BQ 5-60a Segambut
BQ 5-60a Segambut
BQ 5-60a Segambut
SITE CLEARING
1-4-1 Clearing & grubbing construction site of all grass on site 34.10 m2 6.00 204.60
of all grass, lallang, belukar, shrubs and tree less than
600mm measured from the ground level with all debris
and other wastes to be removed from the site and
dispose to location provided by the Contractor or as
directed by the Engineer.
DEMOLITION
2-1-3 Supply all machineries and manpower to use generator 41.48 m3 44.00 1,825.12
set & air compressor hacker to site to break up existing
concrete block drain, pudu cut drain, rubble wall and
brickwall in headwall, wingwall, slabs, manholes,
culverts, drains, rock, etc. and dispose of rubble at site
to be provided by contractor or as directed by the
Engineer.
EXCAVATION WORKS
2-2-7 Excavate to drain for drain laying to depth not 41.48 m3 8.60 356.73
exceeding 1.5m in pre-approved length to minimise
inconvenience to pedestrian and vehicular traffic, get
out and remove to a tip to be provided by the
contractor away from work site, including where
directed cutting site slopes to angles as specified. On
completion of drain laying return selected spoil and
ram sides of drains. Include all necessary timbering.
Refer to clause 3.3. of the specification.
CART AWAY
2-2-5 -ditto- as per item 2-2-3 - but all surplus excavated 41.48 m3 5.80 240.58
earth and cart away to tips to be provided by the
Contractor.
DRAINAGE WORKS
2-8-3 - do - but straight 300mm dia. H.R.G.W. channel. 17.00 m 24.00 408.00
2-3-1 Supply approved FILLING MATERIAL and backfill side 35.70 m2 26.00 928.20
slopes or elsewhere as specified and directed by the
Engineer
CRUSHER RUN
5-2-3 Supply Crusher Run Stone from an approved quarry and 130.35 m2 9.00 1,173.15
spread over formation, fill interstices with a proportion
of smaller gauge stones packed to a consolidated
thickness or not less than 100mm and roll with a roller
of not less than 2 tonne weight true to line, camber and
level.
REINFORCEMENT
2-20-5 Supply and lay BRC FABRICc No. A8 or equivalent, 130.35 m2 33.00 4,301.55
include for fixing, bending if necessary and for
overlapping sheets 300mm along cross wires
at joints and all cutting and waste.
2-20-1 Supply and fix in position MILD STEEL BARS of dia 6- 12.79 kg 5.00 63.94
16mm. Include for cutting, bending and waste and for
tying up bars, and keeping them rigidly in
position.
BRICKWORK
2-16-02 Supply approved wire cut clay bricks and construct 35.70 m2 85.50 3,052.35
225mm thick brickwork walls in English bond over
concrete foundations at sides of inverts
(measured separately). Include for laying and jointing in
cement mortar (1:3) and for rendering all exposed
surfaces with cement mortar 12 mm thick (1:3 where
applicable include for forming a recess 115x89/100/125
mm deep to receive slabs.
RENDERING
2-16-04 Rendering to concrete or brick surfaces with portland 46.92 m2 18.00 844.56
cement mortar 20mmmixture 1:3 finished with steel
float and include for any necessary
screed backing and preparatory work.
M.S. FRAME
2-20-38 Supply and install, Galvanised Mild Steel base frame 18.00 no. 160.00 2,880.00
overall size 610mm x 405mm x 5mm thick with angle
plate 50mm x 50mm x 5mm thick as per detail in the
JKPB Standard Drawing
FORMWORK
2-19-01 Wrot timber formwork and shuttering to concrete 141.97 m2 40.00 5,678.72
columns, piers, retaining wall abutments etc. not
exceeding 1.5m high. Include for all fixing, supply of
timber and fastenings, cutting and waste and for
removal on completion.
3-1-2 Excavate trench to kerb and foundation not exceeding 31.00 m 10.00 310.00
450mm and 300mm depth in pre-approved length and
minimize inconvenience to pedestrian & vehicular
traffic and remove immediately excavated material to
tips provided by the contractor
PRECAST KERB
3-4-13 Supply and lay straight precast concrete GRADE 30 Kerb 31.00 m 178.00 5,518.00
Type MI of size 610mm x 150mm with horizontal (2 Top
& 2 Bottom) T8 and 3 link R8.
Transport to site and lay to line, level and gradient on
prepared concrete bed. Include for bedding and
jointing of kerb in cement mortar (1:2).
HAUNCHING
3-3-4 - do - as per item 3-3-1 but for Kerb ype Ml size 375 x 31.00 m 10.00 310.00
100mm thick foundation & 255 x 150mm triangle
haunching to kerb & channel blocks.
CHANNEL BLOCK
3-4-12 Supply and lay Channel Block GRADE 30 of size 600mm 31.00 m 80.00 2,480.00
x 150mm x 75mm straight over prepared concrete bed
and to line, level and gradient and include for bedding
and jointing in cement mortar (1:2).
CONCRETING TO DRAIN
2-5-1 Provide and lay concrete (1:3:6 - 38mm aggregate) in 0.85 m3 328.00 278.80
base and haunching to block drain, "Pudu Cut" drain
and H.R.G.W channels all as per details in Drawing No.
