THIS DOCUMENT IS INTENDED FOR USE BY ADCO AND ITS NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND SUPPLIERS.
DESCON ENGINEERING
1 INRODUC TION 4
1.1 Project Overview 4
1.2 Definition of Terms 4
1.3 SUPPLIER’s Responsibilities 5
1.3.1 Deviations and clarifications 5
2 SCO PE O F WORK 5
2.1 SUB-CONTRACTOR’s Main Items 5
2.2 SUB-CONTRACTOR Recommended Spare Parts 5
2.2.1 Construction and Pre-Commissioning Spares 5
2.2.2 Commissioning spares 6
2.2.3 1st Year Operation Spares List 6
2.2.4 Insurance spares 6
2.2.5 Operating spares 7
2.3 Operating materials 7
2.4 Surface Painting and Rust Prevention 7
2.4.1 Surface Painting 7
2.4.2 Rust Prevention 7
2.4.3 Preservation 7
2.5 Inspection requirements 8
2.5.1 Definitions 8
2.5.2 Criticality Rating & Inspection Class 8
2.5.3 Inspection/Release Requirements 10
3 QUA L IT Y A SSURANC E SYST EM R EQU IREM EN TS 11
3.1 Quality system 11
3.2 Release for Manufacture 11
3.3 Non Conformities and Concessions 12
3.4 Codes and Regulations 12
3.5 Material Identification 12
3.6 Weather Protection & Transportation 12
4 PR ESER VAT ION AND PACK ING 12
4.1 Packing & Preparation for Shipment Requirements 12
5 SU PPL IER DOCU M ENT AT ION R EQU IR EM EN T S 13
5.1 Documentation 13
5.2 SDRL – General Instructions 13
5.2.1 General 13
5.2.2 Presentation 13
5.2.3 Submission 14
5.2.4 Review Cycle 14
5.2.5 SUB-CONTRACTOR Design Documentation 14
South East (SE) Group of Fields of Abu Dhabi Company for Onshore Petroleum Operations (ADCO)
consists of Sahil, Asab, Shah, Quashwira and Mender fields. The Asab, Sahil, Shah and Quashwira
fields are located in a desert area approximately 100, 160, 220 and 225 km respectively south of
Abu Dhabi city. Asab started production in 1973, Sahil and Shah a little later. Sahil, Shah, Quashwira
and Mender are essentially satellite fields to Asab. All are sour to some extent except Quashwira.
Asab Field:
Conversion of Twenty Five (25) nos. of existing Oil Producers to Gas Lift (GL) wells and
Tie-in them to the Lift Gas Flowlines/Manifolds in respective RDSs.
Shah Field:
Tie-in of Twenty (20) nos. of new Artificial Oil Producer Wells (ESP)
Tie-in of Two (2) nos. of new Water Disposal Wells (WDW)
Installation of Three (3) nos. of new Multi Selector manifolds (MSM)
Qusahwira Field:
Tie-in of Eleven (11) nos. of new Natural Oil Producer Wells
Tie-in of Three (3) nos. of new Water Injection Wells
Tie-in of One (1) no. of Gas Injection (GI) well
Installation of new OHL for Five (5) nos. of ESP Oil Producer wells
BUYER has no responsibility to discover any deviation entered in order parts of SUB-
CONTRACTOR’s Documents and BUYER will not accept any other deviation than
those placed on the accepted deviation list.
[√ ] The SUB-CONTRACTOR’s scope of work and supply shall fully comply with the
requirements of this requisition and referenced attachments except for the deviations
listed.
2 SCOPE OF WORK
The term “1st year operational spares” is used to cover spares required from the
point of Ready For Commissioning (RFC) until end of the 1st year of operation.
They are required for initial start-up and running-in and should cover the first year
of operation.
These shall be delivered to site in time for plant commissioning and will be stored
locally until delivered to operations possibly prior to commissioning.
SUB-CONTRACTOR shall recommend the spares suitable for two (2) year
operation and provide a price list.
2.4.3 Preservation
SUB-CONTRACTOR shall provide preservation procedure at the work site in
accordance with applicable specification.
2.5.1 Definitions
Surveillance
Surveillance comprises all SUB-CONTRACTOR activities performed to verify that
goods meet the specified requirements, including audit, design review, and
inspection.
