Cadangan Pembangunan Sistem Pengairan Tersier di bawah Program NKEA (Pertanian)EPP 10, Lembaga Kemajuan Pertanian Muda (MADA),

Negeri Kedah/ Perlis bagi Pakej C.

BILLS OF QUANTITIES
BLOCK CCLBD 8
WORKDONE
CONTRACT PREVIOUS CURRENT TODATE
Rate Amount Amount Amount Amount
Item No. Code No. Description Unit Qty Qty Qty Qty
(RM) (RM) (RM) (RM) (RM)

7.15.11 PIPE JACKING

Item for special laying methods is deemed to include mobilisation and


demobilisation

Pipe Jacking - Road crossing for 900mm R.C Pipe Jacking for irrigation
crossing as per specification

7.15.11.1 A520 TEMPORARY WORKS


A A523.1 Construct cofferdams and remove upon completion; fixed charge sum 26,500.00 1 26,500.00 100% 26,500.00 - - 100% 26,500.00

B A523.2 Maintain cofferdams for duration of construction; time-related charge sum 10,000.00 1 10,000.00 100% 10,000.00 - - 100% 10,000.00

C A524.1 Install pump for pumping/dewatering and remove upon completion;fixed sum 5,000.00 1 5,000.00 100% 5,000.00 - - 100% 5,000.00
charge

D A524.2 Operation and maintenance of pump sum 500.00 1 500.00 100% 500.00 - - 100% 500.00

7.15.11.2 F100 EXCAVATION

Foundation

Excavation for foundation shall include upholding sides of


excavation, preparation of excavated surface, additional
excavation to provide working space, backfilling and removal of
dead services.

A F141 Excavate for jacking and receiving pit irrespective of depth including m³ 10.50 65 682.50 65.00 682.50 - - 65.00 682.50
walling, anchor foundation, backfilling with excavated spoil and
disposing surplus spoil or material not suitable as directed (by
mechanical equipment)

Total Carried To Collection Page 42,682.50 42,682.50 42,682.50


F2/K/Bill 7.10.7-1
Cadangan Pembangunan Sistem Pengairan Tersier di bawah Program NKEA (Pertanian)EPP 10, Lembaga Kemajuan Pertanian Muda (MADA), Negeri Kedah/ Perlis bagi Pakej C.

BILLS OF QUANTITIES
BLOCK CCLBD 8
WORKDONE
CONTRACT PREVIOUS CURRENT TODATE
Rate Amount Amount Amount Amount
Item No. Code No. Description Unit Qty Qty Qty Qty
(RM) (RM) (RM) (RM) (RM)

7.15.11.3 H100 PILING WORKS

PLANT AND EQUIPMENT

A H110 Provision of all necessary piling plant and equipment, transportation to sum 14,500.00 1 14,500.00 100% 14,500.00 - - 100% 14,500.00
the Site, handling, assembling, and removal off the Site after
B H120 Moving and handling of all piling plant and equipment within the Site sum 15,000.00 1 15,000.00 100% 15,000.00 - - 100% 15,000.00
and from location to location as often as is, and whenever necessary
H300 PILES
Items for piling work shall be deemed to include piling records
and disposal of excavated and surplus materials.

C H391 Supply in 150mm x 150mm R.C piles, 6m long nr 90.00 24 2,160.00 - - - - - -

D H392 Drive 150mm x 150mm R.C piles, 6m long m 28.00 144 4,032.00 - - - - - -

7.15.11.4 O300 Pipes


Item for culvert shall be deemed to include all joints, water stop,
concrete base, and concrete surround unless otherwise stated

Jacking Pipe Class 1.5Z


A O339 Supply, haul, handle, jack in and proper install 900mm diameter pipe m 3,190.00 20.0 63,800.00 20.00 63,800.00 4.00 12,760.00 24.00 76,560.00
culvert in standard length of 3.050m for the road culvert.

Total Carried To Collection Page 99,492.00 93,300.00 - 106,060.00

F2/K/Bill 7.10.7-2
Cadangan Pembangunan Sistem Pengairan Tersier di bawah Program NKEA (Pertanian)EPP 10, Lembaga Kemajuan Pertanian Muda (MADA), Negeri Kedah/ Perlis bagi Pakej C.

BILLS OF QUANTITIES
BLOCK CCLBD 8
WORKDONE
CONTRACT PREVIOUS CURRENT TODATE
Rate Amount Amount Amount Amount
Item No. Code No. Description Unit Qty Qty Qty Qty
(RM) (RM) (RM) (RM) (RM)

7.15.11.5 CONCRETE WORKS

IN SITU CONCRETE DESIGN MIX

Rate for in situ concrete designed mix shall be deemed to include


placing and compaction of concrete.

Grade 15
A I111 Concrete blinding, 100mm to structure base m³ 11.00 13 143.00 10.00 110.00 - - 10.00 110.00

Grade: C 30

B I149 Concrete blinding, 100mm to structure base m³ 300.00 12 3,600.00 10.00 3,000.00 - - 10.00 3,000.00

7.15.11.6 I400 FORMWORK

Rate for formwork shall be deemed to include the projections and


intrusions and any temporary staging required.

A I419 F2: Fair finish all structural component m² 28.80 85 2,448.00 68.00 1,958.40 - - 68.00 1,958.40

7.15.11.7 I500 REINFORCEMENT

Rate for reinforcement shall be deemed to include labour for


cutting, bending, and placing.

A I522.1 High tensile steel fabric - mesh BRC A10 t 14.00 100.00 1,400.00 80.00 1,120.00 - - 80.00 1,120.00

Total Carried To Collection Page 7,591.00 6,188.40 - 6,188.40

CONTRACT PREVIOUS CURRENT TODATE

F2/K/Bill 7.10.7-3
Cadangan Pembangunan Sistem Pengairan Tersier di bawah Program NKEA (Pertanian)EPP 10, Lembaga Kemajuan Pertanian Muda (MADA), Negeri Kedah/ Perlis bagi Pakej C.

BILLS OF QUANTITIES
BLOCK CCLBD 8
WORKDONE
CONTRACT PREVIOUS CURRENT TODATE
Rate Amount Amount Amount Amount
Item No. Code No. Description Unit Qty Qty Qty Qty
(RM) (RM) (RM) (RM) (RM)

COLLECTION PAGE

Total brought forward from Page F2/K/Bill 7.15.8-1 42,682.50 42,682.50 - 42,682.50

Total brought forward from Page F2/K/Bill 7.15.8-2 99,492.00 93,300.00 - 106,060.00

Total brought forward from Page F2/K/Bill 7.15.8-3 7,591.00 6,188.40 - 6,188.40

Total Carried To Summary Page 149,765.50 142,170.90 154,930.90

F2/K/Bill 7.10.7-4