Blue Print PP
Blue Print PP
103
Phosphorus India Ltd
PROJECT MANAGER
Mr.
MODULE EXPERTS
FICO : Mr. Gokul
MM :
PP : Mr. Y. M. Reddy
SD : Mr. Krishna Mohan
FI-CO MM SD PP HR
Mr. Mortin
Mrs. Meenakshi Mr. Arvind Mr. GiriPrasad Mr. N.Gulhane Mr. Suresh
Mr. Venu Mr. Madhav Mr. G. Ravikumar Miss. Sangeeta
Mr. Jawar Miss. Bindi Priya
Mr. Srikanth
104
Phosphorus India Ltd
TABLE OF CONTENTS
1. INTRODUCTION
2. PURPOSE
3. SCOPE
4. BUSINESS BENEFITS
a) GENERAL
b) PP-RELATED
5. ORGANIZATION
o GENERAL EXPLANATION
o NAMING CONVENTION
o DEFINITION OF ORGANIZATIONAL UNITS
I. CLIENT
II. COMPANY CODE
III. PLANT
IV. STORAGE LOCATION
105
Phosphorus India Ltd
106
Phosphorus India Ltd
23. Introduction
Phosphorus India Ltd is a corporate giant in the Agrochemical and Industrial Chemicals
sector in India and has major presence
• The Specialty Chemicals (Insecticide, Fungicides, herbicides, fumigants and
rodenticides)
• Caustic Chlorine
• White Phosphorus
• Industrial Chemicals
• Captive Power Generation of 48.5 MW
The group has major products in the Insecticide, Herbicide, Vidicide, Fumigant, and Industrial
Gases. Apart from this, the group also has manufacturing facilities in UK, USA, China and
Argentina.
Phosphorus India Limited today, has the widest range of generic agrochemical and other
chemical intermediates. Over and above, good markets in India, these agrochemicals are
exported to more than 100 countries in the world.
24. PURPOSE
The purpose of the Business Blueprint is to document the detailed System and
Business Process Requirements, and to implement the SAP R/3 System. This document
summarizes the proposed decisions associated with implementation as they relate to the
configuration of SAP.
25. SCOPE
The Implementation Scope includes the following SAP R/3 Sub-Modules in Production
Planning:
7.1 MASTER DATA
• Material master
• Bill of material
• Work center
• Routing
7.2 PRODUCTION PLANNING
• Sales & Operations Planning
• Demand management
7.3 MATERIAL REQUIREMENT PLANNING
107
Phosphorus India Ltd
a) General
• SAP will provide Access to Real-Time, On-Line Information with timely processing.
• SAP will offer stronger, more robust Reporting Tools.
• SAP’s Integrated Database eliminates the need for data replication and stand-alone
systems, decreasing the chance for human errors. This will reduce non-value-added work
while improving overall data integrity and give broader information access.
• SAP is “Packaged” Software, which is readily scalable. As such, the SAP software will
serve as a facilitator of future growth.
b) PP-Related
• Entire Production Planning and Control process will be captured for the first time in a
computerized SAP R/3 system.
• Part numbers for semi-finished product defined, so that stock valuation at various WIP
stages can be done through SAP.
• Material requirement planning will be performed through a much accurate MRP run
process in SAP. Material will be planned from the raw materials till the finished product
stage.
• For the Material Type Production resources, consumables and tools, consumption based
planning will be undertaken.
• Planned Scrap outcome of the production process will be accounted through the SAP
system automatically and back-flushed to Scrap store.
• Capacity planning, Production scheduling with the PIL Shift sequence will be performed
through SAP.
• Product Costing to be obtained through SAP.
• Standard SAP reports will be generated for all production processes.
• All the Work Centers in PP are assigned to Cost center. All the production costs will
automatically get accumulated in the cost centers.
• All the PP master data will be loaded on to the system resulting in generation of the
planned costs of the production processes. Actual production can be confirmed in the
system, which will generate the actual costs. Variance in the planned and actual costs can
be identified and the desired improvements can be effected in order to improve and further
control the production process. This is only possible through the integration of the various
modules.
27. ORGANIZATION
SAP an organizational structure consists of the following units: -
The client is the top level of the organizational level. Several company codes can be assigned
to one client. In turn, several plants can be assigned to a company code, and several storage
locations assigned to a plant.
Plants must always be consecutively numbered for all company codes. Consequently, plants
assigned to different company codes cannot have the same number. However, the numbers of
storage locations can be repeated, as long as they are assigned to different plants.
108
Phosphorus India Ltd
109
Phosphorus India Ltd
PIL
Group
of
Comp.
PIL
PIL Unit-2
Unit-1 Ankleshw
Vapi ar
ISOPROT
Freon URON TCAC ZNP Plant ALP Plant
CPP Plant Plant Plant with Plant
2 Prod.
Line
Semi-Finish Semi-Finish
Storage Storage
110
Phosphorus India Ltd
Plants:
1. PIL Unit-1 Located At Vapi
CPP Plant
CPP
Chloropyripho
Plant Name Products SAP Nomenclature
b. Freon Plant Freon-22 FREP
Freon-12
Freon Plant
ISOP Plant
ISOPROTURON
111
Phosphorus India Ltd
Storage Locations:
1. PIL Unit-1 Located At Vapi
112
Phosphorus India Ltd
Forecast/
Demand
Planning
Production Procurement
PIL PIL
Unit-1 Unit-2
Depot-1 Depot-3
Finance
Invoicing
Collection
113
Phosphorus India Ltd
29. CROSS-APPLICATION/CENTRAL
ORGANIZATIONAL UNITS
a) General Explanation
An organizational unit serving subdivides an enterprise according to production, procurement,
maintenance, and material planning aspects. It is a place where either material is produced or
goods and services provided.
