FRP Procedure Rev D
FRP Procedure Rev D
FRP Procedure Rev D
TABLE OF CONTENTS
2. REFERENCE 2
2.1 General 2
2.2 Codes and Standards 3
2.3 Project Specifications 3
4. ASSEMBLY 5
4.1 Assembly of Pipe and Fitting 5
4.2 Assembly of Flange 10
5. TESTING 10
5.1 Preparation for testing 10
5.2 Safety 11
5.3 Hydrostatic Pressure Testing 12
5.4 Flushing 13
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
1. INTRODUCTION
1.1 Scope
This procedure covers the requirements Fabrication and Installation FRP Pipe for Ujung
Pangkah Development Project.
1.2 Definition
2. REFERENCE
2.1 General
The requirements contained in the latest edition of the following applicable codes,
standards, and construction specifications. The intent of this procedure is not superseding
those codes, standards, and project specifications, but to supplement them as necessary
and stress their importance by reciting their major requirements.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
3.1 Handling
1. Let the factory arrangement of the pipe be your guide for connect supporting and
spacing when rearranging for transport. Do not let pipe or fittings rest on the bed of
the truck where nails, studs and other objects might damage them. Wherever pipe or
fittings come in contact with wood or metal, padding such as excelsior, carpet or
foam should be used.
2. The pipe should be securely fastened directly over the dunnage with tiedowns
consisting of nylon straps or manila rope. Avoid overtightening which may cause
excessive localized deformation in the pipe.
3. Do not allow the pipe to extend more than 3 feet ( 900 mm ) beyond the truck or
trailer bed as permanent damage can result from excessive flexing.
4. Pipe and fittings should never be thrown or dropped under any circumstances.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
5. If load is irregular and cannot be reliably moved by fork truck, or proper equipment
is not available, the pipe should be carefully loaded and unloaded by hand one length
at a time.
3.2 Storage
2. A pipe stack should not exceed 10 ft in height and should have side supports or
blocks to prevent rolling or slipping in the stack.
3. If it is necessary to stack pipe directly on the ground, make sure that the ground
surface is level, soft and free of rocks or sharp objects.
4. Protective end coverings should be left in place until time of installation to protect
the pipe ends and to prevent dirt or other materials from entering the pipe.
5. Fittings, adhesives and tools should be stored in their shipping boxes under cover
and protected from water, mud and extreme heat or cold.
3.3 Inspection
Since pipe and fittings may be subjected to rough treatment during transportation,
storage and handling, it is imperative that they be fully inspected for possible impact
damage, cracking or manufacturing defects.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
4. ASSEMBLY
6. These tolerances can be checked by using e.g the arbor of the shaver
flush with the cut end of the pipe
7. Various types of shavers are avalaible for shaving the pipe ends,
subject to the pipe size
4.1.2 Shaving
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
2. Fix the arbor to the inside of the pipe by turning the central tensioning
bolt clockwise
4. Take care when shaving the first layer, because the pipewall may be
not be equally thick on all sides
4. Sanded surface must have a dull, fresh finish, not a polished look
5. Check the assembly length and mark pipe and fitting for alignment of
elbows, flanges, etc
6. Measure back from the edge of the spigot the required insertion depth
plus 50 mm and scribe a line. After assembly by pulling the joint
together the scribe on the pipe should be 50 mm from the end of the
bell.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
10. Use a clean dry cloth or brush to remove sanding dust etc
11. Do not touch the sanded surfaces after sanding and cleaning
2. Stir thoroughly until no streaks are visible and the mixture has an even
colour ( after 2 to 3 minutes )
3. Make sure that before mixing the adhesive, all preparations have been
done and all parts to be bonded are ready for assembly, because mixed
adhesive has a limited potlife subject to the ambient temperature.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
5. Never use adhesive that has started to cure. This is case when the
mixture gets clotted and toughens
1. When inserting the spigot pay attention to the marks and position and
keep the joint together. Letting the spigot slip back or turning the
spigot after complete insertion may result in a bad joint
2. Hook the 2 winches in the band clamps and start pulling the joint
further together in a smooth movement until the joint is firmly fixed
together and there is 50 mm between the bell end and the mark
3. Do not remove the winches until the adhesive has fully cured
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
1. Wrap the required size Ameron heating blanket around the joint
keeping the power supply cable free from the blanket
5. When the temperature is below 10ºC or the wind has a cooling effect,
insulation material should cover the heating blanket. Insulation
material should overlap the sides of the blanket with at least 100 mm
and should match to the pipe. It should not cover the thermostat
8. Write down on the pipe next to the heating blanket the starting time
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
10. During curing the joint should not be moved, vibrated or otherwise
disturbed
1. Finger tighten all nuts. Bolt threads must be clean and lubricated. Use lubricated
washer under both nuts and bolt heads to protect flange backfacing.
