BQ With Priced (Water Tank)

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 107

BILL NO.

2 - PILING WORKS (ALL PROVISIONAL)


Item Description Unit Qty Rate (RM) Amount (RM)

PILING WORKS

GENERALLY

The Contractor shall take note that the quantities of works


inrespect of Piling Works are Provisional Quantities. The
amount to be paid to the Contractor in respect of the said
work upon completion of this Contract shall be ascertained by
REMEASUREMENT as they are actually executed.

The rates set down by the Contractor against each item in the
Provisional Bills of Quantities, after adjustment if necessary by
the S.O. to his reasonableness, shall become the basis of
valuation for interim payments and variation works.

The Contractor shall be deemed to have read the provisions


in Specifications in regard to Piling Works. All piles supplied
shall be in accordance to JKR standard specifications.

The Contractor shall also note that the prices inserted against
the items for provision, mobilisation and de-mobilisation of all
necessary equipment, plant, tools and ancillaries are on lump
sum basis and are not adjustable whatsoever.

The payable length for driving shall be measured from the toe
of pile to the commencing surface of driving.

The Contractor's prices shall be deemed to include for


driving piles from any other level than the existing ground
level.

Piles shall be driven to the required set or otherwise directed


by the S.O.

The rates shall include for handling, transporting, pitching and


driving piles in singly and or in cluster.

The rates shall include for all items as described in the


Specifications including wastage, carting away remaining
materials, etc.

Hammer should comply with Local Authorities requirement.

TO COLLECTION -
PW/2/1
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

PILING WORKS….Cont'd

GENERALLY….Cont'd

A Allow for the provision of all temporary works including ITEM 2,000.00 2,000.00
staging etc. for piles to be installed on slopes, edges of
building platforms and the like.

B Allow for the protection, maintenance and removal of all ITEM 2,000.00 2,000.00
existing services, pipes, chutes, sewers, manholes, mains,
underground and overhead cables, street lights etc. during the
execution of the Works.

EQUIPMENT AND PLANT

C Allow for provision of all necessary piling equipment, plant, ITEM 15,000.00 15,000.00
cranes, tools and ancillary equipment and for their
transportation to site, at various formation levels, handling,
assembling, erecting, dismantling and removal on completion
of piling works.

D Allow for moving and handling piling equipment, plant, cranes, ITEM 7,000.00 7,000.00
tools and ancillary equipment about the site as often and
whenever necessary for the execution of the whole piling
operation etc. including all idling time and any excavation and
earthwork support for the movement of the piling frames plant,
equipment and tools and any necessary filling in and
compaction including the provision of any hardstanding and
platform and staging required for moving the piling equipment,
plant, cranes, tools and ancillary equipment from differing
levels of the site.

PILING RECORDS

E Allow for the submission of piling results as described duly ITEM 2,000.00 2,000.00
signed by the Contractor and S.O.'s representatives and
delivering same to the S.O. as work proceeds. The Contractor
should submit one set of as-built tracings on polyester film on
piling completion including of as built works on autocad
diskette when directed by the S.O.

F Allow for the submission of piling setting out drawings as ITEM 4,500.00 4,500.00
described duly signed by licensed surveyor before proceeding
with other works.

Soil Investigation

G To carried out mackintosh probe on site all as per Engineer NO 5 3,000.00 15,000.00
approval and instructions.

PW/2/2
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 47,500.00

PILING WORKS….Cont'd

PDA TEST

A Provide Pile Driving Analysis (PDA) integrity test using sonic NO 4 950.00 3,800.00
logging method and providing all necessary materials,
equipments, labour, records and submission of records.

STATIC LOAD TEST

Provide all equipment, kentledge, etc. And test all intial test
pile up to twice working load as required before commencing
the piling works and subsequent removal from site all
materials, equipment and knowledge and reinstate all
temporary excavation necessary for the execution and
complete of the loading

B Static maintain load test on 300mm x 300mm pile working NO 2 10,000.00 20,000.00
load test as approved by engineer

C Subsequent load test on 300mm x 300mm pile NO 3 4,000.00 12,000.00

Supply, delivery and unload of approved precast concrete


piles complete with shoes, spice joints, all necessary
components to the satisfaction of the S.O (extension joints
measured separately) :-

D 300mm x 300mm Initial pile; in 12.00m length M 1,320 68.00 89,760.00


(In 110 nos.)

E 300mm x 300mm Extension pile; in 9.00m length M 990 70.00 69,300.00


(In 110 nos.)

Handle, transport, pitch and drive of approved precast


concrete piles

G 300mm x 300mm (In 110 nos.) M 2,310 6.00 13,860.00

Fillet weld connection between edges of mild steel extension


cap and base plate including two coats of bituminous paint to
all exposed fillet welds surfaces

H 12mm x 12mm; 1200mm girth NO 110 68.00 7,480.00

PW/2/3
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION 216,200.00

PILING WORKS….Cont'd

Cut-off pile head at the required cut-off level including


trimming, stripping, dressing for key, straigthening and
bending bars as necessary in position for pile cap connection,
all necessary tying wires and remove all debris and surplus
length of pile.

A 300mm x 300mm piles NO 110 20.00 2,200.00

B Prepare surfaces of 300mm x 300mm precast concrete pile NO 110 5.00 550.00
head as required to receice pile cap.

TO COLLECTION 2,750.00

COLLECTION

From Page PW/2/2 47,500.00

From Page PW/2/3 216,200.00

From Page PW/2/4 2,750.00

PW/2/4
BILL NO. 2 - PILING WORKS (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TOTAL CARRIED TO SUMMARY OF TENDER 266,450.00

PW/2/5
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

SUBSTRUCTURE

EXCAVATION WORK

Excavating to reduce level; commencing from formation level;


cart away, deposit, spread and level where directed within the
site not exceeding 1.00m deep.

A 150mm thick (Ground slab) M3 102 10.00

Excavate trenches starting from reduced level; including


backfill with approved excavated material, compaction in
layers and disposal of surplus excavated material where
directed within the site not exceeding 1.00m deep

B Ground beam M3 10 10.00

Excavate pit starting from reduced level; including backfill with


approved excavated material, compaction in layers and
disposal of surplus excavated material where directed within
the site not exceeding 2.00m deep.

C Pilecap M3 241 10.00

Bed of hardcore consisting of hard dry broken bricks or stones,


spread or leveled, well consolidated, watered and well blinded
with sand

D 150mm Thick ; under ground slab M2 291 12.00

PLAIN INSITU CONCRETE WORK

50mm Thick Concrete (Grade 15) as described blinding:

E Under pilecap M2 83 9.00

F Under ground beam M2 98 9.00

G Under ground slab M2 291 9.00

CONCRETE WORK

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in :

H Pilecap M3 60 310.00

J Column Stump ( Provisional ) M3 15 310.00

K Ground beam M3 59 310.00

L Ground slab M3 44 310.00

EWT/3/1/6
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TO COLLECTION

CONCRETE WORK...(CONT'D)

Sawn formwork as described to:

A Sides of pilecap M2 140 35.00

B Sides of column stump ( Provisional ) M2 117 35.00

C Sides of ground beam M2 476 35.00

Mild steel (250 N/mm2) rod reinforcement as described :

In column stump ( Provisional )

D 10mm Diameter rod as links, stirrups or binders KG 396 3.80

In ground beam

E 10mm Diameter rod as links, stirrups or binders KG 1,393 3.80

High tensile (460 N/mm2) rod reinforcement as described :

In pilecap

F 12mm Diameter rod as links, stirrups or binders KG 416 3.80

G 16mm Diameter rod as links, stirrups or binders KG 203 3.80

H 20mm Diameter rod KG 8,191 3.80

J 25mm Diameter rod KG 1,527 3.80

In column stump ( Provisional )

K 16mm Diameter rod KG 1,761 3.80

In ground beam

L 12mm Diameter rod KG 688 3.80

M 16mm Diameter rod KG 1,422 3.80

N 32mm Diameter rod KG 1,612 3.80

In ground slab

P 10mm Diameter rod KG 2,290 3.80

0.25mmThick approved polythene sheet (heavy duty) as


described damp proof membrane laid on ground slab and
beam and well lapped at joint (measured nett-no allowance
made for laps)

Q Ground slab M2 291 4.50

EWT/3/1/7
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

TO COLLECTION

ANTI-TERMITE TREATMENT

The termite treatment application shall be carried by termite


control company approved by S.O.

Method of treatment shall be submitted to the S.O. for


approval. All relevant documents, certificates of approval,
guarantee letters, brochures and technical catalogues shall be
submitted to the S.O.before commencement of works

The Contractor shall be held responsible on all work done by


the termite control company

A ITEM 1,000.00
The Contractor and specialist firm shall guarantee the
effectiveness of anti-termite treatment for a period of five (5)
years and undertake to carry re-treatment without charge
should infestation of sub-terranean termites occur at any time
during the warranty period.

Carry out anti-termite treatment in accordance with the


specifications as described to :

B Under Pile Cap M2 83 3.50

C Under ground Beam M2 98 3.50

D Under ground slab M2 291 3.50

TO COLLECTION

COLLECTION

From Page EWT/3/1/1

From Page EWT/3/1/2

From Page EWT/3/1/3

EWT/3/1/8
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

TOTAL CARRIED TO SUMMARY

EWT/3/1/9
R TANK (ALL PROVISIONAL)
Amount (RM)

1,020.00

100.00

2,410.00

3,492.00

747.00

882.00

2,619.00

18,600.00

4,650.00

18,290.00

13,640.00

EWT/3/1/10
R TANK (ALL PROVISIONAL)
Amount (RM)
66,450.00

4,900.00

4,095.00

16,660.00

1,504.80

5,293.40

1,580.80

771.40

31,125.80

5,802.60

6,691.80

2,614.40

5,403.60

6,125.60

8,702.00

1,309.50

EWT/3/1/11
R TANK (ALL PROVISIONAL)
Amount (RM)

102,580.70

1,000.00

290.50

343.00

1,018.50

2,652.00

66,450.00

102,580.70

2,652.00

EWT/3/1/12
R TANK (ALL PROVISIONAL)
Amount (RM)

171,682.70

EWT/3/1/13
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

FRAME

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in:

A Column M3 54 310.00

B Suspended beam M3 112 310.00

C Wall Tank M3 90 310.00

Sawn formwork as decribed to:

D Sides; vertical of column M2 290 35.00

Sides and soffit of the like ; horizontal including strutting not


exceeding 3.50m high.

E Suspended beam M2 292 35.00

Sides and soffit of the like ; horizontal including strutting


exceeding 5.00m high but not exceeding 6.50m high.

F Suspended beam M2 671 35.00

Sides and soffit of the like ; horizontal including strutting


exceeding 6.50m high but not exceeding 8.00m high.

