Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

B015 000-79-41 PLS 01 Rev 1 - Painting Specification

Download as pdf or txt
Download as pdf or txt
You are on page 1of 63

SPECIFICATION Specification No.

FOR SURFACE PREPARATION B015-000-79-41-PLS-01


AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 1 OF 45

JOB SPECIFICATION
FOR
SURFACE PREPARATION
AND PROTECTIVE COATING

Identification system for OSBL


1 17-04-2018 SM SS SG
pipelines – Tech advisory from VR included

0 23-03-2017 Issued as a job specification SM SS SG

Rev. Prepared Approved


Date Purpose Checked by
No by by

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 2 OF 45

Abbreviations:

AS : Alloy Steel
ASTM : American Society for Testing and Materials
AWWA : American Water Works Association
CS : Carbon Steel
DFT : Dry Film Thickness
GI : Galvanized Iron
ID : Internal Diameter
ISO : International Organization for Standardization
LTCS : Low temperature Carbon Steel
MS : Mild Steel
NB : Nominal Bore
OD : Outside Diameter
OSHA : Occupational Safety and Health Act
RCC : Reinforced Cement Concrete
RH : Relative humidity
SS : Stainless Steel
SOR : Schedule of Rate
SSPC : Steel Structure Painting Council
WFT : Wet Film Thickness
NA : Not applicable

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 3 OF 45

Sl. CONTENTS PAGE


No. NO.
1.0 General 4
2.0 Scope 4
3.0 Reference codes & standards 6
4.0 Equipment 7
5.0 Surface preparation, shop primer, coating application, repair 7
and documentation
6.0 Paint materials 16
7.0 Coating systems 23
8.0 Storage 38
9.0 Colour code 39
10.0 Identification of vessels, piping 39
11.0 Painting for civil defense requirements 39
12.0 Quality control, inspection and testing 39
13.0 Guarantee 41
14.0 Qualification criteria of painting CONTRACTOR/sub 41
CONTRACTOR
15.0 Qualification/acceptance criteria of paint coating system 42
16.0 Method of sampling & dispatch for laboratory testing 45

ANNEXURE-1 Identification system for OSBL pipelines


ANNEXURE-2 Colour code for refinery plants

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 4 OF 45

1.0 GENERAL

1.1 This technical specification shall be applicable for the work covered by the contract
and without prejudice to the provisions of various international codes of practice,
standard specifications etc. It is understood that the CONTRACTOR shall carry out
the work in all respects with the best quality of materials and workmanship and in
accordance with the best engineering practice and instructions of Engineer-In-
Charge.

1.2 Wherever it is stated in the specification that a specific material is to be supplied or


a specific work is to be done, it shall be deemed that the same shall be supplied or
carried out by the CONTRACTOR.

Any deviation from this standard without written deviation permit from appropriate
authority will result in rejection of the job.

1.3 This specification covers the requirement for protective coating for new
construction.

2.0 SCOPE

2.1 Scope of work covered in the specification shall include, without being limited to,
the following:

This specification defines the requirements for surface preparation, selection and
application of primers and paints on external surfaces of equipment, vessels,
machinery, piping, ducts, steel structures, external & internal protection of storage
tanks for all services and chimneys, if any. The items listed in the heading of tables
of paint systems are indicative only. However, the CONTRACTOR is fully
responsible for carrying out all the necessary painting, coating and lining job on
external and internal surfaces as per the tender requirement.

2.2 Extent of work

2.2.1 The following surfaces and materials shall require shop, pre-erection and field
painting:

- All un-insulated carbon steel & alloy steel equipment like vessels, columns,
storage tanks, exchangers, parts of boilers etc.

- All un-insulated carbon steel and low alloy plant and related piping, fittings and
valves (including painting of identification marks), furnace ducts and stacks.

- All insulated parts of vessels, boilers, chimneys, stacks, piping and steam piping
and other insulated items present, if any.

- All items contained in a package unit.

- All structural steel work, pipes, structural steel supports, walkways, handrails,
ladders, platforms etc.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 5 OF 45

- Flare lines, external surfaces of MS chimney with or without refractory lining and
internal surfaces of MS chimney without refractory lining.

- Identification of colour bands on all piping, as required, including insulated


aluminium clad, galvanized, SS and nonferrous piping.

- Identification lettering/ numbering on all painted surfaces of equipment/piping


insulated aluminium clad, galvanized, SS and non-ferrous piping.

- Marking / identification signs on painted surfaces of equipment and piping


including hazardous service.

- Supply of all primers, paints and all other materials required for painting (other
than OWNER supplied materials)

- Application of pre-erection/fabrication and shop primer.

- Repair work of damaged pre-erection/ fabrication and shop primer and weld
joints in the field/site before and after erection.

- All CS piping, equipment, storage tanks and internal surfaces of RCC tanks in
ETP plant.

- Quality control, testing and inspection during all stages of work (surface
preparation, application of coating and testing of furnished coating).

2.2.2 The following surfaces and materials shall not require painting in general. However,
if there is any specific requirement by the OWNER, the same shall be painted as
per the relevant specifications:

a. Un-insulated austenitic stainless steel.


b. Plastic and/or plastic coated materials.
c. Non-ferrous materials like aluminum, Cu-Ni alloys, galvanized steel.

In general Galvanized steel doesn’t require painting. However if painting is required


due to OWNERs instructions, contractual or for colour coding requirement then
coating system in Table 4.0 shall be followed.

2.3 Documents

2.3.1 The CONTRACTOR shall perform the work in accordance with the following
documents issued to him for execution of the work.

a. Bill of quantities for piping, equipment, machinery and structures etc.

b. Piping line list.

c. Painting specifications including special civil defense requirements.

2.4 Unless otherwise instructed, final paint coating (i.e. application of field primer,
intermediate and top coats) on pre-erection/ shop primed equipment shall be

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 6 OF 45

applied at site, only after all welding, testing on systems are completed as well as
after completion of steam purging.

2.5 Changes and deviations required for any specific job due to OWNERs requirement
or otherwise shall be referred to EIL for deviation permit.

3.0 REFERENCE CODES & STANDARDS

3.1 Without prejudice to the provision of clause 1.1 above and the detailed
specifications of the contract, latest editions of the following codes and standards
are applicable for the work covered by this contract:

ISO-12944 : Corrosion protection of steel structures by protective


paint system.
ASTM-Vol. 6.01&6.03 : American standard test methods for paints and
coatings.
IS-101 : Methods of sampling and test for paints, varnishes and
related products.
IS-5 : Colours for ready mixed paints and enamels.
RAL DUTCH : International standard for colour shade (Dutch standard).
IS-2379 : Indian standard for pipe line identification-colour code

3.2 Surface preparation standards

The latest editions of any of the following standards shall be followed for surface
preparation:

3.2.1 ISO 8501-1 / SIS-05 59 00: ISO standard for preparation of steel substrates before
application of paints and related products. This standard contains photographs of
the various standards on four different degrees of rusted steel and as such is
preferable for inspection purpose by the Engineer-In-Charge.

3.2.2 Steel Structures Painting Council, U.S.A. (surface preparation specifications


SSPC-SP).

3.2.3 National Association of Corrosion Engineers (NACE), U.S.A.

3.2.4 Various international standards equivalent to Swedish standard for surface


preparations are given in Table-1.

3.3 The CONTRACTOR shall arrange, at his own cost, to keep a set of latest edition of
above mentioned standards and codes at site.

3.4 The paint manufacturers’ instructions shall be followed as far as practicable at all
times for the best results. Particular attention shall be paid to the following:

a. Instructions for storage to avoid exposure as well as extremes of temperature.


b. Surface preparation prior to painting shall be followed as per Table-4 to 13 of
this standard.
c. Mixing and thinning.
d. Application, recommended limit on time intervals in between coats & DFT.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 7 OF 45

4.0 EQUIPMENT

4.1 All tools, brushes, rollers, spray guns, blast material, hand power tools for cleaning,
all equipment, scaffolding materials, shot & grit blasting equipment , air
compressors etc. required shall be suitable for the work and shall be arranged by
the CONTRACTOR in sufficient quantity at the site. The manufacturers test
certificates / data sheets for all the above mentioned items shall be reviewed by
Engineer-In-Charge at site before start of the work.

4.2 Mechanical mixer shall be used for paint mixing operations in case of two pack
systems except in case of specific requirement; the Engineer-In-Charge may allow
the hand mixing of small quantities at his discretion for touch up work only.

5.0 SURFACE PREPARATION, SHOP PRIMER / COATING APPLICATION,


REPAIR AND DOCUMENTATION

5.1 General

5.1.1 Adhesion of the paint film to the surface depends largely on the degree of
cleanliness of the metal surface. Proper surface preparation contributes more to
the success of the paint protective system. In order to achieve the maximum
durability, one or more of the following methods of surface preparation shall be
followed, depending on condition of surface to be painted and as instructed by the
Engineer-In-Charge.

a. Abrasive blast cleaning

b. Mechanical or power tool cleaning

5.1.2 Mill scale, rust, rust scale and foreign matter shall be removed fully to ensure that a
clean and dry surface is obtained. Unless otherwise specified, surface preparation
shall be done as per provisions of relevant tables given elsewhere in this
specification. The minimum acceptable standard, in case of thermally sprayed
metal coatings, in case of mechanical or power tool cleaning shall be St. 3 or
equivalent. In case of blast cleaning, it shall be Sa 2-1/2 as per Swedish standard
SIS-055900 (latest edition) or SSPC-SP or ISO 8501-01.Blast cleaning shall be Sa
3 as per Swedish standard in case of thermally sprayed metal coatings.

Before surface preparation by blast cleaning, the surface shall be degreased by


aromatic solvent to remove all grease, oil etc as per SSPC-SP-1.

5.1.3 Irrespective of whether external or internal surface to be coated, blast cleaning


shall not be performed where dust can contaminate surfaces undergoing such
cleaning or during humid weather conditions having humidity >85%. In case of
internal coating of storage tanks, dehumidifier shall be used to control humidity
level below 60%. Dehumidifier should depress the dew point of air in the enclosed
space, sufficient enough so as to maintain it 3⁰C below the metal substrate
temperature during entire period of blasting and coating application. During the
interval time between application of primer coat and subsequent intermediate and
top coats or between blast cleaning completion and start of application of primer

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 8 OF 45

coat, dehumidifier unit should be in continuous operation to ensure that no


condensation occurs on the substrate.

Dehumidifier should be able to maintain grain drop (moisture removal) at the rate of
25 grains per pound of air per hour. Dehumidifier should have capacity of at least 2
air changes per hour of the enclosed space. All necessary psychometric data
should be collected by the CONTRACTOR for the given site conditions, before
starting operation of dehumidifier, to ensure that desired values of dew point and
moisture content in enclosed space is achieved.

Dehumidification to be maintained round the clock for surface preparation and


painting till the total coating application is over.

Dehumidifier shall not be stopped under any condition till the entire blasted surface
is primed to the satisfaction of the technical representative of the paint
manufacturer. In case the dehumidifier breaks down in middle of the job, the same
shall be replaced at the risk and cost of the CONTRACTOR.

5.1.4 The Engineer in-Charge shall have the right to disallow usage of dehumidifier if the
performance is not meeting the specified requirements. Under such circumstances,
the CONTRACTOR shall remove the equipment and replace the same with
another equipment to provide satisfactory results without any additional cost to the
OWNER.

