A Single Copy of This Document Is Licensed To: Leedsm
A Single Copy of This Document Is Licensed To: Leedsm
A Single Copy of This Document Is Licensed To: Leedsm
leedsm
On
17/03/2021
EC
M
EN
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
SP
and Guide to
EC
o the
Regulation
PRINCIPAL
IM
CDM 2015 Regulations
OK
HANDBOOK
R’S
DESIGNER’S
EN
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
IM
EC
Published by RIBA
A Publishing, Enterprises Ltd,
ublishing, part of RIBA En
Ente Designed and Typeset: Kalina Norton, Studio Kalinka
e, St Nicholas Street, Newc
The Old Post Office, Newcastle upon Tyne,
Illustrations: Pages 6, 12, 13, 33 and 35 - John Banks
NE1 1RH
Pages 7, 9, 14, 15, and 18 - Andrew Leslie
ISBN 978 1 85946 692 6 Page 34 - Grant Bulloch Architect Ltd /
Andrew Leslie
Stock code 87202
Printed and bound by Page Bros, Norwich, UK
The right of The Association for Project Safety to be identified as
the Author of this Work has been asserted in accordance with the While every effort has been made to check the accuracy and
Copyright, Designs and Patents Act 1988 sections 77 and 78. quality of the information given in this publication, neither
the Author nor the Publisher accept any responsibility for the
All rights reserved. No part of this publication may be reproduced,
subsequent use of this information, for any errors or omissions
stored in a retrieval system, or transmitted, in any form or by any
that it may contain, or for any misunderstandings arising from it.
means, electronic, mechanical, photocopying, recording or other-
wise, without prior permission of the copyright owner. www.ribaenterprises.com
CONTENTS
FOREWORD V
About The Association for Project Safety VI
Acknowledgements VI
EN
INTRODUCTION VII
Who can be the Principal Designer? VIII
Role requirements IX
IM
1 THE PRINCIPAL DESIGNER ROLE E 1
1.1 Role overview 2
1.2 Different role responsibilities
ies 6
1.3 Commercial projects 7
1.4 Domestic projects 14
EC
1.5 vice
Partial design service 17
2 THE PRINCIPALPAL
P L DES IGNE
GN R IIN
DESIGNER NPPRACTICE 21
2.1 Appointment
ent and fees 22
2.2 Pre-Construction Information
nstruction Informa 28
2.3 Construction
structio Information
Pre-Construction Inform development 33
SP
2.4 General
eneral Princip of Prevention
Principles o 37
2.5 Particular risks 40
2.6 Design Management
esign Risk Ma
M 42
2.7 paring
aring the
Preparing th Health and Safety File 51
EN
5.3 Client 86
5.4 Principal Designer (Pre-Construction Phase) e) 88
5.5 Designer 90
5.6 Principal Contractor 91
5.7 Contractors 93
5.8 Workers 95
IM
5.9 CDM Adviser 96
REFERENCE 99
Training and support 100
EC
eference
efer ce material
Bibliography and reference 102
SP
IV
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
FOREWORD
This Handbook has been prepared to assist organisations and individuals to
deliver the new Principal Designer role introduced to the construction industry
by the CDM 2015 Regulations on 6 April 2015. It is primarily aimed towards
the needs of the single practitioner or small/medium size practices
ic who offer
Principal Designer services either as a stand-alone service orr in addition to
n add
other design services.
EN
The Handbook is intended to assist the industry achieve
ve a proportio
proportionate
response to Health and Safety Design Risk Management
ement Pre-Construction
ment in the Pre-C
Pre-Co
lth
Phase by helping those who have sufficient healthth and safety skill, k
knowledge
and experience to carry out the Principal Designer
igner they feel confident
er role where the
to do so.
IM
esented
The CDM 2015 Regulations have presented ented the indust
industry with a significant
challenge to change the way it delivers construction health and
elivers design and co
ination
nation of all project
safety coordination. The coordination projec design work and Design
Risk Management with respectpectt to health and ssafety in the Pre-Construction
EC
V
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Acknowledgements
EN
Contributors
Editorial team: John Banks, Andrew Leslie, John Nielsen and Stella Saunders
S
Other contributors
IM
Gillian Birkby and Graham Leech
EC
SP
VI
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
INTRODUCTION
The Principal Designer’s Handbook is aimed specifically at Designers taking
on the role of Principal Designer on a small/medium sized project, and is
intended to help them understand their responsibilities in relation to the CDM
nstr
str
Regulations 2015. The Principal Designer controls the Pre-Construction Phase
of a construction project, relating to health and safety.
EN
This Handbook will not generally reiterate the contentt of the Guidance or
aining Board (CIT
Regulations (L153) or the Construction Industry Training (CITB) guides.
It is assumed that readers will have acquired, read
ead and assimilated the
contents of these documents.
IM
EC
SP
VII
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
EITHER: one of the design organisations or sole practitioner Designers
Design
designing the project.
OR: a separate Designer or design organisation
nisation
sation not part of the
t team
designing the project
IM
The CDM 2015 Regulations and Guidance that the Principal
ance do not specify tth
Designer must actually be designing project.
ng any part of the p
pr
organisational
nisational capability,
capability relevant to the project.
capa
4. The Principal De
Designer must also have knowledge of and the skill to apply
Desig
the principles
nciples of Design Risk Management, and have knowledge of the
ciples o
CDM 2015 ReRegulations.
VIII
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
INTRODUCTION
7. On a domestic project, if a Client fails to appoint a Principal Des
Designer, the
Designer in control of the Pre-Construction Phase becomes mes the
he Pr
Principal
Designer by default.
EN
Role requirements
This Handbook provides the basic support and nd resources you wi
will need
an obtain additional support –
to fulfil the Principal Designer role. You can
IM
including accredited training courses, and access to a web
we
website, CDM helpline
ember
and legal advice – by becoming a membermber of The Asso
Assoc
Association for Project Safety
(APS). While information has been en presented in th
this Handbook to reflect
ll also be directed to a designated area on the
current good practice, you will
APS website that will expandnd on some of ththe p
points and will provide the most
EC
up-to-date information.
SP
IX
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
knowledge and experience
• Is not about an endless round of administration,, but rather proactiv
proacti
proactive
management and practical, design-based focuscus on real risk pre
prev
prevention in
afety
relation to Pre-Construction health and safety
IM
• Is not a role that practising Designersrs should shy away from; on more
complex projects, Designers mayy wish to appoint a sspecialist Health and
Safety Consultant with knowledgeedge and experien
experience in Pre-Construction
heir
Phase to help them fulfil theireir duties as Princi
Prin
Principal Designer.
EC
X
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
THE
EN
PRINCIPAL
OLE
DESIGNER ROLE
IM
1.1 Role overview
sibilities
1.2 Different role responsibilities
EC
ects
1.3 Commercial projects
ts
1.4 Domestic projects
sign service
1.5 Partial design
SP
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Pre-Construction Phase
ion Information
Preparation of Pre-Construction
EC
mestic or comme
(domestic commercial), the size and type of project, and so on.
estic Clients are unlikely to have much information available, but
Domestic
mercial Clie
Commercial Clients should have information about their building and
site. For examp
example, Commercial Clients instructing refurbishment should
have asbestos, structural and services information.
• The Principal Designer and Designers will identify gaps in the Pre-
Construction Information where the Client needs to instruct, either
themselves or through a consultant, further investigations and studies
during the initial design phases.
• The Principal Designer will distribute appropriate
Pre-Construction Information to Designers and Contractors.
2
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
during the Construction Phase, and will liaise with the Princip
Principal
Contractor about how to manage design risks identified
dentified
entified during th
the
Pre-Construction Phase.
Risk management
IM
The Principal Designer must identify,, eliminate or contro
control foreseeable risks
easonably
asonably practicab
to health and safety (so far as is reasonably practicable). They are expected to
wledge and experien
have the necessary skills, knowledge experience for the size and type of
structure(s) on which they are re appointed, in ord
order to work with all Designers
EC
ipal Designe
The Principal Designer must ensure the cooperation of all those involved in a
t. They therefore require
project. req soft skills and people management capabilities.
nyy cases a Princip
In many Princi
Principal Designer will also be a Designer on the project, and
will havee both Princ
Principal Designer and Designer duties. The Principal Designer
has a duty to mak
make sure that the other Designers on the project are also
complying with their Designer duties.