G Suspended beam M2 182 35.00

H Sides of Wall Tank M2 720 35.00

Mild steel (250 N/mm2) rod reinforcement as described :

Column

J 10mm diameter rod as links, stirrups or binders KG 1,529 3.80

Suspended beam

K 10mm diameter rod as links, stirrups or binders KG 5,946 3.80

High tensile (460 N/mm2) rod reinforcement as described:

Column

L 12mm diameter rod KG 36 3.80

M 16mm diameter rod KG 5,950 3.80

EWT/3/2/14
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TO COLLECTION

FRAME.... Cont'd

High tensile (460 N/mm2) rod reinforcement as described: (cont'd)....

Suspended beam

A 12mm diameter rod KG 1,887 3.80

B 16mm diameter rod KG 2,914 3.80

C 20mm diameter rod KG 1,057 3.80

D 25mm diameter rod KG 1,423 3.80

E 32mm diameter rod KG 6,651 3.80

Wall Tank

F 10mm diameter rod KG 4,808 3.80

G 12mm diameter rod KG 2,668 3.80

TO COLLECTION

COLLECTION

From Page EWT/3/2/1

From Page EWT/3/2/2

EWT/3/2/15
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

TOTAL CARRIED TO SUMMARY

EWT/3/2/16
R TANK (ALL PROVISIONAL)
Amount (RM)

16,740.00

34,720.00

27,900.00

10,150.00

10,220.00

23,485.00

6,370.00

25,200.00

5,810.20

22,594.80

136.80

22,610.00

EWT/3/2/17
R TANK (ALL PROVISIONAL)
Amount (RM)
205,936.80

7,170.60

11,073.20

4,016.60

5,407.40

25,273.80

18,270.40

10,138.40

81,350.40

205,936.80

81,350.40

EWT/3/2/18
R TANK (ALL PROVISIONAL)
Amount (RM)

287,287.20

EWT/3/2/19
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

UPPER FLOOR

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in :

Suspended slab

A 300mm thick M3 186 310.00

Sawn formwork as described to:

Sides and soffit of the like ; horizontal including strutting


exceeding 5.00m high but not exceeding 6.50m high.

B Suspended slab M2 617 35.00

High tensile (460 N/mm2) rod reinforcement as described:

C 10mm diameter rod KG 5,328 3.80

TOTAL CARRIED TO SUMMARY

EWT/3/3/20
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TOTAL CARRIED TO SUMMARY

EWT/3/3/21
R TANK (ALL PROVISIONAL)
Amount (RM)

57,660.00

21,595.00

20,246.40

EWT/3/3/22
R TANK (ALL PROVISIONAL)
Amount (RM)
99,501.40

EWT/3/3/23
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)

ROOF

REINFORCED INSITU CONCRETE WORK

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in :

A Roof Slab (200mm thick) M3 88 310.00 27,280.00

B Roof beam M3 19 310.00 5,890.00

C Upper Roof Slab (200mm thick) M3 5 310.00 1,550.00

D Upper Roof beam M3 2 310.00 620.00

Sawn formwork as described to:

Sides and soffit of the like ; horizontal including strutting


exceeding 9.50m high but not exceeding 11.00m high.

E Roof slab M2 441 35.00 15,435.00

F Roof beam M2 236 35.00 8,260.00

Sides and soffit of the like ; horizontal including strutting


exceeding 11.0m high but not exceeding 12.5m high.

G Upper Roof Slab M2 25 35.00 875.00

H Upper Roof beam M2 31 35.00 1,085.00

Mild steel (250 N/mm2) rod reinforcement as described :

In roof slab

J 10mm Diameter rod as links; stirrups or binders KG 3,906 3.80 14,842.80

In roof beam

K 10mm Diameter rod as links; stirrups or binders KG 841 3.80 3,195.80

In Upper roof beam

L 10mm Diameter rod as links; stirrups or binders KG 136 3.80 516.80

TO COLLECTION 79,550.40

EWT/3/4/24
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)

REINFORCED INSITU CONCRETE WORK...(Cont'd)

High steel (460 N/mm2) rod reinforcement as described:

In roof beam

A 12mm Diameter rod KG 340 3.80 1,292.00

B 16mm Diameter rod KG 468 3.80 1,778.40

C 20mm Diameter rod KG 351 3.80 1,333.80

D 25mm Diameter rod KG 517 3.80 1,964.60

E 32mm Diameter rod KG 1,172 3.80 4,453.60

In upper roof beam

F 12mm Diameter rod KG 166 3.80 630.80

In upper roof slab

G 10mm Diameter rod KG 231 3.80 877.80

-----------------------------

H Approved 1500mm x 1500mm x 10mm thick hot deep NO 1 2,500.00 2,500.00


galvanised plate access manhole complete with 10mm
diameter hole embedded on stainless steel including frame,
handhold and accessories all as per Engineer detail drawing.

TO COLLECTION 14,831.00

COLLECTION

From Page EWT/3/4/1 79,550.40

From Page EWT/3/4/2 14,831.00

TOTAL CARRIED TO SUMMARY


EWT/3/4/25
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
TOTAL CARRIED TO SUMMARY 94,381.40

EWT/3/4/26
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)

STAIRCASE AND FINISHES

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in:

A Staircase ; step M3 3 310.00

B Landing slab ; 150mm thick M3 2 310.00

Sawn formwork as described to:

Risers; undercut

C Exceeding 100mm but not exceeding 200mm high M 52 7.00

D Sloping soffit of staircase M2 17 35.00

E Soffit and edges of landing slab M2 12 35.00

Raking side of stair; to profile of treads and risers

F 350mm wide extreme M 27 12.25

High tensile (460N/mm2) rod reinforcement as described:

10mm Diameter rod

G In Staircase KG 173 3.80

H In Landing slab KG 115 3.80

20mm thick cement and sand (1:3) as described paving


trowelled smooth

J Tread; 250mm wide M 52 3.00

K Riser; 150mm high M 52 1.80

L Landing slab M2 6 12.00

20mm thick cement and sand (1:3) as described plastering


finished with a steel trowel

M Side and Soffit of landing slab M 30 35.00

N Sloping soffit of staircase M 17 35.00

P Raking sides of staircase 350mm wide M 27 12.25

Acrylic External Paint

Q Prepare and apply approved 'Wheatherbond' paint to all M2 49 15.00


exposed surfaces of staircase all as per manufacturer's
recommendation and instruction.

TOTAL CARRIED TO SUMMARY

EWT/3/5/27
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Item Description Unit Qty Rate (RM)
TOTAL CARRIED TO SUMMARY

EWT/3/5/28
R TANK (ALL PROVISIONAL)
Amount (RM)

930.00

620.00

364.00

595.00

420.00

330.75

657.40

437.00

156.00

93.60

72.00

1,050.00

595.00

330.75

735.00

EWT/3/5/29
R TANK (ALL PROVISIONAL)
Amount (RM)
7,386.50

EWT/3/5/30
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)

WALL FINISHES

EXTERNAL

20mm Thick cement and sand (1:6) as described plastering


finished with a steel float:

A Wall M2 360 14.00 5,040.00

B Column M2 290 14.00 4,060.00

C Beam M2 1,412 14.00 19,768.00

Acrylic External Paint

Prepare and apply approved 'Wheatherbond' paint to all


exposed surfaces of water tank all as per manufacturer's
recommendation and instruction.

D Wall M2 360 15.00 5,400.00

E Column M2 290 15.00 4,350.00

F Beam M2 1,412 15.00 21,180.00

INTERNAL

20mm thick cement and sand (1:6) as described plastering


finished with a steel trowelled :

G Wall M2 360 14.00 5,040.00

Prepare and apply approved waterproofing system with a


layer insulation foam and serperation felt including all turn-
ups 300mm high at junctions and complete with all necessary
accessories laid in strict accordance to manufacturer's with
ten (10) years guarantee (measured nett-no allowance for
lap).

H General surface of wall M2 360 35.00 12,600.00

Construction Joints

J Construction joint size 38m x 25m x 200mm for elevated M 102 30.00 3,060.00
water tank wall including 25mm x 25mm plastic joint with
approved polysulphate sealant or equivalent as per S.O
approval.

Water Stop

K M 306 85.00 26,010.00


Approved 150mm x 50mm thick rubber water bar dumbbell
including 25mm x 25mm plastic joint to water tank wall.

L M 188 180.00 33,840.00


Approved 1.6mm Thick x 200mm wide copper strip encase in
trunking (approved by SAJ) to water tank wall.

TOTAL CARRIED TO SUMMARY 140,348.00

EWT/3/6/31
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
TOTAL CARRIED TO SUMMARY (RM) (RM)

EWT/3/6/32
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)

FLOOR FINISHES

EXTERNAL

20mm Thick cement and sand (1:3) as described paving


trowelled smooth:

A General surfaces of floor M2 539 12.00 6,468.00

INTERNAL

25mm Thick cement and sand (1:3) as described paving


trowelled smooth:

B General surfaces of floor M2 450 12.00 5,400.00

Prepare and apply approved waterproofing system with a


layer insulation foam and serperation felt including all turn-
ups 300mm high at junctions and complete with all necessary
accessories laid in strict accordance to manufacturer's with
ten (10) years guarantee (measured nett-no allowance for
lap).

C General surface of floor M2 450 35.00 15,750.00

Water Stop

D M 141 85.00 11,985.00


Approved 150mm wide rearguard water stop or equivalent to
water tank slab including 25mm x 25mm plastic joint infill.

Construction Joints

E Construction joint size 38m x 25m x 200mm for elevated M 102 30.00 3,060.00
water tank wall including 25mm x 25mm plastic joint with
approved polysulphate sealant or equivalent as per S.O
approval.

TOTAL CARRIED TO SUMMARY


EWT/3/7/33
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
TOTAL CARRIED TO SUMMARY 42,663.00

EWT/3/7/34
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)

SUNDRIES

Railings

Galvanised Iron railing constructed of 48mm diameter x


3.2mm thick handrail, 38mm diameter x 3.2mm thick
intermediate and 150mm x 75mm x 12mm thick post railing
complete with 2 nos M12 holding down bolts including welded
together and fixing to reinforced concrete slab all finish with
epoxy painting as per engineer detail drawing.

A 1000mm high M 34 180.00 6,120.00

Cat Ladder

Galvanised Iron catledder constructed of 65mm x 10mm flat


bar, 50mm x 50mm x 6mm thick stringer bracket and 24mm
diameter x 2.6mm thick rung complete with 62.5mm x 62.5mm
x 6.3mm thick galvanised iron angle including welded together
and fixing to reinforced concrete slab all finish with epoxy
painting as per engineer detail drawing and manufacturer
detail.

