(MCQ'S) Production Planning and Control
(MCQ'S) Production Planning and Control
(MCQ'S) Production Planning and Control
Branch
Of Engineering
CONCEPT OF PPC
CONCEPT OF PPC
https://lastmomenttuitions.com/mcqs/mechanical-engineering/production-planning-and-control-mcqs/#1608373435695-81fe7cda-9111 1/5
1/24/23, 11:19 AM [MCQ's] Production Planning and Control - Last Moment Tuitions
https://lastmomenttuitions.com/mcqs/mechanical-engineering/production-planning-and-control-mcqs/#1608373435695-81fe7cda-9111 2/5
1/24/23, 11:19 AM [MCQ's] Production Planning and Control - Last Moment Tuitions
14. ___ is the probability that a product will operate properly within an expected time frame.
A) serviceability
B) performance
C) reliability
D) durability
Answer: c
16. Material requirements planning (MRP) is useful for all of the following except
A) erratic orders
B) independent demand items
C) discrete demand items
https://lastmomenttuitions.com/mcqs/mechanical-engineering/production-planning-and-control-mcqs/#1608373435695-81fe7cda-9111 3/5
1/24/23, 11:19 AM [MCQ's] Production Planning and Control - Last Moment Tuitions
19. All of the following are inputs into the MRP process except
A) the planned order report
B) the item master file
C) the product structure file
D) the master production schedule
Answer: a
https://lastmomenttuitions.com/mcqs/mechanical-engineering/production-planning-and-control-mcqs/#1608373435695-81fe7cda-9111 4/5
1/24/23, 11:19 AM [MCQ's] Production Planning and Control - Last Moment Tuitions
23. ___ is the probability of rejecting a lot that has an acceptable quality level is referred to as the
A) acceptable quality level
B) lot tolerance percent defective
C) consumer’s risk
D) producer’s risk
Answer: d