hazards affecting the project or that require monitoring for
mitigation design,
3.3.1.5 S c h e dul e o f S ub s ur f a c e I n v e s t i ga t i o n s
Subsurface investigations are ideally completed as early in the project as possible to allow sufficient
time for geotechnical design, quantity estimation, and consideration of alternatives. Clearly, many of
the project features must already be known to some degree before the Exploration Plan can be
formulated. Right-of-way needs must be established to determine cut and fill slope angles and
heights or the need for retaining structures. Plans that are even more detailed are needed to begin
bridge foundation investigations. Typically, the bridge type, size, and location (commonly referred to
as “TS&L) must be known in order to obtain ground-truth information at the precise bent locations.
Completion of Exploration Plan
Because of these informational prerequisites, the Exploration Plan is usually completed soon after
initiation of the structure TS&L phase with a goal for completion set at the 10% of TS&L completion
with respect to its timeline. The target for completion of preliminary geotechnical recommendations is
set at 2/3 TS&L.
In order to meet this date, there will be less than 50% of the TS&L timeline to complete the
subsurface investigation and provide the needed information to the geotechnical designer charged
with making the preliminary recommendations.
Subsurface investigation performed during preliminary phases may be called for at any time prior to
Phase 2, particularly during the EIS phase depending on the size of the project or any other special
requirements. These investigations are intended to develop project geotechnical constraints and/or to
provide general information to assist in alternative route selection, and to address particular
requirements of the EIS rather than to gain site-specific geotechnical design parameters. Preliminary
subsurface investigation typically takes place on an existing state right-of-way readily accessible
areas so there should not be additional time and money spent in acquiring permits of entry, building
access roads and reclaiming sites.
Instrument Monitoring Periods
An additional aspect of the subsurface investigation schedule that also needs to be determined is the
requirement for instrument monitoring periods. These are particularly important as they commonly
extend before and beyond typical project timelines.
3.3.1.6 E x pl or a t i on S i t e s
One of the primary factors affecting the schedule of the subsurface investigation program is providing
access to drill sites. This includes acquiring the necessary permits as well as the actual physical
occupation of the drill site.
Note:
Preliminary borehole location should have taken place during the initial site reconnaissance and
major requirements with respect to accessibility should have been identified at that time. Since
access to certain drill sites requires a significant investment of time, it is necessary to start acquiring
permits of entry, environmental clearances, and engaging contractors to build access roads or bring
additional resources to move the drilling equipment.
The geotechnical designer should clearly indicate the necessary borehole location tolerances to the
field crews to assist in determining site access. When situating a borehole, consider the following:
• For some sites, a few extra feet of tolerance available will allow a borehole to be accessed
with standard equipment or with minimal disturbance while at others, considerably greater
efforts will be necessary to place the borehole at the precise location.
• Where the location of the exploration is crucial, it may be reasonable to mobilize specialty-
drilling equipment.
• Several factors contribute to the amount of tolerance allowed for an exploration. Among these
are the phase of the investigation for which the explorations are performed, in this case, the
final design explorations would require the more precise location.
• The types of structure, expected subsurface conditions, and surrounding facilities also have
more exacting standards for borehole placement.
• A spread footing on rock, or a tieback wall adjacent to and supporting an existing structure
are examples of cases where relatively minor changes in the subsurface conditions have
very serious consequences during construction and would therefore warrant the extra
expenditure to precisely locate the explorations. In this case, the expenditure for mobilizing
special equipment would be far exceeded by orders of magnitude from ensuing claims or
even, litigation.
3.3.1.8 U t i l i t y L o c a t i on / N o t i f i c a t i on
Underground and overhead utilities in the project area must be identified and approximately located
early in the Exploration Plan development. The presence of utilities may dictate the location of, or
access to exploration points.
Warning:
Encountering underground utilities during site investigations can be detrimental to the exploration
schedule and budget. Digging or drilling into underground utilities or contacting overhead power lines
with drill rig masts or backhoe arms can be lethal. For these reasons, the exact location of all utilities
must be determined before any equipment is mobilized to the project site.
Utility Notification Center
In Oregon, the law requires that the Utility Notification Center is contacted no less than 48 business
hours prior to any ground disturbing operations. This includes all test pit excavation, drilling, and even
hand auguring or digging.
Note:
The Utility Notification Center (or “One-Call” Center) can be reached at 1-800-332-2344.
The Utility Notification Center contacts all of the utility services with facilities in the location(s)
provided to them based on their records. The individual utilities then dispatch their personnel or
contractors to the site to locate and mark the positions of their facilities according to the instructions
provided. The following occurs in relation to utility marking:
• The utilities are also required by law to locate their facilities within 48 business hours. If the
utility operator does not have facilities near the proposed location site, he or she will mark it
as such to indicate that it is safe to proceed. Otherwise, they will mark the approximate
location of their facility in the requested vicinity.
• If the utility is close to the proposed exploration, prudence would dictate that the exploration
be moved slightly to allow for errors in the utility location, and to further prevent the accidental
contact with the utility.