B 5000mm high NO 2 2,000.00 4,000.00

Stainless steel catledder constructed of 500mm wide, 25mm


diameter x 2.6mm thick, 65mm x 12m flat bar, 50mm x 50mm
x 10mm thick stringer bracket and 34mm diameter x 2.6mm
thick rung complete with 62.5mm x 62.5mm x 6.3mm thick
galvanised iron angle including welded together, 16mm
diameter rag bolt and fixing to reinforced concrete wall all
finish with epoxy painting as per engineer detail drawing and
manufacturer detail.

C 4000mm high NO 1 2,000.00 2,000.00

Netlon CE 161

Supply and fix complete in position approved aluminium leaf


and frame with Netlon CE 161 or other equal and approved
insect proof screen as per Engineer detail drawing.

D 1200mm x 900mm high NO 2 1,000.00 2,000.00

----------------------------

E Supply and install complete approved lightning protection as ITEM 3,000.00 3,000.00
per Engineer detail drawing.

TOTAL CARRIED TO SUMMARY


EWT/3/8/35
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate Amount
Item Description Unit Qty
(RM) (RM)
TOTAL CARRIED TO SUMMARY 17,120.00

EWT/3/8/36
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate
Item Description Unit Qty
(RM)

ELEMENT 13 - SUNDRIES

Cat Ladder

Aluminium catladder with 75mm x 20mm thick


aluminium flats and 25mm diameter rings at
300mm centres and including galvanised
mild steel safety ring including fixing to
reinforced concrete all as detailed in drawing
to serve:

A floor height 5000mm NO 2

B Supply and fix complete in position approved NO 4


aluminium leaf and frame with Netlon CE 161
or other equal and approved insect proof
screen

Water Stop

C 238mm Wide rearguard water stop or M


equivalent to reservoir slab including plastic
infill

D 225mm Wide rubber water bar dumbbell M


to reservoir wall

E 1.6mm Thick 200mm wide copper strip to M


reservoir wall

Construction Joints

F Construction joint size 38m x 25m x 200mm M


for reservoir wall and slab with approved
polysulphate sealant or equivalent as detail
in drawing

Inlet Pipe

Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-

A 150mm diameter pipe M

B 250mm diameter pipe M

PP/6/13/37
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)
Rate
Item Description Unit Qty
(RM)
TO COLLECTION

PP/6/13/38
ANK (ALL PROVISIONAL)
Amount
(RM)

PP/6/13/39
ANK (ALL PROVISIONAL)
Amount
(RM)
-

PP/6/13/40
BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL)

SUMMARY

ITEM ELEMENT FROM PAGE AMOUNT (RM)

1 SUBSTRUCTURE EWT/3/1/3 171,682.70

2 FRAME EWT/3/2/2 287,287.20

3 UPPER FLOOR EWT/3/3/1 99,501.40

4 ROOF EWT/3/4/2 94,381.40

5 STAIRCASE EWT/3/5/1 7,386.50

6 WALL FINISHES EWT/3/6/1 140,348.00

7 FLOOR FINISHES EWT/3/7/1 42,663.00

8 SUNDRIES EWT/3/8/1 17,120.00

TOTAL CARRIED TO SUMMARY OF TENDER 860,370.20

SUM/EWT-3/41
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

SITE CLEARANCE & EARTHWORKS

SITE CLEARANCE

A Clear the areas of the site affected by the proposed works of M2 3,100 2.00 6,200.00
all grass, weeds, shrubs, bushes including grubbing up roots,
etc., filling cavities with surplus excavated material and
ramming and removing all debris off the site, construct all
temporary works such as cut off drains, earth drain, dykes and
all other precautionary measure, etc., incidental or deemed
necessary for the proper execution of the whole contract works
and maintain same and removing on completion as directed by
the S.O. (0.74 acres)

EARTHWORKS

GENERAL

B Provide for all temporary works required for the carrying out of ITEM 1,000.00 1,000.00
the earthworks out such as cut-off drains, earth drains, bunds,
silt trap, dykes, and all other precautionary measures,
dewatering etc and including make good land slips erosions
and subsidences as may be required as directed by the
S.O.incidental or deemed necessary for the proper execution
of the whole contract works and maintain same for the
duration of the contract and removal including making good all
existing works disturbed at the end of the contract period.

Excavate to formation levels commencing at existing level to


form platforms, embankment, terraces, etc., filling in to make
up levels as directed and carting away excavated materials to
designated areas on site including deposit, level, consolidate
and rolled.

C M3 2,700 5.50 14,850.00


Cut and fill excavated materials to designated areas on site
and deposit, level, consolidate and compacted as directed.

D Extra over excavation for cutting through rock at any depth, M3 100 50.00 5,000.00
breaking up and removing off site as described

E Cart away surplus excavated materials to Contractor's own M3 1,700 10.00 17,000.00
dump removing off site as described

TO COLLECTION 44,050.00

EW/4/1/42
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

SITE CLEARANCE & EARTHWORKS... Cont'd

TURFING

225mm x 225mm approved turves obtained from


Contractor's own source and including 50mm thick black
earth, watering and tending until well established and
replacing badly grown turves

A Close turfing to slope surfaces including any necessary M2 450 4.50 2,025.00
pegging as specified

TO COLLECTION 2,025.00

COLLECTION

From Page EW/4/1/1 44,050.00

From Page EW/4/1/2 2,025.00

EW/4/1/43
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY 46,075.00

EW/4/1/44
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - INFRASTRUCTURE WORKS (ALL PROVISIONAL)


Item Description Unit Qty Rate (RM) Amount (RM)

ELEMENT 1 - SITE CLEARENCE AND EARTHWORKS

SITE CLEARANCE

A Clear the areas of the site affected by the proposed works of M2


all grass, weeds, shrubs, bushes including grubbing up roots,
etc., filling cavities with surplus excavated material and
ramming and removing all debris off the site, construct all
temporary works such as cut off drains, earth drain, dykes and
all other precautionary measure, etc., incidental or deemed
necessary for the proper execution of the whole contract
works and maintain same and removing on completion as
directed by the S.O. ( 2.10 Acre )

EARTHWORKS

GENERAL

B Provide for all temporary works required for the carrying out of ITEM
the earthworks out such as cut-off drains, earth drains, bunds,
dykes, and all other precautionary measures, dewatering etc
and including make good land slips erosions and subsidences
as may be required as directed by the S.O.incidental or
deemed necessary for the proper execution of the whole
contract works and maintain same for the duration of the
contract and removal including making good all existing works
disturbed at the end of the contract period.

C Approved imported earthfilling as described from Contractor's M3 8,000 18.00 144,000.00


own source in making up levels, spread, levelled,
consolidated, well compacted in layers as described within
10km radius from the site.

TURFING

225mm x 225mm approved turves obtained from Contractor's


own source and including 50mm thick black earth, watering
and tending until well established and replacing badly growns
turves

D Spot turfing; spaced at 450mm centres bothways M2 300 2.50 750.00

IW/4/1/45
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - INFRASTRUCTURE WORKS (ALL PROVISIONAL)


Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY 144,750.00

IW/4/1/46
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

ROADWORKS & KERB

ROADWORKS

Excavate over site to reduce level to form sub-grade to receive


road bottoming and remove excavated materials to
Contractor's own dump including trimming,grading and rolling
sub-grades to required cambers and gradient.

A Average 450mm deep M2 2100 4.50 9,450.00

B 50mm (finished) thick bed of sand rolled to required chambers M2 2100 3.00 6,300.00
and gradients to receive base course

Crusher run base in two layers, each layers 150mm thick laid
to required falls and cambers, blinded by quarry waste laterite
or dust, well rolled with a power roller and compacted as
specified

C 300mm thick (consolidated thickness) M2 2100 23.00 48,300.00

Supply and spray prime coats of bitumen emulsion


uniformly on prepared surfaces of crusher run base
course at the rate of not less than 0.435 litres/m2 as
specified including cleaning the surfaces

D Prime coat M2 2100 1.50 3,150.00

Supply and apply asphaltic concrete binder course (ACB 28)


well rolled to required falls gradient and cambers

E 60mm compacted thickness M2 2100 15.00 31,500.00

Supply and spray tack coats uniformly over the full prepared
surfaces at the rate of not less than 0.326 ( litre/m2) as
specified

F Tack coat M2 2100 1.50 3,150.00

Supply and apply asphaltic concrete wearing course (ACW 20)


well rolled with approved roller to required gradients and
cambers

G 40mm thick M2 2100 12.00 25,200.00

EW/4/2/47
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 127,050.00

ROADWORKS & KERB …..Cont'd

KERB

A Supply and lay precast concrete kerb overall size 150mm x M 220 25.00 5,500.00
300mm high all cast in 600mm length as shown on drawing
including all necessary round, corner, angle, junction, bedding,
excavation, backfilling, cement mortar joint, etc. and concrete
bedding to kerb overall size 375mm wide x 100mm thick
including haunhing back of kerb similiar concrete with 150mm
wide x 150mm high to receive kerb including all necessary
formwork, reinforcement, excavation, backfiling, remove
surplus excavated material to contractor's own dump.

B EXTRA OVER for laying circular-on-plan M 20 5.00 100.00

C EXTRA OVER for outlet opening NO 40 10.00 400.00

D Construct 150mm diameter PVC scupper holes with concrete NO 40 45.00 1,800.00
surround 310mm x 310mm high discharge drain at 6000mm
centres along road side table complete with all necessary
excavation, backfilling pipeworks and connections to kerbs
and drains average 2000mm long.

Prepare and apply two coats of emulsion paint in alternate


white and black colours on general surfaces of precast
concrete kerb

E 600mm wide M 220 2.50 550.00

F EXTRA OVER for laying circular-on-plan M 20 -

G EXTRA OVER for outlet opening size 300mm x 100mm high NO 40 15.00 600.00
overall at 6.00m centre.

TO COLLECTION 8,950.00

COLLECTION

From Page EW/4/2/1 127,050.00

From Page EW/4/2/2 8,950.00

EW/4/2/48
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION 136,000.00

EW/4/2/49
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

ELEMENT 4 - DRAINAGE WORKS

Excavate trench commencing from formation level, get out


and removed excavated materials off site to Contractor's own
dump.

