Steam Generation Plant
Steam Generation Plant
Steam Generation Plant
TABLE OF CONTENTS
SECTION –VI-D
TECHNICAL SPECIFICATIONS
Two numbers bagasse fired boilers, each of 130 t/hr, 65 bar (g),
510 +/- 5 ˚C shall be procured and installed on turnkey basis
including auxiliaries and ancillaries.
The firing floor of the Boilers shall be at 6.0 m above boiler floor
level. The boilers shall be complete with platform and galleries,
staircases, supporting structures etc at all levels.
Price of spares for 2 years normal operation for the Boiler shall be
quoted separately along with list of spares included.
Commissioning spares shall be included in the scope of supply.
Moisture : 50 – 54 %
Ash : 1.5 – 2.5 %
Gross calorific value : 9.5 – 8.7 MJ/kg
Net calorific value : 7.5 – 6.7 MJ/kg
Pressure
- at main steam stop valve outlet : 65 bar
(g)
Temperature
- Steam at superheater outlet : 510 ± 5
°C - feed water at de-aerator inlet : 80 – 85
°C - feed water at de-aerator outlet : 105 °C
Efficiency : 70 ± 1 %
(based on bagasse fuel of 50 % moisture with GCV at
9.50 MJ/kg and feed water inlet temperature 80 °C
100 % MCR rating)
pH : 7–8
TDS, less than : 20 ppm
Hardness : Nil ppm
Temperature : 75 – 85 °C
Dissolved O2 : 0 – 5 ppm
Silica : Nil ppm
J. P. Mukherji & Associates Pvt. Ltd.
2300-4 Layout
The Boilers shall be suitable for starting with only bagasse and/or
furnace oil. The generation capacities shall be net of steam
requirement for soot blowing and any other local consumption of
the boiler.
The steam and water mixture shall be separated in the steam drum
by centrifugal vortex separators and chevron scrubbers to furnish
high steam purity. The entire boiler block shall be provided with
Carbon steel casing and adequate buck-stays designed to take
care of over and under pressure in the furnace.
Piping, valves, fittings and electrical for all items under the scope
and within Terminal points shall be supplied and erected. Detail
specifications for Piping and Electricals are submitted under
Boilers. The same shall be applicable to other sections such as
Steam distribution pressure reducing and de-superheating; DM
plants etc.
2301 BOILERS
Quantity: 2 Nos.
Bagasse Spreaders
Furnace side wall tubes shall be suitably shaped for providing soot
blowers, furnace air burners, peep holes, access doors and shall
have panel welded at top and bottom for connecting to respective
side wall top and bottom headers.
Grate
Effective grate area shall not be less than 67 m 2 and heat release
rate shall not exceed 2.3 x 106 Kcal/m2/h.
Convection Bank
Super heaters
Attemperator
The firing floor will be of RCC. Height of the firing floor above
ground level shall be minimum 6.0 meters.
Economizer
Economizer shall be installed before the air heater and after boiler
bank. Heating surface of the economizer shall be adequately
designed to give the water outlet temperature of 250 to 260 0C. The
economizer shall have facility to bypass gas and water in order to
raise air temperature at the cost of feed water temperature, during
abnormal conditions. The Economizer header material shall be SA-
106, seamless and the material of tubes shall be grade 360 of BS
3059/ part II having 8 SWG or 4.06 mm thickness. Economizer
tubes shall be seamless.
Air heater
The tube material, for first ten rows facing the entry of cold air, shall
be Corton steel ASTMA – 423, Grade – 1 having Chromium 0.5%
J. P. Mukherji & Associates Pvt. Ltd.
The blow down tanks shall be designed as flash tank. The flash
steam shall be utilized as motive steam for De-aerator. Complete
flash system is included in the scope.
2301-1 Forced Draft (FD) Fan with Variable voltage variable frequency
Drive.
Quantity: 2 Nos.
The fan shall be driven by AC, squirrel cage induction motor with
variable frequency drive. Also Pneumatic actuators for fine
automatic control of draught shall be provided for each fan.
2301-2 Induced Draft (ID) Fan with Variable voltage variable frequency
drive
Quantity: 2 Nos.
Designed flue gas temperature for ID fan shall not be less than 170
0
C for capacity but the material of fan shall be suitable to handle
flue gas at 250 0C temperature.
Quantity: 2 Nos.
Secondary air system shall be suitable for using only bagasse or,
only furnace oil (for 50 % MCR generation) or, mixed fuel firing.