All data that is valid for a particular plant, as well as for the storage locations belonging to it, is
stored at plant level. This includes, for example, MRP data and forecast data.
b) Naming Convention
It is being proposed that the following number of plants will be created
CPP Plant Code- CPPP
FREON Plant Code- FREP
ISOPROTURON Plant Code- ISOP
c) Definition of Organizational Unit
An organizational unit serving subdivides an enterprise according to production, procurement,
maintenance, and material planning aspects. It is a place where either material is produced or
goods and services provided.
d) Assignment of Organizational Units
All data that is valid for a particular company code, as well as for the plants and storage locations
assigned to it, is stored at company code level. This includes, for example, accounting data and
costing data if valuation is at company code level.
e) Changes to existing Organization
It had been proposed that 3 plants be created (CPPP, FREP, and ISOP) and assigned to the
company code PIL1. Various storage locations for finished goods, raw material, Semi-finish,
Scrap, and Consumables will be created and assigned to each plant.
1. CALENDAR
Requirements/Expectations
Factory calendar needs to be maintained in the system. In this the working days are to be defined
and the holidays. This information is used in various modules. Country wise calendars are already
maintained in the system.
The Factory Calendar needs to be updated each year based on the decided holidays. The Factory
Calendar acts as the basis for Capacity Planning as it defines the working days in a year. In SAP
there are two types of holidays. Holidays are to be created and then assigned to the factory
calendar.
2. UNITS OF MEASUREMENT
Requirements/Expectations
Units of measure are required to facilitate the procurement and management of various items in
multiple order units.
114
Phosphorus India Ltd
General Explanations
The unit of measure is utilized to describe the unit in which items are procured or stored. There are
over 220 different units of measure provided by SAP.
System Configuration Considerations
Units of measure to be used must be entered in the Purchase Requisition and Purchase Order in
SAP.
Special Considerations: Units of measure that are being used will be configured in
SAP if they do not exist
CPP Product has 4 variants like ethyl CPP 97%, Ethyl CPP 98%, Methyl CPP
97% and Methyl CPP 98%. First We will go for CPP and then after successful
completion of this, we will use variant configuration or Variant BOM
115
Phosphorus India Ltd
b) MATERIALS Types
Sr. No. Material Type Description
1 ROH Raw Materials
2 HALB Semi Finished Products
3 FERT Finished Products
4 ERSA Spare parts
5 HAWA Trading Goods
6 VERP Packing Material
7 LEIH Returnable Transport Packing
8 PIPE Pipeline Material
9 FHMI Production resources / Tools
10 NLAG Non–Stock Materials
1. Multiple BOM
One product can be manufactured from alternative combinations of materials depending on the
quantity to be produced (lot size). The product is represented by a number of alternative BOMs
(alternatives). The differences between the alternative BOMs are only small. Usually the only
difference is in the quantity of individual components. A multiple BOM groups together several
BOMs that describe one object (for example, a product) with different combinations of materials for
different processing methods
116
Phosphorus India Ltd
2. Variant BOM
The term "variant" refers to changes to the basic model of a product. These changes occur when
components are left out or added.
If you are producing several similar products that have a lot of common parts, you can describe
these products using a variant BOM. This is the case, for example, if you replace one material
component with another to make a different product. Variants can also differ by containing different
quantities of a component. You create the new BOM as a variant of an existing BOM.
Variant BOM
In M/s Phosphorus India Ltd variant BOM can be created in case of ethyl CPP
97%, methyl CPP 97, Ethyl CPP 98% and methyl CPP 97% as the final products
vary with only change in 2 Raw Materials.
But initially we will go for one Product CPP. Later on after successful
implementation we will go for variant BOM
b) BOM USAGE
BOM Usage defines the area where a BOM can be used like Production, Engineering/Design, Plant
maintenance, Spares, Costing relevance, sales.
Different BOMs will be maintained for different areas. In the standard system for Production, you can
create a BOM for all material types. You cannot create BOM for Material Type HIBE (Operating
Supplies). Operating supplies are procured externally and are required for producing other products.
c) Group BOM
A BOM that is not assigned to any plant is a group BOM. It is valid across the entire company. A group
BOM is not exploded in material requirements planning and in the production order. Group BOMs are
mainly created in the design phase and then later assigned to one or more plants for production.
d) BOM Group
A collection of bills of material that lets you describes a product or a number of similar products. BOM
group comprises of: -
e) Use Of BOM in PP
The data stored in bills of material serves as a basis for production planning activities such as:
117
Phosphorus India Ltd
• A work-scheduling department uses bills of material as a basis for operation planning and
production control.
• A production order management department uses bills of material to plan the provision of
materials.
The data stored in bills of material is also used in other activities in a company such as:
• Sales orders
As an aid to data entry. You can also create and maintain a BOM specifically for a sales order
(variant configuration).
• Product costing
INTEGRATION
Item category
Categorization of the items in a BOM according to set criteria, such as whether they refer to an object
(for example, material master or document info record) or whether they are kept in stock. This
categorization allows you to process data that is relevant to the individual items in a BOM. The item
category is used to control field selection, default values for BOM maintenance, triggering of specific
system activities, and so on.
• Item Categories for Material Items: You can use the following item categories for
material items:
• Stock Items
• Non-Stock Items
• Variable-Size Items
• PM Structure Elements
• Intra Materials
• Document Items
118
Phosphorus India Ltd
• Class Items
• Text Items
9 Stock item
This item category is used to manage material data that allows an item to be kept in stock.