Inspection
The process of measuring, examining, testing, gauging or otherwise comparing the
items with the applicable requirements.
Hold (H) Inspection
A Mandatory Hold shall be applied to the production schedule and the test shall be
performed with the CONTRACTOR and/or COMPANY in attendance.
Witness (W) Inspection
The CONTRACTOR requires notification of the inspection timing. However, the
inspection is performed as scheduled and if the CONTRACTOR and/or COMPANY
are not present, the SUB-CONTRACTOR can proceed to the next step.
Review (R) Inspection
The CONTRACTOR shall review the appropriate inspection documentation or
certification but does not require a formal notification of the inspection timing. This
inspection is normally performed as part of a scheduled inspection visit by the
CONTRACTOR. If the CONTRACTOR and/or COMPANY are not present, the SUB-
CONTRACTOR can proceed to the next step.
Source
This normally means the SUB-CONTRACTOR’s works where the goods are
manufactured and where surveillance is carried out.
N.B:-
(1) In the event that the cargo exceeds the above figures, SUB-CONTRACTOR shall
prepare his plan. Such is subject to BUYER’s approval.
5.1 Documentation
The SUB-CONTRACTOR shall include the supply of all Documentation to define the
Equipment supplied for the purposes of:
Integration into the Plant Design
Design Code Compliance
Regulatory Authority Approval
Detailed requirement of SUB-CONTRACTOR documents with respective codes are specified
in SDRL attached with the MR. SUB-CONTRACTOR shall prepare Document Register in
accordance with Document Required List and submit for Contractor’s approval.
5.2.1 General
It is a condition of the Purchase Order that all data and drawings (hereinafter called
documents) shall be submitted to the CONTRACTOR in the manner and time period
stated. The Purchase Order will not be considered complete until all documentation
has been submitted and accepted.
5.2.2 Presentation
All documents shall be full size based on ‘A’ series sizes, i.e. A1, A2, A3 or A4. A0 is
not acceptable.
All documents shall be checked before submission. Unchecked documents may be
returned, unreviewed.
All documents submitted shall be clearly marked with the Purchase Order No., Item
No, SUB-CONTRACTOR’s Job No., and Equipment/Tag No. (If applicable), SUB-
CONTRACTOR’s Document No. and CONTRACTORs Document No. In addition
the Project Title Block shall be added by SUB-CONTRACTOR in accordance with
Engineering Procedure 30.99.90.024.
All documents and technical data shall be provided in the English Language.
Dimensions and other units of measurement are defined within the BEDD, document
no. 14.99.91.5610, and shall be SI and other units recognized by SI, preferably: mm,
°C, bar. Except that pipe and bolt diameters may be in inches, pipe wall thicknesses
may be in inches and/or pipe schedules, and tube wall thickness in BWG.
A free space 80mm x 50mm shall be provided adjacent to the document’s title block
for the CONTRACTOR to add his own status review stamp.
5.2.3 Submission
Documents required for submission are indicated in the “At Bid” or “For Approval”
columns of this SDRL.
Documents required to form part of the final documentation which will not be
submitted for individual review are indicated in the data book column only.
Any revision to a document after its first submission shall be clearly identified on the
document in the revision box. Once issued, a document number shall not be changed
or re-used.
All documents shall be sent under cover of a transmittal using the standard project
format (to follow).
The number of copies of each document to be submitted shall be as indicated.
Certified Final submissions shall be made within 14 calendar days of receipt of
document with CONTRACTOR review status of “No Comments”.