3
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• If there is no further design or temporary works design
sign when the Pre-
Construction Phase has ended, the Principal Designer
signer role can ccease and
the Principal Contractor could complete the Health and Safety FFile.
rks design wh
• If there is continuing design or temporary works which ceases
before the end of the project, a Principal
pal Designer must be appointed
IM
(the Client takes on the role by default commercial projects) while
ault for commercia
design continues.
signer appointm
• If design or the Principal Designer appointment continues to the end of
the project, the Pre-Construction
nstruction Phase is as long as the Construction
EC
4
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
cumstances the Pri
ends before the conclusion of the project. In these circumstances Principal
Designer must pass the partially completed File to the Principal Co Contr
Contractor for
completion and handover to the Client, and advise se the Client that th
this has
been done.
IM
EC
SP
5
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Number of contractors on site at any time
More than one contractor Only one contractor
tracto
Client Pre-Construction Information Client Pre-Constructio Information
Pre-Construction
Designer(s) Information with design Designer(s)
ner(s Information with design
Principal Designer Pre-Construction Information /
(written appointment Health and Safety File
by Client)
IM
Contractor(s) Information to workers Contractor Construction Phase
Plan and Information
to workers
Principal Contractor Construction Phase
ase Plan /
(written appointment Health and Safety
ty File
F
EC
by Client)
Duty holders Providing:
ding: Duty holders Providing:
Number
mber of contractors
co on site at any time
More than one contractor
ntract Only one contractor
SP
Client Pr
Pre-Construction Information Client Pre-Construction Information
(undertaken
en by Principal
Prin (undertaken by
Contractor
or or Principal Contractor)
Designer if Principal
Principa
Designer appointed)
i
Designer(s) Information with design Designer(s) Information with design
Principal Designer Pre-Construction Information /
(if appointed) Health and Safety File
Contractor(s) Information to workers Contractor Construction Phase
Plan and Information
to workers
Principal Contractor Construction Phase Plan /
Health and Safety File
Duty holders Providing: Duty holders Providing:
Figure 1.1
6
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
the appropriate skills, knowledge and experience of thehe type and size of
ledge
edge and understan
project as Designers, and have the requisite knowledge unders
understanding of
islation
slation and regulation
construction health and safety, the relevant legislation regulat – and
CDM 2015 in particular.
IM
ADVISER
EC
CLIENT
PLAN
PRINCIPAL
PRINCIPA
DESIGNER
DESIG FILE
SP
PRINCIPAL
ADVISER
CONTRACTOR
PRE-
CONSTRUCTION
PHASE
DESIGNER DESIGNER DESIGNER CONTRACTOR CONTRACTOR
DESIGN
WORK
Figure 1.2
Key relationships in Pre-Construction Phase design work for commercial projects
7
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
If the Lead Designer is capable of undertaking the design work and managing
and coordinating the design team, but is not capable of delivering the health
and safety services required of a Principal Designer, then two choices
are available:
EN
ervice supplied by
full legal responsibility for the Principal Designer service
their consultant, OR
ganisation or individual
• The Client can appoint a separate design organisation indiv as
Principal Designer.
IM
Designers and Contractors on commerciall projects who his historically have not had
to produce Pre-Construction Information, on, Construction Phase Plans and Health
ng in order to comb
and Safety Files will require training combine their CDM 2015 roles with
their traditional roles.
EC
who are carrying out design work. If the Principal Designer appointment
des at the end of the Pre-Construction Phase, the Principal Designer
concludes
and the Health
must hand Hea and Safety File as developed at that date to the Principal
com
Contractor for completion. However, it is better if possible for the Principal
Designer role to continue, to avoid the need to pass completion of the Health
and Safety File to a different person and to deal with the continuing design that
invariably takes place during the Construction Phase on the vast majority
of projects.
8
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
PERIOD
PRINCIPAL DESIGNER
TS PE
PCI - PD CONSTRUCTION PHASE PLAN -
DEFECTS
EN
PRINCIPAL CONTRACTOR
IDEA
DE
DESIGN
TENDER
CONSTRUCTION - PRINCIPAL
L CONTRACTOR
CONT CTOR USE
U
0 1 2 3 4 5
/NEC E
RIBA (& CIC/NEC ALENT)
EQUIVALENT)
6 7
IM RKSTAGES
WORKSTAGES
1 2 3 4 5 6 7 RIAS ASP/2005 WOR
WORKSTAGES
STAGES 8
Figure 1.3
Overlaps between relationships traditionally procured construction project
s in a typical tradition
EC
9
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
The duration of the Principal Designer’s appointment into account
ent should take in
struction Phase, or any
any design work that may continue into the Construction
issues that may arise during construction involving
ving the need to make suitable
modifications to the designs.
IM
For projects involving early work by a concept Designe
Designer, a Project Management
company or where a Design and Build Contractor or novated Designer is
subsequently involved, it may be appropriate fo
for the initial Principal Designer
appointment to be concluded ed and a new Pr
Principal Designer appointed.
EC
cipal Designe
the Principal Designer passes the partially completed Health and Safety File
to the Principal Contrac
Contractor so it can be revised during the remainder of the
project. (For more aabout the Health and Safety File, see page 51.)
10
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
• Submit the notification (F10) to the Health and Safety Executive or check
that the Client has done so
• Check the skills and experience of the Designers or Contractors unless
EN
including their skills, knowledge and experience.
rangements
angements for the project,
• Advise the Client on their health and safety arrangements
including welfare facilities
ase Plan or check tthat it has been
• Review or approve the Construction Phase
implemented
IM
or
• Appoint the Principal Contractor
• Review or approve health and
d safety arrange
arrangem
arrangements on site, including
method statements
EC
sign
ign responsibility for
• Take on overall design fo the project – the Principal
ly to manage health
Designer role is only h
hea and safety during the
ction
tion Phase
Pre-Construction
se or monitor health and safety on site – this is the responsibility
• Supervise
SP
e Principal Contractor
of the Contract
Co
eck
ck or approve designs;
• Check de the Principal Designer role
es the
involves he review
revie of health and safety risks emanating from
gn process.
the design pro
11
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Figure 1.4
The role of the Principal Designer
PREPARE
PRINCIPAL ASCERTAIN
CLIENT DESIGNER BRIEF RESOURCES
BRIEF ------- AND
RECEIVED INFORM CLIENT AGREE ASSOCIATED
OF THEIR WITH FEES
DUTIES CLIENT
EN
PREPARE INITIAL
PREP NITIA
COMPLETE DESIGN HEALTH AND SAFETY
SA
RISK MANAGEMENT AND F
FILE AND AGREE
A WORK WITH
PRE-CONSTRUCTION FORMA
FORMAT ANDND C NTENT
CONTENT DESIGNERS
INFORMATION AND ISSUE WIT LIENT
WITH CLIENT ON DESIGN
TO CLIENT AND POTENTIAL ------- RISK MAN-
PRINCIPAL CONTRACTORS ISSUE IN
IM INTIAL AGEMENT
ISSUE TO DESIGNERS HEALT AND
HEALTH N SAFETY
TO CONFIRM THEIR INPUT FILE TO CLIENT AND
DE
DESIGNERS
EC
Client interface/decisions
interfac
Principal Designer input prior to appointment
Site Visit
THE DOTTED LINE HIGHLIGHTS
Principal Designer input during the Pre-Construction Phase THE CONSTRUCTION PHASE
Work with Designers on Design Risk Management during WHICH INCLUDES THE
CONTINUATION OF THE
the Pre-Construction Phase: Note - this applies to all “stars” PRE-CONSTRUCTION PHASE
Construction Phase Plan and start on site.