9 Document item
This item category is used to manage document data that allows you to process original application
data (for example, graphics created with a graphics program).
9 Class item (for configurable BOMs)
In configurable material BOMs, you can enter a class as a placeholder for selectable items. The class
can contain either materials or documents.
When you assign characteristic values while configuring the BOM, the system replaces the node with
an object that has the same values as those assigned to the characteristic of the configuration. This
makes BOMs with a larger number of variants easier to maintain, as you do not have to enter all items
manually and assign a selection condition to them.
Class items can be relevant to MRP.
a) Recursive BOM
When a header material is a component in a BOM, it is Recursive BOM.
b) CO Products / BY products
A product that is automatically produced when main product is manufactured having considerable
value is Co Product and negligible value is BY Product.
Co product can be considered as a finished or semi finished but this is not the case for a By Product.
In Current situation, only Bi-Product terminology is being used. As per SAP procedure we have
divided these products into Bi-Products and Co-Products, which are mention in above Product
list.
¾ General Explanations
BOMs are used in their different forms in various situations where a finished product is assembled
from several component parts or materials In the case of BOM, simple BOM, variant BOM, and
multiple BOM will be used as applicable.
Multi-level BOMs will be created for various products manufactured in plants CPPP, FREP, ISOP.
119
Phosphorus India Ltd
The first level will contain all the finished products, which are dispatched to the customer and then
the second level and so on.
The last level down the line will have raw materials procured from outside for the purpose of
manufacturing finished or semi-finished components.
¾ Naming/Numbering Conventions
Each BOM for a finished product will have the finished product code as the header.
¾ Description of Improvements
Creation of consistent and uniform master data, for example bill of material, and activities across
the organization for the purpose of Costing, Production and Inventory Management purpose.
Putting the same data say for example the methods of production, time required for production etc
for each and every material at one place.
120
Phosphorus India Ltd
3 Inorganic
Anhydrous HF Acid
kg 60 33 28
4 Chlorine Inorganic
kg 18 0.5 0.5
5 Acid
H2SO4 Sulfuric Acid
kg 22 0.04 0.04 2400 3000
6 Soda Ash Inorganic
kg 10 25 25
7 48%NaOH Inorganic
kg 15 2100 0.012 0.002
8 TCAC Organic
kg 60 1900
9A C N Organic
kg 75 600
10 CuCl Catalyst
kg 90 9
11 Rani Catalyst Catalyst
kg 4
12 DETC Organic
kg 80 1100
13 HNO3 Nitric Acid Inorganic
kg 25 1800
14 Cumin Organic
kg 60 3500
15 Hydrogen Gas
kg 20 90
16 EDC Solvent
kg 25 5000
17 PCU Organic
kg 70 1250
18 Xylene Solvent
kg 55 300
19 Urea Inorganic
Kg 25 550
20 DMA Organic
kg 60 450
21 Packing
HDPE Drum 210 lit
Nos. 400 22.5
22 Jute Bag Packing
Nos. 70 30
23 13.6 lit Cylinder for Packing
Export Nos. 300 10 8
24 MS liner Drum 210 Packing
Lit Nos. 1500 77
25 Carbon Inorganic
Kg 200 0.5
26 Power Utility
KW hr 5.5 3800 450 450 15000
27 Steam Utility
kg 0.66 13700 410 410 15000
28 Water Utility
Kg 0.007 11400 300 300 4000
121
Phosphorus India Ltd
Cost /-
U/ Purchasi
M ng Cost
Sr Material
.N Raw group
o Material Rs.
1 TCAC Organic kg 60 1900 1900 1900 1900 1900
2 ACN Organic kg 75 600 600 600 600 600
3 CuCl Inorganic kg 90 9 9 9 9 9
4 DMTC Organic kg 85 1110 1110
5 DETC Organic kg 80 1100 1100 1100
6 48%NaOH Inorganic kg 15 2100 2100 2100 2100 2100
7 EDC Solvent kg 25 250 260 260 270 270
8 Methanol Solvent kg 40 300 300 300 300
9 Carbon Inorganic Kg 200 0.5 1 1 1
1 Inorganic
0 Catalyst-1 Kg 0.5 0.5
1 Inorganic
1 Catalyst-2 kg 0.5 0.5
1 MS liner Packing
2 Drum 210 No
Lit s 1500 77 77 77 77 77
1 Utility K
3 W
Power hr 5.5 3800 4600 4600 4600 4600
1 Utility
4 Steam kg 0.66 13700 14000 14000 14000 14000
1 Utility
5 Water Kg 0.007 11400 11400 11400 11400 11400
122
Phosphorus India Ltd
2 Weighing Nos 2 2 4 1 2 2
Balance
3 Trolleys Nos 4 4 6 1 2 6
4 Lift Nos 1 1 1 1 1 2
123
Phosphorus India Ltd
5 Samplers Nos 10 10 15 10 5 20
6 Manometer Nos 5 5 5
8 Pressure Nos 5 4 5 2 1 2
Transmitter
9 Chlorine Kit Nos 1 1
10 Torch Nos 2 2 3 2 2 5
12 Shovels Nos 5 5 2 2 2
13 Crane Nos 2
Use
Together with bills of material, work centers belong to the most important master data in the R/3
production planning and control system. Work centers are used in task list operations and work orders.
Task lists are for example routings, maintenance task lists, inspection plans and standard networks.
Work orders are created for production, quality assurance, plant maintenance and for the Project
System as networks.
Data in work centers is used for
Scheduling: Operating times and formulas are entered in the work center, so that the duration of an
operation can be calculated.
