LGOIMA Harriet Gale 21.2.2017 North Shore RTN
LGOIMA Harriet Gale 21.2.2017 North Shore RTN
LGOIMA Harriet Gale 21.2.2017 North Shore RTN
21 February 2017
Harriet Gale
fyi-request-5318-5e6f1302@requests.fyi.org.nz
Dear Harriet
Reference CAS-383791-H0N3S8
Thank you for your email dated 2 February requesting a copy of the Northern RTN Strategic case.
As requested, please find attached the North Shore RTN Strategic Case. This forms the foundation
document for future investigations into cross-harbour public transport planning. The material
contained in the Strategic Case will be updated and reconfirmed at each subsequent business case
phase, as growth, patronage and other key metrics change. Public engagement on emerging options
for future public transport in the North Shore is expected to occur in co-ordination with the New
Zealand Transport Agency’s upcoming Additional Waitemata Harbour Crossing project.
We trust the above information has addressed the matters raised however, should you believe that we
have not responded appropriately to your request, you have the right in accordance with section 27(3)
of the LGOIMA to make a complaint to the Office of the Ombudsman to seek an investigation and review
in regard to this matter.
If you have any further queries, please contact me on (09) 447 4404 during business hours, quoting
Local Government Official Information request number CAS-383791-H0N3S8.
Yours sincerely
Attachment:
North Shore RTN Strategic Case
aucklandtransport.govt.nz
North Shore Rapid Transit
Network Strategic Case
Auckland Transport - Strategy Division
September 2016
FINAL VERSION
Strategic Assessment of the need for an improved North Shore Rapid Transit Network
Approvals
PREPARED BY: REVIEWED BY: ENDORSED BY: APPROVED BY:
PREFACE
In early 2016, Auckland Transport commissioned the North Shore Rapid Transit Network (RTN) study.
This work was initially designed to be a “pre-scoping” study, to inform Auckland Transport’s
involvement in the NZ Transport Agency’s Additional Waitematā Harbour Crossing route protection
planning, regarding future public transport/RTN requirements.
The study was based around understanding the scale of the public transport (PT) problem (a
strategic assessment of cross-harbour PT demand), timing for any interventions, mode and
alignment options and how the RTN might integrate with other projects.
The outcomes of the North Shore RTN Study inform this Strategic Case, as well as contributing to a
Programme Business Case to investigate future improvement to the North Shore RTN.
North Shore Rapid Transit Network Strategic Case
EXECUTIVE SUMMARY
This document outlines the strategic case for investigating improvements to the North Shore Rapid
Transit Network (RTN). The Northern Busway is the core of the current North Shore RTN 1.
Existing access for both buses and general traffic between the city centre and the North Shore is via
State Highway 1, on the Auckland Harbour Bridge (AHB). Growth in travel demand is expected to put
pressure on the AHB infrastructure as well as on city centre transport infrastructure.
Auckland Transport (AT) is planning a range of transport improvements to the city centre network.
However, it is anticipated that improvements to the public transport network will have limitations in
respect to bus capacity and characteristics and do not provide a long-term RTN solution.
Separately, the NZ Transport Agency (NZTA) is planning for an Additional Waitematā Harbour
Crossing (AWHC) to relieve some pressure on the AHB and to provide better state highway network
resilience.
The need to plan for future investment in improvement to the North Shore RTN is pressing. Imminent
land use growth (both on the North Shore 2 and regionally) means that AT needs to investigate future
improvements to the North Shore RTN now, to understand how these fit with planning for an AWHC
and the overall transport network.
As this strategic case outlines, there are several reasons for the immediate need to plan for
improvements to the existing North Shore RTN. For simplicity, this need is explained as two-fold:
(1) Anticipated development on the North Shore over the next 30 years and beyond is expected to
see significant increases in population and employment 3. During the same time, employment in
the city centre is expected to increase by 60 per cent, of which the North Shore represents nearly
a quarter of the total public transport demand into the city centre during the morning peak
period.
As growth occurs, land demand and values will increase. Development pressures will make land
within range of the state highway and public transport networks more sought-after, compounding
the need to plan and protect land needed for future improvements to the North Shore RTN.
Maintaining effective RTN access to the city centre and other employment/education centres
along this key corridor and within the North Shore is crucial to maintain and enhance
Auckland’s economy and enable further economic and urban growth.
(2) The NZ Transport Agency is currently planning for route protection for an AWHC, which offers an
opportunity to enable North Shore RTN. Conversely an inappropriately scoped AWHC could
inhibit the ability to deliver necessary improvements to the North Shore RTN. AT needs to
therefore continue to work with the NZ Transport Agency to define the future transport network
requirements and to protect for future improvements to North Shore RTN as part of an integrated
approach to an AWHC.