JKAL 1260/1A, JKAL 1260/2A and JKAL 1260/40. Include
for all mixing and placing as required.
2-5-2 Provide and lay concrete (1:2:4-19mm agg.) in concrete 5.42 m3 375.00 2,034.00
revetment to side ofH.R.G.W. drains all as per details in
Drg. No. JKAL 1260/2A. Include for all
mixing and placing (casing including struts etc. and float
rendering measured separately).
READY-MIX CONCRETE
2-5-11 - do - but for Ready-Mix Concrete Grade 30 MPa. 22.67 m3 390.00 8,841.30
BROOM FINISHES
5-5-5 Supply all labour (specialist) and equipments to apply 94.60 m2 15.50 1,466.30
BROOM FINISHES surface with desire and approved
pattern over undry concrete surface all in accordance
to the Engineer instruction.
STEEL GRATING
2-20-31 -ditto- but for Grating size 610mm x 610mm 12.00 no. 800.00 9,600.00
DAYWORK RATES - LABOUR
14-1-17 Lorry Driver 5.00 Day 120.00 600.00
14-1-1 General Labour (Male or Female) 12.00 Day 80.00 960.00
DAYWORK RATES - PLANT
14-2-27 Lorries (ordinary) - 8 tonne 32.00 Hour 80.00 2,560.00
14-2-4 Hydraulic Rock Breaker - min. 120 H.P. 32.00 Hour 100.00 3,200.00
14-2-9 Backhoe excavator/loader - min. 70 H.P. 32.00 Hour 85.00 2,720.00
14-2-33 Generating sets - 10 K.V.A 24.00 Hour 20.00 480.00
TRAFFIC MANAGEMENT PLAN
10-5-1 Supply all labour, materials and all necessary
equipment to position and maintain Traffic
Management Plan which include Warning Sign, Water-
Filled Plastic Barrier, Flagman, Blinkers & Traffic Cone
(25m before Work Area, Varies at Work Area & 25m
after Work Area
10-5-4 Type C: For maximum 50m to 100m Work Area 1.00 month 3,750.00 3,750.00
TOTAL 71,040.90
LESS 5% 3,552.04
1.2* b) One coat of approved Ceremic Acrylic Urethane 7.13 m2 7.56 53.90
Undercoat
1.3* c) Two coat of approved Ceremic Acrylic Urethane Gloss 7.13 m2 8.28 59.04
Finish to approved colour(s) as directed. (Each coat to
be paid seperately).
RM 112.94
RM 67,601.79
TAKING OFF SHEET
Tajuk kerja:
KERJA-KERJA BAIKPULIH BEBENDUL JALAN, SIARKAKI DAN LONGKANG SERTA KERJA-KERJA BERKAITAN DI JALAN 5/60A,
SEGAMBUT KUALA LUMPUR.
KERJA-KERJA BAIKPULIH BEBENDUL JALAN, SIARKAKI DAN LONGKANG SERTA KERJA-KERJA BERKAITAN DI JALAN 5/60A,
SEGAMBUT KUALA LUMPUR.
BRC A8 FORMWORK
Item 2-20-5 Item 2-19-01
Slab penutup longkang 18 Frame opening
55.00 (L) 2 no of side
1.10 (W) 0.61 (L)
60.50 m
2
TOTAL 0.15 (W)
3.29
Entrance slab 18
7.50 (L) 2 no of side
2.50 (W) 0.81 (L)
18.75 m
2
TOTAL 0.15 (W)
130.35 m
2
TOTAL 4.37
KERJA-KERJA BAIKPULIH BEBENDUL JALAN, SIARKAKI DAN LONGKANG SERTA KERJA-KERJA BERKAITAN DI JALAN 5/60A,
SEGAMBUT KUALA LUMPUR.
94.60 m
2
Item 2-5-2 TOTAL
Base drain
17.00 (L) STEEL GRATING
1.00 (W) Item 2-20-31
0.30 (D) 10 nos
5.10 m
3
TOTAL Size 0.6 x 0.8
1 nos (0.6 × 0.8 (𝑜𝑛−𝑠𝑖𝑡𝑒))/
(0.61 ×0.61 (𝐵𝑄))
Strut TOTAL 10.00 nos
6 (nos) =1.29 @ 1 𝑛𝑜𝑠
3 (no. of side)
0.80 (L) 2 nos
0.15 (W) Size 0.8 x 0.6
0.15 (D) 1 nos (0.8 × 0.6 (𝑜𝑛−𝑠𝑖𝑡𝑒))/
(0.61 ×0.61 (𝐵𝑄))
0.32 TOTAL 2.00 nos
TOTAL 5.42 m³ TOTAL 12.00 nos =1.29 @ 1 𝑛𝑜𝑠
Tajuk kerja:
KERJA-KERJA BAIKPULIH BEBENDUL JALAN, SIARKAKI DAN LONGKANG SERTA KERJA-KERJA BERKAITAN DI JALAN 5/60A,
SEGAMBUT KUALA LUMPUR.
Backhoe
item 14-2-9
4 day
8.00 hour
TOTAL 32.00 hour
Generating sets
item 14-2-33
3 day
8.00 hour
TOTAL 24.00 hour