Request For Time Extension
Request For Time Extension
አይኤፍኤችኢንጅነሪንግኃ.የተ.የግልማህበር
Dear Sirs,
As you are well aware, the construction of the captioned project has been
significantly retarded mainly due tosuspension of Utility line works and other
delays beyond the contractor’s control. The contractor was committed itself and
tried its best to finalize the works at the contract completion time.
In accordance with the signed contract, the project has to be completed within
180 calendar days after the signing of the contract. Thus, the whole project
was supposed to be completed on December 26, 2014. However, this was not
made practical due to reasons beyond the contractor’s control.As can be seen
from the attached schedule analysis, the planned volume of work for the period
until December 22, 2014 was 96.25 while the actual accomplishment is 52.5%.
This shows a slippage of 50.5 % which is fully attributed to cause of delays due
to mainly associated with the Employer.
2.2Slab culverts (at K0+004 new design & K0+025 existing in the
original contract): Typical sections were not included in the original
contract drawings.It was after our request through letter
‘CRBC/TD/001/14 dated July 14, 2014’ (R ) that the Engineer
04
Sincerely yours
Wang Yang
General Manager