BOQ For PWSSP at BTB
BOQ For PWSSP at BTB
BOQ For PWSSP at BTB
Amount (US
Bill No Description
DOLLARS)
.............................................................. ..............................................................
Mr. Vann Sophal
Managing Director
NORAK Engineering Co., Ltd. OBAYASHI Corporation
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
Water Treatment Plant
External Work WTP Bill 5-1 192,322.73 96,873.00 289,195.73
Bill 5-1 – Access Road and Drainage 176,064.50 89,676.00 265,740.50
General Clearance: Demolition and removal of all articles, objects m2 4,670.0
and obstructions which are required to be cleared except the trees 0.80 3,736.00
with diameter > 200mm 3,736.00
Trees: Clearing and Grubbing Diameter >200 mm nr 100 - 5.00 500.00 500.00
Tree Planting replacement of cleared trees (5 per 1 cleared tree) nr 500 25.00 12,500.00 5.00 2,500.00 15,000.00
Stripping of Top Soil and temporary storage, t=30cm m3 1,000 - 6.50 6,500.00 6,500.00
Top Soil trnasportation m3 1,000 - 2.50 2,500.00 2,500.00
Roadway Excavation, Common m3 466 - 6.50 3,029.00 3,029.00
Embankment, 90% MDD m3 2,050 6.50 13,325.00 7.50 15,375.00 28,700.00
Sub-base material, CBR =>30%, 95% MDD, 20cm thickness m3 802 24.00 19,248.00 12.00 9,624.00 28,872.00
Aggregate Base course, CBR=>80%, 98% MDD, 15cm thickness m3 646 24.00 15,504.00 12.00 7,752.00 23,256.00
Sub-base Shoulder, CBR=>30%, 95% MDD, 30cm thickness m3 341 24.00 8,184.00 14.00 4,774.00 12,958.00
Concrete for Pavement -t=200mm m3 589 95.00 55,955.00 28.00 16,492.00 72,447.00
Concrete curing m3 589 2.50 1,472.50 2.00 1,178.00 2,650.50
Wire Mesh t 36.6 1,050.00 38,430.00 280.00 10,248.00 48,678.00
Grade390 Deformed Reinforcement Bar t 3.1 880.00 2,728.00 280.00 868.00 3,596.00
Mastic Joint Sealer(15*25) Kg 463 12.50 5,787.50 5.00 2,315.00 8,102.50
Plastic Sheeting m2 474 2.00 948.00 0.50 237.00 1,185.00
Flexible Filler m2 10 15.00 150.00 3.00 30.00 180.00
PVC ф25 m 109
2.50 272.50 2.00 218.00 490.50
Road Shoulder, Laterite t=400mm m2 300 2.60 780.00 3.00 900.00 1,680.00
Slope Embankment and Sodding for Protection m2 300 2.60 780.00 3.00 900.00 1,680.00
(2) Drainage Structure for Access Road LS 1 7,100.00 2,584.00 9,684.00
Supply and Installation of Drainage Pipe Culvert φ800, Depth not m 30
exceeding 130.00 3,900.00 30.00 900.00
2.3m
Supply and install drainage manhole1200 x 1400 complete including
RC cover for depth to invert not exceeding 2.3m nr 4 800.00 3,200.00 421.00 1,684.00
Drainage Culvert as specified in the Drawing ls 1 N/A N/A
Other LS 1 9,158.23 4,613.00 13,771.23
Miscellaneous landscaping works specified in the Drawings or the LS 1.00 9,158.2 9,158.2 4,613.0 4,613.00 13,771.23
Specifications but otherwise not included elsewhere in Bill 5.1
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Amount Unit Rate Amount
(US$) (US$) (US$) (US$)
Water Treatment Plant
Earth Work WTP Bill 5-2 572,040.81 791,484.78 1,363,525.59
Bill 5-2 – Earthwork for Water Treatment Plant LS 1 544,800.78 753,795.03 1,298,595.80
General Clearance: Demolition and removal of all articles, objects
and obstructions which are required to be cleared except the trees
with diameter > 200mm ha 1.6 - 8,000.00 12,800.00 12,800.00
Reeceiving Well & Mixing Tank Bill 5-3 39,331.87 17,883.28 57,215.15
Concrete
Concrete
Form
Re-Bar
Curing
WPW
Concrete
Form
Re-Bar
Curing
WPW
Scaffold
Concrete
Support
Form
Re-Bar
Concrete
Filter M.
Filter M.
Filter M.
Filter M.
Filter M.
