Asphalt Method Statement
Asphalt Method Statement
Asphalt Method Statement
2021
Method statement
1.1 INTRODUCTION
This proposal provides a description of the role, tasks and approach that would be undertaken
in the execution of the project awarded to it.
The Work components shall include but not limited to the following:
Repair of potholes, pavement failures, edge breaks and other pavement distress areas.
Repair of damaged embankment side slopes, including reinstatement of shoulders.
DBST/AC repair/overlay of the several lengths of road.
Maintenance of the road during defect liabilities and performance base routine
maintenance.
Method statement
2.1 CONSTRUCTION METHOD STATEMENT
Spades 2 Cleaning
2.1 EARTHWORK
With the direction and instruction of the Engineer, at the designated areas, the graders and
excavators are used to clear, remove, and dispose all vegetation, silt and grubbing roots, down
timber and other unacceptable materials.
Large trees and stumps within construction area is cut down by hand and then be transported
and stockpiled at designated place directed by the Engineer.
Method statement
Small vegetation, roots, and silt is curved by excavators and then is transported to the spoil
area directed by the Engineer.
The clearing and grubbing, unless otherwise instructed by the Engineer, include also the removal of
all roots, stumps, untidy vegetation, rubbish, garbage and to the extent that these materials are not,
in the opinion of the Engineer, obstruct the future maintenance. All unsuitable materials are wasted
and re-spread at designated locations in a neat and orderly way as agreed by the Engineer.
The works shall be composed of common, unsuitable excavation, and the excavation of bituminous
materials. Roadway excavation includes the removal, hauling and proper utilization, or disposal of all
excavated materials, the shaping of excavation and the preparation of exposed surfaces of
excavation on the entire length of roadway. The survey team marks all excavated locations, lines,
level, grades, dimensions, and cross section, which is shown on the Drawings and as directed by the
Engineer.
The work includes the proper utilization and hauling or disposal of all excavated materials,
constructing, shaping and finishing all earthworks involved in conformity with the required alignment,
levels, grades and cross sections. Based on the Drawing, the Survey Engineer set out the level line
and measure the original ground elevation, then figure out the excavation depth according to the
designed bottom elevation, and then mark it up with stakes. During the construction, the channel is
kept drained as far as practicable and the work is constructed in a neat and workmanlike manner.
The unsuitable materials are transported to the spoil area, while the materials that could be used for
sub-grade filling or slope block sodding and formation of embankments are stocked together nearby.
The channel sidelines are
trimmed manually to ensure lines smooth and fluent.
2.1.4 Embankment
This work consists of the construction of embankment by furnishing, placing, compacting and shaping
suitable material of acceptable quality obtained from approved sources in according with the
Method statement
Specification, and to the lines, levels, grades, dimensions, and cross section shown on the Drawings
and as required by the Engineer. The embankment filling materials are tested in accordance with the
Specification to determine the appropriate materials prior to execution. Not until approved by the
Engineer, the filling shall not be started.
Natural ground situated less than 1.5 m below the design surface of the road or side slopes, after
proper clearing and grubbing or scarifying of existing road surface, are compacted to a depth of 150
mm, to not less than 90 % of the maximum dry density of the material as determined by AASHTO
test method T180. If unsuitable materials occur in some areas under embankment or in existing
embankment, such materials are removed to levels as directed by the Engineer, the bottom of the
excavation is compacted, and areas backfilled and compacted layer by layer with suitable material
2.2.2 Sub-base
This work consists of furnishing, placing and compacting sub-base material on a prepared and
accepted sub-grade to the lines, levels, grades, dimensions and cross sections shown on the
Drawing and as required by the Engineer. Based on the Drawing, the Engineer sets out the horizontal
position of sub-base, determine the thickness of spreading, and then mark it up with stakes. Prior to
sub-base spreading, watering cart is used to wet the sub-grade to ensure the cohesiveness between
them.
The sub-base is shaped, compacted and completed for at least 150 m ahead of the placing of the
sub-base course material and subject to the requirements of the Contract for the Engineer’s approval
of the sub-grade before it is covered up. The sub-base is spread in even layers not exceeding 150
mm after compaction. Care is taken to prevent segregation, and oversized particles are hand-picked
from the deposited layer prior to compaction. Immediately after each layer has been spread and
shaped satisfactorily, each layer is thoroughly compacted with suitable and adequate compaction
equipment. Each layer is compacted to at least 95 % of the maximum dry density, as determined by
AASHTO T180.
Method statement
2.2.3 Base Course
This work is determined to execute in accordance with the above method of sub-base.
2.2.4 Description
This work shall consist of repairing existing defective bitumen pavement, including bituminous
surface treatment, longitudinal cracking, block cracking, patches, and edge breaks, which is assigned
for two construction teams to complete for NR3.
Slow setting cationic emulsified bitumen is chosen as the prime coat, whose quantity and quality are
in conformity with the Specification. Pre-distribution is done to check the consistency of bitumen:
The prime coat is sprayed after clearing the cutting left over of existing defective pavement. A
slight application of water is made if the surface is over dry.
It is determined to execute by a bitumen distributor, which is fitted with a handheld, manually
operated bar fed by a flexible line for use on areas too small to be satisfactory sprayed with
the main bar.