This attachment lists all BIDDER’s proposed exceptions to JOB SPECIFICATION. BIDDER
agrees that its PROPOSAL is in full compliance with the JOB SPECIFICATION except for
the exceptions described below
Recommended
Description of Reason for
Item No. Revision
Proposed Exception Proposed Exception
To JOB
SPECIFICATION
ENGINEERING DOCUMENTS/DRAWINGS
(GENERAL)
6 Overhead line route 2W 3X+R 3X+R
7 Overhead line profile 2W 3X+R 3X+R
8 Sag Calculation 2W 3X+R 3X+R
9 Towers typicals and arrangement drawings 2M 3X+R 3X+R
10 Material take Offs 3X+R
Material Specifications,Technical schedule,
11 2M 3X+R 3X+R
Data sheets, and Catalogues
12 As built Drawings. 3X+R
MISCELLANEOUS DOCUMENTS
13 Manufacturing Record Book (MRB) - - - 3X
14 Quality Manual 3X - - -
15 Completed safety instruction sheet - 2M 1R+2X 1R+3X
16 ADCO Project experience summary 3X - - -
17 Painting procedure - 2M 1R+2X 1R+3X
18 Site preservation procedure - 2M 1R+2X 1R+3X
19 Manufacturing Schedule - 2W 1R+2X 1R+3X
20 Fabrication and Testing Schedule 3X 2W 3X+R 3X+R
21 Quality plan / Inspection and Test Plan (ITP) 2M 3X+R 3X+R
QA/QC procedure / Test and Inspection 2M 3X+R 3X+R
22
Procedure
23 Catalogue 3X
24 Vendor Monthly Report Monthly 3X+R
Minutes of Meeting 1W after 3X+R
25
Meeting
ATTACHMENT-04
Quality Requirement Form (QRF)
- Contractor will advise a mutually convenient date for the KOM (generally held within 4 weeks of
the purchase order award)
- Vendor shall provide an advance notice for pre inspection meeting as per Annexure-5.
- A Vendor pre inspection meeting check list of approved minimum submissions (as per annexure-
2) shall be furnished by vendor and the meeting agenda shall be as per Annexure-3.
- Fabrication shall commence only after conducting the PIM, where a PIM is required.
4. Notification of Hold / Witness Points to the Contractor
- The vendor shall provide a minimum of Four (4) weeks written notice of “Hold” and “Witness”
inspections, including FATs and final release for shipment to the contractor. The inspection shall
be further confirmed five (5) days prior to the schedule. Any cost associated with subsequent
delays shall be borne by the vendor.
- Inspection notification format shall be as per annexure-5.
- Work shall not proceed past a Hold point, including a FAT or final release without obtaining
written approval form Contractor.
Definitions:
- For “Hold” inspection, a mandatory hold shall be applied to the production schedule and the
test shall be performed with the Contractor/TPI in attendance (unless a written waiver has been
issued in advance).
- For “Witness” inspection, the Contractor requires notification of the inspection timing. However,
the inspection is performed as scheduled if the Contractor/TPI is not present, the Vendor can
proceed to the next step.
- In “Review” Inspection, the Contractor shall review appropriates inspection documentation /
certification but does not require a formal notification of the inspection timing. This inspection is
normally performed as part of the scheduled inspection visit by the Contract. If the Contractor is
not present, the Vendor can proceed to the next step.
- “Surveillance” comprises all Contractor activities performed to verify that goods meet the
specified requirements, including audit, design review, and inspection.
5. DEVIATIONS / CONCESSIONS
- The Vendor shall issue the relevant forms given in Annexure-6 to apply for the Technical
Deviations / Concessions, if any and shall obtain Contractor’s approval prior to implementation.
6. INSPECTION DOCUMENTATION
Inspection documentation requirements are identified in the Sub-Contractor Document Requirement
List attached to the inquiry/Purchase Order. This list includes documentation to be submitted to the
Contractor. Any additional documentation required by the Inspection and Test Plan shall also be
prepared by the Vendors.
Inspection documentation shall be compiled on an on-going basis and shall be available for audit or
inspection by Contractor’s personnel and/or by their nominated Representative as well as ADCO or
their nominated Representative at Vendor premises. All documentation shall be traceable, legible
and in strict compliance with Contract and Project Requirements. All documentation, including the
quality records / material test certificates etc. Shall be in English language. Welding consumable
requirements for all equipment / items shall be as per Annexure-9 (if applicable).
See Annexure-7 for guidelines on submission of final documentation.
Material certification for O shall be in accordance with the relevant requirement of EN
10204:2004 as detail below:
3.2 3.1 2.2 2.1
9. ANNEXURES
Annexure-1: Additional Project Quality Annexure-6: Technical Deviation/Concession
Requirements Form
Annexure-2: Pre Inspection Meeting Checklist Annexure-7: Guideline for Compilation of Final
Annexure-3: Pre Inspection Meeting Agenda Documentation
Annexure-4: Class of Inspection Annexure-8: Inspection of Test Plan Performa
Annexure-5: Inspection Notification Annexure-9: Requirements for Welding
Consumables
1. The following documents are required to be submitted by Vendors as part of their bid package (the
Contractor shall be informed, if the Product or System is new to the Vendor):
All submittals required by Sub-contractor Document Requirements List (SDRL).
