Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Project Title : PROPOSED 2 STOREY RESIDENCE

Location : Brgy. Navais, Mandurriao


Owner : Engr. & Mrs. Reynaldo Esteves

BILL OF QUANTITIES
I General Requirements MATERIAL LABOR
MATERIAL
SPECIFICATIONS QTY UNIT
+ LABOR
Item Description Material Cost Amount Labor Cost Amount

SUB-TOTAL (General Requirements) 118,000.00 411,250.00 529,250.00


1.0 Building & Occupancy permits to complete Owner Supplied 1 lot 0.00 0.00 0.00
2.0 Documents Facilitations 1 lot 0.00 5,000.00 5,000.00 5,000.00
3.0 Surety bond
a. Contractors all risk insurance 1 lot 25,000.00 25,000.00 6,250.00 6,250.00 31,250.00
b. Performance/guarantee bond 1 lot 0.00 0.00 0.00 0.00
c. Payment Bond 1 lot 0.00 0.00 0.00 0.00
d. Construction Bond 1 lot 0.00 0.00 0.00
4.0 Mobilization/demobilization 1 lot 0.00 15,000.00 15,000.00 15,000.00
5.0 Temporary facilities(including office) 1 lot 20,000.00 20,000.00 5,000.00 5,000.00 25,000.00
6.0 Light & Water bill
Temporary Electric Consumption Owner Supplied months
Subdivision Water Connection Processing Owner Supplied lot
Water Maintenance/Consumption fee Owner Supplied months
7.0 DOLE Safety and Health Program
Safety Officer 5 months 0.00 20,000.00 100,000.00 100,000.00
CSH program 1 lot 0.00 30,000.00 30,000.00 30,000.00
Personal Protective Equipment 40 pax 950.00 38,000.00 0.00 38,000.00
8.0 Project Management and Supervision 5 months 0.00 50,000.00 250,000.00 250,000.00
9.0 As built plans 1 lot 15,000.00 15,000.00 0.00 15,000.00
10.0 Materials sampling/testing fee 1 lot 20,000.00 20,000.00 0.00 20,000.00
Mobilization, Cleaning, Hauling and, Site
II MATERIAL LABOR
Preparation MATERIAL
SPECIFICATIONS QTY UNIT
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Mobilization, Cleaning, Hauling and, Site Preparation) 64,660.00 88,548.00 153,208.00
Clearing 161 sq.m. 0.00 80.00 12,880.00 12,880.00
Layout 161 sq.m. 0.00 12.00 1,932.00 1,932.00
Unsuitable materials hauling 32.2 cu.m. 0.00 50.00 1,610.00 1,610.00
Ground Base Preparation 161 sq.m. 0.00 150.00 24,150.00 24,150.00
Dewatering 1 lot 0.00 10,000.00 10,000.00 10,000.00
Gravel 16.1 cu.m. 700.00 11,270.00 210.00 3,381.00 14,651.00
Others (Contractor to Itemize if any) lot 0.00 0.00 0.00
1.0 Water Proofing - wall
Cementitious Bostik 112 Sq.m 200.00 22,400.00 200.00 22,400.00 44,800.00
2.0 Water Proofing - deck slab
Waterproofing membrain 33 Sq.m 500.00 16,500.00 150.00 4,950.00 21,450.00
3.0 Soil Poisoning
Soil poisoning 161 Sq.m 90.00 14,490.00 45.00 7,245.00 21,735.00
III Excavation MATERIAL LABOR
MATERIAL
SPECIFICATIONS QTY UNIT
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Excavation) 0.00 11,192.00 11,192.00


Foundation Excavation 23.7 cu.m. 0.00 400.00 9,480.00 9,480.00
Tie Beam, Excavation 2.70 cu.m. 0.00 400.00 1,080.00 1,080.00
Wall Footings Excavation 1.58 cu.m. 0.00 400.00 632.00 632.00

IV Backfill MATERIAL LABOR


MATERIAL
SPECIFICATIONS QTY UNIT
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Backfill) 5,999.60 5,999.60 11,999.20


Soil Filling Materials 14.999 cu.m. 400.00 5,999.60 400.00 5,999.60 11,999.20

V Steel Works MATERIAL LABOR


MATERIAL
SPECIFICATIONS QTY UNIT
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Steel Works) 532,467.79 218,300.00 750,767.79