3.5.2.1 S pa c i ng a n d La yo u t S t r a t e gi e s
Because transportation projects are typically linear, explorations tend to be channeled into a relatively
straight and narrow corridor, and are often laid out only along the centerline of many features. This
should be avoided as it most often results in poor development of the subsurface model. To avoid
this, boreholes should be spread out to either side of the centerline to help determine the strike and
dip of the underlying strata, the nature of the contacts (i.e. conformal or non-conformal), and other
changes or irregularities across the subsurface profile. Exploration to reveal or characterize geologic
3.5.2.2 E m b a nk m e n t a n d C ut S l o pe E x pl or a t i o ns
The maximum exploration spacing for embankment fills over 10 feet (3.05m) in height is 200 feet
(61m). Where changeable conditions or problem areas such as those with soft and/or compressible
materials are present, then the exploration spacing should be decreased to 100 feet (30m). In many
cases it will be necessary to conduct additional exploration using cone penetrometers, hand augers,
or backhoe test pits to further define the properties and boundaries of problem foundation conditions.
At least one boring should be located at the point of maximum fill height.
For cut slopes 10 feet (3m) and higher, the maximum boring spacing is 100 feet (30m). Borings
should be staggered to each side of the cut line to help determine the strike and dip of the units in the
cut slope, and one of the borings should be placed at the maximum depth of the cut. For “through-
cuts” where a cut slope will be located on each side of the roadway, boring spacing may be
increased to 200 feet (61m) for each cut slope, but the borings must be staggered so that the total
100 foot (30) spacing continues along the length of the cut.
Additional borings will be required in areas of faulted, sheared, tightly folded, highly weathered, or
other potentially detrimental conditions exist.
Hand augers, direct push (i.e., GeoProbe), air-track drills, test pits, geophysical surveys, and other
alternative exploration techniques can be used to supplement the test borings in proposed cut slopes
to determine the elevations of variable bedrock surfaces and depths to bedrock. Air-track drills may
also be used to penetrate the bedrock surface to determine and further resolve the location(s) of
weathered rock zones and other features within the proposed cut slope.
3.5.2.3 S u b gr a de B or in g s
Where relatively unvarying subsurface conditions are predicted and no other foundations or
earthworks are expected, the maximum subgrade boring spacing should be 200 feet (61m). In areas
where highly variably geology is predicted, the boring spacing should be decreased to 100 feet (30m)
and further decreased to 50 feet (15m) in highly erratic conditions. Where critical subgrade conditions
exist, the boring spacing may be decreased to 25 feet (8m).
3.5.2.4 T u n ne l a n d Tr e n c hl e s s P i pe I n s t a l l a t i o n Bor i ng s
Tunnel construction for highway projects in Oregon is rare; however, trenchless pipe installation is
common. Tunnels and trenchless pipe installations share many common construction and design
issues and are thus treated in a similar manner with respect to subsurface characterization and
exploration. Borehole spacing requirements for tunneling and trenchless pipe installation are highly
dependent on the site geologic conditions and topography. The soil, rock, or mixed-face conditions
predicted will determine the borehole spacing as well as the type of exploration and testing
conducted. The depth of the tunnel/trenchless pipe alignment will greatly influence the total amount of
drilling required.
The actual borehole spacing selected for tunnel or trenchless pipe installation should be determined
by the actual site conditions. These conditions should be identified in advance by preliminary site
review, and in the case of larger projects, preliminary site investigations conducted during the Phase I
field survey. The recommended general borehole spacing for selected conditions is shown in the
following table:
Table 3-1. Tunneling and Trenchless Pipe Installation Recommendations
Recommendations
Soft Ground Tunneling
Adverse Conditions 50-100 feet (15-30m)
Favorable Conditions 200-300 feet (61-91m)
Mixed-Face Tunneling
Adverse Conditions 25-50 feet (8-15m)
Favorable Conditions 50-75 feet (15-23m)
3 . 5 . 2 . 5 S t r u c t ur e - S pe c i f i c B or i ng s
The actual number and spacing for borings for specific structures varies greatly depending on the
predicted geologic conditions and the complexity of the site. In this regard, nearby features such as
streams and environmentally sensitive areas, geologic hazards, and nearby structures will further
prescribe the actual amount of exploration required.
Bridges
For all bridges on ODOT projects, at least one boring will be placed at each bent location. Borings
should be placed at opposite sides of adjacent bent locations when practical as defined below.
• For bridges that are 100 feet (30m) wide and larger, at least two borings will be placed at
each bent.
• When spread footings are proposed, two borings at opposing corners of the footing are
advisable. Spread footings located on the banks of rivers and streams should be investigated
with at least two borings – one on the down-slope and one on the upslope side of the
proposed footing.
• If wing walls greater than 20 feet long are to be constructed, then a boring should be placed
at the end of each wing wall and at 50-foot (15m) intervals from the end of the wing wall to
the bridge abutment.
• Trestle-type bridges (usually for detours) should also be investigated at every bent.
Preferably, the borings should be staggered from opposite ends of adjacent bents.
• Where highly variable conditions are anticipated, then a boring should be advanced at both
ends of each bent.
• For drilled shaft foundations, 1 boring should be placed at the location of each proposed shaft
of 6 feet (1.8m) in diameter and larger. Federal Highway Publication FHWA-NHI-10-016
should be consulted for exploration spacing at drilled shaft foundation locations using smaller
diameter shafts.
The depth of the borings will vary depending on the expected loads being
applied to the foundation and/or site soil conditions. All borings should be
extended to a depth below the bottom elevation of the building foundation a
minimum of 2.5 times the width of the spread footing foundation or 1.5 times the
length of a deep foundation (i.e., piles or shafts). Exploration depth should be
great enough to fully penetrate soft highly compressible soils (e.g., peat, organic
silt, soft fine-grained soils) into competent material suitable for bearing capacity
(e.g., stiff to hard cohesive soil, compact dense cohesion less soil or bedrock).