Copy of ISO 9001 certification of Quality Management System or copy of Quality
Manual.
List of proposed sub-suppliers/vendors and their scope of supply,
Copy of typical Inspection and Test Plans, QC Procedures etc.,
Copies of other approval certificates e.g., ASME U / U2 / PP, API 6D, API 5L, API 5LD, TUV etc.
Audit schedule for previous 12 months (planned and completed).
2. The following documents are required to be submitted by Vendors post purchase order award:
All submittals required by Sub-contractor Document Requirements List (SDRL),
Project Quality Plan, if specified in Page 1 of 2 of the QRF,
Inspection and Test Plan. The pro-forma for each inspection stage shall be referenced in the Inspection
and Test Plan. See Annexure- 8 for a typical Inspection and Test Plan format.
QC Procedures applicable for the Order.
Lessons Learned from execution of similar orders in the past.
3. Whenever revisions to documents are submitted, the changed portions shall be clearly identified (using
cloud marks or track lines with revisions).
6. Inspection Release
Prior to the call for final inspection and product release, the Vendor shall ensure that:
All documents (drawings, data sheets, calculations, procedures, method statements) are approved by
Contractor.
All inspections, examinations, and tests are completed with satisfactory results and documented.
All material certificates are available, reviewed and approved
Product surface protection is complete (varnish, paint, coatings, insulation, fireproofing as applicable).
All Non-conformance Reports are closed out (Vendor NCR's and Contractor NCR's).
All deviation / concession requests are approved by Contractor.
The minimum requirements for Inspection Classes generally be, but not limited to those below. The exact details
shall be as per the approved Inspection and Test Plan.
A. Class I
Full stage inspection carried out progressively from commencement of manufacturing to final acceptance and shall
include:
Attend Pre-Inspection Meeting
Inspection of source material's chemical and physical properties including metallurgical enhancement
Scrutinizing material test certificates
Review of welder qualifications
Monitoring and witnessing key stages of manufacturer's assembly, fabrication, erection and all prescribed tests
Review of NDE reports and records other quality checks done by Vendor and Sub-vendor(s) internally
Scrutinizing manufacturer's quality control system
Witnessing functional tests carried out in accordance with relevant specifications
Witnessing of all pressure and performance tests followed by inspection of disassembled equipment, if
applicable
Witnessing manufacturing repairs, if any
Final visual and dimensional inspection of equipment
Witness acceptance tests
Witnessing Positive Material Identification (PMI)
Verification of packing and marking identification
Verification of equipment loading during shipment (at Vendor's Shop) and at various stages.
B. Class II
Specific stage inspections of a piece of equipment or materials or random batch inspection of bulk materials during
manufacture and final inspection of equipment prior to shipment and shall include:
Attend Pre-Inspection Meeting, if applicable (Pre-Inspection Meeting is optional for Class II)
Scrutinizing material test certificates
Review of welder qualifications
Review of NDE reports and records other quality checks done by Vendor and Sub-vendor(s) internally
Monitoring and witnessing prescribed tests
Witnessing final pressure and workshop performance testing following by inspection of disassembled
equipment, if required
Witnessing manufacturing repairs, if any
Final visual and dimensional inspection
Witnessing Positive Material Identification (PMI)
Verification of packing and marking
Verification of equipment loading during shipment (at Vendor's Shop) and at various stages.
C. Class III
Final condition or 'As Built' examination(s) and test(s): Inspection may be on one or more pieces of equipment or on a
random batch selection of bulk materials and shall include:
Scrutinizing material test certificates
Reviewing all quality control records for conformance
Witnessing final pressure and workshop performance testing following by inspection of disassembled
equipment, if required
Final visual and dimensional inspection
Witnessing Positive Material Identification (PMI)
Verification of packing and marking identification
D. Class IV
Review and acceptance of the Manufacturer's or Supplier's inspection records including material test certificates.