COMMISSIONING PROCEDURE
OWNER
VIETNAM ELECTRICITY
THERMAL POWER PROJECT MANAGEMENT BOARD 3
CONSULTANT
POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 3
CONTRACTOR
THE CONSORTIUM OF CHENGDA-DEC-SWEPDI-ZEPC
SUBCONTRACTOR
THE COMMISSIONING & TEST INSTITUTE OF SICHUAN ELECTRIC
POWER INDUSTRY
SECTI
CONTRACT No.
PROJECT DUYEN HAI 3 THERMAL POWER PROJECT
DH3-05082011
PROJECT CONTROL
DH3-31BB-T-SCT-0009
No.
Contents
1. Objective of Commissioning............................................................................................ 3
2. Content of Commissioning............................................................................................... 3
8. Appendix 1 ....................................................................................................................... 8
CHENGDA-DEC-SWEPDI-ZEPC
1. Objective of Commissioning
1.1 Energize and put into operation of the 6.6kV transformer and 400V/230V busbar
through commissioning.
1.2 Energize the 400V/230V power system.
1.3 Scope of energization:
6.6kV transformer.
400/230V busbar
2. Content of Commissioning
2.2 Inspect the secondary voltage phase sequence and amplitude of 400V/230V busbar
PT, and verify the phase with the secondary voltage of 6.6kV busbar PT.
2.3 Differential protection circuit test of 6.6/0.42kV transformer (in case the load current is
too small, this test shall be made when the load current is heavy).
2.4 The scope of power supply to 400V/230V power system shall be as follows:
Common section, 31A electrostatic precipitator section, 31A boiler section, 31A
turbine section 31B electrostatic precipitator section, 31B boiler section, 31B turbine
section, Section A ash handling section outside the plant, standby electrostatic
precipitator section, desulfurization section of #31 unit, chemical and water supply
section A, coal handling section A, lighting section of #31 unit.
3. Compilation Basis
6. Commissioning Procedure
7.2 HAZID/HAZOP
Num Activity Potential Hazard Factor Potential Hazard Result Prevention Measure
Wear proper work clothes and keep the safe distance with high temperature object. If need to
1 Site work High temperature object surface Personnel scald
contact with high temperature object, wear heat insulated gloves or protective equipment.
High temperature water, steam Wear proper work clothes, keep the safe distance with the discharge , if necessary to work in the
2 Site work Personnel scald
accident leakage vicinity of the equipment, avoid standing on the side of the flange or the front of the discharge.
Check the protective device of rotating parts is in position, and keep safe distance with the
3 Site work Contact rotating device Mechanical injury rotating equipment, if need to work in the vicinity of the rotating equipment, to avoid clothes or
hair to be involved
Understand the voltage level of the work area and equipment before work, check the isolation
Insufficient distance with Electric shock measures correctly and reliably, wear suitable working clothes and shoes, keep the safe distance
5 Site work
energized object casualties with the energized object. Reliable measure for de-energizing is required for the work on the
energized object and the detection and confirmation is needed.
equipment unearthing or ground
6 Site work Electric shock check ground lines install well, measure ground resistance satisfied standard when it is necessary.
line work is unreliable
Falling from high check ditches are covered or not, cover measures should be taken to holes on the ground to
7 Site work holes on the ground uncovered
casualties prevent workers from falling
Reliable climb equipment should be used when highly working; safety belt shall be correctly used
8 Site work Falling from high hurt and casualties
and supervisor shall at side.
Injury due to falling Within special area, provide alert symbols, warning board and fencing; operation personnel must
9 Site work Falling objects from high
objects wear safety protection appliances as required.
Prepare strict fire control measures; sufficient fire apparatus must be provided at site; smoking
10 Site work Fire Fire hazard
while moving around is prohibited; Work out measures properly.
Check charged current and
11 Site work Electric shock Be supervised to avoid others direct contact with the current and voltage circuits.
voltage circuit
8. Appendix 1
Select smallest load
LV side smallest HV side smallest
Transformer LV side primary current LV side smallest HV side primary current HV side smallest Select
No
name ratio (secondary load(cosΦ=0.8) ratio (secondary load(cosΦ=0.8) smallest load
current=50mA) current=50mA)