Determination of Setting Time of Hydraulic Cement

Arc C. Villanueva BCE-22L (7110)

BSCE- STRUCTURAL 03-15-2022

Determination of Setting Time of Hydraulic Cement


Reference Standard
ASTM C 191-42
AASHTO T 131-93

Objectives:
1. To determine time of set of hydraulic cement using Vicat Apparatus
2. To evaluate the setting of the tested Portland cement based on the required
initial setting time.

Apparatus/Material

Portland Cement Sample Balance Sensitive to 0.1 gm


Vicat Apparatus #200 Sieve
Mixing Container Spatula

Drawing:
Observation:
Trial No. Penetration Reading Time
1 0 mm 0 min
2 1 mm 10 min
3 2 mm 20 min
4 3.4 mm 30 min
5 5 mm 40 min

FINAL SETTING TIME= 480 MINUTES


INITIAL SETTING TIME: 40 MINS
Result and Discussion:
A cement is any substance that, by a series of chemical reactions known as setting,
binds other materials together. Cements are dry powders that are not to be mistaken with
concrete or mortar, yet they are a key component of both of these materials, acting as the
'glue' that gives buildings their strength. It is utilized in the construction of many of the
modern world's structures, including buildings, bridges, ports, runways, and roadways. It's
also utilized for building facades and other ornamental elements. Cement is the world's
second most used commodity, behind water, because to the continual need for all of these
constructions, which is progressively coming from the developing world.
The interval between combining cement and water and the mixture starting to lose
its flexibility is referred to as the initial setting. It is the time elapsed until the cement paste
stiffens and the needle cannot go within 5 mm to down. On the other hand, the time it
takes cement to finally set the mixture is known as final setting time.

Initial setting time: 40 mins


Conclusion:
Therefore, the time to reach 5 mm is within 4o mins and to finally set it up is 480
minutes. Setting time are very important in construction. This will decide various factors like
Strength of concrete, Grade of concrete , Work-ability , Type of construction , Curing time ,
and Mixture proportions and many other factors
Post lab question:

1. Are there differences in the standard setting time of the various types of Portland cement?
Why or Why not?
The type of cement used in concrete has a direct impact on its strength, durability,
shrinkage, and life. There are many different types of cement on the market. Ordinary
Portland cement, Portland pozzolana cement, hydrophobic cement, coloured cement, high
alumina cement, quick hardening cement, and so on are only a few examples. All of these
varieties are employed in accordance with our requirements. They're all different depending
on what they're used for.

2. Relate cement fineness to its time of setting and the development of its strength.
The fineness of the cement is determined by the particle size. The needed fineness
of excellent cement is attained in the final phase of the cement manufacturing process by
grinding the clinker. Cement fineness is critical because cement hydration rate is directly
proportional to cement particle size.
Thus, the time setting will help the cement to develop its strength through that is
why there was an initial time where the cement it started to lose it flexibility and it will
reach its final composition as hard, this give enough strength to be compactly durable.