5.1.5 Irrespective of the method of surface preparation, the first coat of primer must be
applied by airless spray/ air assisted conventional spray, if recommended by the
paint manufacturer, on dry surface. This should be done immediately and in any
case within 4 hours of cleaning of the surface. However, at times of unfavorable
weather conditions, the Engineer-In-Charge shall have the liberty to control the
time period, at his sole discretion and/or to insist on re-cleaning before primer
application is taken up. In general, during unfavorable weather conditions, blasting
and painting shall be avoided as far as practicable.

5.1.6 The external surface of R.C.C. chimney to be painted shall be dry and clean. Any
loose particle of sand, cement, aggregate etc. shall be removed by scrubbing with
soft wire brush. Acid etching with 10-15% HCl solution for about 15 minutes shall
be carried out. The surface must be thoroughly washed with water to remove acid
and loose particles and then dried completely before application of paint.

5.2 Procedure for surface preparation

5.2.1 Air blast cleaning with abrasives

The surfaces shall be blast cleaned using one of the abrasives such as Al2O3
particles, chilled cast iron or steel grit, copper slag or nickel slag at a pressure of
7.0 kg/cm2 and at an appropriate distance & angle depending on nozzle size
maintaining constant velocity and pressure. Chilled cast iron or steel shall be in the
form of shot or grit of size in the range of G16 – G42 conforming to SSPC AB1 and
S250 grade size of steel shots (maximum) to obtain a desired surface profile of
35-50 microns trough to peak. For all other abrasives, size shall be in the range of
G16 – G24. The combination of steel grits and shots shall be normally in the ratio

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 9 OF 45

of 3:1. The quality of abrasives shall be free from contaminants and impurities and
shall meet the requirements of SSPC AB1. The compressed air shall be free from
moisture and oil. The blasting nozzles should be venturi style with tungsten
carbide or boron carbide as the material for liners. Nozzle orifice may vary from
3/16” to 3/4”. On completion of blasting operation, the blasted surface shall be
clean and free from any scale or rust and must show a grey-white metallic luster.
Primer or first coat of paint shall be applied within 4 hours of surface preparation.
Blast cleaning shall not be done outdoors in bad weather without adequate
protection. If there is dew on the metal surface, it shall be cleaned. The surface
profile shall be uniform to provide good adhesion (i.e. 35 to 50 microns) to the
paint. If possible, a vacuum collector shall be installed to collect and recycle the
abrasives.

5.2.2 Mechanical or power tool cleaning

Power tool cleaning shall be done by mechanical striking tools, chipping hammers,
grinding wheels or rotating steel wire- brushes. Excessive burnish of the surface
shall be avoided as it can reduce paint adhesion. On completion of cleaning, the
detached rust, mill scale etc. shall be removed by clean rags and /or washed by
water/steam and thoroughly dried with compressed air jet before application of
paint.

5.3 Non-compatible shop coat primer

For equipment on which application of total protective coating (primer +


intermediate + top coat) is carried out at shop, compatibility of finish coat with
primer should be checked with the paint manufacturer. If the shop coat is in
satisfactory condition showing no major defect upon arrival at site, the shop coat
shall not be removed.

5.4 Shop coated equipment (coated with primer & finishing coat) should not be
repainted unless paint is damaged. Repair shall be carried out as per Table-3 of
paint systems depending upon the compatibility of paint.

5.5 Shop primed equipment and surfaces will only be 'spot cleaned' in damaged areas
by means of power tool brush cleaning or hand tool cleaning and then spot primed
before applying one coat of field primer, unless otherwise specified. If shop primer
is not compatible with field primer, then shop coated primer should be completely
removed before application of selected paint system for a particular environment.
5.6 For package units/equipment, shop primer should be as per the paint system given
in this specification. However, manufacturers’ standard can be followed after
review.
As mentioned in section 2.4, all coating application at field (field primer,
intermediate and top coat) on equipment, structures, piping, etc, shall be carried
out only after its erection and all welding, testing, steam purging (wherever carried
out) have been completed.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 10 OF 45

5.7 Coating procedure and application

All coatings shall be applied by airless spray except for the following special cases,
where application can be carried out by brush subject to suitability of the
application of the paint product by brush.

- Spot repair
- Stripe coating on edges
- Small bore parts not suitable for spray application

Irregular surfaces such as sharp edges, welds, small brackets, and interstices may
stripe coated to ensure specified DFT is achieved. Paint manufacturer
recommendation should be followed before deciding for brush application.

5.7.1 Surface shall not be coated in rain, wind or in an environment where injurious
airborne elements exist, when the steel surface temperature is less than 5 0F
above dew point, when the relative humidity is greater than 85%, when the
temperature is below 40oF and when the ambient/substrate temperature is below
the paint manufacturers recommended temperature of application and curing. De-
humidifier equipment shall be used to control RH and Dew point. The paint
application shall not be done when the wind speed exceeds 20 km per hour.

5.7.2 Blast cleaned surface shall be coated with complete application of primer as soon
as practicable but in no case later than 4 hours the same day.

5.7.3 To the maximum extent practicable, each coat of paint shall be applied as a
continuous film with uniform thickness and free of probes. Any spots or areas
missed in application shall be re-coated and permitted to dry before the next coat is
applied. Applied paint should have the desired wet film thickness.

5.7.4 Each coat shall be in proper state of cure or dryness before the application of
succeeding coat. Material shall be considered dry for re-coating when an additional
coat can be applied without the development of any detrimental film irregularities
such as lifting or loss of adhesion of the under coat. Manufacturer’s instructions
shall be followed for inter coat interval.

5.7.5 When the successive coat of the same colour have been specified, alternate coat
shall be tinted, when practical, sufficiently to produce enough contrast to indicate
the complete coverage of the surface. The tinting material shall be compatible with
the material underneath and shall not be detrimental to its service life and shall be
recommended by the original paint manufacturer.

5.7.6 Airless spray application shall be in accordance with the following procedure:
As per steel structure paint manual Vol.1 & Vol.2 by SSPC, USA. Airless spray
relies on hydraulic pressure rather than air atomization to produce the desired
spray. An air compressor or electric motor, issued to operate a pump to produce
pressures of 1000 to 6000 psi paint, is delivered to the spray gun at this pressure
through a single hose within the gun. A single paint stream is divided into separate
streams, which are forced through a small orifice resulting in atomization of paint
without the use of air. This results in more rapid coverage with less over spray.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 11 OF 45

Airless spray usually is faster, cleaner, more economical and easier to use than
conventional air spray.

Airless spray equipment is mounted on wheels, and paint is aspirated in a hose


that sucks paint from any container, including drums. The unit shall have in-built
agitator that keeps the paint uniformly mixed during the spraying. The unit shall
consist of in-built strainer. Usually, a very small quantity of thinning is required
before spray. In case of high build epoxy coating (two packs), 45:1 pump ratio and
0.020-0.023” tip size will provide a good spray pattern. Ideally, fluid hoses should
not have ID less than 3/8” and not longer than 50 ft. to obtain optimum results.

In case of gun choking, de-choking steps shall be followed immediately.

5.7.7 Brush application of paint shall be in accordance with the following:

a. Brushes shall be of a style and quality that will enable proper application of
paint.

b. Round or oval brushes are most suitable for rivets, bolts, irregular surfaces,
and rough/ pitted steel. Wide flat brushes are suitable for large flat areas but
they shall not have width over 5 inches.

c. Paint shall be applied into all corners.

d. Any runs or sags shall be brushed out.

e. There shall be a minimum of brush marks left in the applied paint.

f. Surfaces not accessible to brushes shall be painted by spray, daubers, or


sheepskin.

5.7.8 For each coat, the painter should know the WFT corresponding to the specified
DFT and standardize the paint application technique to achieve the desired WFT.
This has to be ensured in the qualification trial.

5.8 Drying of coated surfaces

5.8.1 No coat shall be applied until the preceding coat has dried. The material shall be
considered dry for re-coating when another coat can be applied without the
development of any film irregularities such as lifting or loss of adhesion of
undercoats. Drying time of the applied coat should not exceed maximum specified
for it as a first coat. If this exceeds, the paint material has possibly deteriorated or
mixing is faulty.
5.8.2 No paint shall be force dried under conditions which will cause chalking, wrinkling,
blistering formation of pores, or detrimentally affect the conditions of the paint.

5.8.3 No drier shall be added to paint on the job unless specifically called for in the
manufacturers’ specification for the paint.

5.8.4 Paint shall be protected from rain, condensation, contamination, snow and freezing
until dried to the fullest extent practicable.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 12 OF 45

5.9 Spot repair of damaged primer

5.9.1 Where pre-erection/shop primer has been damaged at isolated localized spots
during handling and transportation or after erection / welding, its repair shall be
done as given below and as per the Table-3 of this specification.

5.9.2 Repair of damaged inorganic zinc silicate pre-erection/pre-fabrication/shop primer


(F9) after erection / welding in the design temperature of -90oC to 400oC and
damaged silicone aluminium (F-12) pre-erection/pre-fabrication/shop primer after
erection/welding for design temperature range of 401 – 550 °C.

Surface preparation: Quickly remove the primer from damaged area by mechanical
scraping and emery paper conforming to SSPC-SP-3 to expose the white metal.
Blast clean the surface, if possible. Feather the primed surface, over the intact
adjacent surface surrounding the damaged area, by emery paper.

Primer coating: One coat of F-9 shall be applied wherever damage was observed
on pre-erection / pre fabrication or shop primer of inorganic zinc silicate coating (F-
9). Similarly one coat of F-12 shall be applied wherever damage observed on pre-
erection / pre-fabrication/shop primer of silicone aluminium (F-12).

5.9.3 If damaged areas are found to be extensive and spread over large areas, then
entire pre-erection/pre-fabrication/shop primer shall be removed by blasting to
achieve SSPC-SP-10 and entire blasted surface shall be primed again with F-9 or
F-12, as applicable, for the intended design temperature. (See note of Table-3).

5.10 Paint application

5.10.1 Shop priming/pre-erection priming with F9 or F12 shall be done only on blasted
surface (SSPC-SP-10).

5.10.2 Shop priming / pre-erection priming with F9 or F12 shall be done only with airless
spray or Air assisted pressure pot.

5.10.3 Assessment of painting requirement

The paint system to be applied for a specific job shall be arrived at sequentially as
given below:

- Identify the environment from area classification details and choose the
appropriate table.

- Identify the design temperature from the technical documents.

- Identify the specific field paint system and surface preparation requirement from
the above identified table and temperature range.

- Identify the shop priming requirement from based on compatibility of the above
paint system.
- Identify the need of repair of shop primer and execute as per Table-3.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 13 OF 45

5.11 Documentation / records

5.11.1 A written quality plan with procedure for qualification trials and for the actual work
including test and inspection plan & procedure for approval before start of work.

5.11.2 Daily progress report with details of weather conditions, particular of applications,
no. of coats and type of materials applied, anomalies, progress of work versus
program.

5.11.3 Results of measurement of temperatures, relative humidity, surface profile, film


thickness, holiday detection, adhesion tests with signature of appropriate authority.