A Exceeding 1.00m but not exceeding 2.00m deep M3 70 10.00 700.00

50mm Thick plain concrete (Grade 15) as described in:

B Under concrete base; blinding M2 60 9.00 540.00

Plain concrete (Grade 30) as described in:

C 325mm Thick concrete hunching M3 40 290.00 11,600.00

Sawn formwork as described to:

D Edges of base slab M 434 7.00 3,038.00

Precast concrete (Grade 25) as described including all


moulds, finishing fair on exposed faces and hoisting, fixing,
bedding, jointing and pointing in cement mortar (1:3):

E Block drain, cast in 300mm wide x 600mm lengths laid to fall M 160 40.00 6,400.00
and grouted in and pointed in cement and sand (1:3) with and
including a layer of BRC No A6 and grouted and pointed in
cement and sand (1:3) including 1500mm high plastered
brickwall with 100mm x 100mm strut and forming all bends,
stopped ends, junctions, weepholes,cascades, etc as
directed

F Block drain, cast in 450mm wide x 600mm lengths laid to fall M 57 45.00 2,565.00
and grouted in and pointed in cement and sand (1:3) with and
including a layer of BRC No A6 and grouted and pointed in
cement and sand (1:3) including 1500mm high plastered
brickwall with 100mm x 100mm strut and forming all bends,
stopped ends, junctions, weepholes,cascades, etc as
directed

BRICK SUMP

Sump, not exceeding 3.0m deep comprising of 100mm thick


(Grade 25) reinforced concrete as base with 1 layer of BRC
A6, 50mm thick lean concrete (Grade 15), 225mm thick
brickwall with 20mm thick cement and sand (1:3) rendered
on all surfaces, malleable cast iron steps at 300 centres;
including all excavations, disposal of excavated materials,
formwork, bakau pile and building in inlets and outlets of drain
internally all as shown on Engineer's detail drawings.

G Overall size 1500mm x 1500mm internally NO 5 1,463.00 7,315.00

EW/4/3/50
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)
TO COLLECTION 32,158.00

DRAINAGE WORKS …...(CONT'D)

GRATINGS

Hot Dipped Galvanised Sump Cover

Galvanised mild steel gratings constructed of 40mm x 6mm


thick flat at 50mm centres, 25mm x 8.0mm thick mild plate at
35mm centres and including 75mm x 8.0mm thick angle
frame complete with mild steel angle fixed with fish tail to
drain wall including all necessary welding and painting all as
shown on Engineer's detail drawings.

A Overall size 1500mm x 1500mm wide NO 5 65.00 325.00

Connection and Testing

B Allow for drainage system connection to existing drain or ITEM -


sump including hacking, excavation and make good upon
completion to the S.O. satisfaction

C Test and commission the whole drainage systems as ITEM -


described and make good all defects, retest and leave whole
in perfect working order to the satisfaction of the S.O. and the
Authorities (Note : Method of testing shall in accordance with
the S.O/Authority requirement)

--------------------------

D M2 320 -
Supply and constructed of 300mm thick (average) approved
rubble pitching wall complete with 75mm diameter weephole,
50mm thick concrete capping including all neccessary
excavation, lean concrete, hardcore, concrete base, and
reinforcement all as per Engineer detail drawing.

TO COLLECTION 325.00

COLLECTION

From Page EW/4/3/1 32,158.00

From Page EW/4/3/2 325.00

EW/4/3/51
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION 32,483.00

EW/4/3/52
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

ELEMENT 4 - WATER RETICULATION WORKS

Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-

A 150mm diamater pipe M

B 250mm diameter pipe M

C Reinforced concrete (Grade 20) as described thrust block M3


average size 450mm x 530mm deep to mild steel pipe
including all necessary excavation, reinforcement and
formwork.

Mild Steel Cement Lined Pipe

Supply and install mild steel cement lined pipe as described


including all necessary bend, tee and other accessories and
jointing with mild steel collars fillet-welded and painted; and
preparing end of mild steel concrete line pipes for jointing;
laying in trench with and including filled trench 250mm high
and all above with compacted sand all as shown on Engineer's
drawings.

D 150mm diamater pipe M

E 250mm diameter pipe M

Valve and fitting

F Supply and install 150mm Diameter sluice valve including NO


flanged joints and rubber gaskets

F Supply and install 150mm Diameter scour valve including NO


flanged joints and rubber gaskets

F Supply and install 50mm Diameter air valve including flanged NO


joints and rubber gaskets

G Supply and install extra 150mm diameter end cap including all NO
necessary fittings.

H Supply and install extra 150mm diameter tee including all NO


necessary fittings.

H Supply and install extra 150mm diameter 'S bend including all NO
necessary fittings.

TO COLLECTION -

IW/4/4/53
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

WATER RETICULATION WORKS …..(CONT'D)

Valve Chamber

Valve Chamber overall size 530mm x 605mm x 1500mm deep


constructed of 100mm thick precast block with 19mm thick
cement plaster to exposed faced, 50mm thick screed, 150mm
thick concrete grade 15 base with 12mm chippings fill and
25mm diameter MS bar staggered steps at 225mm centres,
cover with 150mm thick concrete slab at the top and 530mm x
605mm unbreakable steel plate cover single seal hinged with
steel frame complete with key and locking gear of heavy
patterned type including forming pipe outlet and inlet and
including all excavation, formwork, backfill and all as per
Engineer's detail drawing.

A Sluice valve NO

Pipe Marker

Precast reinforced concrete (1:2:4) as described with splayed


top inscribed with countersunk including all moulds, finishing
fair on exposed faces, painting post in oil based paint, all to
approval and fixing firmly in position into ground

212mm x 62mm x 750mm high

B Indicator post with "Sluice Valve" sign NO

Bulk Meter

C Approved 100mm diameter bulk meters hydrant including all NO


the necessary pipe fittings, valves, concrete platform, thrust
block , etc. All as shown in Engineer's detail drawing.

D Approved 150mm diameter bulk meters hydrant including all NO


the necessary pipe fittings, valves, concrete platform, thrust
block , etc. All as shown in Engineer's detail drawing.

IW/4/4/54
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION -

WATER RETICULATION WORKS …..(CONT'D)

Testing and Commissioning

A Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.

B Allow for hydraulic tests (pressure and leakage) as specified ITEM


and as directed by the S.O

TO COLLECTION -

COLLECTION

From Page IW/4/4/1 -

From Page IW/4/4/2 -

From Page IW/4/4/3 -

IW/4/4/55
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY -

IW/4/4/56
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

FENCING AND GATE

Chain link Fencing

Chain link fencing constructed of PVC green cover coated


consisting of 50mm x 50mm mild steel angle post at 3.00m
centres with bottom and embedded in concrete (Grade 25 )
and with 50mm diamond mesh pvc coated chainlink fence
including three stands of No. 8 galvanised wires threaded
horizontally through at top, intermediate and bottom and
including 3 rows of barbed wire, including excavation
works,125mm x 375mm high concrete stump, 100mm x
100mm high concrete kerb with cement plaster finish and the
whole to be erected in position including anti-rust primer and
painting to steel work as per Architect Detail Drawing.

A 1800mm high M 250 60.00 15,000.00

Main Gate

Mild steel swing main gate constructed of 100mm x 50mm x


4mm thick mild steel hollow main frame fixed horizontally,
vertically and diagonally secondary frame, infill with 25mm x
25mm x 4mm thick vertically balusters 100mm centres steel
sections, all welded together with 100mm diameter metal
wheel on 70mm x 70mm mild steel angle track, 150mm
diameter mild steel posts and all necessary fitting bolts and
padlock and plates,hinges, turn buckle, 10mm diameter mild
steel rod, barrel bolt stopper etc and mild steel post embedded
in reinforced concrete (Grade 25) footing and concrete base
slab and fixing in position with and including all necessary
excavation formwork, roller and painting to steelworks
complete all as per Architect Detail Drawing no: NA/SIRIM/
KEJORA/IKS-BT(2009)/DD/GCL-02 and S.O approval.

B Overall size 8000mm x 3000mm high double swing gate NO 1 2,500.00 2,500.00
comprising of 2 nos each size 4000mm x 1800mm high.

EW/4/4/57
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY 17,500.00

EW/4/4/58
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

ELEMENT 6 - WORK OUTSIDE BOUNDARY

ROADWORKS AND PAVEMENTS

Excavate over site to reduce level to form sub-grade to receive


road bottoming and remove excavated materials to
Contractor's own dump including trimming, grading and rolling
sub-grades to required cambers and gradient

A Average 460mm deep M2 60 4.60 276.00

B 50mm (finished) thick bed of sand rolled to required chambers M2 60 3.00 180.00
and gradients to receive base course

Crusher run metal in two layers, each layers 4.5" thick laid to
required falls and cambers, blinded by quarry waste laterite or
dust, well rolled with a power roller and compacted as
specified

C 300mm thick (consolidated thickness) M2 60 18.00 1,080.00

Supply and spray prime coats of bitumen emulsion


uniformly on prepared surfaces of crusher run base
course at the rate of not less than 0.435 litres/m2 as
specified including cleaning the surfaces

D Prime coat M2 60 1.00 60.00

Supply and apply asphaltic concrete binder course (ACB 28)


premix macadam well rolled to required falls gradients and
cambers

E 60mm compacted thickness M2 60 23.00 1,380.00

Supply and spray tack coats uniformly over the full


prepared surfaces at the rate of not less than 0.326
(litre/m2) as specified

F Tack coat M2 60 1.00 60.00

Supply20)and
(ACW apply
premix asphaltic
macadam concrete
well rolled wearing roller
with approved course to
required falls,

G 50mm thick M2 60 15.00 900.00

IW/4/6/59
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION 3,936.00

WORK OUTSIDE BOUNDARY......(CONT'D)

ROADWORKS AND PAVEMENTS.......(CONT'D)

KERB

A Supply and lay precast concrete kerb overall size 150mm x M 135 28.00 3,780.00
300mm high all cast in 600mm length as shown on drawing
including all necessary round, corner, angle, junction, bedding,
excavation, backfilling, cement mortar joint, etc. and concrete
bedding to kerb overall size 375mm wide x 100mm thick
including haunhing back of kerb similiar concrete with 150mm
wide x 150mm high to receive kerb including all necessary
formwork, reinforcement, excavation, backfiling, remove
surplus excavated material to contractor's own.

