PEA List of Field Test
PEA List of Field Test
PEA List of Field Test
APPENDIX 8
Lists of field tests
(For Turnkey Project)
This document describes the requirements for the field tests of 22 kV & 33 kV indoor switchgears
at site prior to the acceptance. The Contractor shall perform the field tests according to the
following:
Individual tests
1. Switchgear
1.1 Visual inspection (completeness of equipment and accessories, fastening of
individual cubicles, etc.)
1.2 Conformity of assembly with drawings and instructions
1.3 Verification of wiring against drawings and specification
1.4 Construction check
1.5 Circuit-breaker test (see 3. Circuit-breaker)
1.6 Disconnecting and earthing switch test (see 4. Disconnecting sw.)
1.7 CT test (see 5. Current transformer)
1.8 VT test (see 6. Voltage transformer)
1.9 Phase arrangement check
1.10 Main circuit resistance measurement
1.11 Sequence test
1.12 Gas leakage test (GIS only)
1.13 Gas monitoring equipment test (GIS only)
1.14 Moisture content test (GIS only)
1.15 Dew point of SF6 bottles test (GIS only)
1.16 SF6 gas purity test (GIS only), after filling
1.17 Insulation resistance test (5,000 VDC)
1.18 Power frequency withstand test (at 80% of routine test voltage)
1.19 Heater (including heating circuit) test
2. Station service transformer
2.1 Construction check
2.2 Insulation resistance test (5,000 VDC) including polarizing index of winding
2.3 Insulation resistance test of all accessories
2.4 Insulation power factor or loss tangent (δ) test (10 kV AC)
2.5 Ratio test
2.6 Inductance measurement
2.7 DC resistance measurement
2.8 Vector group check
2.9 AC excitation current test
2.10 Oil insulation test
PROVINCIAL ELECTRICITY AUTHORITY
POWER SYSTEM STANDARD DIVISION
22 kV INDOOR SWITCHGEARS
Specification No. M-8/2017 Approved date : 7/7/2548 Rev. No. : 1 Form No. 8.3-5 Page 105 of 132
3. Circuit-breaker
3.1 Construction check
3.2 Vacuum test
3.3 Insulation resistance test (5,000 VDC)
3.4 Insulation resistance test of all accessories
3.5 Contact resistance measurement
3.6 Timing test at rated voltage and minimum voltage close & trip
3.7 Measurement of initial charging time
3.8 Operation test including
(a) Local electrical testing of the closing and tripping of the circuit-breaker including
interlocking operations
(b) Emergency trip test
(c) Position indicator and operation counter test
(d) The number of close and/or open operation
(e) Correctness confirmation of the spring charged indicator to indicate the state
of energy stored in the spring
4. Disconnecting switch and earthing switch
4.1 Construction check
4.2 Insulation resistance test (5,000 VDC)
4.3 Insulation resistance test of all accessories
4.4 Contact resistance measurement
4.5 Operation test
(a) Close & open by manual
(b) Close & open by electrical
4.6 Mechanism (including mechanical interlock) check
4.7 All interlock check
4.8 Operating torque test
5. Current transformer
5.1 Construction check
5.2 Magnetization curve test
5.3 Insulation resistance test (high side 5,000 VDC, low side 500 VDC)
5.4 Ratio test
5.5 Polarity test
PROVINCIAL ELECTRICITY AUTHORITY
POWER SYSTEM STANDARD DIVISION
22 kV INDOOR SWITCHGEARS
Specification No. M-8/2017 Approved date : 7/7/2548 Rev. No. : 1 Form No. 8.3-5 Page 106 of 132
6. Voltage transformer
6.1 Construction check
6.2 Insulation resistance test (high side 5,000 VDC, low side 500 VDC)
6.3 Ratio test
6.4 Polarity test
7. Power fuse
7.1 Construction check
7.2 Operation check
7.3 Insulation resistance test (5,000 VDC)
8. AC & DC boards
8.1 Wiring check
8.2 Metering instrument test including tests of at least as specified elsewhere for relevant
instrument
8.3 AC automatic change over switch operation check (for AC board)
8.4 DC automatic change over switch operation check (for DC board)
8.5 Insulation resistance test (500 VDC)
8.6 Molded case circuit-breaker characteristic test
8.7 Air circuit-breaker function test (if any)
8.9 Operation test
9. Battery charger
9.1 Insulation resistance test (500 VDC)
9.2 Operation test of voltage adjusting range (manual)
9.3 Operation test of load voltage compensator, rated current, etc.
9.4 Operation test of automatic float and boost charge setting
9.5 All alarm test
9.6 AC ripple test
9.7 Metering instrument test including tests of at least as specified elsewhere for relevant
instrument
10. Battery set
10.1 Polarity check of each cell
10.2 Extra charging (0.1 ca according to charge characteristic from manufacturer)
10.3 Voltage, specific gravity and temperature test of each cell at the end of charging
10.4 Discharge characteristic test
PROVINCIAL ELECTRICITY AUTHORITY
POWER SYSTEM STANDARD DIVISION
22 kV INDOOR SWITCHGEARS
Specification No. M-8/2017 Approved date : 7/7/2548 Rev. No. : 1 Form No. 8.3-5 Page 107 of 132
Functional tests
1. Remote manual control for all remote manual functions of each equipment with has this
requirement.
2. Function test (electrical and mechanical) of circuit-breaker, circuit-breaker truck/rack,
earthing switch
3. Proper function of control, measuring and protective equipment including heating and
lighting
4. All protective device functions at service setting test
5. Proper function of all interlocks
6. Sequence operation control of all relay contacts to actuate associated equipment by
mean of secondary or primary injection test.
7. Recloser operations.
8. Protective operation of DC source.
9. Operation of annunciators and alarms.
10. Operation of lamp test circuit.
Final tests
1. Measurement of Insulation Resistance.
Measurement of insulation resistance of the equipment shall be performed by 5,000 V
insulation tester before and after energizing, under the following procedures :
Insulation resistance (phase to phase and phase to ground) of the equipment shall be
measured under the conditions that the 22 kV (or 33 kV) equipment are connected with
the 22 kV (or 33 kV) system. In this case, the 22 kV (or 33 kV) circuit-breakers and
disconnecting switches shall be closed for the test.
2. Energizing test.
After completion of the measurement of insulation resistance mentioned above, AC
energizing test shall be applied by the normal operating voltage of the existing power
system for 24 hours in accordance with the following procedures:
The AC energizing test for 22 kV (or 33 kV) equipment including the station service
transformers shall be performed. Normal operating voltage shall be charged on the
equipment and bus.
During the test, the following shall be recorded or checked
(a) The indicating value of meters mounted on the control panel shall be recorded on the
test record sheet.
(b) The current and voltage magnitude and phasing shall be checked at the relay test
terminals in order to confirm correct connection of all AC secondary circuits.
PROVINCIAL ELECTRICITY AUTHORITY
POWER SYSTEM STANDARD DIVISION
22 kV INDOOR SWITCHGEARS
Specification No. M-8/2017 Approved date : 7/7/2548 Rev. No. : 1 Form No. 8.3-5 Page 110 of 132