5.11.4 Particulars of surface preparation and paint application during trials and during the
work.

5.11.5 Details of non-compliance, rejects and repairs.

5.11.6 Type of testing equipment and calibration.

5.11.7 Code and batch numbers of paint materials used.

The coating applicator must maintain a job record consisting of all the information
as per 5.11.2 -5.11.7 above as well as the approved procedure of work (5.11.1
above). The job record consisting of information in accordance to 5.11.2 – 5.11.7
shall be entered on daily basis and should be daily signed by Engineer-in-charge.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 14 OF 45

TABLE-1: SURFACE PREPARATION STANDARDS

VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
Manual or hand tool
cleaning

Removal of loose rust, St 2 SSPC-SP-2 -


loose mill scale and
1
loose paint, chipping, This method is
scrapping, standing and applied when the
wire brushing. Surface surface is
should have a faint exposed to
metallic sheen. normal
Mechanical or power atmospheric
tool cleaning conditions when
other methods
Removal of loose rust St 3 SSPC-SP-3 - cannot be
loose mill scale and adopted and also
loose paint to degree for spot cleaning
specified by power tool during
2
chipping, de-scaling, maintenance
sanding, wire brushing painting.
and grinding, after
removal of dust,
surface should have a
pronounced metallic
sheen.
Dry abrasive Blast cleaning
3
There are four common grades of blast cleaning:
White metal

Blast cleaning to white Extremely clean


metal cleanliness. surface can be
NACE
3.1 Removal of all visible Sa 3 SSPC-SP-5 expected to have
No.1
rust. Mill scale, paint & prolonged life of
foreign matter 100% paint system.
cleanliness with desired
surface profile.
Near white metal The minimum
requirement for
Blast cleaning to near chemically
white metal cleanliness, resistant paint
SSPC-SP- NACE
3.2 until at least 95% of Sa 2½ systems such as
10 No.2
each element of epoxy, vinyl,
surface area is free of polyurethane
all visible residues with based and
desired surface profile. inorganic zinc

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 15 OF 45

VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
silicate paints.
Also for
conventional paint
systems used
under fairly
corrosive
conditions to
obtain desired life
of paint system.
Commercial Blast For steel required
to be painted with
Blast cleaning until at conventional
least two-third of each paints, for
NACE
3.3 element of surface area Sa 2 SSPC-SP-6 exposure to mildly
No.3
is free of all visible corrosive
residues with desired atmosphere and
surface profile. for longer life of
the paint systems.
Brush-off Blast

Blast cleaning to white


metal cleanliness,
NACE
3.4 removal of all visible Sa 1 SSPC-SP-7 -
No.4
rust, mill scale, paint &
foreign matter. Surface
profile is not so
important.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 16 OF 45

6.0 PAINT MATERIALS

Typical characteristics and codes of various paint materials used in this specification
are as follows.

TABLE-2: PAINT MATERIALS


(Refer to general notes at the end of this section)

DESCRIPTION P-6 P-7 P-4


Epoxy Zinc Cold Galvanizing Etch Primer/Wash
Phosphate Primer product Primer
Technical name

Two component One pack synthetic Two pack polyvinyl


polyamine cured resin based zinc butyral resin medium
epoxy resin medium, galvanizing containing cured with phosphoric
pigmented with zinc min 92% of electrolytic acid solution pigmented
phosphate. zinc dust of 99.95% with zinc tetroxy
Type and purity. chromate.
composition

Volume solids % 49 37 9
Minimum
DFT per coat,
40-50 40-50 8-10
μ
Theoretical
covering capacity 8-10 4m²/kg 8-10
in m2/coat/ litre
Weight per litre in
1.4±0.05 2.67 kg at 15oC 1.2±0.05
Kg/litre
Touch dry at
10 min. 2 hrs.
30oC (max.) 30 min.

Hard dry at
30oC (max.), 8 24 24
hrs
Over-coating
interval, hrs Min. 8 Min. 4 Min. 4-6

Pot life at
30⁰C for two 6-8 NA NA
component
paints, hrs
Adhesion
(ASTM D 4541) >7 NA NA

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 17 OF 45

Temperature
resistance (min)
80 50
⁰C NA
(ASTM D 2485 Dry service Dry service
method B)

TABLE- 2: PAINT MATERIALS (Contd.)

DESCRIPTION F-2 F-3 F-6A/B F-6C


Acrylic Chlorinated Epoxy-High Solvent less
Polyurethane rubber based Build coating epoxy coating
Technical name
finish paint finish paint

Type and Two-pack Single pack F-6A Two- Two pack,


composition aliphatic plasticized Pack Aromatic cured with
isocynate chlorinated polyamine Amine Adduct;
cured acrylic rubber based cured epoxy catalyzed epoxy
finish paint medium with resin medium resin suitably
(free of chemical and suitably pigmented
alkyd/polyeste weather pigmented.
r resins). resistant F-6B:
pigments. polyamide
cured epoxy
resin medium
suitably
pigmented

Volume Solids % 40 36 57 98
Minimum.
DFT per coat, μ
30-40 30-40 100-125 250-500
Theoretical
covering
10-15 11-15 5-6 2-3
capacity in
m2/coat/litre
Weight per liter in
1.15±0.03 1.15±0.03 1.42±0.03 1.40±0.03
Kg/litre
Touch dry at
30 min. 30 min. 3 hrs 3 hrs
30⁰C (max)

Hard dry at 30⁰C 8 8 16 16


(max.), hrs

Full cure at 30⁰C


NA NA 5 days 5 days
(for immersion/ high
temperature service)

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 18 OF 45

Over-coating
Min. Overnight
Interval, hrs Min.12. Min. Overnight Min. 8.
Max. 5 days
Max. 48

Pot life (approx.) at


30⁰C for two 5-8
NA 3-6 0.5
component paints,
hrs
Adhesion
(ASTM D 4541) >5 >4 >7 >8

<300 mg /1000
Abrasion Resistance cycles/CS17
(ASTM D4060) OR NA NA NA
For 1000 g load <100 mg /1000
cycles/CS10

Temperature
resistance (min.) 80 60 80 120, dry service
⁰C Dry service Dry service Dry service 50, immersion
(ASTM D 2485
method B)

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 19 OF 45

TABLE- 2: PAINT MATERIALS (Contd.)

DESCRIPTION F-7 F-8 F-9 (primer) F-11 F-12


Technical name High build coal Self priming Inorganic zinc Heat Heat
tar epoxy type surface silicate resistant resistant
coating. tolerant high Coating synthetic silicone
build epoxy medium Aluminium
coating based two Paint suitable
(complete rust pack up to 540°C
control Aluminium dry temp.
Coating) Paint suitable
up to 250°C
dry temp.

Type & Two pack Two pack A two pack air Heat Single pack
composition polyamide cured epoxy resin drying self resistant silicone resin
epoxy resin based suitable curing solvent synthetic based
blended with pigmented and based medium medium with
coal tar medium, capable of inorganic zinc based two Aluminium
suitably adhering to silicate pack flakes.
pigmented manually coating with Aluminium
prepared minimum 80% paint suitable
surface and old zinc content up to 250°C.
coating. on dry film.
The final cure
of the dry film
shall pass the
MEK rub test
as per ASTM
D4752.
Volume Solids % 62 75 57 35 18
Minimum.
DFT per coat in
100-125 100-125 65-75 15-20 15-20
μ
Theoretical
covering capacity 5.2-6.5 6.0-7.2 8-9 10-12 8-10
in M2/coat/ litre
Weight per liter in
1.40±0.03 1.41±0.03 2.3±0.03 0.95±0.03 1.00±0.03
Kg/litre
Touch dry at 30oC
(maximum), hrs 4 3 0.5 3 0.5
Hard dry at 30oC
(maximum), hrs 48 24 12 12 24

Full cure 30oC (for


immersion /high
5 days 5 days NA NA NA
temperature
service)

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 20 OF 45

Min. 24 hrs Min. 12 hrs


Over-coating interval,
max.5days Min. 10 at 20oC Min. 24 Min. 24
hrs
& 50% RH
Pot life at 30oC for
two component 4-6 1.5 4-6 NA NA
Paints, hrs
Adhesion MPa
(ASTM D 4541) >5 >5 >5 NA NA

Temperature
80 80 400 250 540
resistance⁰ C (min)
Dry service Dry service Dry service Dry service Dry service
(ASTM D 2485
method B)

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 21 OF 45

TABLE- 2: PAINT MATERIALS (Contd.)

DESCRIPTION F-14 F-15 F-16 F-17 F-20


Technical name Polyamine Two- Ambient Novolac epoxy Glass flake
cured coal component temperature phenolic coating reinforced vinyl
tar epoxy Epoxy curing Poly cured with ester coating.
phenolic Siloxane/ inert Polyamine
coating cured polymeric adduct hardener
with coating suitable
Polyamine for under
adduct insulation for CS
hardener and SS.

Type & Specially Two pack Suitable for high Novolac Two component
composition formulated ambient temperature epoxy phenolic glass flake filled
polyamine temperature service and coating cured vinyl ester lining
cured coal curing epoxy under insulation with Polyamine for under
tar epoxy phenolic coating for CS, adduct hardener immersion
suitable for coating alloy steel and services up to
application system SS 90 deg. C.
under suitable for
insulation application
under
insulation
Volume Solids % oCS/SS
Minimum. 67 piping67 58 98 98
DFT per coat
100-125 75-100 75-100 300-450 500-600
in microns
Theoretical
covering 5-8 4-5 7.0- 9.0 6.5 – 8
capacity in 1.6 minimum
M2/coat/ litre
Weight per liter
in Kg/litre 1.45±0.03 1.65±0.03 1.3 1.7 >1.2
(mix paint)
Touch dry at
4 3 1 2
30oC (max) , 2
hrs
Hard dry at
24 24 16 24
30oC (max), hrs 4

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 22 OF 45

Full cure
30oC (for 168 hrs 168 hrs 168 hrs
NA 96 hrs
immersion (7 days) (7 days) (7 days)
/ high temp (4 days )
service)
Over-coating Min. 6 hrs Min. 36 hrs Min.16 hrs Min. 16 hrs Min. 4 hrs
interval Max.5 days Max.21 days Max. Not Max.21 days Max.3 days
applicable

Pot life at 30⁰C,


hrs 4 4-6 1 1
(for two 50 min-1 hr
component
paints)
>7,
Adhesion, MPa >8 : siloxane
(ASTM D 4541) >6 >7 NA: for inert >8 Tensile strength
polymeric matrix >20N/mm2
(ASTM D 638)
Temperature
resistance (min) -45 to 125 -45 to 150
-45 to 150 90
⁰C Under Under 550
Immersion immersion
(ASTM D 2485 insulation & insulation & Under insulation
service service
method B) immersion immersion

General notes for TABLE-2:

1. Covering capacity and DFT achieved per coat depends on method of application.
Covering capacity specified above is theoretical. For estimation of actual quantity of
paints required, include the losses during application. Minimum specified DFT should
be maintained in any case.
2. All primers and finish coats should be ambient temperature curing and air drying unless
otherwise specified.
3. All paints shall be applied in accordance with manufacturer's instructions for surface
preparation, intervals, curing and application. The surface preparation, quality and
workmanship should be ensured. Wherever a deviation is noticed from the specification
in manufacturer data sheet, more stringent one between the data sheet and the
specification shall prevail e.g. if this specification recommends Sa 2 ½ and the
manufacturer data sheet requires Sa3, the surface preparation shall be done as per Sa
3. However in another case if this specification requires the surface preparation of Sa
2 ½ and the manufacturer data sheet recommends only Sa 2 as minimum, the surface
preparation shall be done as per Sa 2 ½.
4. Technical data sheets for all paints shall be supplied at the time of submission of
quotations.
5. Higher specific gravity of F-9 is also acceptable.
6. Internationally recognized & acceptable testing method shall be used for lab testing (for
clause – 15.1) wherever testing standard is not mentioned.
7. Theoretical covering capacity, hard dry, full cure period & over coating interval shall be
as per manufacturer’s data sheets and no testing is required. Slight variation in the

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 23 OF 45

values of these parameters may be permissible with the discretion of engineer-in-


charge.

