Sheltar House Estimate
Sheltar House Estimate
Sheltar House Estimate
05, RATANNAGAR
DETAILS & ABSTRACT OF COST
CIVIL WORK
S.N
O. B.S.R.NO. Item No. L B H QTY Unit Rate Amount
1 E010100
10101 short point (upto 3Mtr.)
New structure 18 P.point 160 2880
Existing structure 2 P.point 160 320
10102 Medium point (upto 6 Mtr.)
New structure 16 P.point 242 3872
Existing structure 2 P.point 242 484
10103 Long point (upto 10 Mtr.)
New structure 24 P.point 342 8208
Existing structure 3 P.point 342 1026
Wiring of 3 pin 6 amp. light plug point with 1.5 sq. mm
FR PVC insulated unsheathed flexible copper conductor
1.1 kV grade and 1.5 sq.mm FR PVC insulated
unsheathed flexible copper earth conductor 1.1 kV grade
(IS:694) of approved make in surface / recessed ISI
marked medium duty PVC conduit & it's accessories, 18
SWG M.S. box with earth terminal, screwless cage
connectors for neutral looping in switch board & false
ceiling point, 6 A switch, 6 A socket, 3.0 mm thick
phenolic laminated sheet, zinc plated / brass screws,
cup washers, making connections, testing etc. as
2 E010700 required. GROUP I
E010702 short point (upto 3Mtr.) 18 P.point 263 4734
E010703 Medium point (upto 6 Mtr.) 16 P.point 331 5296
E010704 Long point (upto 10 Mtr.) 24.000 P.point 424 10176
ABSTRACT OF ESTIMATE
S.N. PART BSR TOTAL AMOUNT
1 PART A : CIVIL BUILDING WORK PWD BSR BUILDING 2013 3354876
PART B : SANITARY, WATER SUPPLY
2 AND DRAINAGE WORK PWD BSR BUILDING 2013 119489
PART C : ELECTRICAL WORKS
3 (INTERNAL AND EXTERNAL) PWD BSR ELECTRICAL 2012 95786
4 PART D : ROAD WORK PWD BSR JAIPUR 367855
TOTAL 3938006
AMOUNT SAY IN LACS 39.38
O&M COST FOR FIVE YEARS 30
GRAND TOTAL 69.38