1.0 Isolated Footings
Rebar, 16mm dia, GR-40 309.14 kgs 70.00 21,639.80 28.70 8,871.84 30,511.64
G.I. Tie wire, Ga-16 20 kgs 70.00 1,400.00 28.70 573.97 1,973.97
2.0 Reinforced Concrete Tie Beam
Rebar, 16mm dia, GR-40 main bars 681.84 kgs 70.00 47,728.80 28.70 19,567.75 67,296.55
Rebar, 10mm dia, GR-40 stirrups 217.77 kgs 70.00 15,243.90 28.70 6,249.66 21,493.56
G.I. Tie wire, Ga-16 60 kgs 70.00 4,200.00 28.70 1,721.91 5,921.91
3.0 Wall Footings
Rebar, 10mm dia, GR-40 long bars 780.52 kgs 70.00 54,636.40 28.70 22,399.71 77,036.11
G.I. Tie wire, Ga-16 60 kgs 70.00 4,200.00 28.70 1,721.91 5,921.91
4.0 Slab On Fill
Rebar, 10mm dia, GR-40 1835.5 kgs 70.00 128,484.30 28.70 52,675.72 181,160.02
G.I. Tie wire, Ga-16 120 kgs 70.00 8,400.00 28.70 3,443.81 11,843.81
5.0 Reinforced Concrete Columns
Rebar, 16mm dia, GR-40 1486.8 kgs 70.00 104,075.30 28.70 42,668.57 146,743.87
Rebar, 10mm dia, GR-40 374.24 kgs 70.00 26,196.80 28.70 10,740.11 36,936.91
G.I. Tie wire, Ga-16 100 kgs 70.00 7,000.00 28.70 2,869.84 9,869.84
6.0 Reinforced Concrete Beam
Rebar, 16mm dia, GR-40 937.49 kgs 70.00 65,624.30 28.70 26,904.51 92,528.81
G.I. Tie wire, Ga-16 70 kgs 70.00 4,900.00 28.70 2,008.89 6,908.89
7.0 Reinforced Concrete Roof Beam
Rebar, 16mm dia, GR-40 main bars 379.23 kgs 70.00 26,546.10 28.70 10,883.31 37,429.41
8.0 RC Staircase
Rebar, 16mm dia, GR-40 main bars 99.7 m 75.00 7,477.50 30.75 3,065.61 10,543.11
Rebar, 10mm dia, GR-40 temperature bars 49.5 m 29.30 1,450.20 12.01 594.55 2,044.74
Rebar, 10mm dia, GR-40 nosing bars 99 m 29.30 2,900.39 12.01 1,189.10 4,089.49
G.I. Tie wire, Ga-16 5.2 kgs 70.00 364.00 28.70 149.23 513.23

VI Concrete Works SPECIFICATIONS QTY UNIT MATERIAL LABOR


MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Concrete Works) 725,320.96 289,100.00 1,014,420.96


1.0 Isolated Footings
Concrete mix, 3000 psi 14.256 cu.m. 4,600.00 65,577.60 1,833.48 26,138.06 91,715.66
Gravel 14.256 cu.m. 1,350.00 19,245.60 538.09 7,670.95 26,916.55
2.0 Reinforced Concrete Tie Beam
Concrete mix, 3000 psi 8.595 cu.m. 4,600.00 39,537.00 1,833.48 15,758.74 55,295.74
Gravel 8.595 cu.m. 1,350.00 11,603.25 538.09 4,624.85 16,228.10
3.0 Wall Footings
Concrete mix, 3000 psi 13.176 cu.m. 4,600.00 60,609.60 1,833.48 24,157.91 84,767.51
Gravel 13.176 cu.m. 1,350.00 17,787.60 538.09 7,089.82 24,877.42
4.0 Ground Flr Slab
Concrete mix, 3000 psi 37.342 cu.m. 4,600.00 171,770.95 1,833.48 68,464.84 240,235.78
Gravel Base Course 37.342 cu.m. 1,300.00 48,543.96 518.16 19,348.76 67,892.72
5.0 Reinforced Concrete Columns
Concrete mix, 3000 psi 15.44 cu.m. 4,600.00 71,024.00 1,833.48 28,308.90 99,332.90
Gravel Base Course 15.44 cu.m. 1,300.00 20,072.00 518.16 8,000.34 28,072.34