7.0 COATING SYSTEMS

The coating system should be selected based on the plant location as given below:

Classification based on plant location:

a) Plant located in inland area (more than 50 km from coast).


Environment classification – Industrial

- For offsite areas: Table-5 to be followed.

- For all unit areas including DM, CPP and cooling tower: Table-6 to be
followed.

b) Plant located on sea coast or within 50 km from sea coast.


Environment classification- Industrial marine

- For offsite area, unit areas including DM, CPP, cooling tower etc.: Table-6
to be followed.

c) For external surface of above ground tanks, Table-8 to be followed for all
locations (inland or coastal)

General notes for clause 7.0:

1. Coating systems (primers, finish paints etc.) based on area


classification/environments/applications are tabulated in Table-4 to Table-13

2. Repair of pre-erection/pre-fabrication & shop priming after erection/ welding


shall be done as per Table-3.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 24 OF 45

TABLE-3: REPAIR OF PRE-ERECTION/PRE-FABRICATION OR SHOP PRIMER AFTER


ERECTION/WELDING
(For all un-insulated CS, LTCS & low allow steel items in all environments)

Total DFT
Sl. Design Temp. in Surface Coating
o in Microns Remarks
No. C Preparation System
(min.)
3.1 -90 to 400 SSPC-SP-3 1 coat of F-9 65-75 See Note-1
below and
clause
3.2 401 to 550 SSPC-SP-3 1 coat of F-12 20 5.9.3

Notes for Table-3:

Note-1: The application and repair of pre-erection/pre-fabrication or shop primer given in


above tables shall be done for all the items to be painted. In case the damages of
primer are severe and spread over large area, entire primer shall be removed by
blasting to achieve SSPC-SP-10 and surfaces to be primed again with F-9 or F-12
as applicable.

TABLE-4: COATING SYSTEM FOR GI HAND RAILS & GI ITEMS


(Refer clause 2.2.2)

Design
Sl. Total DFT
Temp. Coating System Remarks
No. in Microns (min.)
in oC
Hot Dip Galvanizing to 80-85
microns (600-610 gm/m2)as per
80 of finish coat
Up to IS 4759, 2629, 4736, 2633 +
4.1 (excluding the thickness -
60 1 coat of P-6 @ 40µ DFT/coat + 1
of galvanizing )
coat of F-2 @ 40 microns
DFT/coat

General notes for Table-4:

1. No galvanized specimen shall have thickness less than 80 microns.


2. Repair of the damaged areas of galvanized coatings due to welding during erection
shall be carried out as per recommended practice IS: 11759, using cold galvanizing
spray process. Organic paint systems are not acceptable for the repair.
3. After repair of damaged galvanized coating by cold galvanization (P-7), the repaired
area shall be top coated with paint system as given in table-4 above (i.e. 1 coat of P-6
@ 40µ DFT/coat + 1 coat of F-2 @ 40µ DFT/coat).
4. Suggested cold galvanizing manufacturers are ZINGA, LOCTITE or Z.R.C.
5. Galvanized gratings don’t require painting in general until otherwise specified
elsewhere or as per the requirement of the OWNER. Ladders, stairways & hand rails
require painting to meet the colour coding requirement of the OWNER. Contractor has
to ensure the applicable colour coding prior to application of coating as per this clause.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 25 OF 45

TABLE-5: COATING SYSTEM FOR NORMAL CORROSIVE AREAS (OFFSITES)


(For all un-insulated above ground CS, LTCS & low allow steel piping, equipment, valves,
vessels & columns etc.)

Surface Coating System Total


Sl. Design Preparation & Final DFT
No Temp. in Pre- in Remarks
. o
C erection/Shop Primer Finish Coat Microns
Primer (min.)
SSPC-SP-10;
1coat of F-9 @
5.1 -45 to -15 - None 65-75 No over-
65-75µ
DFT/coat coating
shall be
1coat of F-6B
SSPC-SP-10; done on
1 coat of @ 100 µ
1coat of F-9 @ F-9
5.2 -16 to 80 P-6 @ 40 DFT/coat+ 1 245-255
65-75µ
µ DFT/coat coat of F-2 @
DFT/coat
40µ DFT/coat
SSPC-SP-10; 2 coats of F-
1coat of F-9 @ 11 @ 20µ
5.3 81 to 250 - 105 F-12 shall
65-75µ DFT/coat
be ambient
DFT/coat (2x20=40)
temperature
SSPC-SP-10; 2 coats of F-
curing type
1coat of F-9 @ 12 @ 20µ
5.4 251 to 400 - 105-115
65-75µ DFT/coat
DFT/coat (2x20=40)
2 coats of F-
SSPC-SP-10; This system
12 @20µ
5.5 >400 1coat of F-12 @ - 60 is suitable
DFT/coat
20µ DFT/coat up to
(2x20=40)
540 ⁰ C

General notes for Table-5:

1. The list of items given in the heading of the above table is not exhaustive. There may
be more items for a particular contract where these specifications are used. The
CONTRACTOR is fully responsible for completing painting including prefabrication
primer for all the items supplied and fabricated through his scope of work as per
tender document.
2. Flare line within unit or offsite areas shall be coated as per clause 6.3 of Table-6.
3. If the application of pre-erection/pre-fabrication/shop primer has already been
completed, the same shall not be repeated in the field. In case the damages to the
primer coat are severe and are spread over large areas, the Engineer-In-Charge may
decide & advise re-blasting and re-application of the primer coat. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table-3.
4. In case of paint systems as per sl. nos. 5.4 and 5.5, the colour bands shall be applied
over the aluminum paint as per the colour coding requirement for specific service of
the piping.
5. All coating system including surface preparation, primer, intermediate and finish coat
for piping is recommended to be done at field only until otherwise specified.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 26 OF 45

6. For equipment, vessels, columns & valves etc scope of surface preparation,
application of primers to finish coat including repair shall be as per applicable
contractual documents like SOR, MR and PR etc.

TABLE-6: COATING SYSTEM FOR CORROSIVE AREAS (PROCESS UNITS, COOLING


TOWER, DM AND CPP)
(For all un-insulated above ground CS, LTCS & low allow steel piping, equipment, valves,
vessels & columns etc.)

Surface Coating System


Total
Preparation
Design DFT
& Pre-
Sl. Temp. oC in Remarks
erection/Sho
No. Primer Finish Coat Microns
p Primer
(min.)

SSPC-SP-10;
-45 to -15 1coat of F-9
6.1 - - 65-75
@ 65-75µ
DFT/
coat

2 coats of F- a) No over
6B @ 100 µ coating on F-
DFT/coat + 9 is allowed
SSPC-SP-10; 1 coat of 1 coat of F-2
-16 to 80 1coat of F-9 P-6 @ @ 40µ b) F-12 shall
6.2 345-355
@ 65-75µ 40 DFT/coat be ambient
DFT/ µ DFT/ (2x100 + temperature
coat coat 40= 240) curing type

2 coats of F-
SSPC-SP-10;
12 @ 20µ
81 to 400 1coat of F-9
6.3 - DFT/coat 105-115
@ 65-75µ
2x20=40
DFT/
coat
2 coats of F-
SSPC-SP-10; 12 @ 20-
>400 1coat of F-12 This system
6.4 - 25µ 60
@ 20-25µ DFT/coat is suitable up to
DFT/coat (2x20=40) 540 ⁰ C

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 27 OF 45

General notes for TABLE-6:

1. The list of items given in the heading of the above table is not exhaustive. There may
be more items for a particular contract where these specifications are used. The
CONTRACTOR is fully responsible for completing painting including prefabrication
primer for all the items supplied and fabricated as per tender document and scope of
work.
2. If the application of pre-erection/pre-fabrication/shop primer has already been
completed, the same shall not be repeated in the field. In case the damages to the
primer coat are severe and spread over large areas, the Engineer-In-Charge may
decide & advise re-blasting and re-application of the primer coat. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table-3.

3. For external surface of MS chimney with or without refractory lining and for internal
surface without refractory lining, paint system as per 6.3 above shall be followed.

4. For external surface of RCC Chimney, 2 coats of F-6 B@ 100µ DFT/coat to obtain a
total DFT of 200 µ shall be applied after proper surface preparation as per guidelines
in 5.1.6.

5. In case of paint systems as per sl. nos. 6.3 and 6.4, the colour bands shall be applied
over the aluminum paint as per the colour coding requirement for specific service of
piping given in clause 9.0.

6. For piping, equipment, vessels, columns & valves etc, scope of surface preparation,
application of primers to finish coat including repair shall be as per applicable
contractual documents like SOR, MR, and PR etc.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 28 OF 45

TABLE-7: COATING SYSTEMS FOR EFFLUENT TREATMENT PLANT (ETP)

Coating system Total


Sl. Design DFT in
Surface Preparation Finish Remarks
No. Temp. in oC Primer Microns
Coat (min.)
For external surfaces of C.S./M.S. items: screens, walk way bridges, baffles, dual
7.1 media filters, vertical pumps, piping in treated effluent sump, bio sludge pump, screw
pump and pump house, CS tanks, sumps and vessels.
2 coats of
F-6A
@100µ
1 coat of
DFT/coat +
F-9 @ 65-
-14 to 80 SSPS-SP-10 1 coat of 305-315 -
75µ
F-2 @ 40µ
DFT/coat
DFT/coat
(2x100+40
=240)
For internal surfaces of CS/MS Items: bio-sludge sump, filter feed sump, process
7.2 sump, sanitary sump, transfer sump, sludge, slop oil tank, scrapping mechanism in
clarifier.
3 coats of
1 coat of F-6A
F-6A @ 65- @100µ
-14 to 80 SSPS-SP-10 300 Note-1
100µ DFT/coat
DFT/coat. (3x100=30
0)
All R.C.C./concrete surfaces exposed to effluent water / liquid such as tanks,
7.3 structures, drains etc. in process sump, TPI separator (process and oil), aeration tank
and transfer sump etc.
Epoxy
screed
Blast cleaning to lining shall
SSPC-SP guide lines be applied
and acid etching with as per
-14 to 80 Epoxy screed lining 3000
10-15% HCl acid manufactur
followed by thorough er and
water washing. Engineer-
In-Charge
instructions
C.S/M.S dual media filters (internal), chemical dosing tanks(internal) such as di-
7.4
ammonium phosphate (DAP) and urea
1 coat of clear two
component solvent free
vinyl ester primer @
Up to 60 SSPC-SP-10 1100 -
100µ DFT/ Coat + 2
coats of F-20 @ 500µ
DFT/ Coat
Note-1
The paint /coating manufacturers shall provide their quality control test certificate of coating
materials (F-6A) for immersion service of the exposed effluent.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 29 OF 45

TABLE-8: EXTERNAL COATING SYSTEMS FOR UN-INSULATED CARBON


STEEL AND LOW ALLOY STEEL STORAGE TANKS

Coating system Total


Design Surface (Note-1) DFT
Sl. Preparation
Temp. in in Remarks
No. o
C Microns
Primer Finish Coat
(min.)
All external surfaces of shell, wind girders, appurtenances, roof tops of all above ground
8.1 tank including top side of external and internal floating roof and associated external
structural works.
F-6 should
1coat of F-9 @ 2 coats of F-6B @
be suitable
65-75µ DFT/coat 100µ DFT /coat +
SSPC-SP- for
8.1.1 -14 to 80 + 1coat of P-6 @ 1 coat of F-2 @ 345-355
10 occasional
40µ DFT/ coat 40µ DFT/ coat
water
immersion
1 coat of F-15
1 coat of F-15
primer @ 80µ
finish coat @80µ
SSPC-SP- DFT/ coat + 1
8.1.2 81 to 150 DFT/ coat + 1coat 240 -
10 coat of F-15
of F-2 @ 40µ
intermediate coat
DFT/ coat
@ 80µ DFT/coat
For higher
design
2 coats of F-12 105-115 temperatur
@20 µ DFT/ coat es, system
SSPC-SP- 1coat of F-9 @
8.1.3 151 to 400 or or as per
10 65-75µ DFT/coat
1 coat of F-16 @ 8.2.3 of
125 µ DFT / coat 190-200 this table
is
applicable
8.2 External surfaces of bottom plate (soil side) for all storage tanks.