2. Tighten all nuts following the sequences shown under tightening sequence.
5. TESTING
1. All vent and other connections, which can serve as pressure test vents shall be open
during filling so that all air can be vented prior to applying test pressure to the
system
3. Before pressure testing, all lines or systems shall be inspected to ensure that all
connected parts to be excluded from the test are isolated by blinds
5. Adequate temporary supports should be used where volume and weight of water
may cause line deflection
6. Hydrostatic test loops shall have all high points in the piping with a vent and all low
points with a drain, regardless of whether or not they are specifically shown on the
drawings. When filling, the test fluid shall be introduced at the lowest point of the
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
system to minimize the risk of entrapped air and all vents shall be opened. Vents and
drains shall be closed once a continuous flow of fluid is obtained through the vent or
drain.
7. Hydro testing shall be performed via a manifold. The test pump shall be isolatable
from the system with its own pressure gauge. Valves, hoses used in tests shall be
suitably rated.
8. At least 2 gauges shall be installed in the test system, one near the pressure generator
( at the lowest point ) and the other at the highest point, both of which to be
positioned so that they can be easily reached and observed
9. When testing underground systems, the line should be partially backfilled and
temporarily blocked at directional changes to prevent excessive movement during
the test
10. Care should be taken to prevent above ground systems from buckling or moving
excessively during test or in case of sudden depressurization
5.2 Safety
2. Do not make any adjustments on pressurized fittings under pressure. For example, if
an adapter or flange joint is leaking, take the pressure off the line before attempting
to tighten
3. The test operation should be well planned and carried out with all due precautions. It
is always best for one man to be in charge of the operation so that all other persons
on the job take their direction from him
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
5. This work shall be carried out in open space or shelter with sufficient ventilation
3. Vents shall be open during filling of water so that air is vented prior to applying
pressure to the system. Vents will then be closed to permit pressurization to
commence
4. The pressure shall be brought up slowly and gradually to allow for equalizing
for strain during the test, and in stages to allow checking for leaks and
inspection of the system
5. Once attained, the test pressure shall be held for a period of two hours or such
time as required for a full visual inspection of the system to be made. During
the first half hour of hydrotest, if pressure drops it is necessary to bring up to
test pressure and test for two hours or such times as required for a full visual
inspection of the system. A ±4% pressure change during hydrotest is
acceptable.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D
AMERADA HESS (INDONESIA - PANGKAH) LIMITED
UJUNG PANGKAH DEVELOPMENT PROJECT
6. Flushing
1. Flushing to be conducted by “ end to end “ method and carried out after hydrotest
2. All in line valves and ball valves shall be flushed in fully open position
3. All instrument leads shall be disconnected prior to flushing. Soft seated valves should be
removed before flushing
5. Blind off all pipe ends if they are not connected yet to prevent ingression of debris or foreign
material.
____________________________________________________________________________________________________________________
UPD-IJ-G3-CS-PR-2008 Rev.D