Balugaun Kalyan Mandap Final Estimate 05-11-14
Balugaun Kalyan Mandap Final Estimate 05-11-14
Balugaun Kalyan Mandap Final Estimate 05-11-14
Balugaun
Sl.No. Description of items Amount
A Civil work `5,069,842.58
B Internal Electrical work `414,080.00
C P.H. Work `392,640.00
D Total `5,876,562.58
E Add Contigency @ 1% of D `58,765.63
Grand Total `5,935,328.21
Say `5,935,000.00
In word-Rupees Fifty six lakh twelve thousand Only.
ESTIMATE FOR THE CONSTRUCTION OF KALYAN MANDAP AT BALUGAUN
SL ITEM DESCRIPTION
QTY UNIT RATE
NO
1 Single under reamed 300mm Dia pile
foundation upto a depth of 6m with R.C.C. M20
using 12mm size black hard granite (crusher
broken)stone chips including cost of boreholes
but excluding cost of M.S. rod/Tor steel and
labour chrages for cutting, bending and binding
of steel including labour sundries T&P etc 382.91 Rmt `1,116.84
complete and as per direction of engineer -in-
charge.
A Ground floor
i Pile cap 47.24 Cum `5,695.50
Total
AMOUNT
`427,649.20
`7,138.96
`24,521.31
`1,139.80
`7,235.72
`16,596.83
`46,759.83
`12,186.25
`24,174.26
M-20 grade in Column base,
aujja, fin, lintel, stair case, jali ,
minimum compressive strength
r mixing and test conducted in
ver sand for mortar and 10 mm.
ed quality from approved quarry,
ed quality of cement including
watering and curing for 28 days
ng the debrises away from the
s or beads wherever necessary
all materials , cost of all labours,
espect but the excluding cost &
harges for straightening, cutting,
the grills and placing in proper
`269,055.42
`80,622.38
`152,166.10
`9,560.03
`510.84
`1,440.18
`764.00
`10,334.17
`168,204.96
`14,895.44
`977.45
`60.64
`48.51
`34.43
`21,263.79
`16,531.04
`673,099.97
`452,958.84
`37,530.69
`12,913.20
`1,893.55
`19,870.35
`36,726.92
`10,369.42
`58,118.48
`215,343.09
`7,329.68
`10,155.27
`15,457.69
`7,421.10
`141,578.60
`11,513.73
`23,823.41
`22,242.99
`23,791.12
`9,068.49
`11,661.73
`34,985.18
`7,624.98
`1,483.44
`72,421.47
`40,190.05
`91,862.97
`23,076.15
`39,506.64
`1,760.70
`1,111.27
`66.97
`6,633.49
`13,266.98
`2,700.00
`5,400.00
`900.00
`18,807.04
`18,807.04
`5,069,842.58
Sl.
Description of items. Qnty Unit. Rate. Amount
No.
1 Wiring to light points with 1.5 sq. mm. PVC insulated
110 v grade multi standard FR copper conductor wire
for phase, neutral and earth continuity conductor as
loop earth to fittings & fixtures run inside 2mm thick
PVC Conduit pipe surface or recessed in wall /column
etc. of the building including supply of all reqd.
materials such as flush type switch backlite cover
ceiling rose angle holder jn.box etc complete as per
site requirement and direction of the E.I.C.
i. Single light point controlled by one 6 amp. switch 86 Nos. `550.00 `47,300.00
ii. Ceiling Fan point 23 Nos. `632.00 `14,536.00
iii. 05 amps plug points with same board 6 Nos. `150.00 `900.00
iv. Exhaust fan point 8 Nos. `550.00 `4,400.00
2 Wiring for circuit and sub main with following nos.
and sizes of FR PVC insulated 1100 v grade
multistandard copper conductor wire run inside 2 mm
thick non-metallic PVC Conduit pipe as prepaid in the
building as per the direction of E.I.C.
i. 2nos. S.C .2.5 sq. mm copper wire for phase and 200 Mtr.
neutral 01 no. 1.5.sq.mm. copper wire for earth
continuity conductor from F.D.B to S.B at F.F and `120.00 `24,000.00
MDB to S.B at G.F
ii. 02 nos. S.C copper 04.0 sq mm wires for phase, 70 Mtr.
neutral & 01 no 2.5sq.mm S.C. copper wire for earth
continuity conductor from BDB to A.C point (For 02 no `161.00 `11,270.00
of 1.5 ton. Split type A.C)
iii. 04 nos. S.C copper 10.0 sq mm wires for phase, 20 Mtr.
neutral & 01 no 06.0 S.C. copper wire for earth
continuity conductor from MDB(G.F) to FDB (F.F) `550.00 `11,000.00
iii. Supply, fixing and testing of 20 watt CFL lamp with 17 Nos.
angle holder complete as per the site requirements. `300.00 `5,100.00
With o/c, s/c, E/F and 04 no 200 amps bus bar with
E.C strips, Voltmeter, Ammeter ,R-Y-B indicating
lamp with fuse complete as per the site requirements.
Total `409,976.00
Add. CESS @ 1 % `4,099.76
G. Total `414,075.76
Or say Rs. `414,080.00
40mmMake:
dia ASTRAL/ASHIRBAD/SUPREME/EQUIVALENT 40 Mtr `310.50 `12,420.00
25mm dia 11 Mtr `172.80 `1,900.80
20mm dia 15 Mtr `132.40 `1,986.00
15mm dia 10 Mtr `111.30 `1,113.00
Supplying all material, labour , T&P & fitting ,and fixing the
following different water supply fittings of ISI approved
make with ISI mark including supply of all necessary
2 jointing materials etc. all complete as directed by the
Engineer-in-charge Conforming to IS-778
Make :
ASTRAL/ASHRIBAD/SUPREME/EQUIVALENT
i) 50mm dia. Ball Valve 1 Nos `1,620.00 `1,620.00
ii) 40mm dia. Ball Valve 1 Nos `1,040.00 `1,040.00
Supplying all labour ,T&P and cutting holes in bricks or
stone masonry wall in all floors for taking pipes through
3 and mending good the damages with supply of all required
materials etc. complete as per the direction of the Engineer-
in-charge.
For 15mm to 50mm PVC pipe to pass in 125mm to 250mm
`27.70 `387.80
thick wall 14 Each
Supplying all labour ,T&P and cutting holes in RCC chajja or
roof cornice & beams in all floors for taking pipes through
4 and mending good the damages with supply of all required
materials etc. complete as per the direction of the Engineer-
in-charge.