F-7 should
be suitable
3 coats of F-7@ for
SSPC-SP- 1 coat of F-9 @
8.2.1 -14 to 80 100µ DFT/coat 365-375 immersion
10 65-75µ DFT/ coat
(3x100=300) service of
the
products
given
1 coat of F-15
primer @ 80µ
DFT/ coat + 1 1 coat of F-15
SSPC-SP-
8.2.2 81 to 150 coat of F-15 finish coat @ 80µ 240 -
10
intermediate coat DFT/ coat
@ 80µ DFT/coat
(80+80=160)

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 30 OF 45

This
system is
suitable for
SSPC-SP- 1 coat of F-16 @ 1 coat of F-16 @ design
8.2.3 151 to 450 250
10 125 µ DFT/coat 125 µ DFT/coat temperatur
es up to
5500C

8.3 For underside of the bottom plate (in case tank is not lifted during PWHT) (Note- 2)
For CS
SSPC SP-
10
-180 to 650 1 coat of inert 1 coats of inert
8.3.1 (Note-3) For SS polymeric matrix polymeric matrix 250-300 -
SSPC-SP-7 coating @ 125 µ coating @ 125 µ
(15-25µ
surface
profile)

Notes for TABLE-8:

1. All paint coating application including primer for tanks shall be carried out at field after
erection and completion of entire welding.

2. For underside of bottom plate :


a) Painting shall be carried out before laying the bottom plate for tanks with non-Post
Weld Heat Treatment (PWHT).
b) For tanks with PWHT, painting shall be carried out after PWHT.
c) In case tank is not lifted during PWHT then painting shall be applied before laying
the bottom plate, clause no.8.3.1 shall be followed.
3. The temperature range indicated (-180 to 650 deg C) corresponds to the temperature
resistance of coating material i.e. inert polymeric matrix coating.

Caution: PWHT temperature shall not exceed 650oC

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 31 OF 45

TABLE-9: INTERNAL COATING SYSTEMS FOR CARBON STEEL AND LOW ALLOY
STORAGE TANKS

Coating system Total


Design Surface DFT
Sl.
Temp. in Preparation in Remarks
No. o
C Primer Finish Coat Microns
(min.)
Crude oil, ATF, turpentine oil, lubricating oil:
Underside of floating roof, internal surface of cone roof, inside of bottom plate, internal
9.1 surfaces of shell - including wetted and free board height, oil side surfaces of deck
plates, oil side surfaces of pontoons, roof structures, structural steel, ladders and other
CS internals.
1 coat of F-15
intermediate coat
1 coat of F-15
@ 80µ DFT/coat
9.1.1 -14 to 90 SSPC-SP-10 primer @ 80µ 240 -
+ 1 coat of F-15
DFT/ coat
finish coat @ 80µ
DFT/ coat
Petroleum products & intermediates like LDO, HSD, gas oil, feeds of FCC-PC, FCC-
LCO, VGO-HDT, ISOM, DHDT, reformate, DCU, NHT & gasoline, naphtha, isomerate
and kerosene:
9.2 Underside of floating roofs, internal surface of cone roof, inside of bottom plate,
internal surfaces of bare shell for full height, underside of floating roof, oil side
surfaces of deck plates, oil side surfaces of pontoons, support structures and ladders
etc.
1 coat of F-9
@
9.2.1 -14 to 45 SSPC-SP-10 - 65-75 -
65-75 µ
DFT/coat
1 coat of F-15
intermediate coat
1 coat of F-15
@ 80µ DFT/coat
9.2.2 46 to 90 SSPC-SP-10 primer @ 80µ 240 -
+ 1 coat of F-15
DFT/ coat
finish coat @ 80µ
DFT/ coat
Potable, Raw & Fire water
9.3
All internal surfaces, accessories and roof structures of cone and dome roof tanks
2 Coats of F-6A
1 Coat of F-6A
@ 100µ DFT/
9.3.1 -14 to 60 SSPC-SP-10 @ 300 Note-1
Coat
100 µ DFT/coat
(2x100=200)
De-mineralized (DM) water & Condensates etc.:
9.4
All internal surfaces, accessories and roof structures of cone and dome roof tanks.
Single coat
1 Coat of F-6A 2 coats of F-6C @ of F-6C @
9.4.1 -14 to 60 SSPC-SP-10 @ 200µ DFT/ coat 500 400 µ is
100µ DFT/coat (2x200=400) also
acceptable

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 32 OF 45

1 coat of F-15
intermediate coat
1 coat of F-15 @ 80µ DFT/coat
9.4.2 61 to150 SSPC-SP-10 primer @ 80µ + 1 coat of F-15 240 -
DFT/ coat finish coat @ 80µ
DFT/ coat
(80+80=160)
Hydrochloric acid (HCl) 10 %:
9.5
All internal surfaces, accessories and roof structures of cone and dome roof tanks
1 Coat of clear
two component
solvent free 2 Coats of F-20 @
9.5.1 -14 to 60 SSPC-SP-10 1100 -
vinyl ester 500µ DFT/ Coat
primer @ 100µ
DFT/ Coat
Aggressive solvents like hexane, hexene, benzene, xylene and toluene:
9.6
All internal surfaces, accessories and roof structures of cone and dome roof tanks

1 coat of F-9
9.6.1 -14 to 65 SSPC-SP-10 @ 65-75µ DFT/ - 65-75 -
coat

Ethylene glycol tanks:


9.7
Internal shell-full height, bottom plate, underside of roof and all accessories
3 coats of vinyl
chloride co-
9.7.1 All SSPC-SP-10 - polymer @ 225 -
75µ /Coat;
(3x75=225)
9.8 Inside pontoon and inside of double deck of all floating roofs
1 coat of F-8 @ 1 coat of F-8 @
9.8.1 -14 to 80 SSPC-SP-3 200 -
100µ DFT/coat 100µ DFT/coat
Wet slops, amine solutions, sour water , water draw off:
9.9
All internal surfaces, accessories and roof structures of cone and dome roof tanks
1 coat of F-15
intermediate coat
1 coat of F-15 @ 80µ DFT/coat
9.9.1 -14 to 90 SSPC-SP-10 primer @ 80µ + 1 coat of F-15 240 -
DFT/ coat finish coat @ 80µ
DFT/ coat
(80+80=160)
Vacuum residue, fuel oil , dry slop, bitumen and other high temperature hydrocarbon
liquids:
9.10 Underside of floating roof, internal surface of cone roof, bottom plate, inside of bare
shell- including wetted and non wetted surfaces, oil side surfaces of deck plates,
oil side surfaces of pontoons, roof structures, structural steel and ladders
1 coat of F-17 @
Up to
9.10.1 SSPC-SP-10 375µ DFT/coat 375-425 -
150oC
Alkalis up to 50 % concentration:
9.11
All internal surfaces, accessories and roof structures of cone and dome roof tanks

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 33 OF 45

1 coat of F-15 2 Coats of F-6 A


Up to
9.11.1 SSPC-SP-10 primer @ 80µ @ 100µ DFT/coat 280 -
60oC
DFT/ coat (2x100=200)

Notes for TABLE-9:

1. F-6 A shall be suitable for drinking water service and should have competent authority
certification.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 34 OF 45

TABLE-10: COATING SYSTEMS FOR EXTERNAL SIDE OF UNDERGROUND CARBON


STEEL PLANT PIPING AND VESSLES

Surface Coating system Total


Preparation
Design DFT
Sl. & Surface
Temp. in in Remarks
No. o Shop Preparation & Finish Coat
C Microns
Primer Primer (min.)
10.1 Underground carbon steel plant piping
3layer
As per
polyethylene
document
(3LPE) coating as
10.1.1 25 to 75 - B016/B015- -- --
per document
000-79-41-
B016/B015-000-79-
PLS-04
41-PLS-04

SSPC-SP-10;
1 coat of F-17 @
10.1.2 76 to 150 - 1 coat of F-17 800 -
400 DFT/coat
primer @400 µ
DFT/ coat
This
SSPC-SP-10; system is
1 coat of F-16
10.1.3 151 to 450 - 1 coat of F-16 250 suitable
@125µ DFT/ coat
primer @ 125µ up to
DFT/ coat 5500C
10.2 External side of un-insulated underground storage vessels
SSPC-SP
-10;
1 coat of 3 coats of F-7 @
10.2.1 -40 to 80 - 365-375 -
F-9 @ 100µ DFT/coat
65-75µ DFT/
coat

1 coat of F-17
SSPC-SP 1 coat of F-17
10.2.2 81 to 150 primer @400 µ 800 -
-10 @400µ DFT/ coat
DFT/ coat

SSPC-SP
This
-10;
1 coat of F-16 system is
1 coat of
10.2.3 151 to 450 - finish coat @125µ 250 suitable
F-16 @
DFT/ coat up to
125µ DFT/
5500C
coat

Notes for TABLE-10:

1 For underground vessels, scope of surface preparation, application of primers to finish coat
including repair shall be as per applicable contractual documents like SOR, MR, PR etc.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 35 OF 45

TABLE-11: COATING SYSTEMS FOR UNDER INSULATION (ALL UNIT AREAS &
OFFSITES)
(For insulated piping, equipment, storage vessels, tanks, columns etc. of carbon steel, LTCS,
alloy steel & stainless steels in all environments.)