Note - Assessment of the Construction Phase Plan is not
part of the Principal Designer’s duties
12
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
OBTAIN FURTHER
PRE-CONSTRUCTION WORK WITH
WO WORK WITH
INFORMATION VIA CLIENT, INFORM CLIENT OF NEED DESIGN RS TO
DESIGNERS DESIGNERS
PRINCIPAL DESIGNER, FOR FURTHER ASCERT N
ASCERTAIN ON DESIGN
DESIGNERS OR OTHERS PRE-CONSTRUCTION APS IN PR
GAPS PRE- RISK MAN-
AND UPDATE INFORMATION CONSTRUCTION
NST UCTIO
IM AGEMENT
PRE-CONSTRUCTION INFORM
INFORMATIONO
INFORMATION
EC
OBTAIN FURTHER
OBT
ASCERTAIN AND LIST P
PRE-CONSTRUCTION
WORK WITHH LIAISE WITH
ADDITIONAL DESIGNER INFORMATION AS REQUIRED
SIGNERS
DESIGNERS PRINCIPAL
CONTACTS WORKING FOR BY TEMPORARY WORKS
ON DESIGN
ESIGN CONTRACTOR OVER
OR IN CONJUNCTION WITH DESIGNERS/DESIGN CHANGES
RISK MAN-
AN- ADDITIONAL/CHANGED
PRINCIPAL CONTRACTOR -------
AGEMENT
AGE PRE-CONSTRUCTION
(INCLUDING TEMPORARY Y CONTINUALLY REVIEW AND
INFORMATION
WORKS DESIGNERS) UPDATE THE HEALTH AND
SP
SAFETY FILE
OBTAIN FURTHER
IF APPOINTMENT LASTS
PRE-CONSTRUCTION
UNTIL THE END OF THE WORK WITH WORK WITH
INFORMATION AS REQUIRED
CONSTRUCTION PHASE DESIGNERS DESIGNERS
BY TEMPORARY WORKS
(RECOMMENDED): ON DESIGN ON DESIGN
DESIGNERS/DESIGN CHANGES
RISK MAN- ------- RISK MAN-
COMPLETE HEALTH AGEMENT AGEMENT
CONTINUALLY REVIEW AND
AND SAFETY FILE
UPDATE THE HEALTH AND
AND ISSUE TO CLIENT
SAFETY FILE
13
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
the Principal Contractor, or to the Principal Designer if appointed in writ
writing.
IM
ADVISER?
EC
DUTIES BY APPOINTMENT
A OINT
CLIENT
DUTIES PASS TO
CONTRACTOR
PR CIPAL
PRINCIPAL
DESIGN
DESIGNER FILE
SP
ADVISER?
ADVISE PRINCIPAL
T N
TRAINING? CONTRACTOR PLAN
PRE-
CONSTRUCTION
PHASE
DESIGNER DESIGNER DESIGNER CONTRACTOR CONTRACTOR
DESIGN
WORK
Figure 1.5
Key relationships in Pre-Construction Phase design work in domestic projects
14
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Designers and Contractors who historically have not had to notify projects,
produce Pre-Construction Information, Construction Phase Plans and Health
and Safety Files will require training in order to combine their CDM 2015 roles
with their traditional roles, whether or not they decide, initially, to appoint a
Sub-consultant to advise them.
EN
management of the project, including acting as Contract act Administrator.
IM
CDM 2015 PROJECT LIFELINE
INE
TY FILE - PRINCIPAL
HEALTH AND SAFETY CI L DESIGNER
DES FUTURE REFERENCE
EC
PRIN
PRINCIPAL DESIGN R
DESIGNER
DESIGN
DESIG
TENDER
TE
SP
Figure 1.6
Overlaps between relationships in a typical domestic construction project
15
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
consent and regulation approval – the Client cannot assumesume the role of
Principal Designer unless they are also in businesss as a Designer. D Designers
who have a limited involvement in the project may ay become Principa
Principal Designer
by default for the period of their appointment.
IM nowledge and experience
The Client’s lack of health and safety knowledge expe should be
esigners providing
compensated for by the professional Designers providi suitable advice and
guidance during their appointment nt and by Contractors
Contract for the duration of
their involvement.
EC
SP
16
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
and a short and simple Construction Phase Plan and Health and Safety F File.
17
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
PERIOD
PRINCIPAL DESIGNER
ECTS P
PCI - PD
DEFECTS
PRINCIPAL CONTRACTOR
EN
IDEA
DESIGN
D
TENDER
CONSTRUCTION - PRINCIPAL
L CON
CONTRACTOR
ACTOR USE
US
Figure 1.7
Overlaps between typical domestic construction project with partial
en relationships in a typ
design service
SP
For the Domestic Client, the blue area in the diagram represents construction
procurement
ement and is a period
perio when neither design nor construction is taking place. This
is also a period where ther
there may be a considerable delay between completion of design
work and commencement of construction.
nd commencem
18
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
e
• The Health and Safety File as developed to that date
orr the projec
• A statement that the Principal Designer role for project
has concluded
urement of a Princi
• Advice about how to proceed with procurement Principal Contractor;
IM
the Principal Designer should ensure re that the Client is made aware that
the Principal Contractor needs to o demonstrate CDCDM 2015 capability as
nd track record.
well as technical capability and
EC
er should be appoin
Designer appointed, or the Principal Designer duties could be
ried
ed out by the Principal
carried Princ
Pr Contractor. The tendering Contractors, one of
om
whomm will be respon
responsible for any design changes during the construction
d, should
period, hould aals
also be advised
lie should ensure that the tendering Contractors can
• That the Client
demonstrate Principal Contractor awareness and capability, including:
track record
ability to deal with significant risks identified in the Pre-Construction
Information
provision of references from other Clients/Advisers.
19
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Client’s responsibility
The Client should then issue the following to the tendering Contractors:
EN
Large domestic projects
rojects are small and
It is important to note that not all domestic projects an simple.
Designers should only take on the Principal Designer role if they
t have the
pable to help them discharge their
capability to do so or have someone capable
IM
duties. Larger or more complex projects cts may require the
t appointment of
a Construction Health and Safety (CDM)CDM) Adviser to advise and assist the
ner.
Client and/or Principal Designer.
EC
do not appoint
ppoint a Princ Designer in writing.
Principal D
20
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
THE PRINCIPAL
N PRACT
DESIGNER IN PRACTICE
IM
2.1 Appointment and fees
rmatio
2.2 Pre-Construction Information
EC
EN
Extent of the Principal Designer’s function and
d duties
Principall Designer.
http://www.aps.org.uk/publications
www.aps.org.uk/pub
ww.aps.org.uk/
22
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Separate roles
It is important when acting as both Lead Designer and Principal Designer
to identify the services being provided for the Principal Designer role,
and the period in the project programme during which these services are
EN
technical design services. Separate forms of appointment
ntment or bespoke
appointment letters should be used which clearly services
rly set out the ser
being provided and the fees being charged for or these services. Use of the
APS Terms of Appointment is recommended.
IM
Determining a fee
• Stafff time
al res
• Additional reso
resources required, including specialists
• Overheads
• Travel for site visits and attendance at design/project
team meetings
• Assisting the Client in providing the Pre-Construction Information and
the delivery of documents, such as drawings, reports, any Designer
deliverables and the Health and Safety File(s).
23
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
When working for Domestic Clients, Designers who are in n control of the
EN
Pre-Construction Phase (usually the Architect) may find nd themselves being
bein
asked to undertake the Principal Designer role by thehe Client. Bear in mind
m that
rincipal Designer, then
if the Client does not appoint the Designer as Principal th that
Designer may well find that they are taking on n the role by defaul
default, only without
any agreed fee for doing so.
IM
dvised to provide their
Designers on domestic projects are advised t Client with a fee
for both the design services and for undertaking the th Principal Designer duties
ens
ensur that they have sufficient
with their initial fee proposal if they wish to ensure
charge
harge their roles.
resources allocated to discharge role It is advisable for the Designer
EC
res
re
to make a record within their fees of the resource allocated to each service
they are providing, in n order to be able to demonstrate that they have made
adequate provision.on.
n.
http://aps.legallio.com/aps-principal-designer-adviser-resource-estimator/183/11/16/3
egallio.com/aps-principa
gallio.com/aps
Site visit
The Principal Designer should visit the site to assess the health and
safety issues affecting the project, preferably before the fee agreement is
concluded. If this is not possible, the use of Google Street View is useful
but should always be supplemented by an actual site visit.
