Project Management-3
Project Management-3
Project Management-3
Management
Learning Objectives
Describe project management objectives
Describe the project life cycle
Diagram networks of project activities
Estimate the completion time of a project
Compute the probability of completing a
project by a specific time
Learning Objectives – con’t
Determine how to reduce the length of a
project effectively
Describe the critical chain approach to
project management
Project Management
Applications
What is a project?
Any unique endeavor with specific objectives
With multiple activities
With defined precedent relationships
With a specific time period for completion
Examples?
A major event like a wedding
Any construction project
Designing a political campaign
Project Life Cycle
Conception: identify the need
Feasibility analysis or study: costs
benefits, and risks
Planning: who, how long, what to do?
Execution: doing the project
Termination: ending the project
Network Planning Techniques
Program Evaluation & Review Technique (PERT):
Developed to manage the Polaris missile project
chemical industry
A complex undertaking, but individual tasks are
© Wiley 2007
Step 1-Define the Project: Cables By Us is bringing a new
product on line to be manufactured in their current facility in
existing space. The owners have identified 11 activities and their
precedence relationships. Develop an AON for the project.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Step 2- Diagram the Network for
Cables By Us
Step 3 (a)- Add Deterministic Time
Estimates and Connected Paths
Step 3 (a) (Con’t): Calculate
the Project Completion Times
Paths Path duration
ABDEGHJK 40
ABDEGIJK 41
ACFGHJK 22
ACFGIJK 23
The longest path (ABDEGIJK) limits the
project’s duration (project cannot finish in
less time than its longest path)
ABDEGIJK is the project’s critical path
Some Network Definitions
All activities on the critical path have zero slack
Slack defines how long non-critical activities can be
delayed without delaying the project
Slack = the activity’s late finish minus its early finish
(or its late start minus its early start)
Earliest Start (ES) = the earliest finish of the immediately
preceding activity
Earliest Finish (EF) = is the ES plus the activity time
Latest Start (LS) and Latest Finish (LF) = the latest an
activity can start (LS) or finish (LF) without delaying the
project completion
ES, EF Network
LS, LF Network
Calculating Slack
Late Early Slack
Activity
Finish Finish (weeks)
A 4 4 0
B 10 10 0
C 25 7 18
D 16 16 0
E 30 30 0
F 30 12 18
G 32 32 0
H 35 34 1
I 35 35 0
J 39 39 0
K 41 41 0
PERT Technique
Optimistic Most likely Pessimistic
Activity Description
time time time
A Develop product specifications 2 4 6
B Design manufacturing process 3 7 10
C Source & purchase materials 2 3 5
D Source & purchase tooling & equipment 4 7 9
E Receive & install tooling & equipment 12 16 20
F Receive materials 2 5 8
G Pilot production run 2 2 2
H Evaluate product design 2 3 4
I Evaluate process performance 2 3 5
J Write documentation report 2 4 6
K Transition to manufacturing 2 2 2
Using Beta Probability Distribution to
Calculate Expected Time Durations
A typical beta distribution is shown below, note that it
has definite end points
The expected time for finishing each activity is a
weighted average
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
Calculating the Probability of Completing
the Project in Less Than a Specified Time
When you know:
The expected completion time
Its variance