For 15mm to 50mm PVC pipe to pass in 125mm to 250mm
`87.10 `696.80
thick RCC chajja/roof cornice/beams 8 Each
Supplying all materials and labour, T&P for fitting and fixing
white glazed vitreous china ware porcelain wash down
water closet (European pattern water closet 580mm x
440mm x 290mm) of approved make, ISI marked, including
supply of matching 'P' trap to the floor with wooden plug and
chromium plated screws including jointing the trap with soil
5 pipe in cement mortar (1:1) etc. all complete including cost 3 Nos `1,682.90 `5,048.70
of W.C. Pan, PVC seat cover with CP brass hinges &
rubber, buffers etc. all complete including cost, taxes and
conveyance complete as per specification and direction of
Engineer-in-charge. Make : PARRY WARE/NEYCER/CERA
WITH ISI MARK
Supplying all materials and labour, T&P for fitting and fixing
of large standing type (Magnum) white glazed vitreous china
ware flat back, lipped front urinal basin of size (590mm x
390mm x 375mm) confirming to IS and of approved make
along with supply of necessary component parts like supply
of 32mm dia CP dome waste , 15mm CP spreaders
8 including connection from the inside supply pipe, CP pipe of 3 Nos `2,915.00 `8,745.00
15mmx450mm long and all complete as per specification &
direction of the Engineer-in-charge.
Make : PARRY WARE/NEYCER/CERA WITH ISI
MARK
Supplying all materials, labour & T&P for fitting and fixing
125mm dia CP on brass grating on top of floor traps with
9 cement mortar (1:4) all complete as per specification & 5 Nos `52.90 `264.50
direction of Engineer-in-charge.125mm grating
Supplying all materials, labour & T&P for fitting and fixing CP
on brass towel rail 25mm dia x 600mm long of approved
quality with CP on brass brackets including cutting the wall
and making good the damages with cement concrete (1:2:4)
10 with hard granite chips including supply of wooden blocks,
screws etc., all complete as per direction of the Engineer-in-
charge.
Make :
JAQUAR/MARC/EQUIVALENT
25mm x 600mm towel rail 3 Nos `700.00 `2,100.00
Supplying, fitting and fixing of 20mm and above thick white
marble urinal partition plate of size 900mm x 600mm for
separating the standing urinals including cost, conveyance,
11 taxes for all materials, labour, T & P including cutting and
moulding etc. complete as per direction of the EIC.
Make: SINTEX /
EQUIVALENT
Supplying all materials, labour, T&P & fitting and fixing
(600mm x 450mm) size bevelled edge plate glass mirror of
superior glass minimum 6mm thick & of approved make
13 mounted on 6mm thick AC sheet or masonite sheet & fixed
to wooden plugs with CP brass cup screws, washers etc. all
complete including cost, conveyance, taxes of all materials
complete as per specification and direction of the Engineer-
in-charge.
600mmx450mmx6mm size bevelled edge plate glass mirror
`610.10 `6,101.00
10 Nos
Supplying & laying in trenches UPVC rain water pipes&
fittings and specials of the following outside dia for all
classes including jointing with supply of approved solvent
cement by non heat application method including testing as
per standard specification including earthwork in excavation
of trenches in all kinds of soil in required depth & refilling of
15 pipe line trenches in 0.3048 Mtrs or fixing to walls, floors
with supply of necessary clamps, nails, wall plugs etc. all
complete as per direction of Engineer in Charge.
Make :
ORIPLAST/SUPREME/EQUIVALENT
15mm dia CP Bibcock (CP on brass) short body 13 Nos `520.00 `6,760.00
15mm dia angle stop cock (CP on brass) 10 Nos `480.00 `4,800.00
15mm dia concealed stop cock (CP on brass) 2 Nos `600.00 `1,200.00
C.P. Extension pipe 6 Nos `80.00 `480.00
C.P. Towel ring with bracket 4 Nos `494.80 `1,979.20
2/3 rd of
excavated earth 52.94 Cum
5 Providing and Laying plain cement concrete 1: 4: 8 .( 1 cement : 4 sand : 8 stone Agregate
40mm nominal size ) As levelling course in foundation and plinth etc. complete all depth and
height.
Front Verandha
and steps 2.00 12.41 0.83 0.33 6.80
Staircase stpes 0.5 18.00 3.91 0.91 0.50 16.01
0.5 20.00 3.91 0.91 0.50 17.79
Total 40.60 Cft
Or 1.15 Cum
7 Providing anti terminate treatment to bottom and sides of column,pits,walls,trenches
foundation and plinth filling below floors side corners and junction of walls and floors, jambs
and seals of door and windows using chemicals as per approved specifications and instruction
of engineer-in-charge including cost,conveyance,and taxes of all materials,labour etc.complete
(As per IS specification)(Plinth area Ground Floor shall be considered for payments).
8 Providing Fly Ash brick masonry work in Foundation & Plinth with fly ash bricks 25cm x12
cm x8 cm tolerance of ± 2% size bricks having crushing strength not less than 75 kg/cm2 with
cement mortar 1 cement: 6 sands with all necessary projection, splay cutting, circular
moulding, corbelling, etc., including cost of all materials, labour, conveyance, loading ,and
unloadining, taxes, royalties, scaffolding, watering, curing, sundries, tools and plants, etc., as
per the direction of the Engineer-in-charge.
Ground floor
Ground floor
Grid F'(5-5') 1 12.25 0.41 10.00 50.23
Grid 5'(F-F') 1 9.41 0.41 10.00 38.58
Grid 5'(F'-G) 1 4.33 0.41 10.00 17.75
Deduction
D2 1 3.25 0.41 7.00 -9.33
D3 1 2.45 0.41 7.00 -7.03
Total 90.20 Cft
Or 2.55 Cum
Firstfloor
Grid B'(3'-5) 1 4.33 0.41 11.00 19.53
Grid D'(1-1') 1 4.33 0.41 11.00 19.53
Grid C(1-4) 1 20.66 0.41 11.00 93.18
Grid 1' & 3'(A-B') 1 7.33 0.41 11.00 33.06
Grid 7(B'-D) 1 3.50 0.41 11.00 15.79
Deduction
D3 1 2.45 0.41 7.00 -7.03
Total 174.05 Cft
Or 4.93 Cum
11 Providing, lifting, hoisting and laying Reinforced Cement Concrete of M-20 grade in Column
base, Column Footings, Raft Foundation,Stem of the Columns, beams, chaujja, fin, lintel, stair
case, jali , shelves and slab etc as per approved designs and drawings having a minimum
compressive strength ( in work test) 20N. / Square mm. in 15 cm. cubes at 28 days after
mixing and test conducted in accordance with I.S. 456 and I.S. 516 using screened & washed
sharp river sand for mortar and 10 mm. to 20 mm. size black hard crusher broken granite
stone chips of approved quality from approved quarry, washed and cleaned to be mixed in
concrete mixture with approved quality of cement including hoisting, lowering, laying and
compacting concrete by using vibrators, watering and curing for 28 days including, centering
and shuttering then after dismantling and removing the debrises away from the work site and
finishing the exposed surface smooth providing grooves or beads wherever necessary
including cost, conveyance, loading, unloading, royalties and taxes of all materials , cost of all
labours, scaffolding, sundries, T&P required for the work etc. complete in all respect but
the excluding cost & conveyance of M.S. rods or Tor Steel and Binding wires and labour
charges for straightening, cutting, bending etc. of M.S. rods or Tor steel and binding wires
and tying the grills and placing in proper position as directed by the Engineer-in-charge.