24
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Constantly reassess the Principal Designer role
• Be proactive in any dialogue with the Client
• Seek changes to the terms of the Principal appointment where
al Designer appoint
appointm
r, or where significa
significant changes to the project occur, significant under-
IM
compliance by any party increases the Designer workload
he Principal Desig
Design
• Inform other appointees of any changes to your
your instructions.
ins
EC
If the Designer
esigner appointed
appoint a as Principal Designer has been novated to the
Design n and Build Contr
Contractor and can no longer fulfil the Principal Designer
e Client mus
role, the must appoint a new Principal Designer. One obvious choice for
the role willl be th
the Design and Build Contractor. Even if they have no Designers
working for them in-house, the Design and Build Contractor could fulfil the
role as Principal Designer by making arrangements with one of the novated
Designers to carry out those functions. There is no problem with this under the
Regulations. If the same Designer acts as Principal Designer throughout, this
has the added advantage of providing continuity.
25
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Late appointment
In the case of late appointment, the Principal Designer will need to inform the
Client of any significant health and safety implications, which can include:
EN
satisfactory planning; managing and monitoring of thehe Pre-Construction
Pre-Constr
rss
Phase, and the coordination of all relevant matters
• Time required to enable the Principal Designerner to revisit design
igner desi work to
es
esigns
check suitability and compatibility of designs
IM
cipal Contractor
• Time for cooperation with the Principal Contractor to ensure they have all
eed
ed to proceed
the relevant information they need
minate, reduce
mina
• Missed opportunities to eliminate, reduce
duce and
an manage risk and reduce
whole-life costs
EC
26
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
additional CDM 2015 services (see Chapter 5.9 - the Adviser) but
he CDM Advis
ertake the
should carefully consider their capability to undertake these.
Exemplar letters
IM
rom the Principa
Some typical wordings for letters from Principal Designer to the
Client are included in Chapter 4.
EC
SP
27
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
File, an asbestos survey, structural drawings, services, s, etc.), or which is
straightforward to obtain through reasonable enquiry. iry. The Client shshou
should expect
the Principal Designer to help bring the Pre-Construction Information together
nstruction Informat
orss involved.
and provide it to the Designers and Contractors
IM
Appendix 2 of L153 gives further guidance
nce provisio of Pre-Construction
ce on the provision
oportionate
ortionate inform
Information, which must include proportionate informa
information about:
ient
ent brief and key da
• The project, such as the Client dates of the Construction
Phase
EC
• The planning and management of the p project, such as the resources and
time being allocated
ated
ed to each stag
stage oof the project and the arrangements to
here is cooperation between duty holders and that the work
ensure that there
ated.
ted. It is a Client du
is coordinated. d
duty to supply this information. It is not a
SP
28
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Structural/building safety reports
ead,
ad, asbesto
• Survey reports for hazardous materials (e.g. lead, asbestos)
• Survey reports for hazardous areas (e.g. confined
onfined
fined spaces)
nss (e.g. fragile roof a
• Survey reports for hazardous locations access)
IM
• Site access and other restrictionss
ons and adjacent la
• Local environmental conditions land uses
ls,
s, petro
• Neighbours (e.g. schools, petrol stations,
ns ssupermarkets and
stations,
EC
major roadways)
alth and Safety Fil
• The current Health File
d sites, proposed
• For occupied pr posed si
site rules (e.g. existing permit to
stems)
ms)
work systems)
SP
ximity
imity of watercourses,
• Proximity water
watercours
co transport systems and so on
• Any history of previ
pre
previous damage (e.g. from fire or floods)
29
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Provide details of the type of work and activities thatt the Client foresee
foresees
or intends to undertake
tion
• Provide details of any ongoing use or occupationon of parts of the ssite or
areas adjoining the site so the Designers can take
ake this into ac
acc
account when
considering space, access and methods dss of wo
work
IM
• Alert the Designers to health andd saf
afety
ety hazards associated
safety ass
as with the site
ile the Constructio
or its surroundings or use while Construction Phase is under way
angements
gements already in place and/or expected by
• Provide details of the arrangements
EC
• Create a ‘le
level
vel playi
‘level playing field
field’ for pricing (so that those offering to carry out
ign
gn work will be less
design l likely to put in a low price because of omissions
of health
ealth and safety management).
30
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Pre-Construction considerations
Most project design work is ‘preparing for construction’,
with decisions being made that affect health and safety.
The following may affect the Pre-Construction Information:
31
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Take account of the nature, scale and complexity of the health or safsafety
matters involved in the project and activities requiredd for the whole life
EN
ments as Prin
of the project when establishing suitable arrangements Principal
ction Phase
Designer for, and throughout, the Pre-Construction Phase.
IM
EC
SP
32
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
specific issues and continuing communication.
• Be relevant
IM
ail
• Have an appropriate level of detail
kss in
• Be proportionate to the risks involved.
involved.
EC
PROPORTIONALITY
P
ACT
ACTIONS
SP
SIGNIFICANT
CONTROL
TO C
RISKS
RISKS
33
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
taking place.
Figure 2.1
When passing Pre-Construction Information to Contractors who may be tendering for
the work, written information is almost always required, even on smaller projects - but
information on drawings may be all that is required on simple projects
34
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Principal Designer
EN
Significant remaining risk information from Designers
ers
aining
ining risk from Des
When receiving information on significant remaining Designers,
check the following:
IM
d in a form
• Is the information clear, precise and form suitable for others?
n be on a drawing?
• Could or should the information
The Principal Designer should ld log the rresponses
esponse from Designers; it is easy
esponses
he Principal Desi
to lose track of returns. The Designe
Designer should be proactive about
EC
seeking information.
NO
DESIGN/ IDENTIFY ELIMINATE
SP
DESIGN
RE-DESIGN HAZARD HAZARD
DO NOT SWAP
YES A LOW RISK FOR
TOO RISK
RISKY TO BUILD A HIGHER ONE
THEN RE-DESIGN
CREATES YES
NO HIGHER
RISK
YES NO
SAFE
COMMUNICATE REDUCE RISK
TO BUILD
35
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Contractor’s Designers
36
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
naging
aging health an
The following information is taken from HSE’s L153 ‘Managing and
EN
safety in construction’, Appendix 1 part 2.
• Avoid risks
IM
e avoided
• Evaluate the risks which cannot be av ded
• Combat the risks at source
ividual,
dual, especially rregarding the design of
• Adapt the work to the individual,
EC
lace
ace the dangero
• Replace dangerous by the non-dangerous or the less dangerous
elop
lop a coherent
• Develop ccoheren
ere overall prevention policy which covers technology,
ation
tion of work, working conditions, social relationships and the
organisation
influence of ffactors relating to the working environment
• Give collective protective measures priority over individual
protective measures
• Give appropriate instructions to employees.
37
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
ERIC
Once the Principal Designer has evaluated the risk, theyy must consi
consider
orm, Control
how to control it. Think ‘ERIC’: Eliminate, Reduce, Inform,
EN
of significant risks resulting from building/use/maintenance
aintenance by the
Contractor/Principal Contractor/Structure Users.rs.
IM
EC
SP
38
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The Principal Designer and other Designers must have the skills, knowledge
and experience to identify the risks associated with the:
• Site conditions
• Site surroundings
EN
• Materials used in their design
gn
n a reality
• Work activities necessary to make their design
re forr its whole life
• Maintenance and cleaning of the structure
IM
ntss forming the des
• Replacement of the parts or elements desi
design
• Impact and effect the carrying out
ut of any of the abo
above work may
have on the people affected by the construction
• Use of the structure as a place of work.
k.
work.
EC
SP
39
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Designer should review the responses to the Particular ar Risks with the
Principal Contractor, as these may have an impactt on buildability, u use
and maintenance.
ork
3. Workk with ionising rra
radiation requiring the designation of controlled
upervised
pervised ar
or supervised area
areas under regulation 16 of the Ionising Radiations
tions
ons 199
Regulations 1999.
40
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Some of these Particular Risks will not occur on many
any projects, par
partic
particularly
small and domestic projects.
41
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
design decisions or provisions. Only as a last resort should
hould Designers re rely
rel
on actions by the Contractors on site to provide the e means of protec
protectio
protection for
workers and others during work activities. (Remember
IM member ERI ERIC – see page 38.)
EC
SP
42
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
• What is being built? What should it look like, and what is its function?
• Where is the project being built?
EN
or how long does th
• When will it be built, how long will it take to build (or the
Client want to allow)?