6.0 Reinforced Concrete Beam

Concrete mix, 3000 psi 8.721 cu.m. 4,600.00 40,116.60 1,833.48 15,989.76 56,106.36
Gravel Base Course 8.721 cu.m. 1,300.00 11,337.30 518.16 4,518.85 15,856.15
7.0 Steeldeck Slab
Concrete mix, 3000 psi 11 cu.m. 4,600.00 50,600.00 1,833.48 20,168.26 70,768.26
Steeldeck, 1.0mm 104 sq.m. 600.00 62,400.00 239.15 24,871.53 87,271.53
8.0 Reinforced Concrete Beam RB
Concrete mix, 3000 psi 4.545 cu.m. 4,600.00 20,907.00 1,833.48 8,333.16 29,240.16
Gravel Base Course 4.545 cu.m. 1,300.00 5,908.50 518.16 2,355.02 8,263.52
9.0 RC Staircase
Concrete mix, 3000 psi 1.8 cu.m. 4,600.00 8,280.00 1,833.48 3,300.26 11,580.26

VII Form Works and Scaffolds SPECIFICATIONS QTY UNIT MATERIAL LABOR
MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Form Works and Scaffolds) 95,805.06 30,400.00 126,205.06


12.0 Reinforced Concrete Tie Beam
Formwork Area 2 sides formwork 0 sq.m. 400.00 0.00 126.92 0.00 0.00
13.0 Reinforced Concrete Columns
Formwork Area 0 sq.m. 400.00 0.00 126.92 0.00 0.00
14.0 Reinforced Concrete Beam 2nd flr
Formwork Area 53 sq.m. 400.00 21,200.00 126.92 6,726.99 27,926.99
15.0 Reinforced Concrete Beam roof beam
Formwork Area 61.8 sq.m. 400.00 24,720.00 126.92 7,843.93 32,563.93
16.0 RC Staircase
Formwork Area 11 sq.m. 400.00 4,400.00 126.92 1,396.17 5,796.17
17.0 2nd floor ceiling
Rough Lumber 2x2; 400x400 spacing 733.63 bd.ft. 62.00 45,485.06 19.67 14,432.91 59,917.97

VIII Roofing Works SPECIFICATIONS QTY UNIT MATERIAL LABOR


MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Roofing Works) 274,586.36 115,500.00 390,086.36


Roof Framing and Roofing
ROOF, RIB; 0.5mm Thickness 125 sq.m. 486.00 60,750.00 204.43 25,553.44 86,303.44
Bended Items 76 m 363.64 27,636.36 152.96 11,624.76 39,261.12
C-Purlins, 2x3 1.0, 6m 49 pcs 700.00 34,300.00 294.44 14,427.70 48,727.70
HSS 8x3x0.188 Rafters, 6m 13 pcs 5,300.00 68,900.00 2,229.35 28,981.59 97,881.59
Fascia frame 63 m 1,000.00 63,000.00 420.63 26,499.86 89,499.86
Misc. Consumables 1 lot 20,000.00 20,000.00 8,412.65 8,412.65 28,412.65

IX Masonry Works SPECIFICATIONS QTY UNIT MATERIAL LABOR


MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Masonry Works) 437,249.10 154,000.00 591,249.10


1.0 Reinforced Concrete Beam
Finishing: 61.8 sq.m. 500.00 30,900.00 176.10 10,883.04 41,783.04
2.0 CHB Wall
Finishing Area 212.8 sq.m. 1,600.00 340,481.60 563.52 119,918.29 460,399.89
4.0 Reinforced Concrete Columns
Finishing: 7.74 sq.m. 500.00 3,867.50 176.10 1,362.14 5,229.64

5.0 Reinforced Concrete Beam 2nd flr and slabs

Finishing: 124 sq.m. 500.00 62,000.00 176.10 21,836.52 83,836.52

X Plumbing & Electrical Works SPECIFICATIONS QTY UNIT MATERIAL LABOR


MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Plumbing & Electrical Works) 583,340.00 180,890.00 764,230.00