In addition to the exploration requirements in Table 3-2 (Specific Field Investigation Requirements),
groundwater measurements, conducted in accordance with Chapter 3, should be obtained if
groundwater is anticipated within the minimum required depths of the borings as described herein.
3.5.2.6 C r i t i c a l - Ar e a I n v e s t i ga t i o n s
In areas where critical geologic conditions or hazards such as highly irregular bedrock surfaces,
extremely weathered or altered rock, compressible materials, and caverns or abandoned
underground facilities are predicted from detailed background study or preliminary exploration, it may
be necessary to further investigate the area with additional explorations. Such investigations normally
involve drilling on a grid pattern over the area in question. An initial, wider grid pattern may be
selected to locate the area of most concern with a closer grid pattern used later to further
characterize the area of concern. Grid pattern investigations may consist of hand auger holes, direct
push holes, or cone penetrometers in addition to the more conventional test borings. Geophysical
surveys may also be used to establish or refine the boundaries of the grid pattern investigation.
3.5.2.7 L a n ds l i de s
The number and layout of test borings for landslide investigation depends upon the size and nature
of the landslide itself and on the results of detailed site mapping and initial subsurface models based
on the mapping. Since information about the subsurface is unknown initially, landslide investigation
largely becomes an iterative process as new data obtained provides information that is used to
further develop enough knowledge of the landslide to begin stability analysis.
The approach to landslide investigation is very complex and involves numerous techniques and
procedures, and is discussed in greater detail in Chapter 13. This chapter is intended to convey a
general sense of the layout of the borings needed for a “typical” landslide investigation.
3.5.3.1 T e r m i na t i o n De p t h s
When competent bedrock is encountered, test borings may generally be terminated after penetrating
15 feet (4.5m) into it. Where very heavy loads are anticipated, test borings may be extended to a
considerable depth into the bedrock depending on its characteristics and verification that it is
underlain by materials of equal or greater strength. For most structures, it is advisable to extend at
least one boring into the underlying bedrock even when the remaining borings are terminated in soils
of adequate bearing capacity.
As with all other aspects of subsurface investigation, considerable professional judgment is needed
to determine the final depths of planned explorations. Generally, previous subsurface information is
needed to determine the approximate depth of the proposed borings on the Exploration Plan. Where
this information is unavailable, general guidelines can be used to establish the preliminary exploration
depths and quantities. These guidelines are outlined for specific geotechnical features in the following
sections.
3.5.3.2 E m b a nk m e n t a n d C ut S l o pe E x pl or a t i o n De pt h s
For embankments of 10 feet (3m) or greater in height, the test borings should penetrate from 2 to 4
times the proposed fill height or more depending on the final width of the roadway and the actual
materials encountered. If suitable foundation materials are encountered such as dense granular soils
or bedrock, the depth may be decreased up to a minimum depth equaling the height of the
embankment. Where confined aquifers with artesian pressures or liquefiable soils are present, the
exploration depth should be extended to fully penetrate these units.
Cut slopes with a depth of 10 feet (3m) or more should be explored to a depth that is two times the
height of the proposed cut. When bedrock is encountered in a cut slope boring, the boring should
extend at least 15 feet below the finish grade of the cut. Cut slope borings should be extended if
sheared surfaces or other evidence of landslide susceptibility are encountered that could affect the
performance or constructability of the finished slope.
3.5.3.4 T u n ne l a n d Tr e n c hl e s s P i pe I n s t a l l a t i o n Bor i ng s
A “rule-of-thumb” for tunnel exploration is the amount of exploration drilling should be 1.5 times the
length of the tunnel. This should be considered as a bare minimum for exploration cost estimating for
tunnel/trenchless installation projects will shallow alignments in very favorable conditions, and does
not include horizontal drilling along the tunnel/pipe profile. Clearly, the amount of drilling for any given
length of tunnel/trenchless installation alignment is dependent on several factors that include, among
others, the depth of the invert, diameter of the tunnel/pipe, geologic conditions, and contingencies.
Typically, tunnel/trenchless installation borings should be extended at least 1.5 tunnel/pipe diameters
below the proposed grade of the invert. It may be beneficial to further extend the borings to as much
as 3 times the tunnel/pipe diameter as a contingency if the final tunnel alignment has not been
determined. The depth of the borings should be increased further to evaluate any unforeseen or
unfavorable geologic conditions encountered that may affect the tunnel or pipe design and
construction. Wherever practical, horizontal borings should be taken along the tunnel profile because
of the advantages of having a full-length representation of the actual tunnel/pipe horizon conditions.
3.5.3.5 S t r u c t ur e - S pe c i f i c B or i ng s
The guidelines for boring depths presented in Section 3.5.3 stem from structure-specific boring
guidelines developed by AASHTO and other agencies. Follow these guidelines:
• It is highly desirable for all structure-specific borings to penetrate at least 15 feet (4.5m) into
bedrock.
• For drilled shaft installations, the test borings should be advanced 1.25 times the total
projected shaft length beyond the predicted shaft base elevation.
• If the shaft base is to be founded in soil or rock with an RQD of 50% or less, then the test
borings should be extended an additional depth below the proposed bottom of the shaft equal
to the larger of 20 feet (6m) or 3 times the shaft base diameter. Shafts are most commonly
designed to bear on competent bedrock, thus, where the RQD is greater than 50%, the test
boring should also be advanced to the greater of 20 feet (6m) or 3 times the shaft base
diameter below the estimated shaft base elevation.