Costing: Formulas are entered in the work center, so that the costs of an operation can be calculated.
A work center is also assigned to a cost center.
Capacity plans: The available capacity and formulas for calculating capacity requirements are entered
in the work center.
Processing of the work centers involves the maintenance of the following data:
Basic Data
Capacity data
124
Phosphorus India Ltd
Scheduling data
Costing data
General Explanations
• The work centers represent the different processing centers or production line responsible
for the production of the finished product.
• The work center master data is divided into different screens like, basic data, capacity
overview, capacity header, scheduling, cost center, defaults etc. The different screens are
controlled by the work center category, whereas the capacity data is differentiated
according to the capacity category.
• The basic data view includes the description of the work center, the task list usage and the
standard value key. The usage describes the usability of the work center in routings or
other task lists.
• The standard value key supports the parameters, which represent the individual
operational segments like machining and labor etc.
• The capacity view contains all the data for the availability of the capacity and the different
formulas for the capacity requirement calculation.
• The scheduling view contains the scheduling data.
• The cost center view contains the costing data.
Naming/Numbering Conventions
Each work center/production line would be identified by their alphanumeric codes.
The first two letters denotes the location of the work center/production line (plant wise), the next
two letters will denote the type of the machine and number (like 1,2,3 …etc) will identify machine .
125
Phosphorus India Ltd
10.1 INTEGRATION
A Logistics work center can be assigned to either an organizational unit or a work center in the Human
Resource Management System (HRMS). Assignments to other HR-objects, for example employees or
qualifications, can be maintained via the HR work center.
Costing: Formulas are entered in the work center, so that the costs of an operation can be calculated.
A work center is also assigned to a production cost center and the production cost center has been
assigned to appropriate activity types. The prices for these activity quantities are calculated using the
activity prices.
10.2 CAPACITY
Capacity planning comprises the following partial components:
¾ Capacity evaluation
In the capacity evaluation, available capacity and capacity requirements are determined and
compared with each other in lists or graphics.
126
Phosphorus India Ltd
¾ Capacity leveling
The objectives of capacity leveling are:
• Optimal capacity commitment
• Selection of appropriate resources
In most applications, you can use two types of planning table (graphical and tabular
versions) to display the capacity situation and to carry out capacity leveling.
For machines which are automatic no breaks are scheduled. 30 Min break time for lunch
No. of (BCT
Work W.C.
Work in
Center Description Categor Activity Type
cente Hrs/bat
y
rs ch)
127
Phosphorus India Ltd
128
Phosphorus India Ltd
(ISOPRO Crystallizat
ISCR 2 12 Machine Set, Mach, Lab, Pow,
TURON) ion
Centrifugin
ISCN 3 13 Machine Set, Mach, Lab, Pow,
g
Vacuum
ISRV 1 6 Machine Set, Mach, Lab, Pow,
Drying
ISO
Screening
ISPC 1 6 Machine Set, Mach, Lab, Pow,
and
Bagging
Amm. Sul.
ISEV Evaporatio 1 8 Machine Set, Mach, Lab, Pow,
n
Bi-
Product Vacuum
ISVD 1 6 Machine Set, Mach, Lab, Pow,
Stage Drying
Amm. Sul.
ISAP 1 4 Labor Labor
Packing
129
Phosphorus India Ltd
130
Phosphorus India Ltd
Name in Hrs)
DCAC React.
TCDC 6 70
Cum Dist.
HCL Scrubber
24 Hrs
TCHCL1 in DCAC 1
Running
Section
Sodium
Stage-1 TCNa Sulphite 2 12
Evaporator
Na2SO3 final
TCNaRVD Moisture 2 12
removal
TCAC TCAC Reactor 6 48
TCAC
TCDI 2 24
Stage-2 Distillation
HCL Scrubber
24 Hrs
TCHCL2 in TCAC 1
Running
Section
131
Phosphorus India Ltd
33. ROUTING
INTRODUCTION:
Routings enable you to plan the production of materials (products). Therefore, routings are
used as a template for production orders and run schedules as well as a basis for product
costing.
132
Phosphorus India Ltd
Rate Routing
A routing for whose operations the production quantity and a fixed duration has been defined.
Thus the production rate is also defined.
General Explanations
A routing is assigned to a specific plant, which is defined in the routing header. However, you can
assign individual operations of a routing to a different plant, if one or several operations are to be
carried out in another plant. The plants specified in the individual operations and the one specified
in the routing header must belong to the same company code.
Naming/Numbering Conventions
Each routing will be maintained for the finished good, as the header material.
Benefits
Online and close monitoring of the production, scheduling, capacity requirement calculation and
costing will be done for which at present there is no system.
133
Phosphorus India Ltd
134
Phosphorus India Ltd
CPN to
Scrap CPN Distillation 30% HCL Acid
48% NaOH
Hydrolysis
Water
ETP1
Filtration
NaTCP
Cake
135
Phosphorus India Ltd
MEE Water
CPP Washing
LDO EDC Storage
Tank
Rec.EDC
EDC Distillation in HVD
7 CPP Washing 10 12 4 48 40
8 LVD 10 12 4 48 40
9 HVD 10 12 4 48 40
136
Phosphorus India Ltd
90 Kg
Stage-2 PCU Section Hydrogen Hydrogenation
Separation
PCU Distillation
137
Phosphorus India Ltd
DCU Reaction
50 kg 48% NaOH
De-Hydration Washing at room Temp
4000l lit 26 % Ammo.