Integrated planning for the North Shore RTN and an AWHC is crucial to achieving cost-
effective regional road and public transport outcomes.
1
See Figure 1.
2
See Section 7.3, Figure 9.
3
See Appendix 4.
North Shore Rapid Transit Network Strategic Case
This strategic case and subsequent business case work will follow the guidance of the Auckland
Transport Alignment Project (ATAP) process, which is a joint project including Auckland Transport,
Auckland Council, the NZ Transport Agency, Ministry of Transport, the Treasury and the State
Services Commission. ATAP highlighted that the AHB has limits on its ability to cater for heavy traffic
growth, but that the very high opportunity costs of a new harbour crossing require significant
consideration before investment. ATAP also recommended that route protection for a new crossing
needs to progress in a way that integrates further roading and public transport requirements 4.
4
ATAP references are included in Appendix 5.
THE STRATEGIC CASE
1. INTRODUCTION
1.1 Purpose
This strategic case outlines the case for continuing to investigate future improvements to the North
Shore Rapid Transit Network (RTN). It seeks confirmation of funding for co-investment in a
Programme Business Case to develop a preferred programme for further investigation.
Auckland’s North Shore is currently home to around 23 per cent of the region’s population 5, with a
corresponding 23 per cent of the region’s morning peak period trips into the city centre by public
transport 6. The existing North Shore RTN, the Northern Busway, is shown in Figure 1.
Albany
Albany Station
Metro
Centre
Constellation
Station
Sunnynook
Station
SH18 SH1
Takapuna
Smales Farm Metro
Station Centre
Akoranga
Station
AHB/SH1
5
Including Rodney and Hibiscus Coast, Statistics NZ, Census 2013
6
2013 ART3 run using 2013 Census land use data
Auckland is growing at an unprecedented rate. Growth in the Auckland over the next 30 years is
expected to be more than the total population of the Canterbury region 9. Anticipated development on
the North Shore over the next 30 years is expected to see a 30 per cent increase in population
(approximately 100,000 additional people) and a 16 per cent increase in employment (approximately
40,000 more jobs) 10. During the same time, employment in the city centre is expected to increase by
60 per cent 11. While a substantial portion of future travel demands are expected to be within the
North Shore, nearly a quarter of regional public transport demand into the city centre during the
morning peak period is expected (southbound) across the Waitematā Harbour 12. There is a strong link
between transport access and land use development. This can be seen clearly in Auckland’s urban
development. Appendix 3 provides a summary of land use development on the North Shore, Figure
3.1 shows temporal land development patterns.
As growth occurs, land demand and values will increase, as has been shown in the Auckland housing
market in recent years. Development pressures will make land within range of the state highway and
RT networks more sought-after, expensive and intensely developed, compounding the need to plan
and protect land for improvements to the future North Shore RTN.
Recent decisions on the Auckland Unitary Plan have set out a clearer basis of land use expectations
and Auckland Transport will need to continue to work with Auckland Council to determine the best
transport network to support the newly confirmed land use zonings, as well understanding the way
land use development and staging can support the transport network.
An initial analysis of the ongoing performance of the Northern Busway into the future shows that at
some point in the foreseeable future (potentially during the mid 2030’s depending on growth
projections), peak demand is expected to overtake the practical capacity of the busway, even taking
into account planned improvements. Some form of higher-capacity solution is therefore likely to be
required for future North Shore RTN.
Maintaining effective RTN access to the city centre and other employment/education centres
along this key corridor and within the North Shore is crucial to maintain Auckland’s economy
and enabling further economic and urban growth.
The NZ Transport Agency is currently planning for route protection (designation) of an Additional
Waitematā Harbour Crossing (AWHC). The Notice of Requirement is expected to be notified in 2017.
In parallel, planning, design and procurement for the AWHC as a physical project (as opposed to the
route protection exercise) will continue. Given the overlapping corridors and potential interaction
between travel demand drivers, an AWHC offers the opportunity to enable future improvements to
North Shore RTN, or conversely an inappropriately scoped AWHC could inhibit the ability to deliver
necessary improvements to the North Shore RTN. AT needs to therefore continue to work with NZTA
to define the future transport network requirements and to protect for future improvements to North
Shore RTN as part of an integrated approach to an AWHC.
8
Northern Busway southbound AM peak patronage = 6,569, other southbound North Shore buses = 3,234, mid-March 2016
vs Britomart AM peak alightings = 9,162, average March 2016.
9
See Appendix 4, Figure 4.1.
10
See Appendix 4, Figure 4.2.
11
See Appendix 4, Figure 4.3.
12
See Appendix 4, Figure 4.4 and Section 3.4.1, Figures 3, 4 & 5.
- “A land transport system that addresses current and future demand for access to economic
and social opportunities”
- “A land transport system that provides appropriate transport choices.”