B EXTRA OVER for laying circular-on-plan M 30 5.00 150.00

C EXTRA OVER for outlet opening NO 28 10.00 280.00

D Construct 150mm diameter PVC scupper holes with concrete NO 28 30.00 840.00
surround 310mm x 310mm high discharge drain at 6000mm
centres along road side table complete with all necessary
excavation, backfilling pipeworks and connections to kerbs
and drains average 2000mm long

Prepare and apply two coats of emulsion paint in alternate


white and black colours on general surfaces of precast
concrete kerb

E 600mm wide M 135 2.50 337.50

F EXTRA OVER for laying circular-on-plan M 30 2.50 75.00

G EXTRA OVER for outlet opening NO 28 15.00 420.00

ROAD MARKINGS AND SIGNAGES

Prepare and apply two coats of approved reflective


thermoplastic road marking paint as specified and as detailed
in drawing on road surfaces

H 150mm wide x 300mm length x 300mm gap give way line M 100 2.50 250.00
marking

J 150mm wide continuous line M 165 2.50 412.50

K Arrow Straight NO 4 15.00 60.00

L Arrow Left and Straight NO 1 15.00 15.00

IW/4/6/60
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TO COLLECTION 6,620.00

WORK OUTSIDE BOUNDARY......(CONT'D)

ROAD MARKINGS AND SIGNAGES......(CONT'D)

Supply and install in position complete all road signboard, with


post including sign lettering and colour on aluminium sheet all
as specified and detailed in drawings including all necessary
excavation, footing and remove surplus excavated materials
away

A Speed Limit Sign NO 2 280.00 560.00

B Give Way Sign NO 2 280.00 560.00

TURFING

225mm x 225mm approved turves obtained from


Contractor's own source and including 50mm thick black
earth, watering and tending until well established and
replacing badly grown turves

C Spot turfing; spaced at 450mm centres bothways M2 50 2.50 125.00

TO COLLECTION 1,245.00

COLLECTION

From Page IW/4/6/1 3,936.00

From Page IW/4/6/2 6,620.00

From Page IW/4/6/3 1,245.00

IW/4/6/61
2 UNIT KILANG INKUBATOR GMP DI BANDAR TENGGARA

BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)

Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY 11,801.00

IW/4/6/62
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

ELEMENT 1 - SITE CLEARANCE AND EARTHWORKS

SITE CLEARANCE

A Clear the areas of the site affected by the proposed works of M2 40,560 2.00 81,120.00
all grass, weeds, shrubs, bushes including grubbing up
roots,cut, fell and remove in bulk all trees irrespective of
diameter and heights all trees including trees unless otherwise
stated except trees marked by the S.O, etc., filling cavities with
surplus excavated material and ramming and removing all
debris off the site, construct all temporary works such as cut
off drains, earth drain, dykes and all other precautionary
measure, etc., incidental or deemed necessary for the proper
execution of the whole contract works and maintain same and
removing on completion as directed by the S.O. (10.0 acres)

STRIPPING TOP SOIL

B Strip 150mm thick vegetation top soil stockpile to designated M2 40,560 2.00 81,120.00
area by the Employer for re-use and depose of unsuitable
material off site to Contractor's own dump (Approx 10.00
acres)
DEMOLITION WORKS

The Contractor shall carefully dismantle, locate and install


existing structures that may obstruct the construction works
other than specified (whole construction area) and cart away
as directed to client's own storage area within the site:

C Existing Garaj Bas (Approx 220 m2) LS 3,000.00

D Exsiting Bengkel (Approx 377 m2) LS 5,000.00

E Exsiting Kabin (4 nos) LS 1,000.00

F Existing Pondok Rehat (Approx 9 m2) LS 150.00

EARTHWORKS

Note : The Contractor shall allow herein his pricing an ample


time for the surcharge (minimum 3m high at 6 months) other
than the building area as directed by the Engineer. No addition
claim in term of cost and time will be entitled due to the
negligence of these note.

TO COLLECTION 171,390.00
IW/6/1/63 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

SITE CLEARANCE & EARTHWORKS...(Cont'd)

EARTHWORKS...(Cont'd)

A Provide for all temporary works required for the carrying out of ITEM 5,000.00
the earthworks out such as cut-off drains, earth drains, bunds,
dykes, and all other precautionary measures, dewatering etc
and including make good land slips erosions and subsidences
as may be required as directed by the S.O.incidental or
deemed necessary for the proper execution of the whole
contract works and maintain same for the duration of the
contract and removal including making good all existing works
disturbed at the end of the contract period .

Excavate to formation levels commencing at existing level to


form platforms, embankments, terraces, etc including loading
transport, multiple handling and deposited in temporary spoil,
filling in to make up levels as directed and carting away
excavated materials to designated areas on site including
deposit, level, consolidated and rolled in layers not exceeding
150mm thick

B Approved imported earthfilling as described from Contractor's M3 7,900 15.00 118,500.00


own source in making up levels, spread, levelled,
consolidated, well compacted in layers as described.

C Allow for approved imported material for platform surcharge M3 29,022 10.00 290,220.00
including all necessary levelling, temporary works and carting
away all in accordance to Engineer's details and instruction

TO COLLECTION 413,720.00

COLLECTION

From Page IW/6/1/1 (R) 171,390.00

From Page IW/6/1/2 (R) 413,720.00

TOTAL CARRIED TO SUMMARY 585,110.00

IW/6/1/64 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

ELEMENT 2 - ROADWORKS, CARPARKS & KERB

Excavate to formation level from reduced level, including


trimming, grading, cambers and filling in make up level as
directed including consolidation and rolled in layers with power
roller 150mm thick and remainder, cart away from site to
Contractor's own dump

A Average 430mm deep M2 7670 3.40 26,078.00

B 50mm thick Unwashed compacted sand bed M2 7670 4.00 30,680.00

Crusher run base in two layers, each layers 135mm thick laid
to required falls and cambers, blinded by quarry waste laterite
or dust, well rolled with a power roller and compacted as
specified

C 305mm thick (consolidated thickness) M2 7670 15.00 115,050.00

Supply and spray prime coats of bitumen emulsion


uniformly on prepared surfaces of crusher run base
course at the rate of not less than 0.435 litres/m2 as
specified including cleaning the surfaces

D Prime coat M2 7670 1.00 7,670.00

Supply and apply asphaltic concrete binder course (ACB


28) well rolled to required falls gradients and cambers

E 50mm compacted thickness M2 7670 20.00 153,400.00

Supply and spray tack coats uniformly over the full


prepared surfaces at the rate of not less than 0.326
(litre/m2) as specified

F Tack coat M2 7670 1.00 7,670.00

Supply and apply asphaltic concrete wearing course


(ACW 20) well rolled with approved roller to required falls,
gradients and cambers

G 50mm compacted thickness M2 7670 21.00 161,070.00

IW/6/2/65
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)
TO COLLECTION 501,618.00

ROADWORKS AND PAVEMENTS (CONT'D)

KERB

Supply and lay precast concrete Grade 20 kerb all cast in


600mm length as shown on drawing including all necessary
round, corner, angle, junction, bedding on in situ concrete
Grade 20 bedding, excavation, backfilling, cement mortar joint,
formwork, reinforcement, remove surplus excavated material
to contractor's own dump.

A Overall size 250mm x 300mm high chamfered top edge on M 1916 35.00 67,060.00
one side (Type A)

B EXTRA OVER for laying circular-on-plan M 107 35.00 3,745.00

C EXTRA OVER for outlet opening size 125mm x 250mm high NO 256 20.00 5,120.00
overall at 7.50m centre

Construct scupper pipe discharge drain at 7500mm centres


along road side table including in situ concrete Grade 15 in the
pipe complete with all necessary excavation, backfilling
pipeworks and connections to kerbs and drains average
1500mm long

D 225mm diameter Vitrified Clay Pipe NO 256 600.00 153,600.00

Prepare and apply two coats of emulsion paint in alternate


white and black colours on general surfaces of precast
concrete kerb

E 450mm wide M 2023 8.00 16,184.00

ROAD MARKINGS AND SIGNAGES

Prepare and apply two coats of approved reflective


thermoplastic road marking paint as specified and as detailed
in drawing on road surfaces

F 100mm wide x 1000mm length x 1700mm gap center line M 710 2.00 1,420.00

H 100mm wide unbroken lane line M 30 2.00 60.00

J 150mm wide edge line M 1916 3.00 5,748.00

K 300mm wide stop line M 16 6.00 96.00

L Arrow Straight NO 6 50.00 300.00

M Arrow Turn Right or Left NO 10 50.00 500.00

N Arrow Straight and Turn Left or Right NO 10 65.00 650.00

IW/6/2/66
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

TO COLLECTION 254,483.00

ROAD MARKINGS AND SIGNAGES

Prepare and apply two coats of approved reflective


thermoplastic road marking paint as specified and as detailed
in drawing on road surfaces

A Arrow 2 way NO 12 65.00 780.00

Supply and install in position complete all road signboard, with


post including sign lettering and colour on aluminium sheet all
as specified and detailed in drawings including all necessary
excavation, footing and remove surplus excavated materials
away

B Stop At Intersection Sign NO 5 350.00 1,750.00

C Road Junction on the Right Sign NO 4 350.00 1,400.00

D Road Junction on the Left Sign NO 4 350.00 1,400.00

E Parking Sign NO 3 350.00 1,050.00

F Awas Sign NO 5 350.00 1,750.00

TURFING

225mm x 225mm approved turves obtained from


Contractor's own source and including 50mm thick black
earth, watering and tending until well established and
replacing badly grown turves

G Spot turfing; spaced at 450mm centres bothways M2 6,470 3.00 19,410.00

H Close turfing to slope surfaces including any necessary M2 4,314 4.50 19,413.00
pegging as specified

CALIFORNIA BEARING RATIO TEST

J Test and commission the whole roadworks systems as ITEM 1,000.00


described and make good all defects, retest and leave whole
in perfect working order to the satisfaction of the S.O. and the
Authorities (Note : Method of testing shall in accordance with
the S.O/Authority requirement)

IW/6/2/67
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

TO COLLECTION 47,953.00

COLLECTION

From Page IW/6/2/1 501,618.00

From Page IW/6/2/2 254,483.00

From Page IW/6/2/3 47,953.00

IW/6/2/68
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

TOTAL CARRIED TO SUMMARY 804,054.00

IW/6/2/69
UNIVERSITI TUN HUSSEIN ONN MALAYSIA, BATU PAHAT

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )

Item Description Unit Qty Rate (RM) Amount (RM)

ELEMENT 3 - WALKWAY

A Supply and lay 80mm thick interlocking paver as described M2 835 65.00 54,275.00
driveway including all necessary excavation, concrete edging,
50mm compacted sand and including make good to all
disturbed works to manufacturer's details colour & pattern to
Architect approval.

