Construction Methods and Project Management Notes
Construction Methods and Project Management Notes
Key Decisions
Deciding which projects to implement
Selecting a project manager
Selecting a project team
Planning and designing the project
Unique, one-time operations designed to accomplish Managing and controlling project resources
a specific set of objectives in a limited time frame. Deciding if and when a project should be
terminated
Project Manager Responsible for: Project Network – Activity on Arrow
Work
Quality
Human Resources
Time
Communications
Costs
Ethical Issues
Temptation to understate costs
Withhold information
Project Network – Activity on Node
Misleading status reports
Falsifying records
Comprising workers’ safety
Approving substandard work
Project Life Cycle
Network Conventions
Time Estimates
PERT and CPM Deterministic - Time estimates that are fairly
PERT: Program Evaluation and Review Technique certain
CPM: Critical Path Method Probabilistic - Estimates of times that allow
Graphically displays project activities for variation
Estimates how long the project will take
Indicates most critical activities Example 1
Show where delays will not affect project
The Network Diagram
Network (precedence) diagram – diagram of
project activities that shows sequential
relationships by the use of arrows and nodes.
Activity-on-arrow (AOA) – a network diagram
convention in which arrows designate activities.
Activity-on-node (AON) – a network diagram
convention in which nodes designate activities.
Activities – steps in the project that consume
resources and/or time. Example 1 Solution
Events – the starting and finishing of activities,
designated by nodes in the AOA convention.
Path - Sequence of activities that leads from the
starting node to the finishing node
Critical path - The longest path; determines
expected project duration
Critical activities - Activities on the critical path
Slack - Allowable slippage for path; the difference
the length of path and the length of critical path
Computing Algorithm Example 5 Time Estimates
1. Network activities
ES: early start
EF: early finish
LS: late start
LF: late finish
2. Used to determine
Expected project duration
Slack time
Critical path
Path Probabilities
Probabilistic Time Estimates
Optimistic time - Time required under
optimal conditions
Pessimistic time - Time required under worst Z indicates how many standard deviations of the path
conditions distribution the specified tine is beyond the expected
Most likely time - Most probable length of path duration.
time that will be required
Probabilistic Estimates Example 6
Expected Time
Example 5
Advantages of PERT Summary
Forces managers to organize Projects are a unique set of activities
Provides graphic display of activities Projects go through life cycles
Identifies PERT and CPM are two common techniques
- Critical activities Network diagrams
- Slack activities Project management software available
Linear Time-Cost Tradeoff Which Activities are the Best Candidates for Crashing?
In theory, the normal or expected duration of a task Any activity that is on the critical path
can be reduced by assigning additional resources to Activities with relatively long durations
the task Bottleneck activities (that appear on multiple
critical paths)
Activities with relatively low costs to crash
Activities that are not likely to cause quality
problems if crashed
Activities that occur relatively early in the
schedule and are labor intensive
Crashing Summary
Network Crashing Example
Initial Total
= $450
In planning, crashing can pull your project into the
Direct Cost
B E
Total delivery window
= 25 units
Once started, a late project can get pulled back in
Duration
6 8
A C G Select activity “A”
[smallest slope] and
to schedule compliance
3 10 6
reduce time by 1 unit (x
in next panel indicates Crashing can increase the size of the “critical
D F activity crashed by
maximum core,” thereby reducing flexibility
11 5 Capability in MS Project
Total
= $470
B E Direct Cost
Total
6 8 Duration = 24 units
A C G
2x 10 6
D F Activities Changed
A
11 5 $20
Total
Direct Cost = $495
B E
Total
Duration = 23 units
6 8
A C G
2x 10 6
D F Activities Changed
D
10 5 $25