High pressure secondary air/ over fire air shall be injected into the
furnace through heat resistant nozzles mounted in the front and
rear walls of the furnace to create turbulence for complete and
efficient combustion of the volatiles.
a) Super heater
J. P. Mukherji & Associates Pvt. Ltd.
b) Convection bank
c) Economizer
Ducting
Furnace oil shall be the auxiliary fuel to all Boilers. Each boiler shall
generate at 50 % MCR i.e. 65 t./h when operating on furnace oil,
and shall furnish 100 % MCR when bagasse and furnace oil are
being used together.
- Sulphur – 3%
- Calorific value - 40000 kJ/kg
J. P. Mukherji & Associates Pvt. Ltd.
The furnace oil system shall be common to all boiler, the system
shall comprise including but not limited to following
1. Day tank
2. Oil pumps
3. Oil heaters
4. Oil burners
5. Piping
6. Instrumentation
Wet Scrubber
Individual separate system with pumps, tanks and stirrers for each
boiler shall be provided for high and low pressure chemical dosing
system.
a) The set point of boiler to adjust the fuel (bagasse) firing rate
required for maintaining the steam generation.
j) All valves and flow meters within the terminal points shall be
included in the scope of supply. For details refer Drawing No.
2FD-931.
DCS system shall have additional at least 450 Analog I/O ports and
350 Digital I/O ports for power plant utilisation. One PC / Control
desk with one hot stand by for each boiler shall be provided. Two
printers (one working and one standby) shall be provided for
report / records generation. All records such as pressure,
temperature and flow shall be printed at central control room. Field
installed recorders are not required. Two operator’s stations shall
be installed. All communication should be through Ethernet. All
transmitters for field instrumentation shall be smart type with local
indication.
The Supply of electrical shall include all the electric motors for
various drives, Variable voltage and Variable Frequency
Controllers, Motor Control Centres [MCC], Distribution Boards [DB],
Push button stations, Capacitors, Earthing, Power and Control /
Instrumentation cables, cable laying in air on separate structures
and supports with trays, cable termination, Interconnection and
interlocks, earthing of all the electrical equipments installed by the
Contractor. For all motors above 200 kW, soft starters shall be
provided except VFD motors. For all switch gears above 400 A
rating, MCCBs shall be provided and below 400 A, switch fuse units
shall be provided. For switchgear rating above 1000 A, ACBs/VCBs
shall be provided. Bus bars shall be Electrolytic grade copper. All
circuit breakers shall be electrically operated.
J. P. Mukherji & Associates Pvt. Ltd.
Feed water system shall be common, suitable for two boilers, each
of 130 t/hr. Exhaust steam condensates from process and DM
water shall be used as feed water.
Quantity: 1 No.
Quantity: 2 Nos.
J. P. Mukherji & Associates Pvt. Ltd.
Two feed water transfer pumps two operating and two standby shall
be installed below hot wells.
2302-3 De-aerators
Quantity: 2 Nos.
Each De-aerator shall have 225 m3/hr capacity to heat feed water to
specified temperature. De-aerators shall be designed to give 105 0C
water temperature, at de-aerator outlet.
Quantity: 2 Nos.
Quantity: 6 Nos.
Six feed water pumps, four operating and two standby shall be
provided. The pumps shall draw feed water from de-aerated feed
water storage tank and deliver the same to the boiler top drums
through economizer. The pumps should be capable of handling
feed water at a temperature of 105 0C average and 110 0C
maximum. The minimum delivery head of the pump shall be 950
meters of liquid column. Feed water pumps shall be connected to
different power sources/MCC. Hence, turbo feed water pump is not
considered.
Boiler feed water pumps and transfer pumps shall be provided with
motorised discharge valves suitable for operation from control
room.
Quantity: 1 No.
One start up feed water pump shall be installed. This pump shall be
similar to Electrically driven feed pumps except the capacity shall
be 75 m3/hr. Suitable TEFC electrically driven motor and other
fittings to be supplied. The minimum delivery head of the pump
shall be 950 meters of liquid column.
J. P. Mukherji & Associates Pvt. Ltd.
Quantity: 2 Nos.
One HP heater shall be provided for each boiler to heat the feed
water to 160oC. HP heater shall be located in delivery side of the
feed water pumps. The type of heater shall be U tube and shell type
heat exchanger. Heating medium shall be steam at 8 bar-a
pressure.
Quantity: 2 Nos.
- Cation Exchanger
- Anion Exchanger
- Mixed Bed
- Degasification System
- Degasser Air Blower And Degasser Water Pump
- Regeneration Facilities.