Note:
The geotechnical designer must exercise judgment concerning the nature of the facility with respect
to the total and economical amount of drilling needed for the specific structure. Borings for sound
walls, small traffic structures, or culverts may not be required to obtain core samples in bedrock, but
for bridge foundations, bedrock drilling would certainly be needed.
3.5.3.7 L a n ds l i de s
Considerable flexibility must be built into the Exploration Plan for any landslide, and particularly with
respect to the depth of the explorations. Follow these guidelines:
• Typically, the cross-section drawn along the centerline of the landslide is used to develop the
preliminary exploration depths.
• Circular, elliptical, or composite curves drawn from the headscarp to the toe bulge are
projected onto the cross-section to show the possible depths of slide movement. These
curves are commonly exaggerated to conservatively estimate the slide depth.
• The preliminary boring depths should extend 20 feet (6m) or more below the projected slide
plane to assure that the zone of movement is fully penetrated, and to secure instruments
below the slide plane for the best results.
• Firm, resistant strata, bedrock projections, and irregular surfaces will also affect the geometry
of the slide plane, and subsequently, the final depths of individual borings.
• Landslide borings should always be extended to a depth that clearly identifies which
materials are involved in the current slope movement, which underlying materials are
presently stable, and the location of the slide surface(s). This is not only important to the
development of a stability analysis, but will become important once again during construction
when the precise locations of mitigation efforts will be determined. There is often a possibility
that the observed landslide activity is an accelerated portion of a slower, deeper-moving
landslide that may only be detected by instrumentation. For this reason, at least one boring
should be extended far below the predicted slide surface to divulge such activity. Any
Exploration Plan for landslide investigations should contain the flexibility to extend borings to
considerable depth during the site exploration.
3.5.4.1 S oi l S a m pl i n g f or Cor r os i o n As s e s s m e nt
The corrosion potential of buried or exposed metal structures depends primarily on the electro-
chemical nature of the soil and the presence of oxygen and moisture. An assessment of these
properties and conditions is necessary to properly determine the corrosion potential of culverts
and structure foundation materials. Electro-chemical tests provide quantitative information
related to the aggressiveness of the subsurface materials and surface water environments.
Electro-chemical soil testing typically includes testing for pH and resistivity and sometimes
sulfate, and chloride contents. Surface water should also be tested in coastal regions where the
potential intrusion of brackish (salt-water) water may occur in tidal streams.
Corrosion of culverts, steel piling and other buried structural elements is most likely to occur at
or above the water table and in disturbed stratified soils such as man-made fills, especially
those containing cinders, slag or ash. Guidance on the amount and extent of soil and
groundwater sampling and testing for corrosion assessment is provided in the later chapters of
this manual that are dedicated to specific structures.
3.5.5.1 S t a n da r d P e ne t r a t i on T e s t i n g
All Standard Penetration Tests must be performed according to ASTM D 1586-99. The Standard
Penetration Test (SPT) is the most common method for field testing and sampling of soils. Some
variations with respect to standard intervals and refusal criteria occur throughout the industry
however the fundamental procedure still adheres to the ASTM standard. The SPT uses the following
methods:
• This sampling method uses the standard configuration 2-inch (5cm) outside diameter split
spoon sampler at the end of a solid string of drill rods. The split spoon is driven for a 1.5-foot
(0.45m) interval using a 140 Lb. (63.5 Kg) hammer dropped through a 30-inch (76cm) free
fall.
• The number of hammer blows needed to advance the sampler for each 6-inch (15cm)
interval is recorded on the boring log and sample container.
• The Standard Penetration Resistance or uncorrected “N”-value is the sum of the blows
required for the last two 6-inch (15cm) drives. Refusal is defined as 50 blows in 6 inches
(15cm) of penetration and recorded on the log as 50 blows and the distance driven in that
number of blows.
• The hole is advanced and cleaned out between sampling intervals for at least the full depth of
the previous sample.
This general procedure can be used with larger diameter samplers and heavier hammers for the
purpose of obtaining additional sample volumes, but the blow counts do not provide standard
resistance values. Prior to the commencement of drilling operations, the hammer energy must be
measured to determine the actual hammer efficiency. This information can usually be obtained by the
drill manufacturer. If it is not available, a competent technician must be engaged to measure the
hammer energy for each drill rig.
3.5.5.2 T hi n - W a l l e d Un di s t ur be d Tub e S a m pl i n g
Undisturbed samples of cohesive soils should be taken with 3-inch (7.6cm) diameter Shelby Tubes
according to the standard practice for thin-walled tube sampling of soils in
ASTM D 1587-00. This method obtains relatively undisturbed samples by pressing the thin-walled
Oregon Department of Transportation 3-30
Geotechnical Design Manual
December 2016
tube into the subject strata at the bottom of the boring. Thin-walled sampling is simply a method for
retrieving a sample for laboratory testing. There is no actual field-testing involved with thin-walled
sampling unless a Torvane or Pocket Penetrometer test is performed on the end of the sample.
Pressures exerted by the drill rig while pushing Shelby tubes are frequently recorded for general
reference but do not provide repeatable test results. After the unfavorable effects of the sampling
procedure, transport, handling, and storage, a truly undisturbed sample cannot be realistically tested
in the laboratory. However, with appropriate care, valid samples can be taken for shear strength,
density, consolidation, and permeability testing.