• What are the constraints and circumstancess affecting the desi
desig
design
and construction?
IM
• Who else is designing this, and whatt elements or aspe
aspec
aspects are
they addressing?
djacent
jacent sites or area
• What is happening on the adjacent areas?
• What will be continuing to be done or us
used on the site during the
EC
Construction Phase?
re that
• Is this a structure hat will be use
used as a workplace and/or used by the
ic?
general public?c?
• How will this
is structure or el
element be maintained (risks to site workers,
SP
43
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
and pre-stressed concrete bridge beams)
d
• Design in features to reduce risks, (i.e. from working at height, deep
excavations, etc.)
an interacting or
• Ensure that designs are suitable and compatible with any
IM
interrelating designs
ace (Health, Safety and
• Take into account the Workplace a Welfare) Regulations
1992 (and Amendments)
EC
44
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
agement resp
significant risks and issues and coordinated management responses –
ndustry
dustry Council (CIC
see RIBA Plan of Work and the Construction Industry (CI
(CIC) Scope
of Services, Stages 2, 3 and 4
jacent
acent sites
• Ensuring effective cooperation with adjacent
IM
• Keeping adequate records of the Design Management process –
esign Risk Manage
not everything; everything that iss significant
• Reviewing hazard and risk inf
nformation
ormation befor
information before design information
is issued
EC
nd risk information
• Providing hazard and information in a clear, concise and
mat.
appropriate format.
Information
ion sharing – prac
practical advice
SP
It is the
he
e Principal Desig
Designer’s duty to ensure, so far as is reasonably practicable,
that information being passed on to those who need it, when they need
rmation is b
it – even though
ough tthey may not know they need it – including what is needed
by the Client, other Designers, those tendering, Principal Contractor and, if
necessary, other Contractors.
45
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
ken
• Identify ownership of risk/hazard issues to ensure actions are taken
• Ensure all Designers are included in the process
EN
on is finalised and
• Try to close out risk/hazard issues before information
passed on to those who need it.
ncipal
cipal Designer
The Principal Design
Desig should ensure that Designers contribute to the agreed
sign Ris
project Design Risk Management method (using a consistent pro-forma).
They must talk,k communicate by other means and keep all appropriate
parties in the loop. They must also provide information about their design for
construction and the Health and Safety File.
46
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Designers should critically assess their design proposals at an early stage, and
then throughout the design process, to ensure that health and safety issues
are identified, integrated into the overall design process and addressed as they
go along. It is pointless to complete the design first, and to then try to address
the risks that the design has introduced. By then, all of the key decisions
EN
Evaluating the Design Risk Management procedure
cedure
edur
explain
xplain the implica
implicat
implications of the lack of records should an investigation
e made later
be
explain
n the iimplications should changes to the design be required in
order to build the structure due to lack of information
request that Designers provide records of their Design Risk Management
procedures and actions on hazard elimination and risk reduction.
47
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Below are examples of high and significant risks that Designers are
likely to be able to eliminate or manage through good design.
EN
• Manual lifting of cladding/glazing panels
n a windowless room
• Application of solvent-based floor adhesive in
• Welding in confined spaces
IM
• Noise, dust and vibration from concrete
rete scabbling
ned
ed space.
• Maintenance of plant in a confined space
48
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
NO
DESIGN/ IDENTIFY ELIMINATE
RE-DESIGN HAZARD HAZARD
EN
CREATES YES
NO HIGHER
RISK
YES NO
SAFE
COMMUNICATE REDUCE RISK
TO BUILD
IM
Figure 2.3
The Design Risk Management procedure
dure in practice
EC
Significant risk
SP
49
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Summary
Designers do not have to eliminate all risks, but if they let them remain they
do need to justify this. They must identify foreseeable significant residual
risks and communicate these clearly to others. The Principal Designer should
ask questions and prompt the Designers to comply with good Des es
Design Risk
Management and the intentions of CDM 2015.
50
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
update and revise it as the project progresses. The Principal
rincipal
incipal Designer mmust
also pass the completed Health and Safety File to the
he Client to keep.
keep
51
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Key structural principles and safe working loads forr floors and roofs
• Hazardous materials used (e.g. lead paints and special coatings)
coatings)
• Information regarding the removal or dismantling
ntling of installed plant and
mantling
equipment
IM
ut equipment provid
• Health and safety information about pro d for cleaning or
provided
maintaining the structure
• The nature, location and markings
rkings of significa
signific
significant services
EC
52
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
There should be enough detail in the Health and Safety File to allow the likely
risks to be identified and addressed by those carrying out work in the future.
The level of detail should be proportionate to the risks. Information must be in
The Health and Safety File is an information resource that at is needed by tthe
EN
Client to inform them of any residual health and safetyy issues and for the
them to
actor/Principal Co
hand to any Designer/Principal Designer or Contractor/Principal Cont
Contractor
isting
sting structure/buil
involved in a new construction project on the existing structure/bui
structure/building. The
information in the Health and Safety File will, or example, allow the Client
l, for
to develop fire risk assessments and to be e able to develop risrisk assessments
IM
for the maintenance of structures, and requirements of specific
d to meet any requi
requir
uipment.
pment.
warranties attached to material/equipment.
importance. The Client should be advised tthat any relevant information from
uld
ld be added to the Health and Safety File. This would
a future project should
ed by a Principal De
usually be provided Designer or Principal Contractor, but it
should be noteded that information to update the File could come from a one-
contractor piece
ece of work, wher
where the Regulations do not require a Health and
SP
ile to be prepa
Safety File prepared.
53
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The Health and Safety File does not need to include information that
will be of no help when planning future work, such as:
EN
uction Phase)
assessments, written systems of work and (Construction
COSHH assessments
ompl
mpleted
ted structure or its
• Details about the normal operation of the completed
parts or elements
IM css
• Construction Phase accident statistics
• Details of all the Contractors, Suppliers,
uppliers, Manufact
Manufacturers and Designers
involved in this and previous projects
project
• Contractual documents
EC
ion containe
Information contained in oth
other documents can be cross-referenced in the file
oid
d duplication of inf
to avoid i
information.
54
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
LIAISON WITH THE
PRINCIPAL CONTRACTOR
ONTRA
IM
3.1 The Construction Phase
ring the Construction
3.2 Continuing liaison during ru Phase
EC
ty period
3.3 The defects liability
SP
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
project this will occur at the end of RIBA Stage 4 (or CIC/NEC equivalent); in
IC/NEC equivalent)
tage from RIBA S
a design and build project this could occur at any stage Sta
Stage 3
onwards. In all cases the information is passed to the tendering Co Contractors so
ation
on provided and m
that they can take account of the risk information make suitable
resource provision for dealing with them. The Pre-Construct
Pre-Constructi
Pre-Construction Information
IM
may be on drawings and in a stand-alone one Pre-Construction Information
e Pre-Constructi
Pre-Constructio
document, or incorporated into the tender
nder documents.
documents
Contractor acceptance
EC
misinterpretations
pretations that
th may affect the validity of the tender.
Initial arrangements
rrangeme
angeme for liaison
The Regulations require the Client to ensure that a Construction Phase Plan
is drawn up by the sole Contractor if there is only one, or by the Principal
Contractor if there is more than one, before construction work begins. In
EN
Commercial Clients will need assistance with this duty.ty.
y. The Principal Des
De
Designer
has no duty to review the content of the Constructionon Phase Plan.
There is no requirement in the Regulations for or any duty holder tto check the
on Phase Plan. How
sufficiency or suitability of the Construction However, the Client
IM
has an absolute obligation to ensure that Construction Phase Plan is
hat the Constructio
alth
drawn up, so that it sets out the health h and safety arra
arran
arrangements and site rules
and takes account of specific risks ks on the project iin question. If a Client is not
gation:
atio
confident in fulfilling this obligation:
EC
ncipal Designer
The Principal Designe has a duty to liaise with the Principal Contractor for
uration
ration of their ap
the duration app
appointment, and this includes liaison regarding design
pment
ment during tthe Construction Phase, and the coordination of health
development
and safetyy matters during the Construction Phase.