Sulphate
1500 kg ISOPROTURON
138
Phosphorus India Ltd
Pressure Reaction
SbCl5 Catalyst
Bi-Product
30% HCL Acid 4500 kg/hr
FFE for HCL Scrubbing
Gas Compression
Co-Product Freon-11
330 kg/hr during Distillation Unt-1
Freon-12 Production
Distillation Unt-2
Freon-22 or Freon-12 to
storage Tank (1660/1330
kg/hr)
Filling Station For Filling Station for Filling Station for Filling Station for
Tuner 74kg Cylinder 50kg Cylinder 13.6 kg cylinder
139
Phosphorus India Ltd
Stage-1
MCAA Sulfer FeCl3 Chlorine
SO2 Gas
HCL
HCL Gas Scrubbing
DCAC Reaction + Distillation
BCT-70Hrs System
30%HCL
Na2SO3
8000lit/day
Chlorine
Na2SO3 Evaporation
Pyridine
Tanker loading
RVD
99%
Tanker loading
TCAC
140
Phosphorus India Ltd
Coarse Material
ZNP Tech(80%)
ZNP
141
Phosphorus India Ltd
142
Phosphorus India Ltd
DEMAND AMANGEMENT
Creation Planned Ind. Requirement
using MD61
Planned Order
` Check Availability
Components Capacity
Order
Settlement
Production Order
Goods Movement
Order Release Confirmation To FG Store
CO15/CO11N
143
Phosphorus India Ltd
Process Flow
1. Sales and Distribution take requirements as concrete customer requirements from the market.
2. In Demand Management, sales are planned in advance via a sales forecast.
The result is the independent requirement, that is, the requirement for the finished product,
tradable assemblies, trading goods and replacement parts. This result triggers material
requirements planning.
3. In order to cover these requirements, MRP calculates procurement quantities and dates as
well as plans the corresponding procurement elements. The procurement element in the
planning run is the planned order or, for external procurement, the purchase requisition. Both
procurement elements are internal planning elements that can be changed, rescheduled or
deleted at any time.
4. If a material is produced in-house, the system also calculates the dependent requirements,
that is, the quantity of components required to produce the finished product or the assembly,
by exploding the BOM. If a material shortage exists, planned orders are created at every BOM
level to cover requirements.
5. The system then converts these planned procurement elements into exact procurement
elements: production orders for in-house production and purchase orders for external
procurement.
6. The progress of the order for materials produced in-house is controlled by using the
production order. The production order contains its own scheduling procedures, capacity
planning and status management. Cost accounting is also carried out via the individual
production order.
7. Materials that are procured externally trigger the purchasing procedure. In this case, you
must have chosen suitable vendors or you must have drawn up outline agreements.
8. The quantities made available by production or by external procurement are placed in stock
and are managed by Inventory Management.
Sales & Operations Planning (SOP) is a flexible forecasting and planning tool with which sales,
production, and other supply chain targets can be set on the basis of historical, existing, and estimated
future data. Rough-cut planning can also be carried out to determine the amounts of the capacities
and other resources required to meet these targets. SOP is particularly suitable for long- and medium-
term planning.
For planning purpose, the required sales plan can be gathered from various sources like Forecasting,
Sales Information Systems and Co-PA (Cost-Profitability analysis) or can be created manually.
Based on sales plan, the production plan is created and the requirements are then transferred to
demand management.
144
Phosphorus India Ltd
c) ISOP PLANT
The product group of the ISOP PLANT is identified as “ISOPROTURON” with 100%
production share.
INTEGRATION
Sales and Distribution (SD)
145
Phosphorus India Ltd
• Or, you may want both sales orders and stock orders in the demand program. If
the production time is relatively long in relation to the standard market delivery
time, you may want to produce the product or, at least, certain assemblies before
any sales orders exist. In this case, the sales quantities are preplanned (for
example, with the aid of the sales forecast).
Based on the Manufacturing scenario of respective Finish Products, following Planning Strategies are
listed for Finish product for PIL1 as well as PIL2. We will be looking for CPPP, ISOP, and FREP Plant
only.
FREP Plant
8 Freon-12 10 MTS REM
146
Phosphorus India Ltd
To-Be: To capture above problem and give systematic solution, in SAP R/3 system MRP gives solution
in following ways.
a) MRP CONTROLLER
b) PRODUCTION PLANNING AND PROCUREMENT PLANNING
c) CAPACTY PLANNING
What is MRP: The main function of material requirements planning is to guarantee material
availability, that is, it is used to procure or produce the requirement quantities on time both for internal
purposes and for sales and distribution.
This process involves the monitoring of stocks and, in particular, the automatic creation of procurement
proposals for purchasing and production.
In doing so, MRP tries to strike the best balance possible between
So, when MRP run is carried out using PD (normal planning) as MRP type, the PLANNED ORDERS
are generated according to the demand mgmt (Planned Independent requirements). The MRP
controller checks the scheduled dates of the planned orders and converts them into the production
orders.
Material requirements planning take current and future sales as its reference points. Depending on
planning strategy, actual requirements trigger the MRP calculation. In MRP the requirements include
sales orders, planned independent requirements, material reservations, the dependent requirements
created by exploding the BOM and so on.
In case of in-house production the system creates planned orders for planning of production quantities.
When planning is complete planned orders can be converted into production orders.
In case of external procurement the system creates either a planned order or directly creates a
purchase requisition or a schedule line for a pre-existing scheduling agreement for planning the
external purchase order quantity.
147
Phosphorus India Ltd
MRP Controller is the person responsible for a group of components in Material Requirement Planning
in a plant or company. Material that takes part in MRP must be assigned to a MRP controller. The field
for MRP Controller is located in the MRP 1 view of the Material Master.
