Open Cycle Gas Turbine Power Plant in Mossel Bay: Additional Units
Open Cycle Gas Turbine Power Plant in Mossel Bay: Additional Units
Open Cycle Gas Turbine Power Plant in Mossel Bay: Additional Units
Box 509
George
6530
November 2006
CONTENTS
Since then, there has been continued high growth in the demand for electricity.
Using the planning processes in place, Eskom has established that there is a need
for additional peaking capacity in order to meet the projected growth in demand for
electricity. The most feasible option to meet these needs by the winter of 2008 is to
install an additional 1050 MW of open cycle gas turbines. It is proposed that this
capacity be added to the Atlantis and Mossel Bay sites which are both currently
under construction. In order to meet the higher growth rate, Eskom has decided to
upgrade the OCGT power plant (which is currently under construction) by adding
three additional OCGT generating units immediately adjacent to it. Accordingly, in
terms of the National Environmental Management Act (NEMA) (No. 107 of 1998),
Eskom has appointed Ninham Shand Consulting Services to undertake this EIA for
the proposed three additional OCGT units and any additional supporting
infrastructure.
This Plan of Study for Environmental Impact Assessment (PoSEIA) has been
compiled in terms of Regulation 29 of the regulations published in Government
Notice No. R. 385, under Chapter 5 of NEMA. Its purpose is to ensure that the next
phase of this EIA process satisfies the requirements of the national Department of
Environmental Affairs and Tourism (DEAT) and the provincial DEA&DP.
1
Detailed background information is provided in the Scoping Report and accordingly only the
essential elements are reiterated here.
Conservation Act (ECA) (No. 73 of 1989), while the additional units will be
considered under the requirements of NEMA2.
At this point, it may be pertinent to clarify the terminology used in the current EIA
process:
This PoSEIA outlines the anticipated process and products for the EIA Phase of the
EIA process.
The proposed additional units would be located immediately to the west of the
present OCGT power plant and will be incorporated into the general OCGT power
plant precinct, i.e. the entire area would be fenced off with a single access road.
• A fuel storage facility with a total storage capacity of 5.4 million litres;
• Two conservancy tanks, each with a capacity of 6 000 litres;
• A control room;
• A fuel supply pipeline;
• A water supply pipeline; and
• A High Voltage (HV) yard.
At this stage of the feasibility and planning process, it is likely that the fuel storage
and conservancy tanks would be located between the existing OCGT units and the
proposed additional units. Fuel and water supply would be by means of
continuations of the existing pipelines within the OCGT precinct. The HV yard would
be located immediately north of the proposed two units and would enable the transfer
of the electricity generated via bus bars to the HV yard associated with the OCGT
power plant currently under construction. From there, electricity would be
2
ECA regulations pertaining to the undertaking of EIAs were replaced by NEMA regulations
in July 2006
transported to the Proteus substation via the authorised, and presently being
constructed, 400 kV transmission lines.
The following potential environmental impacts were identified and studied in depth by
appropriate specialists during the EIA for the approved OCGT plant:
• Impacts on flora;
• Impacts on avifauna;
• Impacts on air quality;
• Impacts of water consumption;
• Effluent impacts;
• Impact on traffic and access;
• Noise impacts;
• Socio-economic impacts;
• The impacts of existing infrastructure
• Visual impacts; and
• Impacts on heritage resources.
These potential impacts will be addressed in the EIA Phase of the present EIA
process. However, given the nature and extent of the proposed development of
three additional units, the most likely impacts of these impacts to require revision of
the specialist studies already undertaken are:
Each of these possible impacts will be the subject of a specific study that will be
reflected in a revision of the existing report dealing with that particular specialisation.
This section outlines the proposed method for assessing the significance of the
potential environmental impacts outlined above. As indicated, these include both
operational and construction phase impacts.
For each impact, the EXTENT (spatial scale), MAGNITUDE and DURATION (time
scale) would be described. These criteria would be used to ascertain the
SIGNIFICANCE of the impact, firstly in the case of no mitigation and then with the
most effective mitigation measure(s) in place. The mitigation described in the EIA
Report would represent the full range of plausible and pragmatic measures but does
not necessarily imply that they would be implemented.3
The tables on the following pages show the scales used to assess these variables,
and defines each of the rating categories.
The SIGNIFICANCE of an impact is derived by taking into account the temporal and
spatial scales and magnitude. The means of arriving at the different significance
ratings is explained in Table 2.
3
The proponent will be requested to indicate at the Draft EIA Report stage which mitigation
measures they are prepared to implement.