57
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
The effort the Principal Designer and the Principal devo to
all Contractor devote
carrying out this liaison should be in proportionn to the size and co
com
complexity of
the project and the nature of risks involved. Thee Principal Contr
Cont
Contractor should
expect and receive help from the Principal al Designer, and anany other duty
IM
ng the risks associa
holders on larger projects, in identifying associated with the work
and determining the necessary controls
ntrols
ls that need to bbe put in place. Regular
ost effective manag
meetings will usually be the most manage
management tool.
EC
ncipal Contractor
While liaising with the Principal Contractor, tthe Principal Designer’s objectives
must include:
e-Construction Info
• Sharing of Pre-Construction Infor
Information that may affect the planning,
managementent and monitoring of both the Pre-Construction and the
ction
Constructionn Phase
Phases
SP
ordination
rdination of matt
• Coordination matter
matters relating to Pre-Construction Health and Safety
sion of the Pre-Construction
• Provision Pr
P Information needed by the Principal
tor
or to rreview and update the Construction Phase Plan
Contractor
• Effective management of ongoing design, especially design changes
• Obtaining information for the Health and Safety File.
58
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Liaison with the Principal Contractor for the Health and Safety File
Unless the Principal Designer’s appointment finishes before the end of the
Construction Phase, the Principal Designer should continue to liaise with the
Principal Contractor regarding information for the Health and Safety File. If the
ssly
The Regulations do not expresslysly require the PPri
Principal Designer to check
ation in the Heal
the accuracy of the information Health aand Safety File, but everyone
hould make sure th
providing information should that it is accurate, comprehensible
and provided at the appropriate
ppropriate time. Ho
H
However, the duty on the Principal
ew, update and revi
Designer to ‘review, revis
revise [the File] from time to time …’ does
ctive response to ex
require a proactive existing or missing information.
59
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
It is quite common for there to be a list of incomplete works when the project
onst
nst
is handed over to the Client for occupation. These works are construction
works and should be considered to be a part of the project, to be comcompleted
as soon as possible by the Principal Contractor. This will require approp
appropriate
EN
welfare to be provided along with management of the construction and
the risks associated with the new circumstances – i.e. working withwithin an
occupied building. This is not a new project, but will require the Cli
Client,
Clie
Principal Designer and Principal Contractor to establish arrang
arrange
arrangements that
reflect the changed circumstances. The Principal
rincipal Designer sshould provide
IM
new or reworked Pre-Construction Information
ormation Principal Contractor
mation to the Prin
Pr
undertaking the defects rectificationn work. This may entail
en
e creating a post-
occupation risk register and an addendum to the Construction
Co
C Phase Plan.
EC
Designer’s
r’s appointment
appointm will in the majority of projects have ended at the time
the Health
alth and Safety File
ealth F was handed over. Where complex reworking of failed
construction
uction is required,
require it will almost certainly be necessary to appoint a
requ
Principal Designer.
esigner
Reactive rectification
60
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
STANDARD AND
D
EXEMPLAR DOCUME
DOCUMENTS
IM
4.1 Resourcing, fees and appointment
oint
EC
ormatio
4.2 Pre-Construction Information
agement
4.3 Design Risk Management
afety File
4.4 The Health and Safety Fil
SP
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• A Brief for the role of Principal Designer is agreed withith
th the Client. This
o written Client B
will be based on the Client Brief (if received). If no Brief
is forthcoming, it is recommended that a Client by the
nt Brief is provided b
iscussions
cussions with the Client
Principal Designer recording the briefing discussions
in writing.
IM
uired hours) should be assessed
• Input required (personnel and required
incipal
ncipal Designer has
once the Brief for the role of Principal ha been agreed (and
it is recommended that the Principal Designer B Brief is agreed before
red
assessing the input required d by the Principal Designer). Input required
EC
needs to identify who iss doing what and w when (using the programme
agreed within the Client
lient Brief and Prin
Principal Designer Brief).
ded that an Associ
• It is recommended Associa
Association for Project Safety Form of
Appointmentnt for the role of Pri
Prin
Principal Designer is used.
SP
(http://www.aps.org.uk/publications)
www.aps.org.uk
www.aps.org.uk/publica
62
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
1.4 The project is to be carried out
as a one/two-stage tender:
1.5 The intended programme is:
Construction commencement:
Completion:
IM
2.0 APPOINTMENT
2.1 Our appointment will be in accordance
ordance with The Association
Assoc for Project
Safety Form of Appointmentt ass Principal Designer 2015.
EC
3.0 PROFESSIONAL
AL INDEMNITY
IIN
NDEM
MNITY
T COVER
COVE
OVERR (PI)
3.1 The practice
tic
icee carries PI cover on an each and every
claim basiss …………...............................................................................................................
………….................
…………...
SP
3.2 The
hee maximum liability
liabil attached
att to the practice resulting from
this
his contract will be contract
co
c value up to £……….................................................................
3.3 Without
thout prejudice.............
ithout prejudice.
prejudic the liability of [Practice Name]
shall be
e further limited ….........
Please remember to discuss disclosure of information regarding PII cover with your Insurer
63
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
5.0 CLIENT’S ROLE
5.1 llowing
llowing duties:
Under CDM 2015 the Client or their Adviser has the following dutie
IM
6.0 ASSUMPTIONS/INFORMATION BY OTHERS
THE
HERRS
EC
7.0 FEES
1. incipal Designer role
Our fees for the Principal r will be a lump sum/time and material (delete
e) of £.............. Our fee proposal is also subject to the programme noted
as appropriate)
within 1.5 above. Should the programme
progr
prog be elongated beyond the dates noted we will
advise on any additional fees payable.
p This fee is exclusive of VAT but inclusive/exclu-
SP
sive (delete
delete as appropriate)
appr of
o expenses.
2. The
he fees are to be paid
pa ini ..............monthly instalments of £............exc VAT.
[add
add payment terms]
3. Additional
ditional costs
osts if required:
64
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
This is example text for a letter from the Principal Designer explaining why a
change in the programme is necessary in order to deal with health or safety
risk management.
Dear XXXXXX
IM
In reviewing the overall construction andnd design programme(
programme(s)
for the project we are concerned aboutt the amount of tim time that
has been allowed between preparing ring the design for [[x] and the
issuing of tender documentation.on. There would appear
appea to be
insufficient time to adequatelyy prepare the Pre-Construction
Pre-Co
Information for issuing to
o potential Principal
Principa Contractors who
EC
We also consider
ider that insufficient time
tim may have been allowed
for the Principal
ncipal Contractor to plan
pl and prepare for construc-
tion work, preparation of the Construction Phase
k, including preparatio
SP
In
n our view it would ttherefore be appropriate to consider adjust-
ing
ng the start date
da by a suggested period of [X days/weeks] to
[date]. We suggest
sugg that, if necessary, this should be discussed
and resolved
esolved at the next design/project team meeting.
Sign off
This and other sample letters can be downloaded from the APS website at
www.aps.org.uk/guidance/principal-designers-handbook
65
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The following is sample wording for a letter from the Principal Designer to
the Client – this example assumes that a Principal Contractor is already
appointed. The letter can be adapted according to the circumstances.
EN
Address line 1
Address Line 2
Address line 3
Postcode
Dear XXXXXX
IM
Appointment as Principal Designer under
der the Construction
Constructi
(Design and Management) Regulations
ulations 2015
follows
lows to achieve effective design and project risk management
and compliance from this point forward:
66
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Sign off
SP
This and other sample letters can be downloaed from the APS website at
www.aps.org.uk/guidance/principal-designers-handbook
67
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• On health and safety hazards, including design and construction
d con
construction hazards
ruction hazar
and how they will be addressed
• In any existing Health and Safety File
The following sets out the main areas thatt must be covered iin the Pre-
IM
Construction Information, and suggests structure this information.
ts a way to structur
• Project description
• Key dates
• Project directory
ctory – details
details
de other parties
ils of ot
oth
• Extent and existing
nd location of exist records and plans
SP
Client’ss arrangem
arrangements and requirements
68
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
• Site security
• Welfare provision
• Environmental restrictions and existing on-site risks
• Significant design and construction hazards
EN
Environmental restrictions and existing on-site
te risks
Health hazards
• Asbestos
IM
• Storage of hazardous material
• Contaminated ground
EC
Safety hazards
ces
• Existing services
ion
• Informationn contained in ea
ear
earlier designs, e.g. pre-stressed concrete
SP
plankss or post-ten
post-tensioning
Other
• Boundaries
• Adjacent land uses
69
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
IM
EC
SP
70
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
tion work
• Carrying out or liable to be affected by construction
• Maintaining or cleaning a structure
lace.
lac
• Using a structure designed as a workplace.