Surface Coating system Total DFT


Sl. Design Preparation & Remarks
Microns
No. Temp. o C Pre-erection/Shop Primer Finish paint
(min.)
Primer
Carbon steel, LTCS and Low alloy steel Piping, Storage tanks, Vessels,
11.1
Equipments etc

2 coats of
SSPC-SP-10;
F-15 @75µ
11.1.1 -45 to 125 1coat of F-15 @ None 225
DFT/coat
75µ DFT/coat

This
system is
2 coats of suitable
SSPC-SP-10;
126 to 450 F-12 @20µ
11.1.2 1 coat of F-12 None 60 up to
(CS) DFT/coat 540 0 C
@20µ DFT/coat
for low
alloy
steels
11.2 Stainless Steel, Alloy Steel, Alloy-20 Piping, Vessels & Equipments
SSPC-SP-7;
(15-25µ surface 2 coats of
11.2.1 -45 to 125 profile) None F-15 @75µ 225
1 coat of F-15 @75 DFT/coat
µ DFT/coat
SSPC-SP-7;
(15-25µ surface
1 coat of
profile)
11.2.2 126 to 550 None F-16 @125μ 250
1 coat of
DFT/coat
F-16 @125μ
DFT/coat
11.3 Cyclic service of CS, LTCS, SS, & Alloy Steels
SSPC-SP-10 For
CS, LTCS & low
Alloy steel. 2 coats of
-45 to 150 SSPC-SP-7 for F-15 @75µ
11.3.1 None 225
(Note-1) SS; (15-25µ DFT/coat
surface profile)
1 coat of F-15 @75
µ DFT/coat

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 36 OF 45

SSPC-SP-10 for
CS, LTCS & Alloy
steel.
1 coat of Inert
SSPC-SP-7 for SS
polymer matrix
(15-25µ surface (Note-3 &
-180 to 650 coating @ 250
11.3.2 profile) None 4)
(Note-2) 125µ DFT/coat
1 coat of Inert
polymeric matrix
coating @ 125µ
DFT/coat

Notes

1. In case of overlapping of cyclic temperature ranges as mentioned in 11.3.1 and 11.3.2


then clause 11.3.1 shall be followed.
2. The temperature range indicated (-180 to 650 deg C) corresponds to the applicability
of the coating material i.e. inert polymeric matrix coating.
3. Alternatively thermally sprayed aluminium (TSA) coating @ 500μ as per Annexure-1
of 6-79-0020 Rev.0 is acceptable.
4. This coating system is applicable for any other temperature range (-180 to 650 o C) of
CS, SS etc. which are not covered in clauses 11.1 or 11.2.

General notes for TABLE-11:

1. “Cyclic Service” is characterized by rapid or periodical temperature fluctuation or


temperature cycles.
2. The blasting abrasives for SS and alloy steels shall be aluminum oxide or garnet only.
3. For insulated vessels & equipment scope of surface preparation, application of primers
to finish coat including repair shall be as per applicable contractual documents like
SOR , MR, PR etc.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 37 OF 45

TABLE-12: COATING SYSTEM (INTERNAL PROTECTION) FOR CARBON STEEL


COMPONENTS OF COOLERS/CONDENSERS FOR FRESH WATER
SERVICE

Coating System Total


Surface Final
Design
Sl. Preparation & DFT
Temp. in Remarks
No. o Pre-erection/Shop Primer Finish paint in
C
Primer Microns
(min.)
1 coat of F- 2 coats of F-
12.1 Up to 80 SSPC-SP-10 15 @ 80 µ 15 @ 80 80 µ 240 -
DFT/coat DFT/coat
1 coat of
12.2 81 to 140 SSPC-SP-10 --- 1500 -
novolac epoxy

TABLE-13: COATING SYSTEM (INTERNAL PROTECTION) FOR GALVANIZED OR NON


FERROUS OR STAINLESS STEEL/ DUPLEX STAINLESS STEEL
COMPONENTS OF COOLERS/ CONDENSERS FOR FRESH WATER
SERVICE

Coating System Total


Surface
Final
Design Preparation &
Sl. DFT
Temp. in Pre- Remarks
No. o Primer Finish paint in
C erection/Shop
Microns
Primer
(min.)
1 coat of F-15 1 coat of F-15
13.1 Up to 80 Sweep Blasting @ 80µ @ 80µ 160 -
DFT/coat; DFT/coat;
1 coat of
13.2 81 to 140 Sweep Blasting - 1500 -
novolac epoxy

8.0 STORAGE

8.1 All paints and painting materials shall be stored in rooms only which are to be
arranged by CONTRACTOR and approved by Engineer-In-Charge for the purpose.
All necessary precautions shall be taken to prevent fire. The storage building shall
preferably be separate from adjacent building. A signboard bearing the word
“PAINT STORAGE- NO NAKED LIGHT-HIGHLY INFLAMMABLE” shall be clearly
displayed outside. Manufacturers’ recommendation shall be followed for storage of
paint materials.

9.0 COLOUR CODE

As per ANNEXURE-1 (HPCL colour coding) of this document

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 38 OF 45

10.0 IDENTIFICATION OF VESSELS, PIPING ETC.

As per ANNEXURE-1 (HPCL colour coding) of this document

11.0 PAINTING FOR CIVIL DEFENCE REQUIREMENTS

As per HPCL’s requirement and instructions. However for general guidelines, EIL
standard 6-79-0020 may be referred.

12.0 QUALITY CONTROL, INSPECTION AND TESTING

12.1 All painting materials including primers and thinners brought to site by CONTRACTOR
for application shall be procured directly from manufactures as per specifications and
shall be accompanied by manufacturers’ test certificates. Paint formulations without
certificates are not acceptable (see section 14.0 & 15.0).

12.2 The CONTRACTOR must produce test certificate from pre qualified paint
manufacturer for various tests as detailed out in section 15.0 of this document. The
Engineer-In-Charge shall have the right to test wet samples of paint at random for
verifying quality of paint supplied. CONTRACTOR shall arrange to have such tests,
when required by Engineer-in-Charge, performed at his cost at any one of the NABL
accredited laboratories.

Samples for the test will be drawn at random in presence Engineer-In-Charge or his
representations. Following tests to be carried out if called for by Engineer-in-Charge:

- Specific Gravity
- % solids by weight (% zinc content in case of inorganic or organic zinc primer)
- Drying time (touch dry & full curing)
- Adhesion
- Storage stability (pot life)

Test methods for above tests shall be as per relevant ASTM or ISO Standard.

12.3 The painting work shall be subject to inspection by Engineer-In-Charge at all times. In
particular, following stage-wise inspection will be performed and CONTRACTOR shall
offer the work for inspection and approval of every stage before proceeding with the
next stage. The record of inspection shall be maintained in the registers. Stages of
inspection are as follows:

a) Surface preparation
b) Primer application
c) Each coat of paint

Following tests are to be carried out during surface preparation:

- Test for presence of oil/grease and contamination

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 39 OF 45

The steel substrate after degreasing as per SSPC-SP-1 shall be tested as per
following procedure to validate absence of oil and grease contamination:

a) Visual inspection - continue degreasing until all visible signs of contamination are
removed.
b) Conduct a solvent evaporation test by applying several drops or a small splash of
residue-free tri-chloromethane on the suspect area especially pitting, crevice
corrosion areas or depressed areas. An evaporation ring formation is indicative of
oil and grease contamination. Continue degreasing and inspection till test is
passed.

- Tests for surface finish of blasted surface shall be done by visual inspection
using SSPC-VIS1. Clear cellophane tape test as per ISO 8502-3 shall be used
to confirm absence of dust on blasted surface. Checks shall be done on each
component at least once per 200 m2 of blasted surface and a minimum of 3
checks per shift.

- Test for presence of soluble salt as per method ISO 8502-9. Maximum allowable
salt content shall be considered 20 mg/m2.Checks shall be done on each
component at least once per 200 m2 of blasted surface and minimum of 3
checks per shift. In case salt exceeds specified limit, the contaminated surface
shall be cleaned by method as per Annexure-C of IS 12944-4 (water cleaning).
After cleaning, surface shall be retested for salt after drying.

- Blast profile measurement – This shall be done as described in sec 6.2 of


Annexure-I of 6-79-0020 Rev 0 (Specification for thermally sprayed Aluminium).

- Test for blasting Media and Blasting air- this shall be done as described in sec
6.6 of Annexure-I of 6-79-0020 Rev 0 (Specification for thermally sprayed
Aluminium).

In addition to above, record should include type of shop primer already applied on
equipment e.g. zinc silicate or zinc rich epoxy or zinc phosphate. Any defect noticed
during the various stages of inspection shall be rectified by the CONTRACTOR to the
entire satisfaction of Engineer-In-Charge before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, CONTRACTOR shall
be responsible for rectifying any defects found during final inspection/guarantee
period/defect liability period as defined in general conditions of the contract. Dry film
thickness (DFT) shall be checked and recorded after application of each coat and
extra coat of paint should be applied to make-up the DFT specified without any extra
cost to OWNER, the extra coat should have prior approval of Engineer-in-charge.

12.4 Primer Application

After surface preparation, the primer should be applied to cover the crevices, corners,
sharp edges etc. in the presence of inspector nominated by Engineer-In-Charge. The
shades of successive coats should be slightly different in colour in order to ensure
application of individual coats, the thickness of each coat and complete coverage
should be checked as per provision of this specification. This should be approved by
Engineer-In-Charge before application of successive coats.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 40 OF 45

The CONTRACTOR shall provide standard thickness measurement instrument with


appropriate range(s) for measuring dry film thickness of each coat, surface profile
gauge for checking of surface profile in case of sand blasting, holiday detectors and
pinhole detector and protector whenever required for checking in case of immersion
conditions.

Prior to application of paints on surfaces of chimneys, the thickness of the individual


coat shall be checked by application of each coat of same paint on MS test panel. The
thickness of paint on test panels shall be determined by using gauge such as 'Elko
meter'. The thickness of each coat shall be checked as per provision of this
specification. This shall be approved by Engineer-In-Charge before application of
paints on surface of chimney.

At the discretion of Engineer-In-Charge, the paint manufacturer must provide the


expert technical service at site as and when required. This service should be free of
cost and without any obligation to the OWNER, as it would be in the interest of the
manufacturer to ensure that both surface preparation and application are carried out
as per their recommendations. The CONTRACTOR is responsible to arrange the
same.

12.9 Final inspection of finished coating shall consist of the following:

1) Coating dry film thickness check: DFT measurement shall be as per ISO 2808.
Type II electromagnetic gauges should be used for ferrous substrates. DFT gauge
calibration, number of measurement shall be as per SSPC-DA-2. Measured DFT
shall be within + 10% of the dry film thickness, specified in the specifications.

2) Adhesion testing: Adhesion of the primer to the steel substrate and inter-coat
adhesion of the subsequent coat(s) after curing for at least a week after application
of the topcoat shall be examined by a knife test in accordance with ASTM D6677.
For the knife test, if the rating is better than 8, the adhesion is considered
acceptable. The adhesion is destructive and tested areas shall be repaired
afterward using the spot repair procedure. Alternatively, the applicator may perform
the adhesion test on a steel panel coated using the same surface preparation and
coating application procedure as the work piece. Adhesion testing shall be carried
out for each component at least once per 200 m2 of coated surface.
3) Holiday detection check: Holiday testing shall be conducted in accordance with
NACE SP0188. For immersion services, 100% of coated area shall be inspected
for holidays. For atmospheric exposure, 10% of coated area which must include
weld seams, corners and edges to be holiday tested. Voltage at which test is to be
carried out will depend upon DFT of coating being tested and shall be as per NACE
SP0188. Any holiday is unacceptable and should be marked and repaired
immediately.