Medium • High magnitude with a local extent and medium term duration
• High magnitude with a regional extent and construction period or a site
specific extent and long term duration
• High magnitude with either a local extent and construction period duration
or a site specific extent and medium term duration
• Medium magnitude with any combination of extent and duration except site
specific and construction period or regional and long term
• Low magnitude with a regional extent and long term duration
Low • High magnitude with a site specific extent and construction period duration
• Medium magnitude with a site specific extent and construction period
duration
• Low magnitude with any combination of extent and duration except site
specific and construction period or regional and long term
• Very low magnitude with a regional extent and long term duration
Very low • Low magnitude with a site specific extent and construction period duration
• Very low magnitude with any combination of extent and duration except
regional and long term
Neutral • Zero magnitude with any combination of extent and duration
Once the significance of an impact has been determined, the PROBABILITY of this
impact occurring as well as the CONFIDENCE in the assessment of the impact
would be determined, using the rating systems outlined in Tables 3 and 4
respectively. It is important to note that the significance of an impact should always
be considered in concert with the probability of that impact occurring.
With reference to Section 3.2.1 above, and in discussion with the proponent,
authorities and interested and affected parties (I&APs), several impacts have been
The Terms of Reference (TOR) for these specialist investigations are detailed below.
As a consequence, I&APs have the opportunity to comment on the various TORs.
The ToR for the air quality study would be to revise and supplement the
existing air quality study for the OCGT power plant presently being
constructed, by taking into account an additional three OCGT generating
units. The ToR for the original OCGT air quality study are as follows:
o Construction emissions;
o Routine and upset emissions during normal operation;
o Emissions during shutdowns; and
o Effects of mitigation measures e.g. optimum stack height
and other engineering options.
The air quality impact assessment will be undertaken by Renee Thomas and
Yvonne Scorgie of AirShed Planning Professionals.
The ToR for the noise study would be to revise and supplement the existing
noise study for the OCGT power plant presently being constructed, by
taking into account an additional three OCGT generating units. The ToR for
the original OCGT air quality study are as follows:
The ToR for the visual impact assessment would be to revise and
supplement the existing visual impact study for the OCGT power plant
presently being constructed, by taking into account an additional three
OCGT generating units. The ToR for the original OCGT visual impact study
are as follows:
The ToR for the ecological assessment would be to revise and supplement
the existing ecological study for the OCGT power plant presently being
constructed, by taking into account an additional three OCGT generating
units. The ToR for the original OCGT ecological impact study are as
follows4::
4
Derived from the Botanical Society of SA Conservation Unit’s Recommended Terms of
Reference for the Consideration of Biodiversity in Environmental Assessment and Decision-
making. March2005.
The proposed additional units are essentially an upgrading of the OCGT power plant
and accordingly alternative geographical locations will not be considered in this EIA.
In terms of specific sites, the area to the west of the OCGT power plant is the only
feasible option. This is due to the OCGT HV yard to the north, PetroSA’s expansion
plans to the east and the potential expansion of the landfill site to the south.
Alternative technologies for this capacity increase will not be considered in this
Scoping and EIA process. The power station currently under construction comprises
OCGT technology. OCGT technology is essentially off-the-shelf, and using this
technology, from a construction and commissioning period point-of-view, will assist in
meeting the deadline of winter 2008 for the additional units to be operational. OCGT
plant is also the most economical supply side option at low load factors. Hence
process alternatives will not be considered further in this Scoping and EIA process.
Specific mitigation measures will be identified and assessed during the EIA Phase.
The purpose of the Public Participation Process is to provide the I&APs (key
stakeholders and the public) with adequate opportunity to have input into the
environmental process. A comprehensive public consultation process will
underpinned the entire EIA process.
The approach to the public participation has been informed by the NEMA
EIA regulations (Regulation No.385). The key components of the public
participation during the Scoping Phase are summarised below:
The Draft Scoping Report has been finalised in light of all comments received
during the Public Participation Process and submitted to DEA&DP.
DEA&DP’s acceptance of the Final Scoping Report and Plan of Study for EIA
will then allow the EIA Phase to proceed.
Following the completion of the Draft EIA Report (refer to Section 3.2.6
below), it will be lodged at the Mossel Bay and D’Almeida libraries and on
the Eskom website (www.eskom.co.za/eia). Registered I&APs will be
notified of the lodging by means of letters, and given a 30 day period in
which to comment on the report. During the comment period, a public
meeting would be held to enable I&APs to provide feedback on the draft
report. The public meeting would be advertised in the local media and in the
same letters used to inform the I&APs of the release of the Draft Report.
All registered I&APs would be notified in writing of the release of the Record
of Decision by the environmental authority. They would be reminded of their
right to appeal against the authority’s decision, in terms of NEMA.
• A revision of the generic operational phase EMP, which would set environmental
guidelines for the operation phase of the proposed OCGT power plant and
associated infrastructure.
The Draft EIR will be released in the last week of January 2007. Given a 30 day
public comment period, the finalised EIA Report should be available by the end of
February 2007.
___________________________________________________________