IM
ese risks, the Desig
If it is not possible to eliminate these Designer must, so far as is
reasonably practicable:
EC
The Principal
ncipal Designer m
must manage the above process (and ensure it
ns)
happens)s) for each and
a everyone of the Designers involved in the project.
st accom
This is best accomplished by combining the assessed results from Designers
into a Design RRisk Register.
71
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
A Design Risk Register is a live document used to log the risks that have
been identified on a project. This makes them easy for the Principal Designer
and other duty holders to access them as necessary. Further, it enables the
ssessing
sessing the
• Manage the process of Design Risk Management by assessing
EN
input from each and all of the Designers (and re-assessing)
ssessing) as the
project proceeds
• Identify (with Designers) the need for further
err Pre-Cons
Pre-Construction
ction
Information from the Client
IM
• Consider the affects of one design solution designs
olution on other des
de
(and vice versa)
• Identify necessary information
on produced the design for passing to
produced with th
other Designers (as part of the Pre Co
Const
Construction Information)
EC
Principal Contractor/Contractors
ctor/Contractors
ctor/Contractors (as part of the Pre Construction
Information)
essary information produced with the design for inclusion
• Identify necessary
ealth
th and Safety File
in the Health File.
SP
72
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
ILL BE THE CONTRACTOR’S
TENDER ISSUE: SOME DESIGN WILL CONTRAC
C T
OCUMENT
CUMENT SHOULD BE RE-
RESPONSIBILITY AND THIS DOCUMENT
VIEWED AFTER THE PRINCIPAL
AL CONTRACTOR
PAL CONTRA
CONTRACTOR R IS APPOINTED.
A
f. no. in the columns below.
For further revisions, insert the date, by whom and ref. be In the Risk
Register, strike out the text to be amended (do not remove)
e) and insert revised
revis
revi text. Adjust the
risk colour code as required. Revisions can be reviewed
viewed at Design Team meetings.
IM
Date By Ref. Details
EC
SP
Figure 4.1
Sample design risk register
73
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Hazard = Something with a potential to cause harm rm
m
Significant Risk = Risks that are not likely to bee obvious to a competent
compete Con-
com
tractor or other Designer, unusual or likelyy to
o be difficult to manage
mana effectively
manag
Substructure
SP
Superstucture
tucture
ucture
Services
Further information and guidance on Design Risk Management can be found on the APS website
at www.aps.org.uk/guidance/principal-designers-handbook
74
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Pre-Construction Phase, as the project proceeds.
nd of the proje
At the end project, th
the Principal Designer, or where there is no Principal
ner,
er, the Principal Contractor,
Designer, C must pass the Health and Safety File to
ent.
nt
the Client.
The File mustt ccontain information about the current project likely to be
needed to ensure health and safety during any subsequent work, such
as maintenance, cleaning, refurbishment or demolition.
75
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
When preparing the Health and Safety File, information on the following
should be considered for inclusion:
EN
• Hazardous materials used
ntling of installed plant
• Information regarding the removal or dismantling pl
and equipment
quipment provided
• Health and safety information about equipment provided for cleaning
IM
or maintaining the structure
kings of significant
• The nature, location and markings significant services,
s including
upply
pply equipment, fire-fighting
underground cables, gas supply fi services, etc
EC
uilt
ilt drawings of the building,
• Information and as-built b its plant
and equipment.
SP
76
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
A Health and Safety File should be prepared for every project involving more
than one Contractor, and this should be done proportionately depending on the
size and type of project. In some very small projects it may be sufficient for a
EN
ference,
erence, version number
The File should be properly titled with project (job) reference, num
and issue date.
[Project Title]
Health and Safety File
IM
Reference No [Reference Number] Version
Version [Version]
Date December 2015
EC
The File will be developedd at various stages in the life of a project, with
ant residual risks a
information on significant added to the working file as design
and construction work
orkk progresses. It is possible that the File could be issued
in an incomplete form for others to ccomplete – for example, if the Principal
Designer dutyy holder changes or terminates and the duty is handed to the
ractor.
Principal Contractor.
SP
77
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
ISSUE
E
Client [Organisation] [Name] Digital/
Digital/
hard copy
Designer 1 [Organisation] [Name]
me]
Designer 2 [Organisation] [Name]
e]
Principal [Organisation] [Name]
[Nam
IM
Designer
Principal [Organisation]
ation] [Name]
Contractor
EC
The table on Pagess 80 and 81 shows tthe structure of a Health and Safety File
cord with CDM 2015
prepared to accord 2015. It may also include an introduction, and
various appendices
endices necessary.
ndices as necessar
necessa
SP
ble
le also shows th
The table the ttypical sections within the Health and Safety File that
could contain
ontain useful inf in
information to impart to those who will undertake future
ction
ion work, including
construction i cleaning, maintenance, alterations, refurbishment
tion, tto be carried out safely. Descriptions can be omitted if there is
tion
and demolition,
no useful information to be included.
78
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The Client, under the CDM Regulations 2015 has the duty to:
• Ensure that the Health and Safety File is kept available for anyone who
needs it to comply with relevant legal requirements
• Pass the Health and Safety File to whoever takes over the structure and
EN
th health and safety
• Ensure that the Health and Safety File is updated with
information following any future work, maintenance refurbishment that
nce or refurbishm
refurbishmen
IM ore than one contra
falls within the remit of CDM 2015 involving more contractor.
As-built drawings for the works should be listed in tthe File. It is not necessary
rated
ted but they can b
for the drawing to be incorporated be if appropriate, particularly
when the information is provided
rovided
ovided digitally.
EC
ins
Variation Instructions or instructions issued directly to the site.
79
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
(b) Residual Any hazards that havee not
ot
hazards hrou
hrough
been eliminated through
IM
the design and construction
processes, and how they
have beenn addressed (e.g.
surveys information
ys or other informa
informat
EC
ncerning asbestos o
concerning or
contaminated land)
(c) Key structural structural principles
Key structura
principles (e.g. bracing
bracing, sources of
substantial stored energy
substant
SP
80
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
plant and such equipment)
equipment
icles)
vehicles)
81
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
Other information
EN
• Appendix B – asbestos survey (complete document)
nt)
• Appendix C – other survey information
82
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
KEY CDM ROLES
IM S
5.1 Précis of the duties of various duty
ty holders under C
CDM 2015
5.2 General duties
5.3 Client
5.4 Principal Designer (Pre-Construction
re onstruction Phase)
EC
5.5 Designer
5.6 Principal Contractor
ctor
5.7 Contractorss
5.8 Workers
SP
5.9 CDM
M Adviser (non-statutory
(no role)
Throughoutt this b
book, the other CDM 2015 duty holders and non statutory
roles have been referenced as part of the context within which the Principal
Designer works. This chapter explains the key roles and responsibilities of
the non-statutory CDM Adviser who may provide advice and guidance to the
duty holders.
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
are understood.