The MRP controller is responsible for all activities, for specifying the type, quantity and time of the
requirements and he must also calculate when and for what quantity an order proposal has to be
created to cover these requirements. He needs all the information on stocks, stock reservation and
stock on order to calculate quantities and he needs all the information on lead times and procurement
times to calculate dates. The MRP controller determines a suitable MRP and lot-sizing procedure by
material to determine procurement proposals.
The most common lot-sizing procedures are available in the system and can easily integrate user-
defined formulas.
Naming Convention
For MRP controlling, it is proposed that there be one MRP controller in each section within the 3 plants.
The proposed codes to be used in SAP are as below:
Definition: The MRP controller is the person responsible for a group of materials in MRP in a plant or
company. A material that takes part in material requirement planning must be assigned to a MRP
Controller. Each of these areas will have a separate MRP controller. MRP to be run separately in the 3
areas independently.
Choose whether all materials are to be planned or only those with MRP relevant changes.
Planning run types are as fallows
148
Phosphorus India Ltd
• Creation indicator for procurement proposals for materials that are procured externally
Choose whether planned orders, purchase requisitions or schedule lines should be created for
materials that are procured externally.
• Creation indicator for MRP lists: Define whether MRP lists are to be created.
• Planning mode: Determine how the system is to deal with procurement proposals
(planned orders, purchase requisitions, scheduling agreement lines) from the last planning run,
which are not yet firmed, in the next planning run.
• Scheduling: Choose basic date calculation or lead time scheduling
• MRP list
• Stock/requirements list
• Planning result (corresponds to the MRP list with individual evaluation layout)
Planning situation (corresponds to the stock/requirements list with individual evaluation layout)
149
Phosphorus India Ltd
150
Phosphorus India Ltd
After the MRP run, the capacity requirements are created by the system. The load on the entire
bottleneck work centers can be seen in the system. The system will highlight the periods when
overload exists in each work center. In such a situation capacity needs to be leveled so that production
plan becomes final.
In capacity leveling, all the orders, which require that particular work center, will be dispatched to the
committed schedule one after other as per the priority. After leveling, the load on work center will be
evened out for the planning bucket. The revised scenario and schedule will be immediately reflected in
the evaluation.
If the capacity leveling is carried out to such an extent, that it has to be reflected in the schedule of the
dependent materials, then MRP run can be carried out again. At this time the planned orders, which
have undergone changes to schedule (firmed orders) will not be again changed by the system. The
dependent materials will be planned as per the revised schedule.
• Automatically
During the planning run, the system automatically determines the materials to be procured
with the required quantity and the required date.
After the planned order is created either manually or automatically a planned order profile
is allocated and data is processed. The data would include: material, plant, order quantity
and basic order dates. This will trigger the processing of material components, schedule
the planned order, edit account assignment and process the source of supply.
The system will check component and capacity availability and if needed, capacity leveling
can be carried out. Saving the planned order creates a purchase requisition, planned load,
creates dependent requirements and allows the processing of the planned order.
151
Phosphorus India Ltd
In case these requirements are produced in-house, the system creates planned orders that in
turn can be converted to Production orders before actual production execution. Alternatively, if
the requirements are procured externally, these requirements are directly converted into
Purchase requisitions. It would also be possible to convert the planned orders to purchase
requisitions.
NUMBER RANGES FOR PLANNED ORDERS
Phosphorus India Ltd: 1000 to 9999
Production orders are a fundamental part of Production Planning and Control. PP is fully
integrated in the Logistics component and has, among others, interfaces to
This function supports the production of goods in-house using the production order or work
152
Phosphorus India Ltd
1. Order creation
2. Order release
3. Inspection lot processing
4. Goods issues
5. Order confirmation
6. Goods receipt
7. Order settlement
¾ When a production order is created the following actions are carried out:
• A routing is selected, its operations and sequences are transferred to the order
• The bill of materials is exploded and the items in the bill of material are transferred to
the order
• Reservations are generated for bill of material items held in stock
• The planned costs for the order are generated
• The capacity requirements are generated for the work centers.
• Purchase requisitions are generated for non-stock items and externally-processed
operations.
Release of the production order is an important business function, which controls things like
the goods issue for the order, confirmation of the order progress etc. Here either individual
The production order release function is to be exercised in each production order, in the
transaction menu of the order header, after the creation of the production order. This function
sets the "released" status in the order header
After the creation of the production order, the individual operations or the order header itself
can be released as per the release date specified in the material master scheduling margin
key.
153
Phosphorus India Ltd
INTEGRATION
Production orders is fully integrated in the Logistics (LO) component and has, among
others, interfaces to
154
Phosphorus India Ltd
The quantity or partial quantity of a certain material or product that has been produced
according to the same recipe, and represents one homogenous, non- reproducible unit with
unique specifications.
• Legal requirements (for example, the guidelines set out by GMP-Good Manufacturing
Practice) or regulations on hazardous material.
• Defect tracing, callback activities, and regression requirement.
• The need for differentiated quantity-and value-based Inventory Management (for
example, due to heterogeneous yield/result qualities or varying constituents in
Production.
• Differences in usage and the monitoring thereof in materials planning in SD and
Production.
• Production or procedural requirements (for example, settlement of material quantities
on the basis of different batch specifications
This function used to assign a batch with a number that uniquely identifies it.
• Batch Specification
This function used to describe each batch uniquely using characteristics and characteristic
values. It specifies the permitted value range in the allocated material master record.