Shelby tubes do not utilize a sample retention system to hold the sample in place during retrieval
from the borehole, so sample recovery can be unreliable. Thin-walled sampling in general is
successful only in soft to stiff cohesive soils. Soils that are very soft are difficult to recover with
standard Shelby tube while the upper range of stiff and very stiff soils are difficult to penetrate or bend
the tube resulting in a disturbed sample. Oversized clasts and organic fragments in the softer soil
matrix can also be detrimental to thin-walled sampling.
Various samplers that use retractable pistons to create a vacuum in the top of the tube can achieve
greater success in obtaining undisturbed samples of soft cohesive soils as well as granular materials.
3.5.5.3 R o c k C or i n g
Rock core drilling should be carried out according to ASTM-D 2113-99. Successful core drilling is as
much a skill as it is a test procedure. Experienced, conscientious personnel are necessary not only to
run the equipment, but also to interpret the results of the drill action as well as the samples
recovered. Material recovered may not actually represent the subsurface conditions present if not
correctly sampled. Observation and interpretation of the drill action, fluid return, and other
characteristics provide indications of the actual validity of the core sample as well as other
information concerning the actual conditions in the subsurface.
Note:
ASTM states that the instructions given in D 2113-99 cannot replace education and experience and
should be used in conjunction with professional judgment. Qualified professional drillers should be
given the flexibility to exercise their judgment on every alternative that can be used within the
appropriate economic and environmental limitations.
Triple-tube Core Barrel Systems
Because of the close-jointed, highly fractured nature of many rock formations in Oregon, and the
detailed observations desired, rock coring should be performed with triple-tube core barrel systems
that are best suited to such material. These systems provide the best recovery in difficult, highly
fractured, and/or weathered rock, which is extremely important since discontinuity spacing, and
weathering characteristics usually limit the strength of a rock mass with respect to foundation loading,
or the performance of rock excavations. Triple-tube barrels provide direct observation of the rock core
specimen in the split-half of the innermost tube as it is extracted from the inner core barrel. This
allows accurate measurement of RQD and recovery and discontinuity attitudes prior to further
specimen handling. Partial isolation of the sample in the inner split-barrel from the drilling fluids also
preserves much of the discontinuity texture and infilling material that is also very important to rock
mass characterization.
Most rock coring is performed with “H”-sized systems that provide core specimens with a diameter of
213/32 inches (61.1mm).
3.5.5.4 B ul k S a m pl i n g
Bulk sampling should be carried out at all pipe/culvert locations from the actual invert elevation when
test borings are not required. The samples collected are submitted for the appropriate chemical
testing. Typically, bulk samples of 25 lbs. (11Kg) if impermeable bags are used, or 2 gallons (7.5
liters) for jar/bucket samples are collected from each discrete sampling site. Sample receptacles must
be sealed to preserve natural moisture conditions. Bulk sampling may also be conducted for material
source investigations and other surficial applications. All samples collected should be preserved and
transported according to ASTM D 4220-95.
3.6.2.1 M e t h o ds G e n e r a l l y N o t Us e d
Cable-tool, wash, jet, and air-rotary methods are generally not used on ODOT projects for many
reasons. Cable-tool drilling may be useful for some environmental applications and well
installations, but is generally antiquated and not productive for geotechnical investigation. Wash
and jet borings cause down-hole disturbance well past the bottom of the boring, and the fluids
are difficult to recover making them more of a liability than a source of data. Air-rotary drilling
usually causes too much down-hole disturbance to provide reliable SPT data, and difficult to
advance in soft soils. Groundwater typically stops further advancement of air-rotary drills, forms
large voids, and casts sediment-laden water about the site. Air-rotary drilling may be suited to
3.6.2.2 Au g e r B or i ng s
Rotary auger drilling is one of the more rapid and economical methods of advancing exploration
borings. Most modern drilling equipment has enough power to turn augers of considerable diameter
to a substantial depth. Currently, most auguring uses a hollow-stem auger that allows the hole to
remain cased while the various sampling or drilling tools are used and withdrawn from the hole with
drill rods or wireline retrievers. A central “stinger” bit or plug is placed at the bottom of the auger while
the boring is advanced. Solid stem auger use has largely been discontinued due largely to the advent
of hollow stem augers and the more powerful equipment that is capable of turning their larger
diameter drill string. The standard practice for using hollow-stem augers is described by ASTM D
6151-97. Auger boring has many advantages and disadvantages for various materials encountered
as described below.
Auger Boring Advantages
Auger boring has many advantages and disadvantages for various materials encountered. The
primary advantages of augers are the preservation of the natural moisture content of the soil and the
rapid advancement of the drill through soft to stiff soils. Augers are also useful where drill fluids are
difficult to obtain or are an environmental concern, and in freezing conditions where the use of water
is problematic. An additional advantage of augers is that they create a large enough hole to install
larger-diameter standpipe piezometers or nested piezometers in conformance with Water Resources
Department regulations. In addition, the natural piezometric surface is more readily monitored during
drilling. Coring tools are also available for auger systems that provide continuous sampling in soils
and even weak rock materials. These tools can be placed by either rods or wireline into special auger
bits that feed a continuous soil sample into a split barrel that is then retrieved in 2.5 or 5-foot (0.76-
1.52m) sampling intervals. Plastic liners that fit in the auger core barrel can also be used to preserve
soil cores in their natural moisture conditions.