(A) Foundation
(i) Pile cap
2 Pile cap 9 7.00 2.33 2.33 342.02
3 Pile cap 4 29.74 2.50 297.36
4 Pile cap 7 7.00 7.00 3.00 1029.00
Total 1668.38 Cft
Or 47.24 Cum
(vi)Staircase
Waist slab 1 10.25 4.00 0.66 27.06
Landing 1 4.00 8.91 0.33 11.76
Total 38.82 Cft
Or 1.10 Cum
(vii) Roof slab
Bride room 1 15.49 16.24 0.41 103.14
1 5.16 16.24 0.41 34.36
Groom room 1 10.41 14.00 0.41 43.71
1 10.24 14.00 0.41 70.66
Mandap area 1 16.83 14.16 0.41 97.71
1 16.66 14.16 0.41 96.72
1 9.66 14.16 0.41 56.08
1 17.08 19.75 0.41 138.31
1 16.66 19.75 0.41 134.90
1 9.66 19.66 0.41 77.87
1 17.08 4.75 0.41 33.26
1 16.66 4.75 0.41 32.45
Total 640.68 Cft
Or 18.14 Cum
Total 45.60 Cum
(D ) Terrace
(i) Column
C1-C3 4 0.83 1.83 8.00 48.60
Total 48.60 Cft
Or 1.38 Cum
Ground floor
(i) Column
C1-C3 2 4.98 8.67 86.35
C4 & C5 6 4.32 8.67 224.73
C3 in resturant 2 2.49 8.67 43.18
Total 354.26 Sft
Or 32.91 Sqm
(ii)Beam
Grid 1 1 26.74 2.65 70.86
Grid 1' 1 5.58 2.65 14.79
Grid 2 1 11.83 2.65 31.35
Grid 3 n 4 2 14.91 2.65 79.02
Grid 4,6,7,8 4 17.83 2.99 213.25
Ground floor
Outside
Grid A'(7-8) 1 10.50 10.00 105.00
Grid B'(6'-7) 1 6.25 10.00 62.50
Grid F &H(4-8) 2 44.33 10.00 886.60
Grid F'(4-5') 2 12.25 10.00 245.00
Grid 4(F-H) 1 15.41 10.00 154.10
Grid 7(A'-B') 1 15.91 10.00 159.10
Grid 8(A'-D) 1 21.83 10.00 218.30
Grid 7'(F-H) 1 13.83 10.00 138.30
Deduction
W1 1.5 5.00 4.50 -33.75
W3 1 3.00 4.50 -13.50
V 0.5 2.00 2.00 -2.00
D2 0.5 3.25 7.00 -11.38
D3 1 2.45 7.00 -17.15
Collapsable gate 0.5 11.83 8.00 -47.32
Total 1843.81 Sft
Or 171.30 Sqm
Ground floor
Inside
Grid A'(7-8) 1 8.91 10.00 128.30
Grid F & H(4-8) 2 42.66 10.00 853.20
Grid 4(A'-B') 1 12.83 10.00 128.30
Grid 4 (F-F') 1 9.16 10.00 91.60
Grid 4 (F'-H) 1 4.33 10.00 128.30
Grid 7&8(A'-D) 2 19.41 10.00 388.20
Grid 7(F-G) 1 13.83 10.00 138.30
Deduction
W1 1.5 5.00 4.50 -33.75
W3 0.5 3.00 4.50 -6.75
V 0.5 2.00 2.00 -2.00
D2 0.5 3.25 7.00 -11.38
Collapsable gate 0.5 11.83 8.00 -47.32
Total 1755.01 Sft
Or 163.05 Sqm
Ground floor
Ground floor
Grid F(4-8) 2 42.66 0.33 28.16
Grid H(4-8) 1 42.66 0.33 14.08
Grid F'(4-5') 2 11.83 0.33 7.81
Grid 5(F-F') 1 9.08 0.33 3.00
Grid 5(F'-G) 1 4.30 0.33 1.42
Grid 5'(F-F') 2 9.08 0.33 5.99
Grid 5'(F'-G) 2 4.33 0.33 2.86
Grid 7'(F-H) 2 13.83 0.33 9.13
Deduction
D2 1 3.25 0.33 -1.07
D3 1 2.45 0.33 -0.81
Front glass window 1 23.41 0.33 -7.73
Total 62.83 Sft
Ground floor
Toilet 1 6.91 4.33 29.92
Kitchen 1 9.08 11.83 107.42
at door portion
D2 2 3.25 0.83 5.40
D3 1 2.45 0.41 1.00
Total 143.74 Sft
Or 13.35 Sqm
First floor
Toilet 2 4.33 6.91 59.84
at door portion 2 2.45 0.41 2.01
Total 61.85 Sft
Or 5.75 Sqm
Total ceramic tile 19.10 Sqm
Ground floor
Kitchen 1 5.25 6.00 31.50
1 5.91 6.00 35.46
1 5.75 6.00 34.50
Toilet 2 6.91 6.00 82.92
2 4.33 6.00 51.96
Deduction
D3 1 2.45 6.00 -14.70
Total 221.64 Sft
Or 20.59 Sqm
First floor
Toilet 2 4.33 6.00 51.96
2 6.91 6.00 82.92
Deduction
D3 2 2.45 6.00 -29.40
Total 105.48 Sft
Or 9.80 Sqm
Total wall tile 30.39 Sqm
20 providing Ultra/euro make tile over 20mm thick bed CM(1:1) to the Prking area rate is
including rubing , cleaning complete as per the direction of enigineer in charge.
Parking area 1 20.75 31.50 653.63
1 33.75 23.00 776.25
1 10.50 18.75 196.88
Total 1626.75 Sft
Or 151.13 Sqm
21 Painting 2 (two) coats with weather coat paint of Johnson & Nicolson/Asian/Berger of
approved quality and colour,using the required quality of paint as specified by the
manufacturer to give an even shade over a coat of cement wash over the finished external
plastered surface including watering the surface before applying and curing for the required
period as directed by the Engineer-in-charge for all floor including cost of all materials with
taxes and transportation all labour scaffoldings,sundries,T&P etc complete.
Ground floor
Quantity same as 12mm outside Item (14) 171.30
Quantity same as 6mm outside Item (13) Chajja projection 8.92
Fin projection 2.94
Total 183.15 Sqm
First floor
Quantity same as 12mm outside Item (14) 256.01
Quantity same as 6mm outside Item (13) Chajja projection 8.92
Fin projection 33.66
Ground floor
quantity same as 12mm inside Item (14) 26.62 Sqm
quantity same as 16mm inside Item (15) 163.05 Sqm
Deduction for wall tile Item (19) -20.59 Sqm
Total 169.07 Sqm
First floor
quantity same as 12mm inside Item (14) 100.56 Sqm
quantity same as 16mm inside Item (15) 256.01 Sqm
Deduction for wall tile Item (19) -9.80 Sqm
Total 346.77 Sqm
23 Priming the plastered and putty surfaces of the walls with water thinnable wall primer of
approved make and finishing the surface smooth by sand papering to receive wall cement
primer in all floor & at all heights including cost, coveyance, loading , unloading ,stacking and
taxes of all Materials, cost of all Labour,Sundries, Staging,Scaffolding, T&P required for the
work etc. complete in all respect as directed by the Engineer- in- charge.