84
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
85
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
5.3 Client
The Client must:
EN
he project
health and safety risks to persons affected by the
welfare is provided for construction workers
rs
• Ensure arrangements are maintained and
d reviewed
viewed during the
t project
• Provide Pre-Construction Information
on as soon as is practicable
pr
prac to every
IM
Designer and Contractor appointed,
ed, Designers/Contractors
d, or potential De
Desi
• If there is more than one Contractor
tractor
tract any one time, appoint,
or on site, at a
as soon as practicable:
EC
Principal Designer
Principal Contractor
tractor
actor
• Failure to appoint
point the Principal Designer and Principal Contractor results
ppoint
in these roles
les and associated duties defaulting to the Client (except
SP
86
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
• Ensure that:
Principal Designer complies with Principal Designer duties
87
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
Health and Safety Files when:
design, technical and organisational aspects
cts for items of wor
work take place
simultaneously or in succession
estimating the period of time required
ired
red to complete suc
su
such work or
IM
work stages
• Identify, eliminate or control, so far
far as is reason
reasona
reasonably practicable,
foreseeable risks to the health
ealth any person:
lth or safety of an
EC
ure, in relation to th
• Ensure, the Pre-Construction Phase, all persons cooperate
with
h Client, Principal
Principa Designer and each other
he
e Clien
• Assist the Client in provision of Pre-Construction Information
• Provide Pre-Construction Information, promptly and in a convenient
form, to every Designer and Contractor appointed, or being considered
for appointment
88
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
89
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
5.5 Designer
The Designer must:
• Be satisfied that the Client is aware of their duties under CDM 2015
• When designing, take into account the General Principles of Prev
Prevention
and Pre-Construction Information to eliminate, so far ass is reasonab
reasonably
ty of any person:
practicable, foreseeable risks to the health and safety
EN
carrying out or liable to be affected by construction
uction wor
work
maintaining or cleaning a structure
using a structure designed as a workplace
kp
kplace
IM
• If the risks cannot be eliminated, the
he Designer must, so far as is
reasonably practicable:
take steps to reduce or control
ontrol the risks thr
th
through design
EC
provide information
n about those risks tto the Principal Designer
ensure appropriate
riate
ate information is included in the Health
and Safety File
ufficient
fficient information about the design, construction or
• Provide sufficient
SP
maintenance
nance of the structure,
enance structu to adequately assist the Client, other
Designers
gners and Contractors
igners Contrac
Contr to comply with their duties
• If appointing Designers abroad, ensure they undertake duties under
pointing Des
Desig
015
CDM 2015 5 for ddesigns outside Great Britain for construction work within
Great Britain.
ain
90
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
design, technical and organisational aspects are being decided
decide in order
to plan work taking place simultaneously or in succession
estimating the period of time required
d to complete
omplete the work
w or
work stages
IM
• Prepare a suitable Construction Phase
hase Plan before tthe Construction
Phase begins
tween
en Contractors
• Organise cooperation between
EC
• Coordinate implementation
ntation
nt Contractors of applicable legal
ation by Contract
Contracto
requirements for health
ealth and safety
• Ensure that employ
employers necessary for the protection of workers,
ers and, if ne
oyed
yed persons:
self-employed perso
SP
consistently
nsistently apply
app the General Principles of Prevention, and in particular
when
hen complying w wi
with the provisions of Part 4 (General requirements for
lll construction
all constructio sites)
where requ
required, follow the Construction Phase Plan
91
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Liaise with Principal Designer and share information relevant
on re
relevant to the
Construction Pha
planning, management, monitoring of the Pre-Construction Phase and
coordination of health and safety matters during Pre-Construction
ring the Pre-Constr
Phase
• Consult and engage with Workers.
IM
EC
SP
92
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
5.7 Contractors
Contractors must:
• Be satisfied that the Client is aware of their duties under CDM 2015
EN
and safety
rking on a project
• Where there is more than one Contractor working project,
comply with:
directions given by the Principal Designer
esigner or Principa
Principal Contractor
IM
relevant parts of the Construction
ction
on Phase Plan
• If there is only one Contractor project:
or working on the p
consider General Principles
inciples
nciples of Preventio
Preven
Prevention when:
EC
– design, technical
nical organisational aspects are being decided in
ical and organisatio
lan work ttaking
order to plan aking pl
plac
place simultaneously or in succession
– estimating
ating the period of ttime required to complete the work or
ork stages
work
SP
prepare
repare a suitable C
Construction Phase Plan before the Construction
Phase
hase begins
• Not employ
mploy o
or appoint a person unless they are capable
93
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
information on risks to health and safety
other information as necessary
• Not start work:
IM
unless prevention of access by unauthorised perso
persons to the site
ties
es are provided an
is in place and welfare facilities and maintained.
EC
SP
94
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
5.8 Workers
Workers are the people who work for or under the control of Contractors
on a construction site.
afety
ety and welfare
• Be consulted about matters that affect their health, safety welfar
EN
• Take care of their own health and safety and that of others who may be
b
affected by their actions
• Report anything they see which is likely to endanger
ndanger either their
th own
or others’ health and safety
IM
low
ow workers, Contra
• Cooperate with their employer, fellow Contr
Contractors and other
duty holders.
EC
SP
95
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The CDM Adviser need not be a Designer or Contractor, butut should have
EN
considerable and in-depth knowledge of construction health and safety. T
The
CDM Adviser to the Client could be the appointed Principal Designe
Designer, provided
nowledge and expe
they are a Designer and have sufficient skills, knowledge experience.
The main areas on which they can advise include:
clude:
de:
IM
• Preparation of a Client’s brief for the
e project
• Making suitable arrangements for
or managing the p
project, including time
and other resources
ements tto
• Making suitable arrangements o ensure
ure th
that the construction work can
EC
roject
the project
• Pre-Construction
e-Construction Information to be provided by the Client
Construction In
Inf
nstructio
structio Phase Plan drawn up by the Contractor or by the
• The Construction
Principal Contractor
Con
• Preparation of the Health and Safety File during the Pre-Construction
Phase
96
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
• Disposing of the building or structure and handing over
ove the
he Health
and Safety File
• Notification to the Health and Safety Executive,
ve, or the Office of Rail
ive,
Regulation, or the Office for Nuclear Regulation
ion instead of tthe Executive
gulation
as appropriate.
IM
The CDM Adviser can, if required, advise
ise the Client on tthe health and
dvise
safety skills, knowledge, experience
ence and, where it is an organisation, the
eso
organisational capability and resources off propos
prop
proposed Designers and/or
Contractors prior to arrangements
gement being mad
gements made for design or construction
m
EC
work to begin.
In circumstances
cumstances
mstances where the Lead Designer or the other Designers on the
projectt are unwilling
unwillin or incapable of undertaking the Principal Designer role,
but the Client
lient insistent on the Lead Designer (or one of the other Designers)
ent is ins
becoming the ePPrincipal Designer, the Lead Designer (or any of the other
Designers formally appointed as the Principal Designer) can appoint a design
organisation with the capability to undertake the Principal Designer duties, to
act as their Sub-consultant Adviser.
97
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
he appointed Princ
The Sub-consultant will be able to represent the Princi
Principal Designer
as required at design team and Principal Contractor
ontractor
actor liaison m
meetings, and at
site progress meetings.
propriate
ropriate profession
The Sub-consultant will carry appropriate professional indemnity insurance
sultant’s services.
for the delivery of the Sub-consultant’s
EC
98
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
SP
EN
Businesses to support Clients and project teams needing
ding to appoint with
M 2015 role.
confidence those that are capable of fulfilling a CDM
100
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
REFERENCE
h,, sa
to keep up-to-date with the latest issues in construction health, safety and
environmental risk management.The CPD Certification Service vice provid
provides
itation
support, advice and recognised independent CPD accreditationation compatib
compatible
EN
with global CPD principles.
As an APS member you will be kept up-to-date and well informed; you
will have access to the Members area of the APS bi-monthly
PS website, our bi
b
magazine, Digest, keeping you informed of important develodevelopments and
IM nd
issues in the sector, Practice notes, and d regular member eBulletins. In
addition to this you will have accesss to panel and legal advice
o our technical p
pa
ember
embers.
service, free of charge to APS Members.
EC
SP
101
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
EN
APS CDM 2015 – What Commercial Clients need to do:
https://www.aps.org.uk/guidance/cdm2015
CITB guides:
http://www.citb.co.uk/health-safety-and-other-topics/health-safety/construction-
o.uk/health-safety-and
design-and-management-regulations/
anagement-regulations
agement-regulations
SP
RIBA Plan
n of Work 2013: http://www.ribaplanofwork.com/
http://w
htt
Construction
tion Industry Council
ction Cou
C (CIC) Scope of Services:
http://cic.org.uk/services/the-cic-scope-of-services.php
rg.uk/service
uk/servic
102
Licensed copy from CIS: leedsm, LEEDS BECKETT UNIVERSITY, 17/03/2021, Uncontrolled Cop
The Handbook draws from the knowledge, skill and experience of The Association
for Project Safety (APS) and its members. The APS is the leading membership body
for design and construction health and safety risk management and its aims are to
improve and promote professional practice in these areas, through a programme
of delivering standards and providing guidance, education and training.