NZTA Highways and Network Operations (HNO) manage the state highway network and motorway
corridors. NZTA Planning & Investment (P&I) provide funding to co-invest in transport projects and
programmes undertaken by Auckland Transport, Auckland Council and HNO.
The NZ Transport Agency’s role is as custodian of the existing AHB and planning route protection for
an AWHC, which could enable future access for the North Shore RTN. The NZ Transport Agency is a
requiring authority for state highways and cycle ways, it does not have requiring authority status or
financial responsibility for rail and therefore cannot designate for rail.
Auckland Transport is the strategic transport planning authority for Auckland and has responsibility
for all non-state highway transport infrastructure. AT is responsible for giving effect to the Auckland
Plan. Planning and providing for public transport is a core responsibility. In respect of the North
Shore RTN, this includes the Northern Busway, any potential rail services and facilities and includes
arterial and local roads, other bus services and facilities, as well as walking and cycling. Departments
within AT will provide specific advice/feedback on the RTN development.
The Auckland Transport Alignment Project (ATAP) is a joint project including Auckland Transport,
Auckland Council, the NZ Transport Agency, Ministry of Transport, the Treasury and the State
Services Commission. ATAP recognises that Auckland has transport funding shortfalls and
investigates delivery mechanisms. Upcoming business case analysis of the current and future
improvements to North Shore RTN will follow the guidance of the ATAP process, which highlighted
that the AHB has limits on its ability to cater for heavy traffic growth, but that the very high
opportunity costs of a new harbour crossing require significant consideration before investment.
ATAP also recommended that route protection for a new crossing needs to progress in a way that
integrates further roading and public transport requirements. Figure 2 shows the process and
expected programme for AWHC and North Shore RTN planning. Note that in light of ATAP work
which suggests that an AWHC is not required as soon as the project had proposed; a hold has been
put on the planned Programme Review and Financial Review. The NOR will go ahead as planned but
further business case work related to the AWHC will not.
Auckland Council is the most significant of the key stakeholders, and provides direction for
integration between land use and transport development and investment. It is the statutory planning
authority for the Auckland region.
The Council is responsible for the Auckland Plan which provides strategic direction for developing
and managing the Auckland Region. The Auckland Plan outlines overall objectives and funds to
which Auckland Transport is to give effect. Council is also responsible for preparing the Unitary Plan,
which is a key mechanism for delivering the Auckland Plan.
Auckland Council has interests in both the significance of this project, in terms of the strategic and
regional role of an AWHC and the North Shore RTN, and from a statutory and consenting point of
view.
Transport interest groups Needs and aspirations of users of all transport modes
• Problem 1: Inability to effectively meet projected public transport demand to, from and within the
North Shore will constrain Auckland’s economic performance and inhibit urban growth.
• Problem 2: Unresolved public transport integration with the Additional Waitematā Harbour
Crossing (AWHC) will increase cost and risk of achieving regional road and public transport
outcomes.
Problem 1: Inability to effectively meet projected public transport demand to, from and within the
North Shore will constrain Auckland’s economic performance and inhibit urban growth.
Currently committed PT infrastructure and services to, from, and within the North Shore will be
unable to provide sufficient capacity and service quality to support planned residential and
employment growth. If left unaddressed, a lack of adequate PT capacity connecting planned North
Shore growth areas with key employment centres and with the regional public transport network will
inhibit planned urban growth. It will also negatively impact on economic performance by
constraining regional labour market accessibility.
Presently, during the morning peak period, the North Shore RTN (on the AHB) carries around 10,000
people, comparable to Britomart train alightings during the same morning peak period. The AHB is
the only viable cross-harbour road connection and a critical link for journeys to/from the City Centre
and the North Shore. Planning for the North Shore RTN will consider the benefits of improving PT
network resilience with and without an additional harbour crossing.
Forecast growth in population and employment on the North Shore (and Auckland more generally)
will drive future transport demands, including demand for PT. The Auckland Plan land use forecasts
developed in 2011/2012, and subsequently used as a basis for transport planning, recognise the
high expected level of growth. However, since then, three policy changes have affected expectations
for future PT demand growth and the distribution of demands within the network:
• The Auckland Unitary Plan will enable greater levels of urban intensification and greenfield
growth on the North Shore than previous district and regional plans. This will contribute to
accommodating expected population and employment growth, but it may also change the
spatial distribution of that growth.
• Auckland Transport is currently implementing the New Network, which is intended to deliver
greater region-wide PT accessibility by enabling transfers between frequent PT services and
better integration of the bus network and existing rapid transit network. In effect, while
services may still travel to the city centre, enabling connections allows passengers to access a
wider range of destinations by public transport.