Ground floor
quantity same as 12mm inside Item (14) 26.62
quantity same as 16mm inside Item (15) 163.05
Quantity same as 6mm roof slab Item (13) 210.50
Deduction for wall tile Item (19) -20.59
Total 379.57 Sqm
First floor
quantity same as 12mm inside Item (14) 100.56
quantity same as 16mm inside Item (15) 256.01
Quantity same as 6mm roof slab Item (13) 14.89
Deduction for wall tile Item (19) -9.80
Total 361.66 Sqm
Terrace
quantity same as 16mm inside Item (15) 95.63
Quantity same as 6mm roof slab Item (13) 16.30
Total 111.93 Sqm
Ground floor
quantity same as 12mm inside Item (14) 26.62
quantity same as 16mm inside Item (15) 163.05
Quantity same as 6mm roof slab Item (13) 210.50
Deduction for wall tile Item (19) -20.59
Total 379.57 Sqm
First floor
quantity same as 12mm inside Item (14) 100.56
quantity same as 16mm inside Item (15) 256.01
Quantity same as 6mm roof slab Item (13) 14.89
Deduction for wall tile Item (19) -9.80
Total 361.66 Sqm
25 Providing and fixing in position well dressed, naturally seasoned sal wood rebated frames to
doors including two coats of hot bitumen applied to rear of frame in contact with masonry or
concrete surface fixed with MS hold fast of 40x5mm embedded in cement concrete blocks
15x10x10cm of 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal
size) complete with all materials, labours, T & P including panting two coats of synthetic
enamel paints over a coat of primer both of approved brand and shade to exposed surface
including cost, conveyance, loading, sundries, T&P required for the work etc. complete in all
respect as directed by the Engineer-in-charge
Ground floor
D2 1 0.83 0.42 17.25 5.94
D2 1 0.41 0.21 17.25 1.45
D3 1 0.83 0.13 16.45 1.71
Total 9.10 cft
Or 0.26 Cum
First floor
D1 4 0.83 0.42 17.45 24.04
D3 2 0.25 0.42 16.45 3.41
Total 27.46 cft
Or 0.78 Cum
Terrace
D1 1 0.83 0.42 17.45 6.01 cft
Or 0.17 Cum
Total sal wood 1.21 Cum
Ground floor
V 1 2.00 2.00 4.00 Sft
Or 0.37 Sqm
First floor
V 2 2.00 2.00 8.00
Front glass window 1 23.41 8.00 187.28
Total 195.28 Sft
Or 18.14 Sqm
Total 18.51 Sqm
27 Providing and fixing of 32mm thick ISI marked factory made flush door shutters conforming
to IS 2202 (Part-I) both side commercial of approved make , both faces of shutters finished
with 1mm thick lamination , teak edge leaping to the periphery of shutter with polishing , all
hardwares & fixtures, Sliding door bolt (aldrop) -300 x 16mm ,tower bolt- 260 x 10mm &
handle- 125mm with 175x 32mm plate - 2 no, hinges -125mm x 70mm x 4mm -4 nos , door
stopper etc. complete as per the direction of Engineer in charge.
Ground floor
D2 2 3.25 7.00 45.50 Sft
Or 4.23 Sqm
First floor
D1 4 3.45 7.00 96.60 Sft
Or 8.97 Sqm
Terrace
D1 1 3.45 7.00 24.15 Sft
Or 2.24 Sqm
Total 15.45 Sqm
28 Supplying , fitting and fixing fully glazed aluminium framed sliding windows using with
60micron Powdercoating OEL aluminum section 2082 as out section, 9139 as mullion section,
4124 as a shutter section frame with tappered clip of section 4125, aluminum angle, rubber
beading, friction stay and handle etc. with 6mm 1 side reflective glass as per direction of
Engineer-In-Charge.including cost,conveyance,taxes on all materials.at all floors.
Ground floor
W1 3 5.00 4.50 67.50
W3 2 3.00 4.50 27.00
Total 94.50 Sft
Or 8.78 Sqm
First floor
W1 5 5.00 4.50 112.50
W2 5 4.00 4.50 90.00
W3 1 3.00 4.50 13.50
Total 216.00 Sft
Or 20.07 Sqm
Total 28.85 Sqm
Ground floor
W1 3 5.00 4.50 67.50
W3 2 3.00 4.50 27.00
V 1 2.00 2.00 4.00
Total 98.50 Sft
Or 9.15 Sqm
First floor
W1 5 5.00 4.50 112.50
W2 5 4.00 4.50 90.00
W3 1 3.00 4.50 13.50
V 2 2.00 2.00 8.00
Total 224.00 Sft
Or 20.81 Sqm
Terrace
W3 1 3.00 4.50 13.50 Sft
Or 1.25 Sqm
Total 31.22 Sqm
Or 936.46 Kg
Colapsible gate at
ground floor 1 6.91 8.00 55.28 Sft
Or 5.14 Sqm
Or 251.65 kg
M.S rolling shutter 1 11.83 8.00 94.64 Sft
Or 8.79 Sqm
Or 430.82 kg
Quantity of grill*0.5
Ground floor
W1 33.75
W3 13.50
V 2.00
Colapsible gate at
ground floor 125.82
M.S rolling shutter 4.40
Total 179.47 Sft
Or 16.67 Sqm
First floor
W1 56.25
W2 45.00
W3 6.75
V 4.00
Total 112.00 Sft
Or 10.41 Sqm
Terrace 6.75 Sft
Or 0.63 Sqm
31 Providing and fixing 30mm thick factory made PVC rigid foam paneled door shuttes with
frame manufactured by M/s Rajshri/Krishna or equivalent made from M.S. tube of 19 gauge
thickness, size 19x19mm for styles and 15x15mm for top and bottom rails, covered with heat
moulded PVC “C” channel of 5mm thick sheet and 30x50mm wide to form styles and 5mm
thick and 75mm wide PVC sheets for top rail, lock rail and bottom rail on other side and 5mm
thick, 20mm wide cross PVC sheet as gap insert for top rail and bottom rail, paneling of 5mm
thick PVC sheet fitted in the M.S. frame welded / sealed to the styles and rails with 5x30mm
PVC sheet beading on either side and joined together with solvent cement adhesive etc.,
complete as per manufacturers specification including fixing frames with 3 Nos. alumunium
butt hinges complete including one 10 inch aluminium aldrop and two aluminium tower bolts
of 10 inch and 6 inch and two aluminium handles cost of all materials, conveyance, loading,
unloading, and taxes of all materials, cost of all labour, sundries, T&P required for the work as
per direction of Engineer-in-Charge.complete.