1.0 Fixtures, Pumps and accessories
Water closet set, with valves and accessories 5 set 8,000.00 40,000.00 2,400.00 12,000.00 52,000.00
Lavatory set, with valves and accessories 5 set 7,500.00 37,500.00 2,250.00 11,250.00 48,750.00
Lavatory Faucet, Angle Valve and Flex. Hose 5 pcs 2,500.00 12,500.00 750.00 3,750.00 16,250.00
Bath tub set, with valves and accessories 1 set 65,000.00 65,000.00 19,500.00 19,500.00 84,500.00
Shower head set with valves and accessories 5 set 4,000.00 20,000.00 1,200.00 6,000.00 26,000.00
Tissue Holder 5 pcs 500.00 2,500.00 150.00 750.00 3,250.00
Stainless Steel Soap Holder 5 pcs 500.00 2,500.00 150.00 750.00 3,250.00
Towel holder 5 pcs 1,200.00 6,000.00 360.00 1,800.00 7,800.00
Floor drain, T&B 5 pcs 300.00 1,500.00 90.00 450.00 1,950.00
Kitchen Sink set 2 set 4,000.00 8,000.00 1,200.00 2,400.00 10,400.00
Kitchen faucet 2 set 1,000.00 2,000.00 300.00 600.00 2,600.00
Hose bib 3 set 800.00 2,400.00 240.00 720.00 3,120.00
Elecric water heater, wall mount type, multipoint 5 set 10,000.00 50,000.00 3,000.00 15,000.00 65,000.00
Water pump, booster, easybox 1 pcs 15,000.00 15,000.00 4,500.00 4,500.00 19,500.00
Mirror 5 pcs 1,000.00 5,000.00 300.00 1,500.00 6,500.00
2.0 Waterline pipes and fittings
Waterline pipes and fittings 1 lot 25,000.00 25,000.00 12,500.00 12,500.00 37,500.00
3.0 Drainage pipes and fittings
Drainage pipes and fittings 1 lot 30,000.00 30,000.00 15,000.00 15,000.00 45,000.00
4.0 Other items, consumables 0.00 0.00 0.00 0.00
Other items, consumables 1 lot 10,000.00 10,000.00 5,000.00 5,000.00 15,000.00
5.0 Lighting Fixtures
Lighting fixtures and accessories 1 lot 350.00 350.00 87.50 87.50 437.50
Ceiling Fan 1 units 10,000.00 10,000.00 2,500.00 2,500.00 12,500.00
Exhaust fan 2 units 4,000.00 8,000.00 1,000.00 2,000.00 10,000.00
6.0 Power Outlets and Switch
Duplex convenience outlet 49 units 280.00 13,720.00 140.00 6,860.00 20,580.00
Ref. Outlet 5 units 280.00 1,400.00 140.00 700.00 2,100.00
ACCU Outlet 4 units 380.00 1,520.00 190.00 760.00 2,280.00
Water pump outlet 1 units 380.00 380.00 190.00 190.00 570.00
WACU Outlet 3 units 380.00 1,140.00 190.00 570.00 1,710.00
Appliences outlet 5 units 280.00 1,400.00 140.00 700.00 2,100.00
Water heater outlet 6 units 280.00 1,680.00 140.00 840.00 2,520.00
1-Gang Switch 16 sets 150.00 2,400.00 37.50 600.00 3,000.00
2-Gang Switch 10 sets 230.00 2,300.00 57.50 575.00 2,875.00
3-Gang Switch 8 sets 330.00 2,640.00 82.50 660.00 3,300.00
7.0 Wires, Cables & Conductors
125 mm2 THHN Copper wire 100 mtrs 831.00 83,100.00 207.75 20,775.00 103,875.00
22 mm2 THHN Copper wire 50 mtrs 151.00 7,550.00 37.75 1,887.50 9,437.50
50 mm2 THHN Copper wire 10 mtrs 347.00 3,470.00 86.75 867.50 4,337.50
14 mm2 THHN Copper wire 5 mtrs 98.00 490.00 24.50 122.50 612.50
8.0 mm2 THHN Copper wire 100 mtrs 60.00 6,000.00 15.00 1,500.00 7,500.00
5.5mm2 THHN Copper wire 300 mtrs 40.00 12,000.00 10.00 3,000.00 15,000.00
3.5mm2 THHN Copper wire 500 mtrs 26.00 13,000.00 6.50 3,250.00 16,250.00
8.0 Conduits, fittings
20mmØ x 3.00m PVC Pipes 50 length 70.00 3,500.00 17.50 875.00 4,375.00
25mmØ x 3.00m PVC Pipes 30 length 70.00 2,100.00 17.50 525.00 2,625.00
Moldflex uPVC Electrical conduit 20mm 6 roll 800.00 4,800.00 200.00 1,200.00 6,000.00
Misc. PVC adoptors and fittings 264 pcs 15.00 3,960.00 3.75 990.00 4,950.00
Misc. Metal conduits and fittings 1 lot 10,000.00 10,000.00 2,500.00 2,500.00 12,500.00
Utility Box metal #16 107 pcs 40.00 4,280.00 10.00 1,070.00 5,350.00
Junction Box metal #16 w/ Cover 4 pcs 65.00 260.00 16.25 65.00 325.00
Electrical Tape 20 rolls 45.00 900.00 11.25 225.00 1,125.00
Tie Wire #16 10 kilogram 110.00 1,100.00 27.50 275.00 1,375.00
Misc. Consumables 1 lot 20,000.00 20,000.00 5,000.00 5,000.00 25,000.00
9.0 Panel Boards
LP: 1 - 100AT/225AF 2P, 230V B.O. 1 sets 25,000.00 25,000.00 6,250.00 6,250.00 31,250.00
BRANCHES:
10 - 20AT, 2P B.O.
7 - 30AT, 2P B.O.