Auger Boring Advantages and Disadvantages
The disadvantages of auguring are the power needed to turn long strings of auger in dense
formations, the volume of the hole and the cuttings created, and the disturbance of the natural
materials in certain conditions. When hollow-stem augers are used in granular soils below the water
table, the hydrostatic pressure differential between the inside and outside of the auger casing will
force saturated sands, silts, and fine gravels up into the casing effectively loosening the materials
below the auger bit. This can be caused by either the natural differential, or by the pressure induced
during retraction of the “stinger” bit or plug. The augers themselves can also affect the conditions of
loose granular materials and silts ahead of the bit. In both cases, SPT values obtained will be
different than what is true for the natural conditions. To counter this effect, a head of water, or other
drilling fluid can maintained in the auger casing to counteract these effects. Adding fluids to the auger
generally negates their advantages and if such action is necessary, a different drilling technique
should be employed. Hollow stem auguring should not be employed when assessing liquefaction
potential.
3.6.2.3 R o t a r y D r i l l i ng
Rotary drilling is the most common, and usually the most versatile drilling method available. Various
tools and products available for rotary drilling allow it to be adaptable to most drilling conditions and
geologic materials. Rotary boreholes can be uncased holes advanced with a drill bit on rods or cased
holes made with a casing, casing advancer and casing shoe. The casing advancer is a driver
assembly with latches that fit in the bottom of the casing where it holds the center bit at the bottom of
the hole and is subsequently retrieved with a wireline system. This method of drilling involves a
relatively fast rotation speed, fluid circulation, and variable pressure on the drill bit to penetrate the
formation, pulverize the formation particles at the bottom of the borehole. The circulating fluids carry
these cuttings away from the bit, up the borehole annulus, and out of the hole.
When the desired sampling depth is reached, the drill rods or casing advancer are retracted from the
hole and replaced with the desired sampling tool. The sampling/testing is conducted while the hole is
filled with fluid, retrieved from the hole, and then replaced once again with the drilling tool and
borehole advancement continues to the next sampling depth. For uncased holes, the drilling fluid is
relied upon to stabilize the borehole and prevent it from caving or heaving. In particularly weak or
porous formations where drilling fluids are rapidly lost, cased holes are generally used. In uncased
holes, the drilling fluid is usually recirculated from a mud tank or pit at the ground surface. Borings
that use casing advancers typically use pure water that is not recirculated.
Rotary Drilling Advantages
The advantage of rotary drilling is the relative speed of advancement in deep borings while
maintaining borehole stability that best preserves in-situ soil conditions by counteracting soil and
pore-water pressures in partially or fully saturated conditions. It is of particular advantage in very soft
materials that are very sensitive to disturbance by the drilling equipment. Because of its ability to
maintain natural conditions, rotary drilling is usually the best choice when conducting in-situ analysis
such as vane shear and pressure meter testing. The trade-offs for rotary drilling is the introduction of
moisture and other minerals that will influence the natural moisture conditions, and the difficulties with
installing groundwater monitoring instruments although this later can in some cases be rectified by
the use of special drilling fluids and by purging the borehole prior to installation. Special care is
needed to contain drilling fluids during exploration, and for ultimate disposal that may involve
transport off-site.
Drill Rods
A variety of drilling rods, casings, and drill bits are available for various tasks. Most drilling tools come
in standard sizes that are generally adaptable to one another. However, complexities arise when
changing from one size to another when various thread sizes and configurations are used. Use the
following information relating to drill rods and casing sizing:
• Drill rod and casing sizes are designated from smaller to larger by the letters R, E, A, B, N,
and H. Drill rod outside diameters range from 13/32 inches (27.8mm) for R-sized rods to 3.5
inches (88.9mm) for H-sized rods.
3.6.2.4 R o c k C or i n g
Rock core sampling is used to obtain a continuous, relatively undisturbed sample of the intact rock
mass for evaluation of its geologic and engineering characteristics. When performed appropriately,
core drilling produces invaluable subsurface information. Rock coring procedures have generally
remained the same since the advent of the technology: a steel tube with a diamond bit rotated into
the rock. Advancements in the bits, core barrels for retrieving the samples, and improvements to
mechanized equipment overall have greatly enhanced this method.
Note:
Rock core drilling procedures and equipment has largely been standardized by
ASTM D2113-99. The Diamond Core Drill Manufacturers Association (DCDMA) has also
standardized bit, core barrel, reaming shell, and casing sizes similar to drill rods.
Rock coring almost exclusively involves the use of diamond bits, thus the terms “rock coring” and
“diamond drilling” are used interchangeably. Selecting the proper drill bit for the rock coring conditions
is essential. Sample recovery and drill production is dependent upon it. The ultimate responsibility for
bit selection is the driller’s, however, it is important to be familiar with bit types to help determine
recovery problems in the field since they may actually be unrelated to the drilling method. The actual
configuration of the drill bit is selected based on the actual site conditions. The cross-sectional
configuration, kerf, crown, and number of water ports are all determined by the anticipated conditions
and characteristics of the rock mass. Consider the following:
• Incorrect bit selection can be extremely detrimental to core recovery, production, and project
budget.
• Typically, a surface-set bit consisting of industrial diamonds set in a hardened matrix is used
for massive rock bodies.
• Larger and fewer diamonds in the set are used for soft rocks while smaller and more
numerous diamonds are used in hard rock. Hard rock bits commonly have a rounded or
steeply angled crown.
• Flat-headed bits are usually for very soft rock. Impregnated bits consist of very fine diamonds
in the matrix and are generally used for soft, severely weathered, and highly fractured
formations. Some carbide blade and button bits are used for soft, sedimentary rocks. These
are ideally suited for soft rocks with voluminous cuttings that require a considerable amount
bit flushing and cutting extraction.