• Since its development in 2008, demand on the Northern Busway has grown more rapidly than
forecast, in the context of overall growth in demand on the PT network. The Northern
Busway’s success in attracting patronage means that the expected date that it reaches
As a consequence of these policy developments, the forecast scale of PT demand on the Northern
Busway, the North Shore’s PT trunk route, is expected to exceed the capacity of currently planned
infrastructure and service by the mid-2030s at latest. There is already evidence of service quality and
capacity problems on portions of the Busway, particularly when it reaches the City Centre. Attempting
to meet future demand growth within the constraints of the existing infrastructure will result in
inefficient and costly public transport operations and poor customer experience, including extended
and unreliable travel times. Furthermore, capacity constraints and poor service quality on North Shore
PT will reduce the attractiveness of PT relative to private vehicle modes, increasing private vehicle
demand on congested corridors such as the Harbour Bridge and reducing the efficiency of the
region’s road network.
Unaddressed transport problems also create risks that economic and urban growth will be
constrained, or pushed to less optimal locations (e.g. other parts of the North Shore, other parts of
the Auckland region or beyond the region) that are less productive or less attractive for households
and businesses. Limited capacity or long/unreliable travel times on PT services to, from, and within
the North Shore will, over time, reduce households’ accessibility to the City Centre and Metropolitan
centres, which are expected to accommodate significant employment growth for office-based and
retail activities. 13
Reduced PT accessibility will have negative impacts on the region’s economic performance, at it will
reduce the potential for agglomeration economies arising from labour market pooling (i.e. businesses
being able to access a large pool of workers, including workers with specialised skills), supply-chain
efficiencies (i.e. better accessibility between businesses and their customers), and knowledge
spillovers (i.e. exchange of information between firms and workers). Given the scale of Auckland’s
economy, these negative economic impacts are of national significance.
Problem 2: Unresolved public transport integration with the Additional Waitematā Harbour Crossing
(AWHC) will increase cost and risk of achieving regional road and public transport outcomes.
The Northern Busway runs in parallel to the Northern Motorway before crossing the AHB (in mixed
traffic) and entering the City Centre on Fanshawe St (on-street bus lanes). As a result, the design of
the AWHC will have significant implications for the operation of the Busway and future options to
invest in upgrading PT capacity on this corridor. If planning for PT and road infrastructure solutions
for AWHC is not coordinated, it is likely to introduce a number of risks, including significant risks for
the level of public spending required to deliver infrastructure for both modes.
The AWHC project is on an accelerated programme for route protection. Investigations of the road
component of the AWHC are ahead of investigations into public transport requirements. There is a
risk that independent analyses of road and PT requirements will not deliver an integrated, best-value
outcome.
While existing PT arrangements on the North Shore are not expected to reach capacity until the mid-
2030s (although this timing needs to be investigated further), current planning on the AWHC offers
13
Office-based and retail activities are expected to account for a large share of Auckland’s future employment growth. These
activities primarily, although not exclusively, locate in centres, in contrast with industrial and warehousing activities which are
typically more dispersed.
In the absence of integration, there is a significant risk of negative outcomes around the cost and
deliverability of the future transport infrastructure, including:
• Increased capital costs arising from independently planned and delivered road and PT
infrastructure projects, e.g. due to higher costs to ‘retrofit’ a PT solution in the same corridor
after first constructing new road tunnels;
• Increased planning, consenting and design costs if infrastructure projects are pursued
independently;
• Inability to deliver the optimal PT solution due to difficulties securing a corridor or station
locations after road infrastructure is developed;
• Risk of over-building road or PT capacity if modes are planned for independently;
• Loss of opportunity to consider the potential for construction efficiencies (e.g. avoiding
“construction fatigue”, the opportunity for using a single tunnel for both road and public
transport);
• Poorer ongoing transport outcomes if options are pursued independently and result in a less
optimal multi-modal solution;
• Loss of future options for long-term improvements to Auckland’s public transport and road
network, e.g. by failing to future proof for a regional rapid transit network. 14
Coordinated and integrated planning of both long-term PT and road requirements for the Harbour
Crossing presents significant opportunities for both cost savings and improved transport outcomes.
Given the expected cost of the AWHC, any savings could be of a scale that is nationally significant.
There are likely to be synergies in providing road and public transport capacity upgrades
simultaneously, with high-quality public transport provision likely to moderate passenger demand on
the road crossing, reducing risks of poor regional-scale road transport outcomes (e.g. congestion and
unreliable travel times).
The ATAP work notes that “Projected growth in public transport demand appears likely to trigger the
need for a new crossing within the next 30 years… Because any new crossing will be tunnelled, there
is a significant opportunity cost arising from this investment. Fully understanding key drivers,
alternatives, cost and benefits will be crucial before any investment decisions are made… It makes
sense to protect the route for a new harbour crossing in a way that integrates potential future
roading and public transport requirements.”