EW/4/3/70
UNIVERSITI TUN HUSSEIN ONN MALAYSIA, BATU PAHAT

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )

Item Description Unit Qty Rate (RM) Amount (RM)

TOTAL CARRIED TO SUMMARY 54,275.00

EW/4/3/71
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

ELEMENT 4 - DRAINAGE WORKS

ROAD SIDE DRAIN

Excavate trench commencing from formation level, get out and


removed excavated materials off site to Contractor's own dump

A Exceeding 1.00m but not exceeding 2.00m deep M3 2,325 8.00 18,600.00

50mm Thick plain concrete (Grade 15) as described in:

B Under concrete base; blinding M2 2,427 11.80 28,638.60

Plain concrete (Grade 30) as described in:

C 300mm Thick base slab M3 728 240.00 174,720.00

Sawn formwork as described to:

D Edges of slab exceeding 250m not exceeding 500mm high ; M 4,296 17.50 75,180.00
base slab

Common clay bricks in cement mortar (1:6) with plasticiser as


described in :

E 225mm thick brick M2 3,867 60.00 232,020.00

F 340mm thick brick M2 3,867 90.00 348,030.00

20mm thick cement and sand (1:6) as described plastering


finishing with a atrowel steel trowel at exposed faces

G Drain wall M2 8,700 13.00 113,100.00

UPVC pipes as described weephole to drain wall

H 100mm diameter ; 250mm long NO 1594 15.00 23,910.00

Filter media consisting of 25mm to diameter stone or other


approved material

J Overall size 225mm x 225mm x 225mm to side of drain wall NO 1594 10.00 15,940.00

Precast concrete (Grade 25) as described including all moulds,


finishing fair on exposed faces and hoisting, fixing, bedding,
jointing and pointing in cement mortar (1:3) :

K 300mm diameter half round channel cast in 600mm length ; laid M 2,148 130.00 279,240.00
to fall all as per Engineer's detail drawing

TO COLLECTION 1,309,378.60

IW/6/4/72 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

DRAINAGE WORKS … (Cont'd)

Mild Steel Grating Road Side Drain

Galvanised mild steel gratings constructed of 50mm x 10mm


thick flat, 50mm x 10mm thick mild plate at 25mm centres and
including 75mm x 8.0mm thick angle frame complete with mild
steel angle fixed with fish tail to drain wall including all
necessary welding and painting all as per Engineer's detail
drawings.
A Overall size 600mm x 600mm internally M 79 110.00 8,690.00

REINFORCED CONCRETE SUMP

Sump exceeding 1.0m but not exceeding 2.0m deep comprising


of 600mm thick (Grade 30) reinforced concrete as base, 50mm
thick lean concrete (Grade 15), 150mm x 300mm beam 'X'
including all excavations, disposal of excavated materials,
formwork, reinforcement and building in inlets and outlets of
drain internally all as shown on Engineer's detail drawings.

B Overall size 1600mm x 1600mm internally NO 13 1,500.00 19,500.00

Mild Steel Grating Sump Cover

Galvanised mild steel gratings constructed of 2 Nos T32 high


tensile bar at 60mm centres, 75mm x 75mm x 6.0mm thick mild
steel angle frame including all necessary welding and painting
all as per Engineer's detail drawings.

C Overall size 1600mm x 1600mm internally NO 13 500.00 6,500.00

Connection and Testing

D Allow for drainage system connection to existing drain or sump ITEM 500.00
including hacking, excavation and make good upon completion
to the S.O. satisfaction

E Test and commission the whole drainage systems as described ITEM 1,000.00
and make good all defects, retest and leave whole in perfect
working order to the satisfaction of the S.O. and the Authorities
(Note : Method of testing shall in accordance with the
S.O/Authority requirement)

IW/6/4/73 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)
TO COLLECTION 36,190.00

COLLECTION

From Page IW/6/4/1 (R) 1,309,378.60

From Page IW/6/4/2 (R) 36,190.00

IW/6/4/74 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

TOTAL CARRIED TO SUMMARY 1,345,568.60

IW/6/4/75 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Description Unit Qty
(RM) (RM)

ELEMENT 5 - SEWERAGE WORKS

Excavate commencing from formation level get out, part


return, fill in and ram including levelling, grade and ram
bottom, trim side, planking and strutting and deposit and
spread in making up levels where directed and remainder load
and cart away from site.

Trench not exceeding 1.00m deep

A Excavate trench average 920mm deep to falls for 300mm


diameter sewerage pipe M3 23 8.00 184.00

Trench exceeding 1.00m deep not exceeding 2.0m deep

B Excavate trench average 1290mm deep to falls for 300mm


diameter sewerage pipe M3 497 8.00 3,976.00

Bedding

20mm aggregate bedding under sewerage pipe (measured


separately) carefully compacted in two layers and extending
half way up to the sides of pipe

C 600mm wide x 100mm deep; 300mm diameter M3 48 50.00 2,400.00

Mass concrete (Grade 20) as described:

D 600mm wide x 250mm deep bedding extending halfway down M3 48 222.00 10,656.00
to sides of pipe

Vitrified clay pipe (VCP) of approved type by SIRIM


conforming to BS 65, BS 5911 and BS 2494 and to JPP
requirement with rubber ring flexible joints bedded in crusher
run (measured separately)

E 300mm diameter ; pipe laid and jointed to falls in trench M 349 250.00 87,250.00

TO COLLECTION 104,466.00

IW/6/5/76 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Description Unit Qty
(RM) (RM)

SEWERAGE WORKS … (Cont'd)

The following in 11 Nos. Manhole

Manhole

Approved precast concrete (Grade 20) manhole constructed of


300mm thick concrete base slab with 2 layer BRC A8 on
50mm thick lean concrete (Grade 20) blinding, chamber and
shaft rings, taper rings, make-up piece, precast reinforced
concrete cover slab with underside painted with 2 layer of coal
tar epoxy with 150mm thick (minimum) concrete (Grade 20)
surrounds, benching, 200mm half round VCP pipe, steps iron
at 300mm centres, precast reinforced concrete ring with with
20mm thick high alumina cement lining, including approved
standard high duty cast iron and tight manhole cover with
frame bedded in cement mortar (1:3) and two coats
bituminous paint before fixing and sealing cover in grease and
fine sand all as shown on drawing no. K&L\141\KUITTHO\C\
SW\002 including excavation, removal and disposal of surplus
excavated materials, formwork, bakau piles and forming all
outlets.

A Sewer manhole overall size 1200mm diameter (internal NO 3 2,000.00 6,000.00


dimension) with 610mm make up piece including 300mm
diameter vitrified clay half round straight main channel with 1
outlet not exceeding 2.5 deep.

B Sewer manhole overall size 1200mm diameter (internal NO 6 2,000.00 12,000.00


dimension) with 610mm make up piece including 300mm
diameter vitrified clay half round bend main channel with 1
inlet and 1 outlet not exceeding 2.5 deep.

C Sewer manhole overall size 1200mm diameter (internal NO 2 2,000.00 4,000.00


dimension) with 610mm make up piece including 300mm
diameter vitrified clay half round 3 way main channel with inlet
and outlet not exceeding 2.5 deep.

Manhole Cover

Heavy duty ductile iron manhole cover and frame with


embored logo JPP to BS 2789, Grade 500/7 and BS 497; Part
1:1976 all to comply with the specification and manufactured
by approved manufacturer including hinged, locking and lifting
devise and coating with black synthetic resin based paint and
the frame set in cement mortar (1:3) and sealing cover in
grease and sand.

D Overall size 885mm x 885mm wide NO 11 500.00 5,500.00

IW/6/5/77 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Description Unit Qty
(RM) (RM)
TO COLLECTION 27,500.00

SEWERAGE WORKS… (Cont'd)

A Allow for connecting to completed sewerage pipe / manholes ITEM 699.40


including all necessary materials, joint fittings, excavation,
breaking up and making good all works disturbed.

Testing and Commissioning

B Allow for testing and cleaning the whole of the sewerage ITEM 1,000.00
system to the requirement of the Local Authorities and
Superintending Officer including arranging all necessary
documents and obtaining the test certificates.

C Allow for testing and inspection by Local Authorities based ITEM 2,000.00
on CCTV method from manhole to manhole, all to the
requirements and approval of Local Authorities

TO COLLECTION 3,699.40

COLLECTION

From Page IW/6/5/1 (R) 104,466.00

From Page IW/6/5/2 (R) 27,500.00

From Page IW/6/5/3 (R) 3,699.40

IW/6/5/78 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 6 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Description Unit Qty
(RM) (RM)

TOTAL CARRIED TO SUMMARY 135,665.40

IW/6/5/79 (R)
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)

WATER RETICULATION

Mild Steel Cement Lined Pipe

Excavation not exceeding 2.00m deep and get out, part return, fill
in and ram and remove surplus excavated material to
Contractor's own dump site for :-

150mm diameter pipe

A Inlet pipe M 1,988

B Scour Pipe M 16

250mm diameter pipe

C Outlet Pipe and spare outlet pipe M 1,988

D Mass concrete ( Grade 15) as specified thrust block including all M3 264 180.00
necessary formwork and excavation

Mild Steel Cement Lined Pipe

Supply and install Mild Steel Cement Lined pipe as described


including all necessary bend, tee and other accessories and
jointing with mild steel collars fillet-welded and painted; including
wrapping joints with asbestos coal tan saturated felt and
preparing end of steel pipes for jointing; laying in trench with and
including filled trench 150mm high and all above with compacted
sand all as shown on Engineer's drawings.

E 150mm diameter pipe M 1,993 200.00

F 250mm diameter pipe M 1,960 300.00

Ductile Iron Pipe

Supply and install Ductile Iron pipe as described including all


necessary bend, tee and other accessories and jointing with mild
steel collars fillet-welded and painted; including wrapping joints
with asbestos coal tan saturated felt and preparing end of steel
pipes for jointing; laying in trench with and including filled trench
150mm high and all above with compacted sand all as shown on
Engineer's drawings.

G 150mm diameter pipe laid in trench M 22 250.00


( measured serperately)

H 150mm diameter pipe riser fix to concrete structure with M 26 250.00


approved bracket and accessories

TO COLLECTION

EW/4/5/80
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)

WATER RETICULATION...Cont'd

Ductile Iron Pipe...(cont'd)

Supply and install Ductile Iron pipe as described including all


necessary bend, tee and other accessories and jointing with mild
steel collars fillet-welded and painted; including wrapping joints
with asbestos coal tan saturated felt and preparing end of steel
pipes for jointing; laying in trench with and including filled trench
150mm high and all above with compacted sand all as shown on
Engineer's drawings.

A 250mm diameter pipe laid in trench M 16 400.00


(measured serperately)

B 250mm diameter pipe riser fix to concrete structure with M 15 400.00


approved bracket and accessories

Valve and Fittings

C Supply and install 250mm diameter sluice valve including double NO 19 500.00
flanged joints and rubber gaskets

D Supply and install 150mm diameter scour valve including flanged NO 4 550.00
joints and rubber gaskets

E Supply and install with 50mm diameter double air valve at NO 5 250.00
300mm centres including flanged joints and rubber gaskets

F Supply and install 100mm diameter double outlet pillar hydrant NO 1 3,000.00
an including tee off, duck foot, short piece and all necessary
fittings as per authority's requirement.

G Supply and install extra 250mm diameter end cap including all NO 3 350.00
necessary fittings

H Supply and install extra 150mm diameter tee including all NO 5 3,000.00
necessary fittings

J Supply and install extra 150mm diameter 'S' bend at culvert NO 5 150.00
crossing including all necessary fittings, special joints and valves
in accordance to engineer's detail.