Core Barrel
The core barrel is the section of the drill string that retains the core specimens and allows them to be
retrieved as a whole section. Core barrels may be of different types and sizes, and may consist of
numerous components that may be changed depending on the rock mass condition. Core barrels
have evolved greatly over time. Single-tube barrels were originally used and required the entire drill
string to be retracted to withdraw the sample. These have evolved through double-tube systems of
either rigid-types where the inner tube rotates with the outer barrel, or swivel-types where the inner
tube remains stationary. Most core barrels used today are triple-tube systems that employ another
non-rotating liner to a swivel-mounted double core barrel. This split metal liner retains the sample
3.6.2.5 V i br a t or y o r S o ni c Dr i l l i n g
Sonic drilling may be called vibratory or rotosonic drilling. This type of drilling is used for continuous
sampling in unconsolidated sediments and soft, weathered bedrock. It is best suited for use in
oversized unconsolidated deposits enriched with cobbles and boulders such as talus slopes,
colluvium, and debris flows or any other formation containing large clasts.
Benefits
• The primary benefit of this method is recovery of oversized materials in a continuous sample,
rapid drilling rate, reduced volume of cuttings, and fast monitoring well installation.
• This drilling technique is 8 to 10 times faster than hollow stem auguring and produces about
10% of the volume of cuttings.
Drawbacks
• The drawbacks to this method are that it is typically more expensive, and cannot penetrate
very far into bedrock.
3.6.2.6 B e c k e r Ha m m e r Dr i l l i n g
Becker hammer drills are specifically for use in sand, gravel, and boulders. Some Becker hammer
drill operators may also have a scoring system that can also be run for limited applications. Becker
hammer drills use a small diesel-powered pile hammer to drive a special double-walled casing. The
casing can be fitted with an array of toothed bits depending on the application. An air compressor
forces air through the annulus between the casings to the bottom of the hole where it extracts the
materials up through the center of the innermost casing, through a cyclone, and into the sampling
bucket. The materials can be extracted on a set interval as the driller engages the air compressor.
The Becker drill casings range in size from 5.5-inch (14cm) to 9 inches (23cm) for the outer casing,
and 3.3-inch (8.4cm) to 6 inches (15.2cm) respectively for the inner casing. This size of casing allows
retrieval of relatively large, unbroken clasts. As the drill is advanced, blow counts are taken along with
measurements of the hammer’s bounce chamber pressure. Becker hammer drill data can be
correlated to the soil density and strength in coarse-grained soils similarly to the SPT test. In addition,
SPTs can be taken through the inner casing of the Becker hammer string.
3.6.2.7 S u p pl e m e n t a l D r i l l i n g/ E x pl or a t i o n Ap p l i c a t i o n s
A wide assortment of exploration techniques are available to supplement the subsurface information
gathered from test borings at a project site. Typically, any method that can be employed to properly
evaluate the subsurface conditions in a supplementary capacity is acceptable on an ODOT project if
not constrained by environmental considerations. These methods are usually the most simple and
economic to quickly gather subsurface information with minimal cost. In some cases, more extensive
and costly methods are required to obtain critical design information. Generally, supplemental
investigations consist of simple hand auger borings or backhoe test pits to gather more detailed
information and collect additional samples in near-surface or overburden materials.
Hand Tools
Hand augers are available in many forms that allow rapid penetration of near-surface soils and
collection of representative samples. Various bits can be used that are suited to general soil
conditions that help penetrate and retain samples from certain materials. Extra sections of rods can
be added to extend the depth range of these tools. Small engine-powered augers can also be used
to increase the depth of penetration and to reduce the physical workload. Most hand augers are of
sufficient diameter to permit undisturbed Shelby-tube sampling in the boring where soft soils are
encountered. Additional tools such as jacks, cribbing, and extra weights may be needed to retract the
tube after sampling. Most field vehicles are equipped with shovels that geotechnical designers can
apply to subsurface investigations. Hand-excavated pits can provide essential, detailed information
on the near-surface environment.
3.7.2.1 S i t e I n ve s t i ga t io n a nd E x pl or a t i o n
Instruments are regularly used to characterize the initial site conditions during the design phase of a
project. Landslide remediation projects rely on instruments to determine depths and rates of
movement as well as pore water pressures to provide basic information for stability analysis and
mitigation design.
Most project sites require some information concerning the actual depth and seasonal fluctuation of
groundwater that not only affects the project design, but also its constructability.
3.7.2.4 S a f e t y a n d Le ga l P r o t e c t i o n
Instruments can be used to provide early warning of impending failures allowing time to isolate the
problems and begin implementation of remedial actions. Instrument data provides crucial evidence
for legal defense of the agency should owners of adjacent properties claim that construction or
operations have caused damage.
3.7.2.5 P e r f or m a nc e
Instruments are used for the short and long-term service performance of various facilities.
Deformation, slope movement, and piezometric surface measurements in landslides can be used to
evaluate the performance of drainage systems installed to stabilize the landslide. Loads on rock bolts
and tiebacks may be monitored to assess their long-term performance or evaluate the need for
additional supports.
3.7.3.1 Au t o m a t i c Da t a Ac q u i s i t i o n S ys t e m s ( AD AS )
Automatic Data Acquisition Systems (ADAS) can provide significant advantages to a geotechnical
instrumentation program. They can provide numerous readings at set and reliable intervals, and they
can store and transmit data from remote or difficult access locations. ADAS are necessary for real-
time instrument monitoring and relay. They are beneficial at sites where many sensors are present
that would require copious staff time to read manually or for large-scale proof tests with many
concurrently read instruments to be monitored throughout the test.
