Combinepdf
Combinepdf
Combinepdf
Levels
L1 L2 L3
4.0 Detection system, System Independence, Integrated Safety & Input signals of the system mentioned?
Capacity of System response, Electrical equipment, Energy source, Main source of Power supply, Secondary Power
5.0 source, Source of relief & Auxiliary warning source mentioned?
Fire and Gas system viz., Components, Detectors, Connecting cables, Information processing, Fire & Gas Alarm Control
6.0
Panel (FACP) mentioned as per Project requirement?
Fire and Gas system viz., Warning alarms, Audible alarms, Visual alarms, PA/GA (Public Address/General Alarm System)
7.0
& Localization of Alarms mentioned as per Project requirement?
Fire and Gas system viz. Telephone Communication System & Interconnections with the ESD mentioned as per Project
8.0 requirement?
Type of Fire Detection viz., Flame Detector, Smoke Detector, Heat Detector, Pushbutton & VESDA etc., requirement if
9.0
any mentioned as per Project requirement?
Number of Detectors, Localization, Voting Logic & Actions in terms of Fire Detection mentioned as per Project
10.0
requirement?
Type of Gas Detection viz., Gas detectors in Buildings, Gas detectors in Air systems, Hydrogen Detector, Oxygen
11.0
Detector, Methane Detector etc., requirement if any mentioned as per Project requirement?
Number of Detectors, Localization, Voting Logic & Actions in terms of Gas Detection mentioned as per Project
12.0
requirement?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
Design Basis, Fire Zones, Firewater system, Firewater supply and storage, Maximum Firewater demand, Firewater
4.0
Pump and Firewater Distribution and Layout of the system mentioned as per Project requirement?
Details of Firefighting equipment, Fire Hydrant, Fixed Fire Water Monitor, Hose Reels, Fixed Water Spray System of the
5.0 system mentioned as per Project requirement?
Details of Portable and Mobile Firefighting equipment Fire Extinguishers viz., Dry Chemical Powder (DCP), CO2,
6.0
Wheeled type of the system mentioned as per Project requirement?
Details of Fire Protection for Buildings viz., Fixed Carbon Dioxide Fire Extinguishing System, Clean Agent Fire
7.0 Suppression System, Automatic Sprinkler System & Automatic Spray System of the system mentioned as per Project
requirement?
Details of Passive Fire Protection (Fireproofing) viz., General requirements, Identification of Fire Potential Equipment,
8.0 Fire Proofing Zones, Fire Envelope Extension & Fire Proofing Consideration of the system mentioned as per Project
requirement?
Details of Passive Fire Protection (Fireproofing) viz., Equipment Support Structures, Pipe Rack Supports, Fire Proofing
9.0 Materials and thickness for Structures, SDV, BDV & ESDV Fire Proofing requirement of the system mentioned as per
Project requirement?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
7.0 Single Largest worst scenario for arriving the firewater demand mentioned as per Project requirement?
9.0 Firewater Main Electrical Pump Capacity & required parameters mentioned as per Project requirement?
10.0 Firewater Standby Diesel Pump Capacity & required parameters mentioned as per Project requirement?
11.0 Firewater Jockey Pumps Capacity & required parameters mentioned as per Project requirement
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
1.0 Company standard title block, Job Number, Drawing titles, numbers and revision?
4.0 Standards/Codes/Regulations to be followed for complete fire fighting and safety system mentioned?
7.0 Inter-distances between fire fighting and safety equipments as per Project specifications/ International standards?
8.0 Identification of all fire fighting and safety equipment"s with respect to MTO?
10.0 Proper location of fire fighting and safety equipment"s as per Standards/Codes/Regulations?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
1.0 Company standard title block, Job Number, Drawing titles, numbers and revision?
4.0 Standards/Codes/Regulations to be followed for complete fire fighting and safety system mentioned?
7.0 Inter distances between Escape route as per Project specifications/ International standards?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
1.0 Company standard title block, Job Number, Drawing titles, numbers and revision?
8.0 All mechanical construction details specific for the equipment specified?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head
Levels
L1 L2 L3
1.0 Company standard title block, Job Number, Drawing titles, numbers and revision?
Note:
1. Stages 0, 1, 2, 3 for Design Freeze, Issued for design, Vendor data, Approved for construction respectively.
3. □ in the appropriate column shall indicate the check to be performed by the that levels.
4. Check points to be answered with "√"(=Checked) while performing the actual check.
Name
Signature
Date
Signature of Engineering Head