PART 1 GENERAL
1.4 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturers catalogue information. Indicate valve data and ratings.
C. Shop Drawings:
1. Indicate pipe materials used, jointing methods, supports, floor and wall penetration seals.
Indicate installation, layout, weights, mounting and support details, and piping
connections.
2. All shop drawings shall be approved by the Civil Defense
D. Project Record Documents: Record actual locations of components and tag numbering.
E. Operation and Maintenance Data: Include installation instructions and spare parts lists.
F. Maintenance Materials: Furnish the following for Employer/Owner's use in maintenance of
project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Extra Valve Stem Packing: Two for each type and size of valve.
1.7 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
PART 2 PRODUCTS
E. Pipe Passing Through Mechanical, Laundry, and Animal Room Floors above Basement:
1. Galvanized steel pipe or black iron pipe with asphalt coating.
2. Connect sleeve with floor plate except in mechanical rooms.
A. Hangers for Pipe Sizes 15 to 40 mm (1/2 to 1-1/2 inch): Carbon steel, adjustable swivel, split
ring.
B. Hangers for Pipe Sizes 50 mm (2 inches) and Over: Carbon steel, adjustable, clevis.
C. Multiple or Trapeze Hangers: Steel channels with welded spacers and hanger rods.
D. Wall Support for Pipe Sizes to 80 mm (3 inches): Cast iron hook.
E. Wall Support for Pipe Sizes 100 mm (4 inches) and Over: Welded steel bracket and wrought
steel clamp.
F. Vertical Support: Steel riser clamp.
G. Floor Support: Cast iron adjustable pipe saddle, lock nut, nipple, floor flange, and concrete pier
or steel support.
H. Spacing shall be in accordance with NFPA 13 table 9.2.2.1(b) steel pipe except threaded light
wall.
PART 3 EXECUTION
3.1 PREPARATION
A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
B. Remove scale and foreign material, from inside and outside, before assembly.
C. Prepare piping connections to equipment with flanges or unions.
N. When installing more than one piping system material, ensure system components are
compatible and joined to ensure the integrity of the system. Provide necessary joining fittings.
Ensure flanges, union, and couplings for servicing are consistently provided.
3.3 CLEANING
A. Upon completion of work, clean all parts of the installation.
B. Clean equipment, pipes, valves, and fittings of grease, metal cuttings, and sludge that may
have accumulated from the installation and testing of the system.
END OF SECTION