Unit G - Punchlist Basement

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Date : March 23, 2023

Project : 12 UNITS, 3-STOREY RESIDENCE WITH BASEMENT


Location : 4th St. Corner Madison St., New Manila, Quezon City
Subject : FINAL PUNCHLIST FOR UNIT G

UNIT G PUNCHLIST - BASEMENT


ITEMS PHOTOS DESCRIPTION TRADE CONTRACTOR STATUS ACCEPTED BY

A. BASEMENT HALLWAY

a.1 Improper application of sealant Fit - out LBY

a.2 Incomplete floor tile grouting Fit - out LBY

a.3 Alignment of elevator grani Fit - out LBY

a.4 Chip floor tiles rectification Fit - out LBY

Improper installation of rivet and application of


a.5 Fit - out LBY
sealant

a.6 Improper application of sealant Fit - out LBY

a.7 Rectification of pump room door frame Fit - out LBY

a.8 Improper groove granite alignment Fit - out LBY

a.9 Improper painting application Fit - out LBY


a.10 Improper groove of granite Fit - out LBY

a.11 Improper buffing of granite Fit - out LBY

a.12 Improper painting application Fit - out LBY

a.13 Improper wall painting application Fit - out LBY

a.14 Improper rivet and sealant application Fit - out LBY

a.15 Cleaning and Improper application of sealant Fit - out LBY

a.16 Improper wall painting termination Fit - out LBY

a.17 Improper wall painting Fit - out LBY

a.18 Improper application of sealant Fit - out LBY

Termination alignment betwen wall tiles and


a.19 Fit - out LBY
aluminum
B. PUMP ROOM

b.1 Cleaning of Pump room door Fit - out LBY

b.2 Painting of angle bar Plumbing Felix De Jesus

b.3 Improper wall Painting Fit - out LBY

b.4 Improper Painting application Fit - out LBY

b.5 Improper sealant application Fit - out JQ

b.6 Improper Painting application Fit - out LBY

Improper installation of power supply flexible


b.7 Electrical Mylene Peña
hose

b.8 Improper wall painting Fit - out LBY

b.9 Incomplete wall plastering Masonry Mervin Tuazon

C. DIRTY KITCHEN

c.1 Incomplete grouting Fit - out LBY

Improper ceiling painting termination between


c.2 Fit - out LBY
wall tiles and ceiling
c.3 Improper wall tile grouting application Fit - out LBY

c.4 Replacement of chip wall tiles Fit - out LBY

c.5 Incomplete grouting Fit - out LBY

c.6 Incomplete rivet Fit - out LBY

D. PANTRY

d.1 Yellow paintig of gas line Fit - out LBY

d.2 Incomplete ceiling painting Fit - out LBY

E. MAID'S ROOM

e.1 Door panel replacement Fit - out LBY

e.2 Removal of excess wood glue Fit - out LBY


e.3 Improper wall tile grouting Fit - out LBY

e.4 Door casing alignment Fit - out LBY

e.5 Sealant application Fit - out LBY

e.6 Improper installation of door casing Fit - out LBY

Improper wall painting termination between


e.7 Fit - out LBY
dppr casing

e.8 Improper installation of door casing Fit - out LBY

e.9 Incomplete rivet Fit - out LBY

e.10 Replacement of door panel Fit - out LBY


e.11 Improper painting and grouting termination Fit - out LBY

e.12 Replacement of door panel Fit - out LBY

e.13 Application of sealant Fit - out LBY

e.14 Improper application of sealant Fit - out LBY

e.15 Incomplete and Improper application of sealant Fit - out LBY

e.16 Replacement of wood door panel Fit - out LBY

e.17 Replacement of PVC Door

F. LAUNDRY

f.1 Incomplete wall painting Fit - out LBY

f.2 Incomplete ceiling painting Fit - out LBY

G. CARPORT

g.1 Incomplete ceiling painting Fit - out LBY


g.2 Incomplete sealant Fit - out LBY

g.3 Improper painting application Fit - out LBY

g.5 Wall tile façade cleaning Masonry Mervin Tuazon

g.6 CCTV Installation Electrical Mylene Peña

g.7 Incomplete Ceiling Installation Fit - out LBY

g.8 Improper painting application Painting Jay-on Painters

F. DRIVER'S ROOM

f.1 Ceiling painting application Fit - out LBY

f.2 Sealant Application Fit - out LBY

f.3 Sealant Application Fit - out LBY

f.4 Improper grout application Fit - out LBY


f.5 Improper ceiling painting Fit - out LBY

f.6 Improper grouting application Fit - out LBY

f.7 Improper sealant application Fit - out LBY

f.8 Improper sealant application Fit - out LBY

f.9 Improper installation of door lockset Fit - out LBY

Improper installation of window due to


f.10 Fit - out LBY
orientation

f.11 Improper installation of tile baseboard Fit - out LBY

Prepared by;

Engr. Jecyrill Rodriguez


Project Engineer, JMB Management

Noted by;

Ar. Jessie Bernardo


Project Manager, JMB Management