This function used to indicate whether a batch is usable or unusable. We can set this status
155
Phosphorus India Ltd
• Batch Determination
o With this function, we can use various criteria to search for batches that are in stock, for
example:-
o When posting goods issues
o When combining suitable material components for production orders and process orders
o When creating a delivery according to particular customer requirements
o The batch record contains all quality-relevant planned and actual data for the production of
a batch and complies with the GMP guidelines (Good Manufacturing Practices) for the
pharmaceutical industry and food industry.
o The batch where-used list shows the path of the batch from its procurement to its delivery
to your customer.
15.7 CLASSIFICATION
The classification system allows you to use characteristics to describe all types of objects and to group
similar objects in classes – to classify objects
Characteristics
Characteristics describe the properties of objects. The values of a characteristic specify these
properties.
When you create or change a characteristic, you can define the following settings:
• Format For example, numeric format is for figures, and character format is for alphanumeric
characters.
• Units of measure for numeric values
• Templates for entering values
• Required entries for a characteristic (required characteristics)
• Whether intervals are allowed as values
• Language-dependent descriptions and texts for characteristics and characteristic values
• Display options for characteristics on the value assignment screen
• Allowed values
• Default values that are set automatically on the value assignment screen
Class : Classes allow to group objects together according to criteria that is.
• Create classes for certain object types for example, material, workplace, equipment.
• Use the class type to determine which object types can be classified in a class.
156
Phosphorus India Ltd
• Assign characteristics to class. These describe the objects classify in class. When assign a
characteristic to a class, it can adapt (overwrite) the characteristic.
Class type: The class type is a central concept in the classification system. The class
type determines how classes are processed, and how objects can be classified and retrieved in
these classes. Class types for a specific object type, such as materials. Then use classes of
this class type to classify objects of this object type. First create a class, and then enter a class
type for the class. Each class type is a closed system. There is no link between the different
class types.
Purpose
This component can be used for production planning and control in a repetitive manufacturing
environment.
You can use repetitive manufacturing as either make-to-stock REM or make-to-order REM such as in
the automotive industry, for example.
• Creation and revision of production quantities on a period and quantity basis (reduction in
individual lot and order-specific processing).
• Reduction in the production control effort and simpler back flushing tools(with the option of
using the full scope of the PP functionality).
Implementation considerations
You can implement Repetitive Manufacturing if the following is true of your production process:
• You produce the same or similar products over a lengthy period of time.
• You do not manufacture in individually defined lots. Instead, a total quantity is produced over a
certain period at a certain rate per part-period.
• Your products always follow the same sequence through the machines and work centers in
production.
• Routings tend to be simple and do not vary much.
Integration
157
Phosphorus India Ltd
o PP Work Centers
o PP Routings
o PP Bills of Materials
o If required, Line Design for mapping complex production lines
Features
• Master data
There is specific master data required for Repetitive Manufacturing. This includes the repetitive
manufacturing profile and the product cost collector.
• Planning table
Within the framework of repetitive manufacturing, planning and control is carried out on the basis of
time buckets. Starting from the existing requirements situation, you can plan production quantities
based on periods. The scheduling data for products and product groups is thus broken down into a
series of time buckets, the user being presented with period views for the purposes of checking and
revision.
• Sequencing
You can use Sequencing to carry out takt-based scheduling which determines the sequence in which
planned orders are produced on the production line. Sequencing simplifies the dispatching process,
especially for high order volumes, and enables you to display them in a graphic.
• Pull list
You can use the pull list to control in-house material flow, supplying production with materials. The pull
list checks the stock situation at the production line, calculates the missing parts for the components
and triggers replenishment for these missing parts.
• Back flushing
Production completion confirmations are simplified and are made with reference to the material being
produced. The completion confirmation usually includes the backflushing of components and the
posting of production costs.
In repetitive manufacturing, you ususally detemine costs per material or per production version via a
product cost collector (product cost per period).
158
Phosphorus India Ltd
• The repetitive manufacturing profile is set in Customizing for repetitive manufacturing and is
entered in the material master record. You must also authorize the material for repetitive
manufacturing in the material master record.
• You create the production version in the material master record.
• If you want to plan using a planning ID , you must define one and enter it in the material master
record.
• If you want to use a production line for planning purposes, you must create one and enter it in
the material master record.
• If you use repetitive manufacturing in conjunction with the component PP line Design, you can
represent the production line as a line hierarchy. This makes sense if you have complex
production lines, which you want to schedule using takts.
• If you want to plan capacity, you must create a routing and enter it in the production version.
39. REPORTS
Following reports will be provided
The following standard reports are to be used in the Production Planning module:
159
Phosphorus India Ltd
160
Phosphorus India Ltd
MM60 Your company may have so many materials that you will not
always know whether a specific material already exists in the
material master. You can find this out with the help of the
materials list.
CM01 Cap. Planning Evaluation by Work Centers – Load
CM05 This report list displays all work centers and capacities with
overload in the next 60 calendar days.
