WEEKLY PLAN 11
Weekly Periode : 12 Maret – 18 Maret 2023
By Engineering Team
Coal Get
A BARAT Match Factor Match Factor 1.4 7,577 ton
EX-45 CAT330 COAL 152 bcm/hr 41 hrs 6,210.68
Hauler BATUBARA 219 bcm/hr 266 hrs 8,312.88
DT-03 CWE280-1 COAL A BARAT STP 4,400 m 21 120 204 20 38 54 30 71% 31 bcm/hr 38 hrs 1,181.56
DT-04 CWE280-1 COAL A BARAT STP 4,400 m 21 120 204 20 38 54 30 71% 31 bcm/hr 38 hrs 1,181.56
DT-05 CWE280-1 COAL A BARAT STP 4,400 m 21 120 204 20 38 54 30 71% 31 bcm/hr 38 hrs 1,181.56
DT-06 FM260 COAL A BARAT STP 4,400 m 21 120 187 20 38 54 30 71% 31 bcm/hr 38 hrs 1,193.25
DT-08 CWE280-2 COAL A BARAT STP 4,400 m 21 120 170 20 38 54 30 71% 32 bcm/hr 37 hrs 1,164.62
DT-10 CWE280-2 COAL A BARAT STP 4,400 m 21 120 170 20 38 54 30 71% 32 bcm/hr 38 hrs 1,205.16
DT-11 CWE280-2 COAL A BARAT STP 4,400 m 21 120 170 20 38 54 30 71% 32 bcm/hr 38 hrs 1,205.16
OB 89,277 bcm
COAL 20,773 ton
SR 4.30
EWH OB 3,386
EWH COAL 674.52 hrs
TOTAL EWH 4060
prod'ty OB 26.37
Prod'ty coal 30.80