In summary, the ATAP recommendation in respect of the AWHC is to “protect route for a new
crossing, but further analysis of drivers and timing, and better integration with public transport
options is needed before investment decisions are made.”
14
For an overview of the importance of preserving future investment options in transport networks, see Grimes, A. 2011.
Building Bridges: Treating a New Transport Link as a Real Option. Motu Working Paper 11-12 and Ministry of Transport. 2016.
Adaptive Investment Management: Using a real options approach in transport planning. Wellington: Ministry of Transport.
Benefit 3: A high-quality PT service benefits users and increases PT mode-share, improving the
efficiency of Auckland’s wider multi-modal transport network.
The reasons for identifying these potential benefits from successful investment to address the
problems include:
Providing sufficient passenger-carrying capacity on the North Shore’s public transport network,
including the North Shore RTN, will enable planned growth to occur, including employment growth in
North Shore’s Metropolitan Centres and the City Centre and residential growth in existing North
Shore urbanised areas, as well as regional access to greenfield development sites.
Without adequate public transport provision (including connector and feeder networks), the planned
level and location of growth is unlikely to be achievable. In particular, peak-period access between the
North Shore and the City Centre is likely to be constrained, limiting employment growth in the City
Centre and labour market accessibility for North Shore residents. Reduced labour market accessibility
is likely to make residential development on the North Shore less attractive.
Without sufficient capacity and quality on the North Shore PT system, the planned scale and spatial
distribution of residential and employment growth is unlikely to occur, and growth will instead be
pushed elsewhere in the region, elsewhere in the country or even overseas. This may include pushing
growth to locations that are less productive or less attractive to households and firms, e.g. due to
lower levels of accessibility to employment, other firms or amenities.
Planning for the North Shore RTN will consider the benefits of improving PT network resilience with
and without an additional harbour crossing.
An efficient and high-quality PT system for the North Shore can increase regional labour market
accessibility which can in turn benefit regional economic performance. By providing sufficient
passenger-moving capacity and fast and reliable peak-period travel, the PT system can increase the
potential job pool available to workers within a reasonable commute time, or, conversely, the labour
pool available to firms.
Improved accessibility to dense employment hubs, including the Auckland City Centre, can also have
productivity-enhancing agglomeration benefits. Improved transport accessibility can enable the
15
Labour market pooling is one of several mechanisms through which agglomeration economies arise. The others include
better supply-chain linkages and knowledge spillovers.
Upgrades to North Shore RTN capacity and quality will enable continued growth of the Auckland City
Centre as New Zealand’s most significant high-value employment hub and a key destination for
commuters from the North Shore. It will also support increased density and scale of employment in
North Shore Metropolitan Centres.
Providing sufficient PT capacity and a high quality of service on the North Shore will benefit existing
and new PT users through travel time savings, reliability improvements and other service quality
improvements. A high-quality service will also encourage increased PT mode share, reducing private
vehicle demands on congested corridors such as the Auckland Harbour Bridge and generating
regional-scale benefits for road network efficiency.
A low-quality PT service is unlikely to encourage high levels of use, with users choosing private
transport modes with accompanying impacts on road congestion and potentially higher financial
costs for users. An over-loaded PT system (e.g. bus service levels operating beyond the busway’s
functional capacity) will lead to delayed and unreliable journeys.
Providing PT capacity that matches demand will increase the operating efficiency of the PT network by
ensuring that over-capacity operations are avoided (and their accompanying costs of congested
operations including travel time delays, unreliability, crowding and poor customer experience).
There may be opportunities for RTN upgrades to reduce the average operating costs of public
transport provision through utilisation of modern vehicles and technologies.
Providing a long-term rapid transit solution for the North Shore at the same time as the planned
AWHC allows for cost efficiencies in combining infrastructure for both road and PT modes. Cost
efficiencies are possible at the planning, consenting, designing and construction stages of the
projects. Conversely, failing to pursue an integrated solution at the planning and design stage will
increase the cost and risk of successfully delivering on road and PT transport outcomes, e.g. by
increasing the cost to ‘retrofit’ a PT corridor across the harbour after a road corridor is developed, or
by constraining options for corridor alignment and station location.
An integrated road and PT crossing will result in better transport outcomes for the regional network.
For example, simultaneous provision of improved PT alongside an AWHC for road transport may
assist in managing road transport demand and reducing road congestion. An integrated solution is
more likely to reduce risks of closing out alignment options for either road or PT that could result in
sub-optimal solutions being constructed (e.g. PT infrastructure where station location is
compromised or incapable of efficiently serving key origins or destinations).