CM21 This is a report of capacity leveling evaluation-work center
view
MCP3 Report for Production order analysis
T-CODE Description
MMBE STOCK OVERVIEW
CS01 CRT BOM
BOM CS02 CHANGE BOM
CS03 DISPLAY BOM
CA01 CRT ROUTING
ROUTING CA02 CHANGE ROUTING
CA03 DISPLAY ROUTING
WORK CR01 CRT WORK CENTER
CENTER CR02 CHANGE WORK ENTER
161
Phosphorus India Ltd
Plant
Company Code
Material
Date
162
Phosphorus India Ltd
Date
Stage Operation W.C. Work B.No. Raw Materials charged to reactor
Group Centers TCAC A C N CuCl NaOH DETC EDC Cat-1 Carbon
CPHT1 # 23
CPHT2 # 22
CPHT3 # 21
CPHT4 # 20
HTCP
CPHT CPHT5
Reaction # 19
CPHT6 # 18
CPHT7 # 17
Stage-1
CPHT8 # 16
CPDI1 # 15
CPN
CPDI
Distillation CPDI2 # 14
CPHY1 # 13
Hydrolysis CPHY
CPHY2 # 12
CPFI1 # 11
Filtration CPFIL
CPFI2 # 10
CPPR1 #9
Pressure CPPR2
CPPR #8
Reaction
CPPR3 #7
CPP CPRE1 #6
CPRE
Reaction CPRE2 #5
CPWA1 #4
Stage-2 Washing CPWA
CPWA2 #3
Low
vacuum CPLV CPLV
Drying #2
High
Vacuum CPHV CPLHV
drying #1
Total Qty in Kg A B C D E F G H
163
Phosphorus India Ltd
INPUT DATA
Plant Material Month
Production in kg X Date
OUTPUT DATA
Raw WIP Total of RM Receipt RM WIP Closin Consumpti
S Material Openi Openi opening Consumption Closin g Total on Norms
r ng ng stock in Tod Cumm. Tod Cumm. g in Kg Stock of S=M+N-O- . = S/X
. Stock Stock kg (M)= ay (N) in kg ay (O) in kg (P) in Kg Closin R
N (K) in kg K+L (Q) g
o (L) Stock
. Kg (R)
1 TCAC A
2 ACN B
3 CuCl C
4 NaOH D
5 DETC E
6 EDC F
7 Cat-1 G
8 Carbon H
OR
INPUT DATA
Date
OUTPUT DATA
Production in kg G
RM Receipt RM Consumption
Raw Closing
Opening Cumm. Consumption Con. Norms. =
Sr. Materi Today Cumm. (C) Stock in
Stock Receipt Today E=A+B-C-D
No. al
(A) in Kg (B) in kg
in kg Kg (D) E/X
1 TCAC
2 ACN
3 CuCl
4 NaOH
164
Phosphorus India Ltd
5 DETC
6 EDC
7 Cat-1
8 Carbon
7. Products, which have crossed 90% of the shelf life period, should
not be shown in stock list. Once the shelf life falls on 90%, it
should move into Blocked stock.
165
Phosphorus India Ltd
ANNEXURE I
Shift Sequence for PIL1
SHIFT SEQUENCE
BREAK DETAILS
ANNEXURE II
Work Center Formulae
The execution time of an operation is defined as the sum of the set-up time and the processing
time. This is expressed in the following formula.
F=SET+RUN*LOT/B
The meaning of the formula parameters and the origins of their values are given in the
table below.
Meaning Origin
B Base Quantity General Operation Value
LOT Lot Size General Operation Value
RUN Processing time for base Standard Value
Quantity
166
Phosphorus India Ltd
Plant CPP
1. HTCP Reaction
Work Work B.No. Staring End BCT ACN TCAC Temp. TCAC%
center center Qty. kg Qty. kg C
Group Date Time Date Time
CPHT1 #1
CPHT2 #2
CPHT3 #3
CPHT CPHT4 #4
CPHT5 #5
CPHT6 #6
CPHT7 #7
CPHT8 #8
2. CPN Distillation
CPDI CPDI1 #1
CPDI2 #2
167
Phosphorus India Ltd
3. Hydrolysis
Work Work B. No. Start End BCT Water qty. 48% Temp. C Alkali%
center center time Time kg NaOH
Group qty
CPHY1 #1
CPHY
#2
CPHY2
#3
CPHY3
4. Filtration
Work Work B. No. Start End BCT LOD % Temp. C Alkali% in NaTCP CFML
center center time Time CFML Qty. in Gen.
Group Kg
CPFI CPFI1 #1
CPFI2 #2
5. Pressure Reaction
B. Efflu
Work Work No. Start End BCT NaTCP Water 48% Pre Temp. T4C ent
center center time Time Charged qty. kg NaOH s C P% Gen
Group qty erati
on
in
Kg
CPPR1 #1
CPPR
CPPR2 #2
CPPR3 #3
6. CPP Reaction
Work
Work B. Start End EDC DETC in Temp.
center BCT NaTCP%
center No. time Time in Kg kg C
Group
CPRE CPRE1 #1
CPRE2 #2
168
Phosphorus India Ltd
7. CPP Washing
Work Work B. No. Start End BCT Water CPP Org. Effluent
center center time Time charged received in Generation
Group Kg Kg in Kg
CPWA1 #1
CPWA
CPWA2 #2
8. LV Distillation
CPLV #1
9. HV Distillation
CPHV #1
ISOPROTURON
1. Hydrogenation
Hydro
PN gen
Down Down
C Charg
Work Staring End BCT Temp. PNC% time if time
Work B.N Cha ed
center in C in Hrs Reasons
center o. rged Qty.
Group Hr
Qty. kg
Tim Dat Tim kg
Date
e e e
#1
ISHD ISHD1
#2
ISHD2
2. PCU Distillation
169
Phosphorus India Ltd
ISPD ISPD1 #1
3. DCU Formation
4. DCU Washing
ISWA ISWA1 #1
ISWA2 #2
5. De-Hydration
ISDE ISDE1 #1
ISDE2 #2
170
Phosphorus India Ltd
6. DMA Reaction
ISDM ISDM1 #1
ISDM2 #2
7. Crystallization
ISCR ISCR1 #1
ISCR2 #2
8. Centrifuging
ISCN ISCN1 #1
ISRV ISRV1 #1
171