32 Fixing W.I. Clamps to the doors & windows with C.C. 1:3:6 with curing etc. complete.
Ground floor
Door 3 6 18.00
First floor
Door 6 6 36.00
Terrace
Door 1 6 6.00
Total 60 Nos
33 Supplying , fitting and Fixing of Stainless steel of 304 grade in hand railing using 50mm dia of
2mm thick circular pipe with balustrade of size 32mm x 32mm x 2mm @ 0.90 mtr C/C and
stainless steel square pipe bracing of size 32mm x 32mm x 2mm in three rows in staircase as
per approved design and specification , buffing, polishing etc. with cost, conveyance, taxes of
all materials, labour, T&P, etc. required for the complete in all respects.
Ground Floor
Staircase 1 2.00 2.8 5.60 Rm
1ST FLOOR
Staircase 1 2.00 2.80 5.60 Rm
Total 11.20 Rm
34 Grading roof surface at any level for water proofing treatment with Cement Concrete of
proportion (1:2:4)(1 cement : 2 coarse sand : 4 graded stone aggregate ) in top of the roof
surface using 10mm to 20mm nominal size crusher broken H.G Stone chipsl free from
weathered skins , cement and screened & washed sharp river sand for mortar of approved
quality & from approved quarry including hoisting, lowering and laying concrete to the
required level, ramming, watering & curing etc complete to required levels, laid in layers not
exceeeding 15cm thick in each layer including cost, conveyance , loading,unloading,
stacking ,royalties and taxes of all materials, cost of all labour, Sundries, T&P required for the
work etc complete in all respect as directed by the Engineer-in-charge.
Excavation of bore hole (assuming two pits can be constructed per day)
Boring Mistry(Special)
2.00 Nos Each `205.00 `410.00
150 winch operator 0.50 Nos Each `150.00 `75.00
Hire & running charges of Tripod 0.50 Day Perday `450.00 `225.00
Bentonite Powder 2.50 Bag EachBag `291.00 `727.50
Total `1,437.50
Overhead Charges @ 7.5% on total `107.81
a Total `1,545.31
Rcc M20(volume of concrete) 0.88
Rate as per item 8 0.88 cum 1 cum `5,427.00 `4,776.50
add cost of 10% extra cement 0.284 qntl 1qntl `662.50 `188.15
Total `6,509.96
say Rs `6,510.00
Filling the plinth with sand well watered & rammed including cost,conveyance,royality & taxes etc. complete to work
3 site.(for 100 cum)
Labour
Man mulia 12.36 nos @ `150.00 /each `1,854.00
7.5% O.H Charges `139.05
7.5% contracters profit `139.05
Total ( i+ ii+ iii ) `2,132.10 /100 Cum
For 1 cum 2132.1 / `100.00 `21.32
cost of filling sand 1 cum @ `44.00 /cum `44.00
Carraige & Royalty of sand 1 cum @ `367.84 /cum `367.84
C.C (1:4:8) with 4cm size HG Crusher BROKEN metal including all cost, conveyance,royalty & taxes etc.comp.to work site as per
5 specification approved by the department & direction of E.I.C. ( Data for 1 Cum)
a) Materials
4cm size HG metal (H/B) 0.96 cum @ `742.00 /cum `712.32
Sand (screened & washed) 0.48 cum @ `49.00 /cum `23.52
cement 1.72 qntl @ `662.50 /Qntl `1,139.50 `1,875.34
b) Labour
Mason 2nd class 0.18 nos @ `190.00 /each `34.20
Man & Woman mulia(2.5+1.4) 3.90 nos @ `150.00 /each `585.00 `619.20
c) 7.5% O.H Charges (a+b) `187.09
d) 7.5% contracters profit `187.09
e) Conveyance of materials
Metal 0.96 cum @ 635.4 /cum `609.98
Sand 0.48 cum @ 862.9 /cum `414.19
Cement 1.72 qntl @ 186.2 /Qntl `320.26 `1,344.44
f) Royalty
metal 0.96 cum @ 98.784 /cum `94.83
sand 0.48 cum @ 27.44 /cum `13.17 `108.00
Total = (a+b+c+d+e+f) = `4,321.16 / cum
Labour Cess @ 1% `43.21
Total `4,364.38 Cum
6 C.C 1:2:4 with 12mm size hard granite chips
Material
12mm size chips 0.90 cum `1,100.00 `990.00
Course sand 0.45 cum `49.00 `22.05
Cement 3.23 qntl `662.50 `2,139.88
Total `3,151.93
Labour
2nd class mason 0.68 Nos `190.00 `129.20
Mulia 4.60 Nos `150.00 `690.00
Total `819.20
O.H.C & Cp. :- 15.0
`595.67
%
Total `4,566.79
Conveyance
chips 0.90 cum `635.40 `571.86
Royalty of Chips
chips 0.90 cum `98.78 `88.91
Conveyance & Royalty
sand 0.45 cum `890.34 `400.65
cement 3.23 qntl `186.20 `601.43
G.Total `6,229.64
Add for Cess @1% `62.30
`6,291.93
Say: `6,291.93
Brick work with Fly Ash bricks 25cm x 12cm x 8cm size having crusing strength not less then 75Kg/cm2 in cement mortar (1:6) in foundation
8 & plinth per cum.
a) Materials
Brick work with Fly Ash bricks 25cm x 12cm x 8cm size having crusing strength not less then 75Kg/cm2 in cement mortar (1:4) in foundation
10 & plinth per cum.