The investment is primarily targeted at improving ‘network performance and capability’ and ‘cost’
outcomes (from the five outcome classes identified by NZ Transport Agency planning and investment
guidance). Safety, environment and health outcomes may be co-benefits of successful investment, but
are not the primary focus.
Benefit 3: A high quality public • Public transport travel times to key destinations
transport service benefits users and improve
increases public transport mode share, • Public transport travel time variability reduces
improving the efficiency of Auckland’s • PT is an attractive option that can capture higher
multimodal transport network. mode share on key corridors
Benefit 4: North Shore public transport • Public transport operating costs per passenger/km
services operate efficiently and cost- reduce over time due to a combination of increased
effectively. demand and more efficient operation of vehicles.
ATAP notes the following relevant points: ATAP includes good strategic
“…The assumed pattern of employment growth evidence for land use and
(which has been peer-reviewed) includes a very transport relationships, likely
strong focus of growth in the Central Area and a growth patterns and transport
limited number of other major centres. demand. This is reflected in
the ART modelling, the context
Projected growth in public transport demand of which is explained in Section
appears likely to trigger the need for a new 3.4.1 below. An updated land
crossing within the next 30 years. There is use scenario will also be
potential for a shared road/PT crossing but the required to better-understand
Problem 1: costs and benefits of different options require the likely impacts of the
Inability to further analysis. growth enabled by the Unitary
effectively Plan. However, this will not be
meet An early investment focus on route protection and available until after the PBC
projected land acquisition is required to ensure investment stage.
public is able to proceed when required and in a cost-
transport effective way. Route protection helps avoid Good evidence that the
demand to, incompatible development and reduces the cost of functional capacity of the
from and land purchase for key projects.” existing Northern Busway will
within the be insufficient to cater to
North Shore Analysis included in the recent study: North Shore forecast PT demands.
will RTN: Transport and land use deficiency and
constrain opportunity analysis (Aurecon and MRCagney for Reasonably good evidence
Auckland’s Auckland Transport, 2016) provides evidence that supporting PT demand
economic passenger transport demand accompanying forecasts. However, the
performance planned growth in the North Shore and City Centre demand forecasts use various
and inhibit is likely to exceed the functional capacity of the assumptions about land use
urban Northern Busway by the mid-2030s. forecasts and travel behaviour
growth. for which there are inherent
This study also provides evidence that public uncertainties.
transport demands exceeding capacity are likely
to result in poor transport outcomes for both Good evidence establishing the
passengers and operators, including travel time functional passenger-carrying
delay and unreliability. capacity of the North Shore
Busway across its length and
Evidence that poor passenger transport outcomes for evaluation years of 2016,
for the links between the City Centre and 2026, 2036 and 2046.
Metropolitan Centres will result in negative
economic impacts includes research on wider Indicative evidence on the
Because any new crossing will be tunnelled, there Evidence for this problem is
is a significant opportunity cost arising from this generally more limited than for
investment. Fully understanding key drivers, Problem 1, reflecting the fact
alternatives, cost and benefits will be crucial that a certain level of detailed
Problem 2:
before any investment decisions are made. design work and scheme
Unresolved
investigation is required to
public
It makes sense to protect the route for a new identify how alternative staging
transport
harbour crossing in a way that integrates potential and design may affect project
integration
future roading and public transport requirements.” costs and deliverability.
with the
AWHC will
Analysis in this Strategic Case identifies some Some of this evidence is likely
increase the
specific ways in which this problem may lead to to be available from
cost and risk
costs and risks for achieving regional transport engineering feasibility and
of achieving
outcomes. This includes: costing studies. For instance,
regional
costings for combined road
road and
• Increased costs to ‘retrofit’ PT solutions around and PT tunnels versus separate
public
previously developed road infrastructure; tunnels, or costings for
transport
• Increased costs in planning, design, and different tunnel alignments
outcomes.
consenting; and portals could be used to
• Physical constraints on delivering optimal PT provide evidence for the cost
corridors and stations; savings associated with a
• Risk of ‘over-building’ road or PT infrastructure combined solution.
due to a lack of coordination when investing;
• Worse overall transport outcomes due to a lack This is acknowledged as an
of complementarity between road and PT area in which further evidence
solutions; is needed. It is recommended
that further analysis is
• Loss of future options for investing in long-
undertaken to identify the
term transport networks to enable urban and
specific constraints, costs, and
economic growth.
risks that may arise in each
area.
The recent study, North Shore RTN: Transport and land use deficiency and opportunity analysis
(Aurecon and MRCagney for Auckland Transport, 2016) provides forecasts of passenger transport
demand accompanying planned growth on the North Shore and in the City Centre.
The demand forecasts are from the Auckland Regional Transport (ART) Model and are based on the
following key inputs:
• A fixed land use scenario (I9 scenario based on the Auckland Plan ‘medium growth’ projections)
consisting of forecasts for future levels and location of employment and population.