The CONTRACTOR shall arrange for spot checking of paint materials for specific
gravity, glow time (ford cup) and spreading rate.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 41 OF 45

12.11 Final Inspection of coating system

A final inspection shall be conducted prior to the acceptance of the work. The
coating CONTRACTOR and the facility OWNER shall both be present and they shall
sign an agreed inspection report. Such reports shall include:
General
- Names of the coating CONTRACTOR and the responsible personnel
- Dates when work was performed

Coating Materials
- Information on coating materials being applied
- Condition of coating materials received

Environmental conditions
- Weather and ambient conditions
- Coating periods

Surface preparation
- Condition of surface before preparation
- Tools and methods used to prepare surface
- Condition of surface after preparation

Coating application
- Equipment used
- Mixing procedure prior to application
- Coating application techniques used

Testing
- Type and calibration of inspection instruments used
- Type of quality control tests performed, and results

13.0 GUARANTEE

The CONTRACTOR shall guarantee that the chemical and physical properties of
paint materials used are in accordance with the specifications contained herein/to be
provided during execution of work.

14.0 QUALIFICATION CRITERIA OF PAINTING CONTRACTOR/SUB-CONTRACTOR

Painting CONTRACTOR who is awarded any job for EIL, Projects under this
standard must have necessary equipment, machinery, tools and tackles for surface
preparation, paint application and inspection. The CONTRACTOR must have
qualified, trained and experienced surface preparator, paint applicator, inspector and
supervisors. The CONTRACTOR supervisor, inspector, surface preparator and paint
applicator must be conversant with the standards referred in this specification.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 42 OF 45

15.0 QUALIFICATION/ACCEPTANCE CRITERIA FOR PAINT COATING SYSTEM

15.1 Pre-qualification of paint coating manufacturer and his products

Paint manufacturer meeting the following requirements shall be considered by the


CONTRACTOR for supply of the paint products.

- Manufacturer should have been in continuous business of paint coating


formulation and manufacturer for at least past 5 years.

- Manufacturer should posses past experience of supplying his products to


hydrocarbon, petrochemical, fertilizer. Chemical processing industry or offshore
platforms in the past 5 years.

- Coating manufacturer should have supplied at least 10000 litre of an individual


product to hydrocarbon, petrochemical, fertilizer. Chemical processing industry
or offshore platforms.

- The manufacturer’s manufacturing procedure & QA/QC system shall meet ISO
9001 requirements and preferably should posses ISO 14000 certificate.

- The Quality control set up should be manned by qualified paint technologists


whose bio data should be sent along with quality control organization chart.

CONTRACTOR shall procure the paint materials from the qualified manufacturer
meeting above requirements and after obtaining prequalification testing approval as
per requirements mentioned in clause 15.2 below.

15.2 Pre-Qualification Testing procedure:

The paint manufacturer engaged by the mechanical contractor shall carry out the
tests in NABL accredited Govt. laboratories like national test house (NTH) as a part
of qualification. Paint manufacturer shall provide the paint samples to laboratory for
testing of the parameters mentioned in Table-2 (typical characteristics) and Table-15
(tests on coating systems) of this specification. The testing laboratory will confirm the
compliance of the paint material with respect to the acceptance criteria mentioned in
the respective tables. Contractor shall furnish these test certificates along with all
necessary supporting documents/information to EIL site for approval/ acceptance.
The paint manufacturer will be qualified and approved by EIL site for supply of paints
after review/assessment of the submissions made by the contractor.

Test certificates which are more than 3 years old will not be considered. Paint
manufacturers are advised to carryout pre-qualification testing accordingly for paints
supply to EIL projects.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 43 OF 45

TABLE-15: PRE-QUALIFICATION TESTING

SYSTEM REFERENCE CLAUSE TOTAL DFT μ


COATING SYSTEM
No. (from table-3 to 12) (min)
1. F-9+P6+F6B+F2 6.2 345
2. F12+F12+F12 6.4 60
3. F15+F15+F15 8.1.2 240
4. F16+F16 8.2.3 250
5. F17 9.10.1 375
6. F8+F8 9.8.1 200
7. F9+F7+F7+F7 8.2.1 365
8. F-20 9.5.1 1100
9. F6A+F6C+F6C 9.4.1 500
10. Inert Polymeric Matrix 8.3.1 250
11. F6A+F6A+F6A 9.3.1 300

FOR
ACCEPTANCE
S. No. TEST SYSTEM DURATION
CRITERIA
NUMBER
Cyclic Test Shall pass.
Salt Spray : 72 hrs. No chalking,
Drying in air : 16 hrs. cracking,
1. UV-A340 nm weather meter: 80 hrs. 1 4200 hrs flaking,
One cycle: 168 hrs. blistering or
(25 cycles at 168 hrs. each cycle) peeling shall be
(ASTM D5894) observed.
2. Chemical Resistance Test (ASTM D543)

2a. 10% & 40% NaOH 1000 hrs

2b. 5% H2SO4 168 hrs


Shall pass.
3,5,8 & 11*
4 weeks No cracking,
2c. Xylene
discoloration,
2d. *H2SO4 4 weeks
Acetone blistering,
solution pH
peeling or
= 5.0 to
4 weeks softening of film
2e. Ethanol 5.5 for
system 11 4 weeks shall be
2f. Kerosene observed.

2g. Sea water 2000 hrs

Immersion in DM/DI water @900 3,5 & 8 30 days No softening,


3.
(ASTM C868) blistering or film
damage.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 44 OF 45

Shall pass.
No chalking,
Resistance to DM water using water cracking,
4. 9 2000 hrs
immersion. (ASTM D870) flaking,
blistering or
peeling.

1 to 11
100% Humidity Test
5. (except 1440 hrs Shall pass
(ASTM D2247)
system-2 )

Shall pass the


test. No peeling,
Dry Heat Resistance Test cracking,
(ASTM D2485 method B at 540⁰ C 2&4 blistering,
6. -
for system 2 and 550⁰ C for system abnormal
4) discoloration or
loss of
adhesion.

2,3,4 & 10

(For
Thermal Shock Resistance Test;
system-2,
5 cycles @ 30 minutes in furnace at
testing to Shall pass
7. 120 ⁰ C and 15 minutes in water after -
be done
quenching in water for each cycle.
after
(ASTM D2485 method A)
heating the
panels at
175°C for
2 hrs.)
Cathodic Disbondment Test
8. 3&5 - Shall pass
(ASTM G42 @60°C)

Each coating product to be qualified shall be identified by the following

1) Specific gravity of Base and curing agent (Ref. ISO 2811)


2) Ash content (ASTM D1650), volatile and non-volatile matters (ISO 3251) of each
component

The identification shall be carried out on the batch, which is used for the Pre-
qualification testing.

15.3 Information to be furnished during delivery of paint materials:

CONTRACTOR along with delivery of paint material has to furnish following


information from paint manufacturer to EIL for acceptance/approval of products:

a) Batch test certificates:

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


SPECIFICATION
Specification No.
FOR SURFACE PREPARATION B015-000-79-41-PLS-01.
AND PROTECTIVE COATING Rev. 1
VRMP HPCL PAGE 45 OF 45

Along with paint products delivery to site from the pre-qualified coating
manufacturer, CONTRACTOR has to produce test certificate (from paint
manufacturer) for each category of product for the following test items. All test
results must mention clearly the batch no. and category of product tested. Tests
to be conducted for following properties:

- Specific Gravity
- % solids by weight (% zinc content in case of inorganic or organic zinc primer)

b) Product information sheet/ technical data sheet for each category of product.

The contractor shall be fully responsible for the quality of the paints products as
per prequalification testing. After the paint materials are supplied to site, the
supplier shall organize random sampling and testing in a NABL laboratory as
per discretion of the Engineer-in-charge. Failing to meet the specified quality
requirements may cause rejection of the paint products.

16.0 METHOD OF SAMPLING & DISPATCH FOR LABORATORY TESTING

(Pre-Qualification tests (sec. 15.2), Batch testing (sec. 15.3) and Inspection testing
(sec. 12.0))

16.1 Samples of coating materials should be submitted to the laboratory in sealed


containers with batch no. and test certificate on regular format of manufacturer’s
testing laboratory.

16.2 All test panels should be prepared by testing laboratory. Surface preparation for a
system shall be done in accordance with this specification. For individual products
testing, minimum shall be Sa 2.5. Colour photographs of test panels should be
taken before and after the test and should be enclosed along with test report.

Sample batch no. and manufacturer’s test certificate should be enclosed along with
the report. Test report must contain details of observation and rusting if any, as per
the testing code.

16.3 Manufacturers should intimate EIL, details of sample submitted for testing, name
of testing agency, date, and contact personnel of the testing agency.

Format No. 8-00-0001-F1 Rev. 0 Copyright EIL – All rights reserved


ANNEXURE-1
IDENTIFICATION SYSTEM FOR OSBL PIPELINES
ANNEXURE-2
COLOUR CODE FOR REFINERY PLANTS
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page :Page 1 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

1.0 OBJECTIVE:

a. To specify the colour code for the Refinery Plant Systems in Onsite & Offsite
areas
b. The objective of colour code is to ensure clear identification of different
process and mechanical systems.

2.0 SCOPE & APPLICABILITY

a. The colour code covers refinery plant mechanical equipment like pipelines,
supports, structurals, pumps, vessels, exchangers, columns, filters, valves,
storage tanks and such mechanical systems.
b. Identification labeling is part of this colour code.
c. This colour code is applicable to all the existing Refinery Plants and systems
in Onsite & Offsite areas.
d. This colour code is limited to the mechanical systems only
e. This colour code system is not applicable to
i) Civil cement masonry based structures
ii) Pipelines buried underground or submerged in water
iii) Internal painting
f. This code does not envisage the specification of paint systems to be used

3.0 BASIS

This colour code is arrived at, after review of the following information and
standards :

a. HPCL-VR existing Colour Code


b. EIL Colour code
c. BP Colour Code.
d. IS-2379: 1990 "Pipelines-Identification Colour Code"
e. DHT Project colour coding.
f. IS-5: 2007 for the purpose of Colour shade definition and identification.

4.0 RESPONSIBILITY

a. Head-Maintenance is responsible to ensure that this colour code is


implemented in the existing Plants & offsite areas
b. Head-Operations is responsible to ensure awareness of this colour code among
the operating personnel in all Plants.
c. Head-Maintenance Offsites is responsible to ensure that the colour code
remains up-to-date in line with the prevailing statutory and OISD provisions.
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page : Page 2 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

5.0 BASE COLOUR & IDENTIFICATION BANDS:

5.1 Pipe lines & Storage tanks:

5.1.1 Base Colour:

For Pipelines & storage tanks, a combination system of "Base Colour &
Identification Banding-Stenciling" is followed.

Base colour shall be applied throughout the entire length & area of un-
insulated pipes, equipment, storage tanks etc.

Base colour coating of minimum 2 meters length shall be applied on the


following:

a) metal cladding for insulated pipelines


b) on the non ferrous & SS pipes and plastic pipelines

Valves (gate/ globe/ diaphragm/butterfly etc.) except control/safety valves,


shall be painted with the same colour as the main pipe line colour.

5.1.2 Colour Bands:

Colour bands are superimposed on the base colour to distinguish:

One kind or condition of a fluid from another kind or condition of the


same fluid
One fluid from another but belonging to the same group

The Base colour may be common to a group of fluids whereas the colour band
is exclusive to the fluid handled in the Pipeline. This approach is adopted only
for Pipelines & Storage tanks.

For the Pipelines, the width of color band shall conform to following:

Nominal Pipe Size Width of the Band in mm


3" NB and below 75
Over 3" NB upto 4" NB Nominal size x 25
Over4"NBuptol2"OD Nominal size x 50/3
Over 14" OD Nominal size x 1 5
Doc. No. DSI-G-1.2
RefDoc DSI-M-1
VISAKH REFINERY Rev. 0
MAINTENANCE DEPARTMENT Date December 2011
Page : Page 3 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

All uninsulated pipe lines having temperatures above 100 deg.C (Heat
resistant aluminium painted) need not be identified with colour bands. As
special case, if required, colour bands may be applied using Teflon tapes.