a) Materials
Fly Ash brick 25cm x 12cm x 8cm 350 nos @ `4.60 / No. `1,610.00
Sharp sand(screened & washed) 0.28 cum @ `49.00 /cum `13.72
cement .672 qntl @ `662.50 /Qntl `445.20 `2,068.92
b) Labour
Meson special 0.35 nos @ `205.00 /each `71.75
Mason 2nd class 1.05 nos @ `190.00 /each `199.50
Man & Woman mulia 2.96 nos @ `150.00 /each `444.00 `715.25
c) 7.5% O.H Charges (a+b) `208.81
d) 7.5% contracters profit `208.81
e) Conveyance of materials
Fly Ash bricks 350 Nos @ `3.21 / No. `1,122.38
Sand 0.28 cum @ `862.90 /cum `241.61
Cement 0.672 qntl @ `186.20 /Qntl `125.13 `1,489.12
f) Royalty
sand 0.28 cum @ `27.44 /cum `7.68
Total = (a+b+c+d+e+f) = `4,698.60 / cum
Labour Cess @ 1% `46.99
Grand Total `4,745.59 / cum
(i) Brick masonary for super structure in G.F with cess `33.33
`4,778.92 / cum
(ii) Brick masonary for super structure in 1st floor & subsequent higher floors add 15% extra labour over
& above the rates of next lower floor `107.29
a) Materials
20mm size HG metal (C/B) 8.10 cum @ `1,058.00 /cum `8,569.80
10mm size HG metal (C/B) 5.40 cum @ `1,120.00 /cum `6,048.00
Sand (screened & washed) 6.75 cum @ `49.00 /cum `330.75
cement 5.21 /MT @ `6,625.00 /MT `34,516.25 `49,464.80
b) Labour
Male 0.86 nos @ `170.00 /each `146.20
Mason 2nd class 1.50 nos @ `190.00 /each `285.00
Man mulia 20.00 nos @ `150.00 /each `3,000.00 `3,431.20
c) Machinary
Concrete mixture 6.00 hour @ `177.00 /hour `1,062.00
Generator 33 KVA 6.00 hour @ `240.00 /hour `1,440.00 `2,502.00
d) 7.5% O.H Charges (a+b+c) `4,154.85
e) 7.5% contracters profit `4,154.85
f) Conveyance of materials
Chips 13.50 cum @ `635.40 /cum `8,577.90
Sand 6.75 cum @ `862.90 /cum `5,824.58
Cement 5.21 /MT @ `186.20 /MT `970.10 `15,372.58
g) Royalty
Chips 13.50 cum @ `98.78 /cum `1,333.58
Sand 6.75 cum @ `27.44 /cum `185.22 `1,518.80
Total = (a+b+c+d+e+f+g) = `80,599.08 / 15cum
Rate per 1 cum ---in GF `80,599.08 / `5,373.27
Labour Cess @ 1% `53.73
Total `5,427.00 Cum
* For 1st floor add15% extra on labour i.e `34.31
7.5% O.H Charges `2.57
7.5% contracters profit `2.57 `39.46
Labour Cess @ 1% `0.39
`5,466.90 / cum
* For 2nd floor add 15% extra labour over & above the rate of next lower floor
`39.46
7.5% O.H Charges `2.96
7.5% contracters profit `2.96 `45.38
Labour Cess @ 1% `0.45
`5,512.70 / cum
11b Rigid & smooth centering & shuttring for RCC works including false work & dismentling them after casting including cost of materials
complete
(I) RCC floor & roof slab, landing,balconies,projections,sun shades & chajjas upto 4.30 mt height (detail
for 9 sqm)
a) Materials
Non sal wood scantling 0.112 cum @ `19,640.00 cum `2,199.68
Planks 38mm 0.34 cum @ `19,640.00 cum `6,677.60
120mm dia sal bullha 56 mts @ `100.00 mt `5,600.00
carriage of wood 1.142 cum @ `169.00 cum `193.00
b) Labour `14,670.28
Considering the materials to be used 10 times
For once `13,597.27 10 `1,467.03
carpenter 2nd class 2.75 no.s @ `190.00 /each `522.50
semi skilled mulia 2.75 no.s @ `170.00 /each `467.50 `990.00
c) 7.5% O.H Charges (a+b) `184.28
d) 7.5% contracters profit `184.28
Total = ( a+b+c+d ) = `2,825.58
Rate per 1 sqm.-(a+b+c) / 9 `314.00 /sqmt
# For 1st floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor `62.80
`376.80 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor `75.36
`452.20 /sqmt
(ii) (a) For each additional hight of 0.30m over initial hight of 4.30m in ground floor & extra 1sqm
up to ahight of 5.50m `5.00
(b) For each additional hight of 0.30m add extra over 5.50m 1sqm
`8.00
(iii) R.C.C stairs excluding landing but including railing datail for 5.00 Sqm
a) Materials
Non sal wood scantling 0.228 cum @ `19,640.00 cum `4,477.92
Planks 38mm 0.039 cum @ `19,640.00 cum `765.96
`432.10 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate `86.42
of next lower floor
`518.50 /sqmt
(iv) RCC foundation, plinthband & footing bases of column mass concrete pre-cast slabs etc for 10 sqm
a) Materials
25mm thick non sal plank 0.267 cum @ `19,640.00 cum `5,243.88
Non-sal bullah 80mm dia for strutting 12.6 mtr @ `48.00 cum `604.80
carriage of wood 0.3284 cum @ `169.00 cum `55.50
`5,904.18
Considering the materials to be used 10 times
For once `5,904.18 / 10 `590.42
b) Labour
carpenter 2nd class 0.50 no.s @ `190.00 /each Rs95.00
semi skilled mulia 0.50 no.s @ `170.00 /each Rs85.00 `180.00
c) 7.5% O.H Charges (a+b) `57.78
d) 7.5% contracters profit `57.78
Total = ( a+b+c+d ) = `885.98
Rate per 1 sqm.-(a+b+c+d) / 10 `88.60 /sqmt
# For 1st floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor `17.72
`106.30 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor
`21.26
`127.60 /sqmt
(v) R.C.C beams, Column, grider & bressmer, etc. Data for 4.20 sqm
a) Materials
38mm thick non sal plank 0.218 cum @ `19,640.00 cum `4,281.52
120mm dia sal bullha 15.20 mtr @ `100.00 cum `1,520.00
80mm dia sal bullha for braciing 8.00 mtr @ `100.00 cum `800.00
carriage of wood 0.456 cum @ `169.00 cum `77.06
`6,678.58
Considering the materials to be used 10 times
For once 6678.58 / 10 `667.86
b) Labour
carpenter 2nd class 2.75 no.s @ `190.00 /each `522.50
semi skilled mulia 2.75 no.s @ `170.00 /each `467.50 `990.00
c) 7.5% O.H Charges (a+b) `124.34
d) 7.5% contracters profit `124.34
Total = ( a+b+c+d) = `1,906.54
Rate per 1 sqm.-(a+b+c+d) / 4.20 `453.90 /sqmt
# For 1st floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor `90.78
`544.70 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate `108.94
of next lower floor
`653.60 /sqmt
(vi) RCC Lintel (data for 7.80 sqmt)
a) Materials
25mm thick non sal plank 0.413 cum @ `19,640.00 cum `8,111.32
Non-sal bullah 80mm dia for strutting 21 mtr @ `70.00 cum `1,470.00
carriage of wood 0.689 cum @ `169.00 cum `116.44
`9,697.76
Considering the materials to be used 10 times
For once 9697.76 / 10 `969.80
b) Labour
carpenter 2nd class 1.25 no.s @ `190.00 /each `237.50
semi skilled mulia 1.25 no.s @ `170.00 /each `212.50 `450.00
c) 7.5% O.H Charges (a+b) `106.49
`251.20 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate
of next lower floor `50.24
`301.40 /sqmt
(vii) RCC wall and fins including attached pillasters (data for 23.90 sqmt)
a) Materials
38mm thick non sal plank 0.954 cum @ `19,640.00 cum `18,736.56
Non sal wood scantling 0.269 cum @ `19,640.00 cum `5,283.16
120mm dia non-sal bullah 100.8 mtr @ `70.00 mtr `7,056.00
carriage of wood 2.461 cum @ `169.00 cum `415.91
`31,491.63
Considering 10 times use of the materials
For use once 31491.63 / 10 `3,149.16
b) Labour
carpenter 2nd class 13.5 no.s @ `190.00 /each `2,565.00
semi skilled mulia 13.5 no.s @ `170.00 /each `2,295.00 `4,860.00
c) 7.5% O.H Charges (a+b) `600.69
d) 7.5% contracters profit `600.69
Total = ( a+b+c+d ) = `9,210.54
Rate per 1 sqm.-(a+b+c+d) / 23.9 `385.40 /sqmt
# For 1st floor add 20% extra to the respective centering shuttering items over & above the rate `77.08
of next lower floor
`462.50 /sqmt
# For 2nd floor add 20% extra to the respective centering shuttering items over & above the rate `92.50
of next lower floor
`555.00 /sqmt
12 Supplying fitting & placing uncoated HYSD reinforcement including cutting, bendind,binding & placing the steel rods as per drawing &
technical specification with cost of binding wire 18 to 20 gauge ( Taking output - 1MT )
a) Materials
HYSD bar including 5% overlaps & wastage 1.05 MT @ /MT
`51,150.00 `53,707.50
Binding wire 8.00 kg @ `77.00 /kg `616.00 `54,323.50
b) Labour
Mate 0.44 nos @ `170.00 /each `74.80
Black smith (special) 3.00 nos @ `205.00 /each `615.00
Man mulia 8.00 nos @ `150.00 /each `1,200.00 `1,889.80
c) 7.5% O.H Charges on `4,216.00
d) 7.5% contracters profit `4,216.00
e) Conveyance of materials
Steel 1.05 MT @ `14.78 /MT `15.52
Total = ( a+b+c+d+e ) = `64,660.81 / MT
Rate per 1 Qntl in G.F 64,660.81 / `6,466.08 / Qntl
Labour Cess @ 1% `64.66
Total `6,530.70 / Qntl
# For 1st floor add 5% extra on labour i.e `9.45
7.5% O.H Charges `0.71
7.5% contracters profit `0.71 `10.87
Labour Cess @ 1% `0.11
Total `6,541.70 / Qntl
# For 2nd floor add 5% extra labour over & above the rate of next lower floor
`9.92
7.5% O.H Charges `0.74
7.5% contracters profit `0.74 `11.41
Labour Cess @ 1% `0.11
Total `6,553.20 / Qntl
13 6mm thick cement plaster (1:4) to RCC surface including closed deep chiping and all cost conveyance royalty & taxes etc. comp. to work site
per 1sqm.
