Additional No of pits
allowances No of pits considered
Average Soil 30% or required as per
resistivity as minimum 10 (minimum) to revised
Sl No Description of Site per report Ohm taken achieve 1 Ohm drawing
1 RNC Chandimandir 22.301 28.991 9 26
2 NNC, Delhi 15.42 20.045 6 36
3 RNC Pune 0.17 10.000 3 26
4 NLDR 15.108 19.641 6 26
Note:
Each transformer and Genset has 2 Neutral and 2 Body Earthpit which itself comes to 20 earthpits
Remarks
Site space just adequate for 26 pits
Site space just adequate for 26 pits
Site space just adequate for 26 pits
Site space just adequate for 26 pits
Note: Calculation does not include strips which will further reduce the resistance.
Actual numbers will depend on the soil resistivity
Note: Calculation does not include strips which will further reduce the resistance.
Actual numbers will depend on the soil resistivity
Note: Calculation does not include strips which will further reduce the resistance.
Actual numbers will depend on the soil resistivity
Note: Calculation does not include strips which will further reduce the resistance.
Actual numbers will depend on the soil resistivity