For insulated pipe lines, the nominal size means the outside diameter of
insulation.

For storage tanks, the color bands (at three locations) shall be a min. of 500
mm width for tanks upto 30 mts. dia and 1000 mm for tanks above 30 mts.
Dia. These bands shall be painted over the entire height of the shell from
bottom prominently at three locations visible from the approach road.

5.1.3 Lettering :

In case of Pipelines, stenciling is additionally carried out in the immediate


vicinity of the identification bands.

For the Pipelines, the size of lettering shall conform to following:

Outside Diameter of Pipe Size of Letter (mm)


or Covering (mm)
20 to 30 10
Above 30 to 50 20
Above 50 to 80 30
Above 80 to 150 40
Above 150 to 250 90
Over 250 110

5.1.4 Marking of Direction of Flow:

Flow direction shall be indicated by arrows or letters painted near valves,


junctions, walls, etc., and at suitable intervals along the pipe, in a manner best
suited to local conditions (refer the fig. below). The arrows shall be painted
black or white in color and in contrast to the color on which they are
superimposed.
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page : Page 4 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

The size of arrow shall be as per the figure mentioned below. Product names
shall be marked at pump inlet, outlet and battery limit in a suitable size

a) 8" dia & below ( fig 6A)


b) above 8" dia size ( fig. 6B)

6A
t
65

s 30 95

For Pipes DN 200 and BeJow


t
20

6B For Pipes Above DN 200

5.1.5 Visibility of Markings:

Attention shall be given to the visibility of color marking and the letterings.
Where the pipelines are located above the normal line of vision of the
operator, the lettering shall be placed below the horizontal line of the pipes, as
shown in Figure below:
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page : Page 5 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

Preferably coloring shall be all around the pipe wherever possible, if not, the
extent of coloring along the circumference is to be such that the colours and
the markings are clearly visible.

The electrical illumination of plant in the night should be such that the shades
of colors are not affected to ensure proper visibility in the night. Wherever
legends and color bands are indicated, their location should be such that they
are easily visible from floor/ground level during day time and extra
illumination should be provided over them for night time or wherever
visibility is poor.

Overhead pipe racks at road crossings shall be painted with zebra markings in
yellow & black colour.

5.1.6 Locations for Marking Colour Bands

Base colour shall be applied throughout length of the piping whereas colour
bands shall be applied at the following locations:

At battery limit points


- At the intersection points and change of direction points in piping ways
Other points such as mid-way of each piping ways, near valves, walls,
either side of culverts/ road crossings
For long stretch yard piping at 50m interval
- At start & terminating points
- Approaches, roads, overhead pipe rack crossings, stair case/monkey
ladders

Flourescent bands on the pipelines are to be provided for night visibility for
the locations such as overhead pipe racks at road crossings, stair cases,
monkey ladders, wherever human interference is possible.

5.2 Equipment:

For equipment, general category items and miscellaneous items, only base
colour is specified. No colour banding is required for this. Refer Table in
Section 6.0 for base colour system for equipment.

Equipment number shall be stenciled in black and white on each vessel, heat
exchanger, columns & machinery, after painting. Size of the letters printed for
such purpose shall be 150 mm high for columns and vessels, 50 mm high for
pump and other machinery.
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page : Page 6 of 12

DEPARTMENTAL STANDING INSTRUCTIONS


COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

6.0 COLOR SHADES

The following colour shades shall be used.

BASE BAND
s. EQUIPMENT
COLOUR
No./shade COLOUR
No. per
No DESCRIPTION SHADE
per IS-5
SHADE
IS-5
(2007) (2007)
A. GENERAL
1. -Technological Structure Phirozi 176
(columns/beams) Blue
-Equipment structural
(columns/beams)
-Technological structure
Platforms, Equipment
Platforms, Walk-ways
-Pipe Supports
-Spring supports
-Monkey ladder rungs
2. -Staircase side channels Light 557
-Monkey ladder side beam/ Orange
Channel/ cage
-Handrails, toe plates, etc.
3 Overhead monorails Signal Red 537

4 Staircase steps Dark Grey 632

5 Chequered plates Dark Grey 632

6 Gratings Galvanised — — __

7 Davit supports Phirozi 176

Blue
B. EQUIPMENT •
1 Heater Aluminium —
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page .-Page 7 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
s. EQUIPMENT
COLOUR
No./shade
COLOUR *% per
No DESCRIPTION SHADE
per IS-5
SHADE S5
(2 0 0?)
(2007)
HC Vessels/ Drums
2 Aluminium ~

3 Chemical drums Golden 356 — —
Yellow
4 Acid drums/tanks Pale cream 352

5 Columns Aluminium

6 Boilers ( Fired utility boilers/ Aluminium


— —
CO boilers
7 Heat exchangers/ coolers/ Aluminium -- —
condenser shells
8 HRSGs Aluminium

9 Flue gas Stack Black


— — —
10 Safety relief valves (PSV/TSV) Satin blue 177
— —~

11 Control valves Red/


— —
Yellow/blue
12 Valves (gate, globe, Same as
diaphragm, butterfly etc) pipeline
base colour
13 Drums Aluminium — "

14 Pumps in HC service Brilliant 221


(operating temp.upto green
lOOdeg.C)
15 Pumps in HC service Aluminium
(operating temp, above
lOOdeg.C)
16 Pumps ( acid/caustic/ Golden 356 — ~—

chemicals) Yellow
17 Pumps (Water) Phirozi 176

--
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT
^vX^ Date : December 20 11
Page : Page 8 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
S. EQUIPMENT No./shade per
COLOUR COLOUR *%
No DESCRIPTION SHADE
per IS-5
SHADE
(2007) (2007)
Blue •1
18 Compressors, blowers, Aluminium
Ventilators, Vent silencers,
ID fan/FD fan
19 Steam turbines Aluminium

20 Motor, Switch gear , Machines Silver grey 628 —

21 Electrical Transformers
mm —



22 Fire proofing Air craft 693
grey

23 Gas turbines Aluminium

24 HC Storage tanks White Same as


(reflective white piping
for high vapour
presure HC
service)
C. PIPELINES
AIR
1 Instrument Air White Black

2 Plant Air White


•i

3 Nitrogen Lemon 355 ~



Yellow
GASES
1 LPG, Fuel Gas, Propylene Aluminium Signal Red 537

2 Hydrogen Lemon 355 Fire Red 536


Yellow

3 Inert Gas / Nitrogen Lemon 355 Phirozi 176


@
Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev .Q
MAINTENANCE DEPARTMENT Dat; '. December 201 1
Page .-Page 9 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
s. EQUIPMENT
COLOUR No./shade ^fo. per
No DESCRIPTION per IS-5 COLOUR tS-5
SHADE SHADE
(2007) [2007;
Yellow Blue

4 Sour Gas, Off Gas Aluminium Gulf Red 473

5 Liquid Sulphur Canary 309 —


--
yellow
6 Acid gas Internationa 592 —

7 Flare gas
1 orange
Aluminium
JH —

— —
WATER
1 Fire Water Signal Red 537

2 Sea Cooling Water Sea Green 217

JH
3 DM water Sky blue 101

4 BFW Sky blue 101 Sea Green 217

5 Condensate Sky blue 101 Canary 309


yellow

Fresh water / Service water Phirozi 176


6
mm
"- -_.

Blue
7 Drinking Water Phirozi 176 Traffic 368
Blue yellow
8 Tempered Water Sky Blue 101 Light 410
Brown

9 Bearing Cooling Water Sky Blue 101 Black



Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page :Page 10 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
S. EQUIPMENT No./shade No. per
COLOUR COLOUR
No DESCRIPTION SHADE
per IS-5 IS-5
SHADE
(2007) (2007)
10 Sour Water/ Wash water Light 410
— —
STEAM
Brown Mi
1 VHP Steam Aluminium Post office 538
red

2 HP Steam Aluminium Light 557


Orange
3 MP Steam Aluminium Dark 796
Violet

4 LP Steam Aluminium Deep Buff 360

ACIDS & CHEMICALS


1 Caustic & Chemicals Golden 356
Yellow

2 Acids Pale cream 352 -- --

HYDROCARBON
r
1 Hydraulic & Lube Oil Light Grey 631 --

2 Cutter Stock Aluminium


•B Opaline —
275
Green

3 Naphtha (HN, SRN, CRN, Aluminium French Blue 166


NGL), MS

4 Kerosene, ATF, MTO Aluminium Lemon 355


Yellow

5 Diesel Oils (LDO, HDO) Aluminium Brilliant 221


Green

6 LGO, HGO, RCO, Circulating Aluminium Sea Green 217


Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page :Page 11 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
S. EQUIPMENT No./shade per
per IS-5 COLOUR £0.
COLOUR
No DESCRIPTION SHADE
(2007) SHADE ^^
Oil, VGO

7 Vac. Resid, Bitumen, Fuel Oil, Aluminium Black


Clarified Oil

8 Slurry, Slop cut, Disulphate Oil Aluminium Light Grey 631

9 Crude, Slop, Fuel Oil Black


•i
10 JBO / Ballast Aluminium
— —
D. MISCELLANEOUS
1 Air Ducts White

2 Air filters White — —

3 Cable Trays (Power) Sky Blue 101

4 Cable trays (Inst.) Brilliant 221


— —
5 Underground CBD routing
Green
Traffic red
•i
570

6 Underground OWS routing Satin Blue 177 --



7 Underground ABD routing Internationa 592 —

1 orange JHL.
8 Underground CRW ETP Light Olive 278 —

9 Emergency Light Fittings


green
Post Office
mam
538

Red

10 General Light fittings Dark Grey 632 ~ —


Doc. No. :DSI-G-1.2
RefDoc : DSI-M-1
VISAKH REFINERY Rev. :0
MAINTENANCE DEPARTMENT Date : December 2011
Page .-Page 12 of 12
DEPARTMENTAL STANDING INSTRUCTIONS
COLOUR CODE FOR REFINERY PLANTS
(MECHANICAL SYSTEMS)

BASE BAND
s. EQUIPMENT
COLOUR
No./shade
COLOUR
No. per
No DESCRIPTION SHADE
per IS-5
SHADE
IS-5
(2007) (2007)

••
Notes:

a) Heat resistant Aluminium shall be applied for piping/equipment as specified in the


table for the services with temperature above 100 deg.C. Poly urethane (PU)
aluminium shall be applied with temperatures below 100 deg.C.

b) The colours indicated in the above table are indicative only. Adherence to the
colours as per IS-5 shall be ensured.

7.0 APPROVAL & REVISION OF THIS GUIDELINE

a. This guideline is controlled by Maintenance department.

b. Head-Maintenance Offsites is responsible for monitoring various relevant OISD


and other statutory standards concerning the required painting frequencies.

c. Based on the information of any such statutory or OISD requirement, revision in


this guideline should be proposed by the Head-Maintenance Offsites and
approval to be obtained.

Sign ^ if '
i>~ Ae,J
Administered Name l~
S Raja <{
by
Designation Head - Maintenance
Sign
fcJU<3tJ<3t^-, a^r_^ —-
Approved by Name V V R Naraslmham
Designation GM - Operations

You might also like