a) Materials
Sharp sand(screened & washed) 0.01 cum @ `49.00 /cum `0.37
cement 0.04 qntl @ `662.50 /Qntl `24.65 `25.01
b) Labour
Mason 2nd class 0.14 nos @ `190.00 /each `26.60
Man & Woman mulia 0.17 nos @ `150.00 /each `25.50 `52.10
c) 7.5% O.H Charges (a+b) `5.78
d) 7.5% contracters profit `5.78
e) Conveyance of materials
Sand 0.01 cum @ `862.90 /cum `6.47
Cement 0.04 qntl @ `186.20 /Qntl `6.93 `13.40
14 12mm thick cement plaster (1:6) on brick work including all cost conveyance royalty & taxes etc. comp. to work site per 1sqm
a) Materials
Sharp sand(screened & washed) 0.015 cum @ `49.00 /cum `0.74
cement 0.0358 qntl @ `662.50 /Qntl `23.72 `24.45
b) Labour
Mason 2nd class 0.14 nos @ `190.00 /each `26.60
Man & Woman mulia 0.12 nos @ `150.00 /each `18.00 `44.60
c) 7.5% O.H Charges (a+b) `5.18
d) 7.5% contracters profit `5.18
e) Conveyance of materials
Sand 0.015 cum @ `862.90 /cum `12.94
Cement 0.0358 qntl @ `186.20 /Qntl `6.67 `19.61
f) Royalty
sand 0.015 cum @ `27.44 /cum `0.41
Total = (a+b+c+d+e+f) = `99.43 / sqm
Cess @ 1 %` `0.99
Total = (a+b+c+d+e+f) = `100.40
(i) Cement plaster in each subsequent higher floors above ground floor add 5% extra labour over &
above the rates of next lower floor `2.23
7.5% O.H Charges `0.17
7.5% contracters profit `0.17 `2.56 / cum
Cess @1% `0.03
1st floor total `103.00 / cum
(ii) Cement plaster in2nd floors above ground floor add 5% extra labour over & above the rates of next
lower floor `2.34
7.5% O.H Charges `0.18
7.5% contracters profit `0.18 `2.69 / cum
Cess @1% `0.03
2nd floor total `105.70 / cum
15 16mm thick cement plaster (1:6) on brick work including all cost conveyance royalty & taxes etc. comp. to work site per 1sqm
a) Materials
Sharp sand(screened & washed) 0.018 cum @ `49.00 /cum `0.88
cement 0.043 qntl @ `662.50 /Qntl `28.49 `29.37
b) Labour
Mason 2nd class 0.16 nos @ `190.00 /each `30.40
Man & Woman mulia 0.24 nos @ `150.00 /each `36.00 `66.40
c) 7.5% O.H Charges (a+b) `7.18
d) 7.5% contracters profit `7.18
e) Conveyance of materials
Sand 0.018 cum @ `862.90 /cum `15.53
Cement 0.043 qntl @ `186.20 /Qntl `8.01 `23.54
f) Royalty
sand 0.018 cum @ `27.44 /cum `0.49
Total = (a+b+c+d+e+f) = `134.17 / sqm
Cess @ 1% `1.34
Total `135.50 / sqm
(i) Cement plaster in each subsequent higher floors above ground floor add 3% extra labour over &
above the rates of next lower floor `1.99
7.5% O.H Charges `0.15
7.5% contracters profit `0.15 `2.29 / cum
16 Fixing vitrified tiles in floors trades or steps and landing on 25mm bed of cement mortar 1:4 jointed with neat cement slury mixed with pigment
to match the shade of the tiles including rubbing and polishing complete excluding cost of precast tiles per 1sqm (data for 10sqm)
a) Materials
Sharp sand(screened & washed) 0.21 cum @ `49.00 /cum `10.29
cement 1.07 qntl @ `662.50 /Qntl `711.53
White cement 0.08 qntl @ `1,900.00 /Qntl `144.40 `866.22
b) Labour
Mason special 2.16 nos @ `205.00 /each `442.80
Mulia 2.16 nos @ `150.00 /each `324.00 `766.80
c) 7.5% O.H Charges (a+b) `122.48
d) 7.5% contracters profit `122.48
e) Conveyance of materials
Sand 0.21 cum @ `862.90 /cum `181.21
Cement 1.15 qntl @ `186.20 /Qntl `214.13 `395.34
f) Royalty
sand 0.21 cum @ `27.44 /cum `5.76
Total = (a+b+c+d+e+f) = `2,279.07
Rate per 1 sqm 2279.07 / `227.91
`227.91 / sqm
Carriage of tiles `4.88
Total `232.80 / sqm
For flooring in each subsequent higher floors above ground floor add 5% extra labour over & above Rs3.83
the rates of next lower floor
7.5% O.H Charges Rs0.29
7.5% contracters profit Rs0.29 `4.41
(i) 1st floor `237.20
(iii) 2nd floor Rs4.03
7.5% O.H Charges Rs0.30
7.5% contracters profit Rs0.30 `4.63
Total `241.80
(iii) 3rd floor Rs4.23
7.5% O.H Charges Rs0.32
7.5% contracters profit Rs0.32 `4.86
Total `246.70 / sqm
For inside works For Ground floor For 1st floor For 2nd floor For 3rd floor
Fixing Charges `232.80 `237.20 `241.80 `246.70
Cost of tile `660.00 `660.00 `660.00 `660.00
OHC & CP 15% `99.00 `99.00 `99.00 `99.00
Cess @ 1% `9.92 `9.96 `10.01 `10.06
Total rate /sqm `1,001.70 `1,006.20 `1,010.80 `1,015.80
17 Fixing vitrified tiles in floors trades or steps and landing on 25mm bed of cement mortar 1:1 jointed with neat cement slury mixed with pigment
to match the shade of the tiles including rubbing and polishing complete excluding cost of precast tiles per 1sqm (data for 10sqm)
a) Materials
Sharp sand(screened & washed) 0.13 cum @ `49.00 /cum `6.37
cement 2.737 qntl @ `662.50 /Qntl `1,813.26 `1,819.63