XI Tiles Installation SPECIFICATIONS QTY UNIT MATERIAL LABOR


MATERIAL
+ LABOR
Item Description Unit cost Amount Unit cost Amount

SUB-TOTAL (Tiles Installation) 55,989.75 17,500.00 73,489.75


1.0 Slab On Fill
Screened Sand 0.7781 cu.m. 1,200.00 933.75 375.07 291.85 1,225.60
Portland Cement 15 bags 260.00 3,900.00 81.26 1,218.97 5,118.97
Floor Tiles 124.5 sq.m. 360.00 44,820.00 112.52 14,008.81 58,828.81
2.0 RC Staircase
Screened Sand 0.68 cu.m. 1,200.00 816.00 375.07 255.05 1,071.05
Portland Cement 1:4 Cement-Sand Ratio 6 bags 260.00 1,560.00 81.26 487.59 2,047.59
Floor Tiles 11 sq.m. 360.00 3,960.00 112.52 1,237.73 5,197.73
XII Sceptic Tank Works SPECIFICATIONS QTY UNIT MATERIAL LABOR MATERIAL
Item Description Unit cost Amount Unit cost Amount + LABOR

SUB-TOTAL (Sceptic Tank Works) 52,000.00 16,800.00 68,800.00


1.0 Cistern Tank, Septic Tank, Catch Basin

Septic Tank construction 1 lot 50,000.00 50,000.00 16,153.85 16,153.85 66,153.85

Catch basin 2 pcs 1,000.00 2,000.00 323.08 646.15 2,646.15

XIII Ceiling Works SPECIFICATIONS QTY UNIT MATERIAL LABOR MATERIAL


Item Description Unit cost Amount Unit cost Amount + LABOR

SUB-TOTAL (Ceiling Works) 155,301.90 58,800.00 214,101.90


1.0 Ground floor ceiling 150 sq.m. 0.00 0.00 0.00 0.00

HARDFLEX; 4ft x 8ft, 3.5mm thikness 57 pcs 455.00 25,935.00 172.27 9,819.44 35,754.44

S4S Lumber 2x2; 400x400 spacing 902 bd.ft. 62.00 55,924.00 23.47 21,173.80 77,097.80

Assorted Nails 31.06 kgs 70.00 2,174.20 26.50 823.19 2,997.39


Painting Works 150 sq.m. 96.00 14,400.00 36.35 5,452.09 19,852.09
2.0 2nd floor ceiling
HARDFLEX; 4ft x 8ft, 3.5mm thikness 47 pcs 455.00 21,385.00 172.27 8,096.73 29,481.73
Assorted Nails 25.31 kgs 70.00 1,771.70 26.50 670.80 2,442.50
Painting Works 122 sq.m. 96.00 11,712.00 36.35 4,434.37 16,146.37
3.0 Exterior ceiling
Exterior ceiling 55 sq.m. 400.00 22,000.00 151.45 8,329.58 30,329.58
XIV Doors and Windows SPECIFICATIONS QTY UNIT MATERIAL LABOR MATERIAL
Item Description Unit cost Amount Unit cost Amount + LABOR