WPW
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount
Unit Rate Unit Rate
Amount (US$) Amount (US$)
(US$) (US$)
Water Treatment Facility
Service Reservoir and Pump Station Bill 5-5 1,374,822.25 591,548.54 1,966,370.79
Gravel
Lean Concrete
Form
Concrete
Form
rebar
Curing
ws
wp
Concrete
Form
rebar
Curing
Scaffold
ws
wp bitumen
wp
Concrete
Form
rebar
Curing
Scaffold
Concrete
Form
rebar
Curing
Scaffold
Concrete
Fom
rebar
Curing
Scaffold
wp
Concrete
Form
rebar
Curing
Support
Concrete
Form
rebar
Curing
wp bitumen
wp
Gravel
Lean Concrete
Form
Concrete
Form
rebar
Curing
ws
wp
Concrete
Form
rebar
Curing
Scaffold
ws
wp bitumen
wp
Concrete
Form
rebar
Curing
Support
wp
Concrete
Form
rebar
Curing
Concrete
Form
rebar
Curing
Scaffold
Concrete
Form
rebar
Curing
Support
Roof
Vent,Brock
Vent,Brock
plaster
painting
fans
fans
wp bitumen
Dw
Dw
Dw
Dw
steel
steel
SUS
SUS
SUS
LS
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Quotation
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost
Unit Rate Unit Rate
Amount (US$) Amount (US$)
(US$) (US$)
Water Treatment Facility
Drainage Tank Bill 5-6 213,205.84 84,971.03
Construction of the Drainage Basin Base complete and including lean concrete, concrete pouring,
LS 1 79,910.55 26,364.87
curing and all contingencies related to construction
298,176.87
106,275.41
2,784.20 gravel
5,877.75 lean
231.92 lean form
62,622.25 con
3,577.60 form
27,986.59 rebar
2,291.06 curing
904.05 con
167,911.26
41,034.31 con
25,960.22 form
43,697.12 rebar
3,993.88 scaff
1,501.26 curing
13,015.74 con
5,324.80 form
10,321.31 rebar
476.19 curing
819.20 scaff
5,337.45 con
5,190.45 form
6,229.37 rebar
4,814.71 support
195.27 curing
9,791.30
202.00 sus
241.30 sus
366.00 sus
376.00 sus
248.00 sus
3,174.00 sus
5,184.00 sus
14,198.90
14,198.90
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Quotation
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost
Unit Rate Unit Rate
Amount (US$) Amount (US$)
(US$) (US$)
Water Treatment Facility
Sludge Lagoon Bill 5-7 189,251.08 77,774.78
Earth Works of the Drainage Basin including Site clearance, Excavation, Disposal Soil,
LS 1 18,352.00 9,907.30
Compacting Soil and all contingencies related to Earth Works
267,025.86
28,259.30
1,304.80
26,954.50
51,501.30
38,101.32
1,393.95
11,672.34
333.69
114,459.11
3,399.48
5,382.51
1,194.70
16,361.63
3,906.24
10,608.22
21,386.35
782.43
34,532.29
11,394.26
5,312.66
198.35
60,090.63
1,134.00
6,122.00
7,142.00
3,402.00
3,910.00
3,168.00
1,050.00
2,232.00
456.00
15,000.00
175.00
12,906.95
3,392.68
12,715.52
12,715.52
Project For The Expansion Of Water Supply System In Pursat
Date: July 12, 2021
Construction Costs for Administration Building
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Unit Rate
Amount (US$) Amount (US$)
(US$) (US$)
Other miscellaneous items that are specified or shown on the drawings or that the
LS 1.00 11,819.8 11,819.8 5,749.5 5,749.45 17,569.20
Contractor may deem necessary to complete the works in Bill 5-9
0.00 60.00 0.00 0.00
#DIV/0!
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Unit Rate
Amount (US$) Amount (US$)
(US$) (US$)
Water Treatment Facility
Generator Building Bill 5-10 44,538.08 21,476.13 66,014.21
Under and ground floor
Foundation for Desiel Tank LS 1 1,610.80 747.08 2,357.89
Ston 4x6 backfilling and compaction thk=200mm m3 1.51 24.0 36.29 12.0 18.14 54.43
Lean concrete thk=50mm m3 0.76 86.0 65.02 28.0 21.17 86.18
Formwork m2 0.79 14.0 11.06 12.0 9.48 20.54
Steel Bar kg 576.91 0.88 507.68 0.28 161.53 669.21
Formwork m2 28.88 14.0 404.32 12.0 346.56 750.88
Base Concrete m3 6.34 90.0 570.59 28.0 177.52 748.11
Curing Concrete m3 6.34 2.5 15.85 2.0 12.68 28.53
Ground slab LS 1 12,928.63 5,088.22 17,656.86
Ston 4x6 backfilling and compaction thk=200mm m3 13.09 24.0 314.09 12.0 157.05 471.14
Lean concrete thk=50mm m3 6.54 86.0 562.75 28.0 183.22 745.97
Formwork m2 2.34 14.0 32.76 12.0 28.08 60.84
Steel Bar kg 6,307.54 0.88 5,550.63 0.28 1,766.11 7,316.74
