Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Untitled

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 9

-

Description
A. SUB STRA CTVRE
1 EXCA 1 -1 TION AND EARTH WORK
Pit Excavation for pole of 80cmx80cm not exceeding to depth of 150cm
from OGLat 30M interval and as per th
engineer's order

Excavation for laying pvc,


demolishing exsting
lerazzo. cobblestone .etc. Price should include
reconstructing cobble stone.terrazzoo of the same
amount of cobble stone&terazzo

Well compacted back fill after laying PVC pipe and


casting concrete footing using selecting material.
Cart away for surplus excavated materials where by the
order of site Engineer .
Total carried to summary
2. Concrete work (Pole foundation)
10cm thick lean concrete under Pit (C-7)
Reinforced concrete class C-25 pole foundation
Provide, cut and fix in position for form work for footing

by the order of site Engineer

Use Tie stirrups 08mm Hqrizontal mesh as site engineer


recommendation

Use steel reinforcement of 0 10mm vertical mesh pole

foundation

supply and install J-bolt of 1.8 length . diamete 24mm

with nut and washer


Total carried to summary
B. Electromechanical Works
3.EXTENAL LIGHTING AUNDER GROUND
CABLES
Supply and install flexible non metalic or PVC
pipes of outer diameter 50mm
Supply and istall flexible HDP pipes of outer
diameter 75mm
Supply and istall 4 wire .3 phase of 4*l6mm2under
ground CU/XLPE/PVC/PVC cable
(upply and istall 4 wire . 3 phase of 4*!6mm2under
•round CU/XLPE/PVC/PVC cable from KWH metre
o Electric Board and pole
pply and istall cable connector within cable
ermination
c able joint box
Supply and fix ! 6.4 fuse A fine bolder at the base of
the pole connecting the cablex
Total carried to summary

4 FIXTURES FINISHINGS
supply and install a copper conductor. PVC
sheathed 0.6/1 KV 2x2.5ntm2 cable from the box at
the bottom of the pole to the lamp

Supply and install oj high impact energy efficient street


lighting system fixtures with LED street lights which is
equiped with LED driver of input AC voltage 180-270
and output DC voltage 24-36 Quality certificate ISO
or CE and Lab test certificate for LED lamps is
mandatory. It has also SPD of at least 10 Kt7 ,
die cast
Aluminium closures LED street light must be of
120watt.

Total carried to summary


5. REDDER PILLAR
Supply, fix, and test, then commission MDB external
lighting control box, factory-made, containing three
phase switch of 100A, two circuit breakers of80A,
two contactors of 80A, 25 A photocell and 25 A timer
controller, 80A Bus-bars, waterproof and protection
materials, and all other accessories as per
standards, the 'Standards' documents of the control
box shall be approved by the employer's engineer of
80*80*60cm .Supply and Install 2.5 meter Painted
RUS Iron Pole for Hang made from 1.25cm thick
steel sheet tube fixed at RC footing of 50*50*70cm

Total carried to summary


6 POLES & ARM

Supply, erect (Install), test and commission of 7m high


external coaled. 3.0mm thick galvanized circular street
lighting pole with bottom diameter 180mm. top diameter
70mm with standing a gusted wind velocity of 1

60km/hr
screws & cover all material utilized by pole should be
high quality product , manufacturer Authorization
,ISO of manufacturing company &. CE of the products,
thickness of 3.0mm, baseplate 330x330x1 Omni with
single arm standard and pipe type bracket 1500mm long
and 100mm long 60mm diameter and with all
accessories, tying nuts, washer.melal plate.cost should
include flag holder Shall be as included on the detail
drawing. ----------

Total carried to summary


TOTAL
VAT
GRAND TOTAL

Prepared By. -----------


Sign ________________________
Date _
Checked By_
Sign ____
Date _ —
LED Streetlight Waliso-UHDP-CW- 017-2014
Locations In Side H'oliso Town
Description
A .Sub Structure
L Excavation and Earth work

■ faring over site to remove all objectionable materials and


.e tablcs to an average depth of 20 cm. ___

/ rench excavation for masonary wall in ordinary foil to a


depth
of 7Qcm starting from reduced level __

Hack fill with compaction around and below fooling pad w uh


non expansive granular selected material from selected

Cort away surplus unwanted excavated material anddepout


at
L distance not exceeding 2km from out the of site.
Total Carried to summary Birr
__2. Masoiian Work _______

An average of 50cm thick hard tracheytic stone masonry


wall bedded in cement mortar 1
:3 __

An average of 25cm thick hard tracheytic crushed stone for


upper and lower pans of masonary on selected soil with
cement mortar 1
:3
4cm thick cement screed copping at the top of Rc slab with
cement mortar 1
:3 ratio
Total Carried to summary Birr __________________
Total-A
B. Super Structure
I. Concrete Work

Reinforced concrete quality c-25 with 360kgcemcnt M of


concrete filled m to form work and vibrated around rod
reinforcement bars __
a In elevation columns
b Grade beams and Tie beams ___
c suspending slab 20cm thickness

provide . cut and fix in position metal pane! or sou n cigba


form
work
_______

A ir according to Mnctxrul dnn <ng Price


U i cutting be/>di*g. otpo * <f

beam and grade beams.


Diameter 12 mm deformed bars for Tup Slab
1 'tameter Xmm de termed bars f>r S':

2 finishing wyrh

finishing Mtvi shall imlude all surface pre-cleuAOtg


preparation uppluxitusn of finish. pduhsng and lieana at the
end <f finishing wank.
J, TRIXSFOIWFR
USUI RUFO M IMA
n Side H'oliso Town

You might also like