SUB-TOTAL (Doors and Windows) 224,082.50 0.00 224,082.50


1.0 Doors

D01: Panel door 2.8m x 0.9m 1 unit 6,000.00 6,000.00 0.00 0.00 6,000.00

D02: Panel door 2.1m x 0.8m 5 unit 5,500.00 27,500.00 0.00 0.00 27,500.00

D03: PVC door 2.1m x 0.7m 6 unit 2,800.00 16,800.00 0.00 0.00 16,800.00
D04: Flush door 2.1m x 0.7m 2 unit 2,800.00 5,600.00 0.00 0.00 5,600.00
Sliding glass door on aluminum frame 2.3m x 2.9m 1 unit 10,000.00 10,000.00 0.00 0.00 10,000.00
2.0 Windows
W01: Sliding window on aluminum frame 2.35m x 1.7m 1 unit 13,982.50 13,982.50 0.00 0.00 13,982.50
W02: Sliding window on aluminum frame 1.1m x 1.4m 1 unit 5,390.00 5,390.00 0.00 0.00 5,390.00
W03: Swing glass window on aluminum frame 1.4m x 0.75m 1 unit 3,675.00 3,675.00 0.00 0.00 3,675.00

W04: Sliding glass window on aluminum frame 1.4m x 3.175m 1 unit 15,680.00 15,680.00 0.00 0.00 15,680.00

W05: Sliding glass window on aluminum frame 1.4m x 1.3m 4 unit 6,370.00 25,480.00 0.00 0.00 25,480.00

W06: Awning glass window on aluminum frame 0.6m x 0.6m 2 unit 1,800.00 3,600.00 0.00 0.00 3,600.00

W07: Fixed glass window on aluminum frame 3.1m x 1.35m+1.95m 1 unit 25,575.00 25,575.00 0.00 0.00 25,575.00
3.0 Exterior rail
Exterior rail. 12mm thick tempered clear glass
1.2m x 9m 1 unit 64,800.00 64,800.00 0.00 0.00 64,800.00
with connectors and accessories.
XV Cleaning and Turn Over SPECIFICATIONS QTY UNIT MATERIAL LABOR MATERIAL
Item Description Unit cost Amount Unit cost Amount + LABOR

SUB-TOTAL (Cleaning and Turn Over) 100,000.00 37,000.00 137,000.00


1.0 Landscape 0.00 0.00 0.00 0.00

Landscape 1 lot 100,000.00 100,000.00 0.37 37,000.00 137,000.00

XVI Painting Works SPECIFICATIONS QTY UNIT MATERIAL LABOR MATERIAL


+ LABOR
Item Description Unit cost Amount Unit cost Amount
SUB-TOTAL (Painting Works) 123,569.76 51,800.00 175,369.76
1.0 Reinforced Concrete Columns

Painting Works 7.735 sq.m. 96.00 742.56 40.24 311.28 1,053.84

2.0 Reinforced Concrete Beam

Painting Works 12.65 sq.m. 96.00 1,214.40 40.24 509.07 1,723.47


3.0 Reinforced Concrete Roof Beam
Painting Works 61.8 sq.m. 96.00 5,932.80 40.24 2,487.01 8,419.81

4.0 RC Staircase

Painting Works 11 sq.m. 96.00 1,056.00 40.24 442.67 1,498.67


5.0 CHB Wall - Ground 0.00 0.00 0.00
Painting Works 356 sq.m. 96.00 34,176.00 40.24 14,326.46 48,502.46
6.0 CHB Wall - 2nd
Painting Works 388 sq.m. 96.00 37,248.00 40.24 15,614.23 52,862.23
7.0 CHB Wall Plaster 0.00 0.00 0.00
Façade stone cladding 24 sq.m. 1,800.00 43,200.00 754.55 18,109.28 61,309.28

You might also like