POM Lecture5 - Project Scheduling-Uncertain
POM Lecture5 - Project Scheduling-Uncertain
bit.ly/manupom
LECTURE 5:
PROJECT SCHEDULING
(WITH UNCERTAIN ACTIVITY TIMES)
a m b
A - 6
B - 2
C A 3
D A 5
E A 3
F C 2
G D 3
H B,E 4
I H 2
J F,G,I 2
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
C F
3 2
A
6
D G J
End
Start 5 3 2
E
3
H I
4 2
B
2
E 6 9
3
H 9 13 I 13 15
4 2
B 0 2
2
The project completion time is 17 weeks
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
C 6 9 F 9 11
3 10 13 2 13 15
A 0 6
6 0 6
D 6 11 G 11 14 J 15 17
End
Start 5 7 12 3 12 15 2 15 17
E 6 9
3 6 9
H 9 13 I 13 15
4 9 13 2 13 15
B 0 2
2 7 9
E 6 9
3 6 9
H 9 13 I 13 15
4 9 13 2 13 15
B 0 2
2 7 9
Critical path: A-E-H-I-J
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
3 Calculate the CP expected times ET
E(T)
A 6
B 2
C 3
D 5
E 3
F 2
G 3
Expected Project Completion
H 4 Time
I 2
J 2
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
4 Calculate the CP variance 𝜎2
Critical path of A–E–H–I–J resulted in an expected
total project completion time of 17 weeks.
I 1.5 2 2.5
J 1 2 3
A 4 5 12 1.78
E 2 3 4 0.11
H 2.5 3.5 7.5 0.69
I 1.5 2 2.5 0.03
J 1 2 3 0.11
Probability
(T ≤ 20) is 97%
17 20 Time (weeks)