b) Labour
Mason special 2.16 nos @ `205.00 /each `442.80
Mulia 2.16 nos @ `150.00 /each `324.00 `766.80
c) 7.5% O.H Charges (a+b) `193.98
d) 7.5% contracters profit `193.98
e) Conveyance of materials
Sand 0.13 cum @ `49.00 /cum `6.37
Cement 2.737 qntl @ `662.50 /Qntl `1,813.26 `1,819.63
f) Royalty
sand 0.13 cum @ `0.00 /cum `0.00
Total = (a+b+c+d+e+f) = `4,794.03
Rate per 1 sqm 4794.03 / `479.40
Carriage ot tiles `4.88
`484.30 / sqm
For flooring in each subsequent higher floors above ground floor add 5% extra labour over & above Rs3.83
the rates of next lower floor
7.5% O.H Charges Rs0.29
7.5% contracters profit Rs0.29 `4.41
(i) 1st floor `488.70
18 providing 6.5/6.7 mm thick glazed ceramic tiles over 12mm thick bed CM(1:3)
For inside works For Ground floor For 1st floor For 2nd floor For 3rd floor
Fixing Charges `305.10 `311.70 `318.70 `326.00
Cost of tile `381.00 `381.00 `381.00 `381.00
OHC & CP 15% `57.15 `57.15 `57.15 `57.15
Cess @ 1% `7.43 `7.50 `7.57 `7.64
Total rate /sqm `750.70 `757.30 `764.40 `771.79
20 providing Ultra/euro make tile over 20mm thick bed CM(1:1)
26 Supplying,fitting and fixing of 32mm thick factory made (both side 1 mm thick lamination) ) flush door shutters
with as per IS- 2202/92 with solid core block board from seasoned and treated 2nd class hard wood , Battern,
bonded with phenol formal dehide synthetic resign pressed over suitable adhesive including providing stainless
steel hinges, locking arrangement and other fittings & fixtures if required etc. complete as per direction of Engg.- in-
charge.
32 mm Thick factory made flush Door Shutter with both side 1mm thick lamination (For
1.88sqm)
32 mm thick flush door with both 1.88 Sqm
side 1mm thick lamination- M.R-
Rs.1862/ Sqm+ 1.00 % E.Tax+ `2,132.00 `4,008.16
13.5 % VAT
AR-2006-item no-6
Data for 6'10'x7'6"= 51.22 sft=
4.76 sqm
A. Material
Al. section No.9210-8.74Mtr 12.03 kg
@1.377 kg/Mtr
Al. section No.9207-4.374Mtr 6.22 kg
@1.424 kg/Mtr
29 Iron
work wrought and put up in grated doors, windows and cage latrines etc complete. ( Refer -Vide A/R item
No 4 of Iron work at page-225)
For 1.00 qnt.
Data for 0.508 qnt.
Labour
Black smith (Special) 0.75 nos `205.00 `153.75
Black smith (2nd class) 1.00 nos `190.00 `190.00
Fitter (special.) 1.00 nos `205.00 `205.00
Fitter (2nd class.) 1.00 nos `190.00 `190.00
Helper to Blacksmith 1.00 nos `170.00 `170.00
Man mulia 3.25 nos `150.00 `487.50
Total: `1,396.30
30 a 2 Coats Synthetic enamel paint over a coat of primer (Over Wood work)
`103.65
Say: `103.70
(I ) First Floor Avg. Rate `105.60
Rate as above `102.63
Add 3% extra on labour `1.93
Add Over Head -15% `0.29
Add Cess 1% on labour `0.02
Total `104.87
Say `104.90
Avg. Rate `106.80
33 Stainless steel hand rail of 304 grade
Material
6mm size chips 0.01690 cum `740.00 `12.51
(A) WATER PROOFING TREATMENT BEFORE LAYING THE GRADING CONCRETE IN C.C.(1:2:2)
Area of
Centering Rate per Square
Centring rate
Sl No. Description of items and Meter exclud Centring rat
with cess
Shuttering Cess
.
Sqm.
1 R.C.C Raft Foundation 3.00 88.60 265.80 `268.46
6 R.C.C Lintels
Ground floor 14.00 `209.30 `2,930.20 `2,959.50
First Floor 14.00 `251.20 `3,516.80 `3,551.97
Second floor 14.00 `301.40 `4,219.60 `4,261.80
Ground Floor
(a) Column footing,
Pedestal
Cost of concrete `5,427.00
Cost of centering & Sqm `268.46
shuttering
Rate per one Cum `5,695.50
(b) Plinth beam
Cost of concrete `5,427.00
Cost of centering & Sqm `447.43
shuttering
Rate per one Cum `5,874.40
(c) Column & beam
Cost of concrete `5,427.00
Cost of centering & Sqm `3,667.51
shuttering
Rate per one Cum `9,094.50
d) Roof slab
Cost of concrete `5,427.00
Cost of centering & Sqm `3,171.40
shuttering
Rate per one Cum `8,598.40
e) Stair
Cost of concrete `5,427.00
Cost of centering & Sqm `3,273.31
shuttering
Rate per one Cum `8,700.30
f) Lintel
Cost of concrete `5,427.00
Cost of centering & Sqm `2,959.50
shuttering
Rate per one Cum `8,386.50
g) Chajja
Cost of concrete 0.065 5427.00 `352.76
Cost of centering & Sqm `348.85
shuttering
Rate per one Cum/Sqm `701.60
h) RCC wall /Fins/
Parapet
Cost of concrete 0.08 5427.00 `434.16
Cost of centering & Sqm `778.51
shuttering
Rate per one Sqm `1,212.70
First Floor
(a) Column & beam
Cost of concrete `5,466.90
Cost of centering & Sqm `4,401.18
shuttering
Rate per one Cum `9,868.10
b) Roof slab
Cost of concrete `5,466.90
Cost of centering & Sqm
`3,805.68
shuttering
Rate per one Cum `9,272.60