17 Special ceiling plastering 20mm thick
using cement mortar 1:3mix
Kitchen 1 4.04 3.05 12.32
Hall 1 3.14 5.24 16.45
Bed Room-1 1 2.90 4.46 12.93
Toilet 1 2.90 1.52 4.41
Verandha 1 3.14 1.75 5.50
Bed Room 1 2.90 3.95 11.46
add etc.. 0.93
64.00 M2
18 Floor finish with White marble
Kitchen 1 4.04 3.05 12.32
Hall 1 3.14 5.24 16.45
Bed Room-1 1 2.90 4.46 12.93
Toilet 1 2.90 1.52 4.41
Verandha 1 3.14 1.75 5.50
Bed Room 1 2.90 3.95 11.46
add etc.. 0.93
64.00 M2
19 White washing and colour washing
As per item no16&17 351.00
add etc.. 0.00
351.00 M2
SECOND FLOOR
20 R.C.C (1:2:4)for roof,beams, and sunshade
without reinforcement etc.. Including centering and
shurrering complete
Column 16 0.23 0.23 4.89 4.14
Lintel beam 1 56.00 0.23 0.30 3.86
Sun shade 6 1.50 0.60 0.08 0.43
Roof slab (76X.12) 1 9.12
add etc.. 0.45
18.00 M3
21 Steel reinforcement including cutting,
bending,and tying etc..complete.
130 Kg/CM of concrete 2340.64
add etc.. 0.36
2341.00 Kg
22 Brick work using country bricks of standard
size with cement mortar 1:6 mix
For House super structure 1 56.00 0.23 3.05 39.28
Parapet wall 1 35.00 0.23 0.75 6.04
Deduction
Asper item 15x.23 6.67
add etc.. 0.35
39.00 M3
Page 4 of 7
23 Supplying and fixing of Teak wood doors,
Windows and ventilators etc.. Complete
Door (MD&RD) 1 1.00 2.10 2.10
Door D 3 0.90 2.10 5.67
Door D1 1 0.75 2.10 1.58
Window W 10 1.35 1.35 18.23
Ventilator V 1 0.90 0.60 0.54
add etc.. 0.89
29.00 M3
24 Plastering the walls inside and outside
using cement mortar 1:5 mix
Page 5 of 7
ABSTRACT ESTIMATE
FIRST FLOOR
SECOND FLOOR
24 Plastering the walls inside and outside using 340.00 250 M2 85000.00
cement mortar 1:5 mix
TOTAL 3467885.00