Formwork m2 66.48 14.0 930.72 12.0 797.76 1,728.48
Concrete m3 59.87 90.0 5,388.01 28.0 1,676.27 7,064.28
Concrete trowel finishing m2 120.00 - 3.0 360.00
Curing Concrete m3 59.87 2.5 149.67 2.0 119.73 269.40
Ground floor column LS 1 3,405.86 1,855.10 5,260.96
Steel Bar kg 1,357.51 0.88 1,194.61 0.28 380.10 1,574.71
Formwork m2 80.00 14.0 1,120.00 12.0 960.00 2,080.00
Concrete m3 10.50 90.0 945.00 28.0 294.00 1,239.00
Scaffolding m2 80.00 1.5 120.00 2.5 200.00 320.00
Curing Concrete m3 10.50 2.5 26.25 2.0 21.00 47.25
Top Roof slab LS 1 12,245.02 5,660.65 17,905.67
Steel Bar kg 5,936.32 0.88 5,223.96 0.28 1,662.17 6,886.13
Formwork m2 110.96 14.0 1,553.44 12.0 1,331.52 2,884.96
Concrete m3 51.91 90.00 4,672.08 28.00 1,453.54 6,125.62
Curing Concrete m3 51.91 2.5 129.78 2.0 103.82 233.60
Support m3 443.84 1.5 665.76 2.5 1,109.60 1,775.36
Masonery and Finishing Work
Ground floor LS 1 10,554.40 6,032.00 16,586.40
Anti-termite treatment : under ground slab m2 120 8.00 960.00 5.0 600.00 1,560.00
Plastic Sheet 0.15mm m2 120 2.00 240.00 0.5 60.00 300.00
External wall brick 220mm m2 135 9.00 1,216.80 5.0 676.00 1,892.80
Plaster mortar on external wall m2 270.40 4.5 1,216.80 5.0 1,352.00 2,568.80
Emulsion Paint external wall m2 270.40 4.5 1,216.80 3.0 811.20 2,028.00
Partiton wall 120mm m2 52.80 4.5 237.60 5.0 264.00 501.60
Plaster mortar on partition wall m2 105.60 4.5 475.20 5.0 528.00 1,003.20
Emulsion Paint partition wall m2 105.60 4.5 475.20 3.0 316.80 792.00
Emulsion Paint under slab m2 120.00 4.5 540.00 3.0 360.00 900.00
Air intake louvers m2 12.00 18.0 216.00 7.0 84.00 300.00
Discharge fans set 2.00 120.0 240.00 40.0 80.00 320.00
Single swing door (1000 x 2200)mm AD 1 set 1.00 320.0 320.00 80.0 80.00 400.00
Double swing panel door (3160 x 3500)mm AD 2 set 2.00 1,600.0 3,200.00 410.0 820.00 4,020.00
Top Roof Slab LS 1 1,672.50 1,070.40 2,742.90
Epoxy coating on concrete surface m2 133.80 12.5 1,672.50 5.0 669.00 2,341.50
First floor slab with concrete finish with a trowel m2 133.80 - 3.0 401.40 401.40
Other LS 1 2,120.86 1,022.67 3,143.53
Other miscellaneous items that are specified or shown on the drawings or that the
LS 1.00 2,120.9 2,120.9 1,022.7 1,022.7 3,143.53
Contractor may deem necessary to complete the works in Bill 5-10
Project For Provicial Water Supply and Sanitation Project (PWSSP)
Date: July 12, 2021
Construction Costs
Item N° Description Unit Quantity Material Cost Labor Cost Amount Remarks
Unit Rate Unit Rate Amount
Amount (US$)
(US$) (US$) (US$)
Water Treatment Plant
External Work WTP Bill 5-11 7,519.07 5,113.62 12,632.69
Bill 5-11 – Gates, Plaque Shelter and Fencing LS 1 7,161.02 4,870.11 12,031.13
Construction of Main/ Side Gates, Plaque Shelter and fencing
including general preparation, formwork, re-bar arrangement,
concrete, interior and exterior finishing for all floors, walls, bases
and ceilings, roofing, windows, doors, shutters, shelves, supply and
installation of Main gate and side gate, Nameplate Panel with
Ls 1.00 7,161.02 7,161.0 4,870.11 4,870.11 12,031.13
BTBWSA logo, and other miscellaneous equipment specified in the
Drawings and Specifications.
Tree Planting with each approved type tree of initial size 2 m high LS 1.00
& 200 mm
girth including 1 m3 of subsoil and 3 wooden stakes for stabilizing
tree. Maintain tree till the end of Defects Liability Period. - - -
Tree Type-1 (Champey Tree, H=2.5m) nr 7 N/A
Flower Type-3 (Slakgnan Flower, H=2m) nr 25 N/A
Flower Type-4 (Machul Flower, H=1.2m) nr 3 N/A
Miscellaneous landscaping works specified in the Drawings or the LS 1.00 29,628.0 29,628.0 14,565.4 14,565.42 44,193.38
Specifications but otherwise not included elsewhere in Bill 5.13
Service
Reservoir Drainage
Filter and Pump Tank Total
Station
Soil Excavation 215.14 2,637.36 4,669.69 4,141.42 32,383.46 9471.53 53,518.60
Disposal Soil 215.14 2,637.36 4,669.69 4,141.42 32,383.46 9471.53 53,518.60
Backfilling 266.67 2,507.89 3,825.67 4,022.53 15,507.26 6100.33 32,230.35