Before any bitumen distributor is used on the works, the calibration of the nozzle shall be
checked in a series of field tests to maintain appropriate speeds for the proper application of
the bitumen. During the progress of the work, it is sprayed uniformly at one time in ccordance
with the designated bitumen capacity in case of bitumen's flowing to penetrate into the base
course. Oil slick formed on the surface is not permitted. Once any omission occurs, remedial
spraying is done manually. After the spraying, the traffic is strictly regulated in case of any
vehicle or person passing through.
No spraying is carried out on a wet pavement, while rain appears imminent or during high
winds; the extra prime coat bitumen, which has not penetrated into base course, is cleared
immediately.
Method statement
2.2.6 Bituminous Seal Coat
This work shall be applied to the execution of the prime coat. Reference shall be made to 2.2.5.
2.2.7 Sealing Aggregate
Aggregate spreader is used in the execution of construction:
The crushed stone aggregate is spread before emulsion breaking. To ensure a good
cohesiveness between aggregate and bitumen, crushed stone aggregate is spread once
emulsion stops flowing.
The crushed stone aggregate is spread uniformly and not be overlapped, which cover the full
pavement with no exposing bitumen. Manually remedial work is done when any local omission
occurs. The crushed stone aggregate adheres to bitumen emulsion through rolling and
integrates with it after its breaking. Where there is excess aggregate, the unsuitable is
removed immediately to make the surface level uniform.
Pneumatic-tired roller of 10 tons is used to compact, which is executed when the bitumen
becomes fully black and emulsion has been breaking. One to two-time light rolling is done
firstly and re-rolling be started after it is dry.
Communication Equipment
Method statement
Method statement
CLEANING THE ROAD SURFACE
Main contractor’s mechanical broom is going to be used to remove all loose material from the road
surface.
Cold asphalt is a do it yourself alternative to hot asphalt and this permanent repair solution can be
applied easily without having to wait for a drying period, making it the perfect fix for access roads and
driveways. It is used both as a pothole patching material in road pavements and airport runways, and
as a main road pavement in low volume roads, vehicle parking, sidewalks, parks and playgrounds
1. The hot asphalt shall be brought from the mixing plant by trucks and a waterproof canvas to
maintain the temperature and to protect the asphalt from light showers of rain must cover it.
Minimum temperature at loading must 150⁰C.
2. Deliveries shall be made so that spreading and rolling of the mixture can be completed during
day light hours, unless night work is permitted by engineer and artificial, lighting is provided.
3. Any asphalt that is below 120⁰C should be returned to the plant.
Method statement
SPREADING THE HOT PREMIX
1. The temperature of the mix should be tested on arrival using a dial gauge or thermometer or
an electronic thermometer that is capable of measuring up to 240⁰.
2. Check the adjustments of screed tampers, feed chain before dumping the mix in the paver.
3. The tipper shall be directed to the paver and dumps the required mix into the paver.
4. The asphalt paver shall lay the material to the required thickness and level.
5. The mix shall be compacted as soon as possible after the spreading the material. Tandem
roller shall follow the laying operation to carry out breakdown rolling to temperature of 120-
120⁰C. Pneumatic tired roller and tandem roller shall follow break down rolling and sufficient
passes shall be made to achieve the required compaction. During the break down stage the
rollers shall move at a slow but uniform speed (not exceeding 5km/h) with the drive wheel of
the roller nearest the paver.
6. Rolling shall start from the sides and proceed to towards the centre. Each trip of the roller
shall overlap the previous trip by at least 30cm. Roller wheel shall be kept moistened. The
roller shall have to reverse without backlash and shall be free from worn parts.
7. On super elevated curves where the surface has straight cross fall, the rolling shall begin on
the low side and progress to the higher side, uniformly lapping each preceding track, to cover
the entire surface.
8. Full compaction shall be obtained before the asphalt temperatures reaches 100⁰C.
Compaction shall be in accordance with specifications of COLTO standard.
9. The construction joints shall be prepared by cutting the layer vertically down by means of
asphalt saw cutting machines or the blades mounted on the Pneumatic roller. The joints shall
be cleaned well and tack coat material shall be applied on the vertical and horizontal surface
for better bonding. Extremely good care shall be taken when asphalt is laid at construction
joints.
10. The areas not accessible for heavy rollers shall be compacted with plate compactors or hand
tempers.
11. Paving sheets must be filled in for every truck that is surfaced.
Method statement
12. The surface must be protected from damage by putting barricades during and after
construction until such a time the work is finally handed and accepted by the engineer.
MATERIALS TO BE USED
All materials to be procured shall be in accordance with the standards and specifications as set out
in the project document
QUALITY CONTROL
During surfacing Hot box samples shall be collected for laboratory test and the results will be
sent to the Engineer
After work done core drilling will be done and all cores result shall be sent to the Engineer.
Where local skills such as bricklayers and stone masons are available, structures should be
designed to make maximum use of such human resources. For example, a project can specify the
casting of kerbs and culvert pipes on site instead of relying on precast concrete products thereby
increasing the labour intensity, harnessing locally available skills as well as reduce transport and
overall project costs. Even though the above are common concerns of all road designers, the use of
labour-based works technology takes the approach a step further in maximizing the use of local
labour.
CONCLUSION
Our organisation seeks to complete the works to the Client’s satisfaction. The resources stated in
the schedule will comply with all local authority requirements and legislations. We will give the
client a quality product and service with which we pride ourselves in.
Method statement