• A scenario for future transport infrastructure and services, including pricing. The transport
investment scenario used was the Auckland Transport Alignment Project (ATAP) ‘Common
Elements’ scenario.
Based on these inputs, the ART model simulates transport demands between model zones, assigns
these demands to routes and modes, and simulates travel times and costs. Key outputs from the
central ART demand forecasts developed for the North Shore RTN study are summarised in the
following paragraphs.
Figure 3 compares AM peak travel demands from the North Shore study area to the City Centre +
Fringe + Newmarket and from the Study area to the two North Shore metropolitan centres, Albany
and Takapuna. Total passenger demand to the three centres increases by approximately 50 per cent
between 2013 and 2046. Demand for travel from the North Shore to Takapuna is similar to that for
the North Shore to City Centre + Fringe + Newmarket zone, while demand to Albany is about two-
thirds of demand to each of the other centres.
60,000
50,000
Transport demand
40,000
30,000
20,000
10,000
0
2013 2026 2036 2046
Figure 3: Forecast AM peak (7am-9am) travel demand from the North Shore to selected
Metropolitan Centres (ART model ATAP base case).
Figure 4 below provides mode share forecasts for peak-period North Shore trips across the Waitematā
Harbour. This provides an indication of the scale of the public transport task across the Harbour
which increases to around 20,000 passenger trips during the peak 2 hours by 2046. At present,
around one third of all trips on the Waitematā Harbour crossing are public transport trips. By the mid-
2030s public transport demand exceeds general traffic and by the mid-2040s public transport is
forecast to be the dominant mode on the Waitematā Harbour crossing.
The ATAP work also observes this travel demand noting that projected growth in public transport
demand appears likely to trigger the need for a new crossing within the next 30 years.
40,000
35,000
30,000
25,000
20,000 PT journeys
Non-PT journeys
15,000
10,000
5,000
0
2013 2026 2036 2046
Figure 4: Forecast AM peak PT and private vehicle travel demand across the Auckland Harbour
Bridge.
The maps illustrate that the major destination for intra-regional PT demand growth from the North
Shore is to the City Centre zone, and PT demands to other parts of the region are limited. The two
maps also highlight that the bulk of growth in intra-regional passenger transport demand is likely to
use PT rather than private vehicles. This is due in part to road capacity constraints on the Harbour
Bridge, but it is also be affected by factors such as increased reliability of PT travel times at peak
times due to the Northern Busway and increases in the price to park in the city centre. 16 On the basis
of the information available, the ART forecasts are considered accurate and relevant for defining the
strategic ‘task’ for public transport.
Figure 5: Forecast change in AM peak PT and private vehicle travel demand for trips from the
North Shore to zones outside the North Shore.
16
Parking prices can have a strong impact on mode share, as they make up a large share of the overall cost of travel for city
centre-bound private vehicle trips. For instance, the daily rate to park at AT’s Downtown Carpark is currently $24, which is
equivalent to over an hour of travel time based on NZTA’s EEM parameter for average value of travel time on urban arterial
roads during the AM peak ($21.79/hour in 2015 NZD; calculated from Tables A4.3 and A12.2).
While the three-year extrapolation is considered too short to inform a view on a 30 year forecast and
is shown for context, the ten-year extrapolation is a more valid picture of underlying trends. By
2046, the ten-year linear extrapolation is 13 per cent higher than the ART model outputs, which
equates to bringing forward growth or the timing of a required change by about 5 years. Thus, while
it is not expected that travel demands will grow linearly for the next three decades and may be
influenced by a range of factors, the ART model forecast appears to fall at the lower end of likely
demand growth rates.
Figure 6: Comparison of public transport patronage across the Auckland Harbour Bridge from
ART model outputs (I9 scenario), APT model outputs (CRL scenario), and actual
screenline counts.
Conversely, there is a possibility that ART forecasts may overestimate future PT mode share. The ART
model ATAP Common Elements scenario used for future growth and demand analysis does not
include the AWHC, and additional capacity for private vehicle travel across the harbour may reduce
future PT mode share relative to the ART model forecasts.
On balance however, historical patronage growth trends suggest there is a greater risk that ART
forecasts underestimate rather than overestimate future public transport demands. The upside risk
Lastly, we note that land use forecasts underpin transport demand forecasts. Figure 7 below
illustrates ART model inputs for projected changes in population and employment density on the
North Shore. Residential development and accompanying population growth is forecast to be
concentrated in the Metropolitan Centres, Albany and Takapuna, in Birkenhead and Long Bay within
the currently urbanised area and at Silverdale in greenfield development areas. Employment growth is
forecast to be concentrated in the City Centre (contributing to cross-harbour transport demands),
Takapuna, Wairau Valley, Westgate and Orewa.