K 150mm diameter x 90 degree flange bend NO 2

L 250mm diameter x 90 degree flange bend NO 2

M 150mm diameter duckfoot bend NO 2 100.00

N 250mm diameter duckfoot bend NO 2 200.00

P 150mm diameter flanged bellmouth finish with painting NO 5

EW/4/5/81
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)
TO COLLECTION

WATER RETICULATION...Cont'd

Valve and Fittings...(cont'd)

A 150mm diameter Viking Johnson coupling NO 23

B 250mm diameter Viking Johnson coupling NO 8

C Approved pressure gauge complete with stainless steel gate NO 2 10,000.00


valve, short piece, socket saddle plate and all necessary
accessories

D 150mm diameter approved altitude valve complete with pressure NO 2


meter and accessories

E 150mm diameter 90° short bend NO 1

Altitude Valve Chamber

F NO 1 50,000.00
Altitude Valve Chamber overall size 4120mm x 2400mm x
2000mm deep internally constructed of 200mm thick concrete
(grade 25) as specified base reinforced with a layer BRC A6 and
225mm thick reinforced concrete wall, 50mm thick screed,
chequre plate (6mm thick) cover complete with pad lock, 12mm
diameter mild steel bar at 100 centre to centre including all
necessary excavation, formwork, backfill and all as per
Engineer's detail drawing.

Valve Chamber

Valve Chamber overall size 800mm x 845mm x 1500mm deep


internally constructed of 225mm thick brickwall with 20mm thick
cement plaster to exposed faced, 50mm thick screed, 150mm
thick concrete grade 15 base with 12mm chippings fill and cover
with 150mm thick concrete slab at the top and 600mm x 600mm
unbreakable steel plate cover single seal hinged with steel frame
complete with key and locking gear of heavy patterned type
including forming pipe outlet and inlet and including all
excavation, formwork, backfill and all as per Engineer's detail
drawing.

G Sluice valve NO 19 5,000.00

H Scour valve NO 4 500.00

J Air valve NO 5

EW/4/5/82
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)

TO COLLECTION

WATER RETICULATION...Cont'd

Pipe Marker

Precast reinforced concrete Grade 20 as described with splayed


top inscribed with countersunk including all moulds, finishing fair
on exposed faces, painting post in oil based paint, all to approval
and fixing firmly in position into ground.

224mm x 62mm 750mm high

A Indicator post with "Sluice Valve" sign NO 19 30.00

B Indicator post with "Scour Valve" sign NO 4 30.00

C Indicator post with "Air Valve" sign NO 5 30.00

D Indicator post with "Hydrant Valve" sign NO 1 30.00

Bulk Meter

E Approved 150mm diameter bulk meters hydrant including all the NO 1 3,000.00
necessary pipe fittings, valves, concrete platform, thrust block,
etc, all as shown in Engineer's detail drawing.

F ITEM 4,000.00
Allow for road crossing including cutting of existing premix road
using diamond or other approved method, removal of premix
elements, concrete pavers, kerbs, etc. And make good
replacement of all disturbed works to the existing standard and
condition upon completion to the S.O.'s satisfaction.

G ITEM 7,000.00
Supply labour and materials to construct hot tapping connection
between new and existing main supply pipe including ductile iron
alloy saddle, brass ferrule/off take tee, adaptors, concrete base
slab, reducer, stop cock and all necessary temporary works such
as sheet pile, strutting and including excavation, compacted
backfilling etc. all to the S.O.'s satisfaction.

Testing and Commissioning

H Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.

J Allow for hydraulic test (pressure and leakage) as specified and ITEM
as directed by the S.O

EW/4/5/83
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)

TO COLLECTION

COLLECTION

From Page EW/4/5/1

From Page EW/4/5/2

From Page EW/4/5/3

From Page EW/4/5/4

EW/4/5/84
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISO
Rate
Item Description Unit Qty
(RM)

TOTAL CARRIED TO SUMMARY

EW/4/5/85
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)

47,520.00

398,600.00

588,000.00

5,500.00

6,500.00

1,046,120.00

EW/4/5/86
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)

6,400.00

6,000.00

9,500.00

2,200.00

1,250.00

3,000.00

1,050.00

15,000.00

750.00

200.00

400.00

EW/4/5/87
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)
45,750.00

20,000.00

50,000.00

95,000.00

2,000.00

EW/4/5/88
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)

167,000.00

570.00

120.00

150.00

30.00

3,000.00

4,000.00

7,000.00

EW/4/5/89
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)

14,870.00

1,046,120.00

45,750.00

167,000.00

14,870.00

EW/4/5/90
BILL NO. 4 - EXTERNAL WORKS (ALL PROVISONAL)
Amount
(RM)

1,273,740.00

EW/4/5/91
BILL NO. 4 - EXTERNAL WORKS ( ALL PROVISIONAL )
Rate Amount
Item Description Unit Qty
(RM) (RM)

GUARD HOUSE

A NO 1 60,000.00 60,000.00

Guard House overall size 3.20m x 3.0m x 3.0m high


constructed of reinforced concrete ( Grade 25) structure on
reinforced concrete (Grade 35 ) foundation, covered with metal
deck roof covering on 220 pitch roof at wrot timber roof trusses
and fascia board, 3mm thick striated "UAC" superflex sheet
ceiling, plastered brickwall with emulsion paint and approved
tiles floor finishes (to be conformed with architect), aluminium
sliding window with glass, PVC door, sanitary fittings
accessories and hume septic tank (3PE) including mechanical
and electrical fittings nd accessories All as per Architect's
Detail Drawing : PG-22/KEJORA/2010/ARCH-GH/01 and
structure Drawing : PG-22/KEJORA/2010/GH/02,03,04

TOTAL CARRIED TO SUMMARY


EW/4/6/92
BILL NO. 4 - EXTERNAL WORKS ( ALL PROVISIONAL )
Rate Amount
Item Description Unit Qty
(RM) (RM)
TOTAL CARRIED TO SUMMARY 60,000.00

EW/4/6/93
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 5 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

ELEMENT 6 - WATER RETICULATION WORKS

Excavation not exceeding 2.0m deep and get out, part return,
fill in and ram and remove surplus excavated material to
Contractor's own dump site for :-

A 150mm diamater pipe M

B 250mm diameter pipe M

C Plain concrete (Grade 15) as described thrust block average M3


saiz 750mm x 750mm x750mm high to all type of pipe
including all necessary excavation, reinforcement and
formwork.

Mild Steel Cement Lined Pipe

Supply and install Mild Steel Cement Lined Pipe as described


including all necessary bend, tee and other accessories and
jointing with mild steel collars fillet-welded and painted;
including wrapping joints with asbestos coal tan saturated felt
and preparing end of steel pipes for jointing; laying in trench
with and including filled trench 150mm high and all above with
compacted sand all as shown on Engineer's drawings.

E 150mm diameter pipe M

F 200mm diameter pipe M

Valve and fitting

G Supply and install 150mm diameter sluice valve including NO


double flanged joints and rubber gaskets

H Supply and install 150mm Diameter scour valve including NO


flanged joints and rubber gaskets

J Supply and install with 50mm diameter double air valve at NO


300mm centres including flanged joints and rubber gaskets

K Supply and install 100mm diameter double outlet pillar hydrant NO


and including tee off, duck foot, short piece and all necessary
fittings as per authority's requirement

L Supply and install extra 150mm diameter end cap including all NO
necessary fittings

H Supply and install extra 150mm diameter tee including all NO


necessary fittings.

H Supply and install extra 150mm diameter 'S bend including all NO
necessary fittings.

TO COLLECTION -
IW/6/6/94 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 5 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

WATER RETICULATION…..(CONT'D)

Valve Chamber

Valve Chamber overall size 800mm x 845mm x 1500mm deep


constructed of 225mm thick brickwall with 20mm thick cement
plaster to exposed faced, 50mm thick screed, 150mm thick
concrete grade 15 base with 12mm chippings fill and cover
with 150mm thick concrete slab at the top and 600mm x
600mm unbreakable steel plate cover single seal hinged with
steel frame complete with key and locking gear of heavy
patterned type including forming pipe outlet and inlet and
including all excavation, formwork, backfill and all as per
Engineer's detail drawing.

A Sluice valve NO

B Scour valve NO

C Air Valve NO

Pipe Marker

Precast reinforced concrete Grade 20 as described with


splayed top inscribed with countersunk including all moulds,
finishing fair on exposed faces, painting post in oil based paint,
all to approval and fixing firmly in position into ground

224mm x 62mm x 750mm high

D Indicator post with "Sluice Valve" sign NO

E Indicator post with "Scour Valve" sign NO

F Indicator post with "Air Valve" sign NO

G Indicator post with "Hydrant" sign NO

Bulk Meter

H Approved 100mm diameter bulk meters hydrant including all NO


the necessary pipe fittings, valves, concrete platform, thrust
block , etc. all as shown in Engineer's detail drawing.

J Allow for road crossing including cutting of existing premix ITEM


road using diamond or other approved method, removal of
premix elements, concrete pavers, kerbs, etc. and make good
replacement of all disturbed works to the existing standard and
condition upon completion to the S.O.'s satisfaction.

IW/6/6/95 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 5 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)
TO COLLECTION -

WATER RETICULATION…..(CONT'D)

A Supply labour and materials to construct hot tapping ITEM


connection between new and existing main supply pipe
including ductile iron alloy saddle, brass ferrule/off take tee,
adaptors, concrete base slab, reducer, stop cock and all
necessary temporary works such as sheet pile, strutting and
including excavation, compacted backfilling etc. all to the
S.O.'s satisfaction.

Testing and Commissioning

B Allow for testing, cleaning and disinfecting the whole water ITEM
reticulation system to the requirements of the Local Authorities
and make good all defects.

C Allow for hydraulic tests (pressure and leakage) as specified ITEM


and as directed by the S.O

TO COLLECTION -

COLLECTION

From Page IW/6/6/1 (R) -

From Page IW/6/6/2 (R) -

From Page IW/6/6/3 (R) -

IW/6/6/96 (R)
PUSAT SUKAN UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BILL NO. 5 - INFRASTRUCTURE WORKS ( ALL PROVISIONAL )


Rate Amount
Item Description Unit Qty
(RM) (RM)

TOTAL CARRIED TO SUMMARY -

IW/6/6/97 (R)
BILL NO. 4 - EXTERNAL WORKS ( ALL PROVISIONAL )

SUMMARY

Item Description From Page Amount

1 EARTHWORKS EW/4/1/2 46,075.00

2 ROADWORKS EW/4/2/2 136,000.00

3 DRAINAGE WORKS EW/4/3/2 32,483.00

4 FENCING AND GATE EW/4/4/1 17,500.00

5 WATER RETICULATION WORKS EW/4/5/5 1,273,740.00

6 PONDOK PENGAWAL EW/4/6/1 60,000.00

TOTAL CARRIED TO SUMMARY OF TENDER 1,565,798.00

SUM/=W-4/98
BILL NO. 5 - PROVISIONAL SUMS

Item Description Unit Qty Rate Amount

PROVISIONAL SUM

Diversion of Existing Services

A Allow a Provisional Sum of RM 480,000.00 (Ringgit Malaysia : 480,000.00


Four Hundred Eighty Thousand Only) for Diversion of
Exisitng Services to be expended as directed by S.O or
deducted in whole or in part if not expended.