- Pressure Gauges
- Level Indicators
- On Line Conductivity Meter
- Water Meter
- Flow Indicator
- pH Indicator Alarm
- Acid Transfer Pump
- Caustic Transfer Pump.
- Effluent water pump on neutralizing pit
- Complete integral piping, cables and instrumentation.
Quantity: 2 Nos.
Quantity: 2 Nos.
Quantity: 1 No.
J. P. Mukherji & Associates Pvt. Ltd.
Steam distribution header to receive the steam from the boiler and
distribute the same to various end users.
All the nozzles with equalizing connection for above headers shall
be included in the scope of supplier. For details refer Drawing No.
2FD-931.
2308 PIPING
Exhaust steam to 1.5/0.3 bar (g) PRV of motive steam for De-
aerator is included completely in Contractors scope.
This piping including 1.5/0.3 bar (g) pressure reducing valve shall
be entirely in the Contractor’s scope
All 21 bar (g) steam pipe line from PRD station 65/21 bar (g) to inlet
of 3.2 MW turbines shall be provided.
The live steam pipe line from steam distribution header to 3.2 MW
turbines shall be provided estimated fixed length of 100 m running
length. For additional piping , rate per meter length to be indicated
by the Contractor.
J. P. Mukherji & Associates Pvt. Ltd.
All blow down piping for blow down lines from boiler to blow down
tanks, shall be in Contractor’s scope of supply.
Raw water
Chemical dosing
All blow down piping for blow down lines from boiler to blow down
tanks, shall be in Contractor’s scope of supply.
Quantity: 1 No.
Quantity: 2 Nos.
J. P. Mukherji & Associates Pvt. Ltd.
Quantity: 1 No.
Mill wet bagasse from last mill is discharged into the bagasse belt
conveyor No. BC 1 installed inline with the mill. This belt conveyor
BC 1, discharges bagasse into main bagasse conveyor BC 2
installed at right angle to milling tandem below the FFL. The
bagasse in turn is being fed to slat type bagasse elevator BE 3,
which will feed the bagasse to SC 1. Alternatively provision is
made in the system to feed wet bagasse directly to the boiler
through SC 1, only in emergency.
EQUIPMENT SPECIFICATION
The main bagasse carrier of double trough design & all steel
construction of 2400 mm width effective & suitable length of approx.
87.5 m to suit boilers. It should be able to carry bagasse about 200
t/hr. driven by suitable TEFC electric motor through helical gearbox
to give linear speed of 25 m/min shall be provided. It shall have
two strands of chain of 200 mm pitch & confirm to IS: 8466-1977.
The conveyor shall complete with feeding chute to boilers etc & will
have arrangement to feed bagasse to the boilers from bottom
portion of the carrier.
Flat belt conveyor No. BC 5, belt width 2200 mm, conveyor length
120 m (approx.) installed overhead horizontal, complete with drive
system, including support structure, platform, railing, staircases,
ladders etc. This conveyor shall be provided with motorised
travelling V-plough or motorised travelling tripper in either direction,
to discharge bagasse to one side or both sides of the flat belt or
directly below to the belt conveyor No. BC 6.
Flat belt conveyor 1 No. BC 6, belt width 2000 mm, conveyor length
60 m (approx.) installed overhead, horizontal, complete with drive
system, including support structure, platform, railing, staircases,
ladders etc. This conveyor shall be provided with motorised
travelling V-plough or motorised travelling tripper in either direction
to discharge bagasse to one side or both the sides of the flat belt.
Goliath type (IS 3177) or any suitable structure & support for
travelling crane, span 60 m x 120 m long (approx.) to flat belt
conveyor No. BC 6 shall be provided along with Railing
arrangement.
Troughed belt conveyor No. BC 10, belt width 2200 mm, conveyor
length 136 m (approx.) installed next to BC 8, complete with drive
system including support structure, platform, railing, staircases,
ladders etc. This belt conveyor will also receive bagasse from BC 9.
i. Aero Conveyor AC 1
Centre distance between head and tail end shafts of the conveyor
shall be 21 meters. Width of the carrier trough shall be suitable to
accommodate 2200 mm rake width and its cross section suitable
for handling bagasse rate at 200 TPH. Trough depth shall be 450
mm on the carrying (stacking) side to accommodate rake height.
J. P. Mukherji & Associates Pvt. Ltd.
All cables shall be copper and installed as cable trays with suitable
clamps, identification etc., either in underground cable trenches or
overhead cable trays.