Automatic Data Acquisition Systems come in many forms ranging from the very simple, user-friendly
devices to systems requiring significant programming and electronics to install and run. Project
requirements usually dictate what system is selected, but the simplest, most inexpensive, and easiest
to connect to the chosen instruments are best. Follow these guidelines:
• Simple data loggers connected to individual instruments that are retrieved and downloaded
periodically are sufficient for most projects.
• Large, complex problems may require a more intelligent system that can be programmed to
change monitoring routines in response to site or environmental changes.
• Most instrumentation companies also have companion data loggers to go with their products
while several independent companies also manufacture easy-to-use data loggers. Other
companies, such as Campbell Scientific Incorporated, produce more complex systems that
can read multiple installations of different types of instruments as well as store and transmit
data.
3.7.3.2 I ns t r um e nt Us e a n d I ns t a l l a t io n
Instruments have been developed to monitor many specific geologic conditions and engineering
parameters. In many cases, a single instrument can be used or adapted for use on other
applications. For this, the manufacturer and other professionals should be consulted to assure that
the results obtained are valid, or, they may have insights and case histories that are of use for the
situation. The manufacturer’s literature, installation procedures, and other guidance documents
should be followed for proper installation of their products as procedures can vary for different
manufacturers same instrument products. Detailed discussions of instrument installation and
initialization procedures, function, and operation can be found in manufacturer’s documents such as
Slope Indicator Company (SINCO) Applications Guide or in published literature such as Dunnicliff
(1988).
3.7.3.3 I nc l i no m e t e r s
Inclinometers are used on transportation projects mainly to detect and monitor lateral earth
movements in landslides and embankments. They are also used to monitor deflections in laterally
loaded piles and retaining walls. Horizontally installed inclinometers can also be used to monitor
settlement. Inclinometer systems are composed of:
• grooved casing installed in a borehole, embedded in a fill or concrete, or attached to
structures,
• probe and cable for taking measurements at set intervals in the casing, and
• a digital readout unit and/or data storage device.
The installed casing is for single installation use, and the probe, cable and data storage unit are used
for almost all installations.
Note:
It is important to use the same probe for each reading in any particular installation since each probe
must be independently calibrated.
Inclinometers are manually read by a trained technician on a set schedule or in response to
environmental changes such as increased rainfall in the area or observation of surficial signs of slope
movement. In-place inclinometers spanning known or highly suspected zones of movement can be
installed for continuous, automatic monitoring. These usually remain in the hole permanently if
significant slope movement occurs.
• Inclinometer casing installation is essential to successful performance of the instrument.
Shortcuts taken during installation will frequently result in poor performance of the instrument
or render it useless.
• Inclinometers should be installed according to the procedures described in the SINCO
Applications guide with the exception of the grout valve.
• Borings should be initially drilled or later reamed to a sufficient diameter that will
accommodate the inclinometer casing and an attached tremie tube.
3.7.3.4 P i e z om e t e r s
Piezometers used to measure pore-water pressure and groundwater levels can range from simple
standpipes to complex electronic devices or pneumatic systems. Piezometers are typically installed
in selected layers to measure the piezometric pressures in that layer. The layout and target depths of
piezometer installation are determined by actual site conditions and project requirements.
Note:
All piezometers must be installed according to Oregon Water Resources Department regulations
defined by OAR 690.240 and ORS 537.880 through 537.895. Specifications for properly operating
instruments are usually more stringent than these rules apart from the requirements for
abandonment.
The various types of piezometers are generally used for different applications as described below.
• Standpipe piezometers are general-purpose instrument for monitoring piezometric water
levels and are best suited for granular materials. Standpipe piezometers require a water level
indicator to obtain readings.
• Vibrating Wire piezometers utilize a pressure transducer to convert water pressure to a
frequency signal that is read by an electronic device. Vibrating Wire piezometers can be
automated by electronic systems.
• Pneumatic piezometers are typically used to measure pore water pressure in saturated
conditions. Both Pneumatic and vibrating wire piezometers are used for all soil types and are
better suited to fine-grained soils than the standpipe variety due to the response time and
volume of water needed to record changes in water level in that type.
Piezometers should be placed at the desired sensing zone in a porous medium and sealed with the
appropriate materials above and below this zone to assure measurement of the piezometric pressure
in the desired location. Porous mediums or filter packs should be composed of pre-screened
commercial-grade silica sand. All piezometers should be installed and initialized according to their
manufacturer’s specifications.
Property Description:
D-89-16328
37-2W-28 TL 800
IT IS UNDERSTOOD AND AGREED: That this right and license shall be valid until all
exploration is completed unless revoked by grantor before completion. It is further
understood that the Oregon Department of Transportation shall, to the extent permitted by
Oregon law, be responsible for any unnecessary damage done, in connection with said
exploration, this will include any crops or other improvements on said property.
Grantor hereby represents and warrants that he/she is the owner of said property or
otherwise has the right to grant this permit of entry.
Signature:__________________________________
Owner(s)
Signature(s):___________________________________________________________
Project Name:
Highway and Mile Point:
Utility Locate Called By:
Locators Called (When):
Required Information
Caller ID #:
Type of Work:
County/City
Highway:
Mile Point:
Township/Range/
Quarter Section:
Distance from
Nearest Cross
Street:
Overhead Lines:
Special Markings:
Date to Be Located:
Ticket#:
Name of Person Called:
Utilities Notified: