Quick Installation Guide 3-6kW Storage System Inverter

Packing List

A B C D E

F G H I J

K L M N O

P
Object Quantity Description Object Quantity Description
A 1 Inverter I 1 Earth terminal
B 1 Bracket J 1 Communication connector
PV connectors (for Hybrid only)
C 4 K 1 Product manual
(2*positive, 2*negative)
PV pin contacts (for Hybrid only)
D 4 L 1 Quick installation guide
(2*positive, 2*negative)
E 2 AC connectors M 1 CT (with 10m cable)
Battery connectors
F 2 N 1 WiFi/LAN/GPRS (Optional)
(1*positive, 1*negative)
Battery pin contacts
G 2 O 1 Meter (Optional)
(1*positive, 1*negative)
H 5 Expansion tubes& Expansion screws P 1 CT extension connector

1
Inverter Installation

Please make sure the inverter will be installed with a proper distance
as shown below.

Position Min Size


Left 30cm
Right 30cm
Top 30cm
Bottom 30cm
Front 30cm

Step 1: Fix the bracket on the wall

Choose the place you want to install


the inverter. Place the bracket on the
wall and mark the position of the 5
holes from bracket.

Drill holes with electric drill, make


sure the holes are at least 50mm
deep, and then tighten the expansion
tubes.

2
Insert the expansion tubes into the holes and tighten them. Install the
bracket with the expansion screws.

Step 2: Match the inverter with wall bracket


Hang the inverter over the bracket, slightly lower the inverter, and make
sure the two mounting bars on the back are properly fixed with the two
bracket grooves.

3
Serial Port Connections

Communication interface between the inverter and


Meter/Battery/DRM/485 are as follows with Rj45 connectors which should
be inserted corresponding port in the inverter.

PIN
1 2 3 4 5 6 7 8
Port
CT/
Meter Meter
Meter/ 485B 485A CT2+ CT2- CT1- CT1+
485A 485B
485
BMS- BMS- BMS- BMS-
BMS / GND / /
485B CANL CANH 485A
DRM DRM DRM DRM
DRM GND GND DRM0 +3.3V
4/8 3/7 2/6 1/5

Note:
CT1: For Hybrid/AC, CT2: Grid tied inverter (if have).
Compatible Meter type: DDSU666 (CHINT), SDM230 (EASTRON).

4
Wiring Steps

PV Wiring (For Hybrid Only)


· Choose 12 AWG wire to connect the PV module.
· Trim 6mm of insulation from the wire end.

· Separate the DC connector (PV) as below.


Plug Pin contact cable nut

· Insert striped cable into pin contact and ensure all conductor strands
are captured in the pin contact.

· Crimp pin contact by using a crimping plier. Put the pin


contact with striped cable into the corresponding
crimping pliers and crimp the contact.

· Insert pin contact through the cable nut to assemble into back of the
male or female plug. When you feel or hear a “click” the pin contact
assembly is seated correctly.

5
· Unlock the DC connector:

- Use the specified wrench tool.


- When separating the DC+ connector, push the tool down from the
top.
- When separating the DC- connector, push the tool down from the
bottom.
- Separate the connectors by hand.

Battery Wring
· Turn off the DC switch.
· Choose 10 AWG wire to connect the battery.
· Trim 6mm of insulation from the wire end.

10AWG

· Separate the DC connector (battery) as below.


Plug Pin contact cable nut

· Insert striped cable into pin contact and ensure all conductor strands
are captured in the pin contact.

6
· Crimp pin contact by using a crimping plier. Put the pin
contact with striped cable into the corresponding
crimping pliers and crimp the contact.

·➢ Insert pin contact through the cable nut to assemble into back of the
male or female plug. When you feel or hear a “click” the pin contact
assembly is seated correctly.

· Unlock the DC connector


- Use the specified wrench tool.
- When separating the DC + connector, push the tool down from the
top.
- When separating the DC - connector, push the tool down from the
bottom.
- Separate the connectors by hand.

Grid Wiring

Cable dimensions
Model (kW) 3.0 3.7 4.6 5.0 6.0

Cable (AC) 8.0mm² 8.0mm² 8.0mm² 8.0mm² 10.0mm²


Cable (BACK-UP) 4.0mm² 4.0mm² 6.0mm² 6.0mm² 6.0mm²
Micro-Breaker 50A 50A 63A 63A 63A

7
- Trim all the wires to 52.5mm and the PE wire to 55mm.
- Use the crimping pliers to trim 12mm of insulation from all wire ends
as shown in the picture.

L: Brown/Red Wire
N: Blue/Black Wire
PE: Yellow & Green Wire

Note: Please refer to local cable type and color for actual installation.

A. BACK-UP Wiring

· Separate the BACK-UP plug into three parts as below.


1. Hold the middle part of the female insert, rotate the back shell to
loosen it, and detach it from female inset.
2. Remove the cable nut (with rubber insert) from the back shell.

· Slide the cable nut and then the


back shell onto the cable.

· Push the threaded sleeve into the


socket, tighten up the cap on the
terminal.

8
· Push the threaded sleeve to connection terminal until both are locked
tightly on the inverter.

· Loosen the cap on the terminal, pull the threaded sleeve out of the
socket.

B. AC Wiring
· Separate the AC plug into three parts as below.
1. Hold the middle part of the female insert, rotate the back shell to
loosen it, and detach it from female inset.
2. Remove the cable nut (with rubber insert) from the back shell.

· Slide the cable nut and then the back shell


onto the cable.

9
· Push the threaded sleeve into the socket,
tighten up the cap on the terminal.

· Push the threaded sleeve to connection terminal until both are locked
tightly on the inverter.

· Remove the AC connector: Press the bayonet out


of the slot with a small screwdriver or the unlock
tool and pull it out, or unscrew the threaded
sleeve, then pull it out.

Grounding Wiring
Use the crimping pliers to press the ground cable into the ground terminal,
screw the ground screw with screwdriver as shown below.

10
BMS Connection
Step 1: Prepare a standard network cable and cable connector, then insert
the network cable through the cable connector.

Step 2: Crimp the cable with a Rj45 plug which is inside of the cable
connector.

Step 3: Insert the cable connector into BMS port at the bottom of inverter.

11
Inverter Start-Up

Please refer to the following steps to start up the inverter.


1. Ensure the inverter fixed well on the wall.
2. Make sure all the AC wirings are completed.
3. Make sure the meter is connected well.
4. Make sure the battery is connected well.
5. Make sure the external EPS contactor is connected well (if needed).
6. Turn on the PV/DC switch (for Hybrid only), AC breaker, EPS breaker and
battery breaker.
7. Enter the settings page, select START / STOP and set it to start.
Note:
· When starting the inverter for the first time, the country code will be set
by default to the local settings. Check if the country code is correct.
· Set the time on the inverter using the button or by using the APP.

Inverter Switch Off

Please refer to the following steps to switch off the inverter.


1. Enter the settings page, select START / STOP and set it to stop.
2. Turn off the PV/DC switch (for Hybrid only), AC breaker, EPS breaker and
battery breaker.
3. Wait 5 min before you open the upper lid (if in need of repair).