Signages

B Allow a Provisional Sum of RM 20,000.00 (Ringgit Malaysia : 20,000.00


Twenty Thousand Only) for Signages to be expended as
directed by S.O or deducted in whole or in part if not expended.

TOTAL CARRIED TO SUMMARY 500,000.00


PRO/5/99
BILL NO. 5 - PROVISIONAL SUMS

Item Description Unit Qty Rate Amount

PRO/5/100
2 UNIT KILANG INKUBATOR DI BANDAR TENGGARA

CADANGAN PEMBINAAN DUA (2) UNIT KILANG INKUBATOR GMP


DIBANDAR TENGGARA, KULAI, JOHOR DARUL TAKZIM

SUMMARY OF TENDER
BIL DESCRIPTION PAGE NO AMOUNT (RM)

1 PRELIMINARIES 1 - 52 100,000.00

2 PILING WORKS (ALL PROVISIONAL) PW/2/1 - PW/2/4 266,450.00

3 ELEVATED WATER TANK (ALL PROVISIONAL) EW/3/1/1 - SUM/EW-3/1 860,370.20

4 EXTERNAL WORKS (ALL PROVISIONAL) EW/4/1/1 - SUM/EW-4/1 1,565,798.00

5 PROVISIONAL SUMS PRO/5/1 500,000.00

TOTAL CARRIED TO FORM OF TENDER 3,292,618.20

RINGGIT MALAYSIA : .............................................................................................................................................................


....................................................................................................................................................................................................
....................................................................................................................................................................................................

COMPLETION PERIOD : ...................................................... ( ) MONTHS

…………….……………………………………… ……………..………………………………………
(Signature of Tenderer) (Signature of Witness)
Name :……………..……………………………. Name : …………………………………………...

…………….……………………………………… …………….………………………………………
Name and Address of Firm Tendering Name and Address Witness
Date : …………………………... Date : …………………………...

SOT/107(R)
CADANGAN PEMBINAAN TANGKI AIR DI BANDAR MAS, KOTA TINGGI, JOHOR DARUL TAKZIM

SUMMARY OF TENDER
ITEM DESCRIPTION PAGE NO AMOUNT (RM)

1 BILL NO. 1 - GENERAL CONDITIONS PRELIMINARIES 51 -

2 BILL NO. 2 - PILING WORKS (ALL PROVISIONAL) PW/2/4

3 BILL NO. 3 - ELEVATED WATER TANK (ALL PROVISIONAL) SUM/EW/3/1

4 BILL NO. 4 - EXTERNAL WORKS (ALL PROVISIONAL) SUM/AB/4/1

5 BILL NO. 5 - PROVISIONAL SUM SUM/IW-5/1

TOTAL CARRIED TO FORM OF TENDER -

RINGGIT MALAYSIA : ………………………………………………………………………………………………………………………………………

……………………………………………………………………………………………………………………………………………………………………

……………………………………………………………………………………………………………………………………………………………………

COMPLETION PERIOD : NINETY ( 90 ) WEEKS.

............................................................ ............................................................
Signature of Tenderer Signature of Witness

Name : ................................................ Name : ........................................................................

Address : ......................................................................

......................................................................
......................................................
Chop .....................................................................

Designation : ................................................ Designation : ..................................................................

Date : ............................................................ Date : ......................................................... .......

SOT-1/107
PUSAT SERENTI KOTA TINGGI

BILL NO. 3 - BANGUNAN PENTADBIRAN


Rate Amount
Item Description Unit Qty
(RM) (RM)

ELEMENT 1 - SUBSTRUCTURE

EXCAVATION WORK

Excavating to reduce level; commencing from formation level;


cart away, deposit, spread and level where directed within
the site not exceeding 1.00m deep.

A 350mm thick (Ground slab) M3 299 9.50 2,840.50

B 300mm thick (Apron slab) M3 31 9.50 294.50

Excavate trenches starting from reduced level; including


backfill with approved excavated material, compaction in
layers and disposal of surplus excavated material where
directed within the site not exceeding 1.00m deep

C Ground beam M3 71 9.50 674.50

Excavate pit starting from reduced level; including backfill


with approved excavated material, compaction in layers and
disposal of surplus excavated material where directed within
the site not exceeding 2.00m deep.

D Pilecap M3 56 9.50 532.00

Bed of hardcore consisting of hard dry broken bricks or


stones, spread or leveled, well consolidated, watered and
well blinded with sand

E 150mm Thick ; under ground slab M2 1167 10.20 11,903.40

F 150mm Thick ; under apron slab M2 119 10.20 1,213.80

PLAIN INSITU CONCRETE WORK

50mm Thick Concrete (Grade 15) as described blinding:

G Under pilecap M2 53 10.00 530.00

H Under ground beam M2 111 10.00 1,110.00

J Under ground slab M2 1167 10.00 11,670.00

K Under apron slab M2 119 10.00 1,190.00

BW/3/1/103
PUSAT SERENTI KOTA TINGGI

BILL NO. 3 - BANGUNAN PENTADBIRAN


Rate Amount
Item Description Unit Qty
(RM) (RM)
TO COLLECTION 31,958.70

SUBSTRUCTURE …..Cont'd

REINFORCED INSITU CONCRETE WORK

Reinforced concrete (Grade 35) as described (formwork and


reinforcement measured separately) in :

A Pilecap M3 30 310.00 9,300.00

B Column Stump ( Provisional ) M3 2 310.00 620.00

C Ground beam M3 65 310.00 20,150.00

D Ground slab M3 128 310.00 39,680.00

E Apron slab M3 13 310.00 4,030.00

Class F1 formwork as described to:

F Sides of pilecap M2 159 28.00 4,452.00

G Sides of column stump ( Provisional ) M2 31 28.00 868.00

H Sides of ground beam M2 642 28.00 17,976.00

J Edges of apron slab ; not exceeding 250mm thick M 132 7.00 924.00

Mild steel (250 N/mm2) rod reinforcement as described :

In column stump ( Provisional )

K 10mm Diameter rod as links, stirrups or binders KG 160 3.80 608.00

In ground beam

L 10mm Diameter rod as links, stirrups or binders KG 2350 3.80 8,930.00

High tensile (460 N/mm2) rod reinforcement as described :

In pilecap

M 16mm Diameter rod KG 685 3.80 2,603.00

In column stump ( Provisional )

N 12mm Diameter rod KG 91 3.80 345.80

P 16mm Diameter rod KG 20 3.80 76.00

Q 25mm Diameter rod KG 87 3.80 330.60

BW/3/1/104
PUSAT SERENTI KOTA TINGGI

BILL NO. 3 - BANGUNAN PENTADBIRAN


Rate Amount
Item Description Unit Qty
(RM) (RM)

TO COLLECTION 110,893.40

SUBSTRUCTURE …..Cont'd

REINFORCED INSITU CONCRETE WORK …..Cont'd

High tensile (460 N/mm2) rod reinforcement as described :

In ground beam

A 12mm Diameter rod KG 1415 3.80 5,377.00

B 16mm Diameter rod KG 438 3.80 1,664.40

C 20mm Diameter rod KG 368 3.80 1,398.40

D 25mm Diameter rod KG 3580 3.80 13,604.00

BRC steel fabric reinforcement; lapping at joints (measured


nett-no allowance made for laps)

In ground slab

E Reference A252/A8 ; 3.95 kg/m2 M2 2189 26.00 56,914.00

In apron slab

F Reference A393/A10 ; 6.16 kg/m2 M2 532 32.00 17,024.00

0.25mmThick approved polythene sheet (heavy duty) as


described damp proof membrane laid on ground slab and
beam and well lapped at joint (measured nett-no allowance
made for laps)

G Ground slab M2 1167 3.00 3,501.00

ANTI-TERMITE TREATMENT (ALL PROVISIONAL)

The termite treatment application shall be carried by termite


control company approved by S.O.

Method of treatment shall be submitted to the S.O. for


approval. All relevant documents, certificates of approval,
guarantee letters, brochures and technical catalogues shall
be submitted to the S.O.before commencement of works

The Contractor shall be held responsible on all work done by


the termite control company

H The Contractor and specialist firm shall guarantee the ITEM 1,000.00
effectiveness of anti-termite treatment for a period of five (5)
years andundertake to carry re-treatment without charge
should infestation of sub-terranean termites occur at any time
during the warranty period

BW/3/1/105
PUSAT SERENTI KOTA TINGGI

BILL NO. 3 - BANGUNAN PENTADBIRAN


Rate Amount
Item Description Unit Qty
(RM) (RM)

TO COLLECTION 100,482.80

SUBSTRUCTURE …..Cont'd

ANTI-TERMITE TREATMENT (ALL PROVISIONAL)…..Cont'd

Carry out anti-termite treatment in accordance with the


specifications as described to :

A Under ground slab M2 1167 3.50 4,084.50

B Under apron slab M2 119 3.50 416.50

Perimeter Drain

Precast concrete (Grade 25) as described including all


moulds, finishing fair on exposed faces and hoisting, fixing,
bedding, jointing and pointing in cement mortar (1:3) :

C 230mm diameter half round channel cast in 610mm length M 155 40.00 6,200.00
laid to fall; grouted and pointed in cement and sand (1:3)
including all necessary excavation, formwork, 150mm thick
concrete base (Grade 25), 50mm thick mass concrete
bedding, concrete hunching, 1 layer BRC A10, one brickwall
complete with plastering to all exposed surfaces and forming
bend, stopped end, juctions, weepholes, cascades, etc

TO COLLECTION 10,701.00

COLLECTION:

From Page BW/3/1/1 31,958.70

From Page BW/3/1/2 110,893.40

From Page BW/3/1/3 100,482.80

From Page BW/3/1/4 10,701.00

BW/3/1/106
PUSAT SERENTI KOTA TINGGI

BILL NO. 3 - BANGUNAN PENTADBIRAN


Rate Amount
Item Description Unit Qty
(RM) (RM)

TOTAL CARRIED TO SUMMARY 254,035.90

BW/3/1/107