Figure 7: Forecast change in population and employment density 2013 – 2046 (ART model
inputs)
Caveats to modelling
As with any demand forecasts, there are uncertainties about the modelling inputs and changes to
these inputs may significantly change the demand forecast. For example, key uncertainties include:
• The land use forecast. Recent increases in plan-enabled development capacity introduced with
the latest changes to the Auckland Unitary Plan may mean the land use forecast is under-
predicting the scale and/or location of land use change and consequently the level of PT
• Use of a fixed land use forecast. A core assumption underpinning the demand forecast is that
land use is ‘fixed’, or held constant regardless of which transport investments are made. This
assumption is not necessarily realistic, as there is a two-way interaction between transport
infrastructure investment and land use change. For example, North Shore RTN investment may
increase the relative accessibility of North Shore locations and hence its attractiveness,
accelerating land use change and development. Future stages of the business case process will
need to consider how North Shore RTN can shape and enable land use and development, rather
than simply responding to a fixed land use forecasts and associated level of demand.
• Attractiveness of PT modes relative to other modes. There are uncertainties about ART
modelling processes and the modelled attractiveness of PT relative to other modes. For example,
recent PT patronage growth rates exceed modelled growth rates. This may mean that ART
modelling is under-estimating future PT demand growth.
• Impact of the AWHC road crossing on PT demand. The future transport infrastructure scenario
used for modelling demand excludes the Additional Waitematā Harbour Crossing (AWHC) and as a
result the PT demands produced by the ART model may be influenced by the constraints on the
road network.
The recent study, North Shore RTN: Transport and land use deficiency and opportunity analysis
(Aurecon and MRCagney for Auckland Transport, 2016) provides evidence that forecast passenger
transport demand is likely to exceed the functional capacity of the Northern Busway by the 2030s.
This is a problem of regional and national significance due to the importance of the North Shore RTN
in providing passenger transport connections between a major urban residential area (the North
Shore) and New Zealand’s most significant employment hub (the City Centre, currently the location of
over 150,000 jobs, or 23 per cent of Auckland’s total jobs).
Key evidence for PT demand exceeding the functional capacity of the existing Northern Busway is
provided by the North Shore RTN study that compares infrastructure capacity with forecast bus
volumes required to meet modelled growth in PT demand in four evaluation years: 2016, 2026, 2036
and 2046. It finds that:
• Current peak-period bus volumes exceed functional capacity already in 2016 at the City
Centre end of the busway and at Constellation Station.
• Capacity problems are somewhat reduced by 2026 due to implementation of bus
infrastructure improvements in the City Centre. However, Albany Station experiences capacity
problems.
• By 2036 operating bus volumes that are sufficient to cater to forecast demand mean
significant over-capacity operations in the City Centre and at Albany, Constellation and
Akoranga Stations.
• By 2046 capacity problems exist at all major North Shore Stations and in the City Centre.
17
The Independent Hearings Panel’s recently-released report on the Auckland Unitary Plan recommended zoning provisions
that enable greater residential development throughout the existing urban areas on the North Shore, but particularly around
Takapuna and Albany centres. This is likely to support achieving the ART population projections. The Panel also recommended
zoning a significant amount of greenfield land for future growth in the Silverdale area.
Evidence on transport performance impacts from demand exceeding functional capacity and
from inadequacies in Northern Busway infrastructure
The recent study, North Shore RTN: Transport and land use deficiency and opportunity analysis
(Aurecon and MRCagney for Auckland Transport, 2016) provides an assessment of the forecast
performance of the existing Northern Busway in relation to transport indicators including travel speed
and reliability for the four evaluation years: 2016, 2026, 2036 and 2046.
The status of the evidence is somewhat limited, and forecast impacts are confined to qualitative
assessment based on comparisons of PT demand with the functional capacity of the busway stops
and corridors. Later stages of the business case will need to further investigate and quantify travel
time and travel time variability performance under a ‘base case’ Northern RTN infrastructure scenario.
The findings from the North Shore RTN (2016) assessment are organised by the following main
components of the existing North Shore RTN:
• Busway
• Harbour Crossing
• City Centre
• limited capacity, slow travel speeds and variable travel times for the missing segment of busway
between Constellation and Albany.
• inadequate size and capacity of Constellation Station to accommodate a large volume of bus
services and passenger demand.
However, by 2026, the joint AT/ NZTA Northern Corridor Improvements (NCI) project is anticipated to
have completed the missing section of the busway, constructed a new Rosedale Busway station and
provided and additional platform to Constellation Station, therefore improving these deficiencies.
Nevertheless, by 2026, increased patronage on the busway and busway stations is likely to manifest
in over capacity conditions and poor operational performance at Albany Station due to large volumes
of commencing services in the AM peak which use up a lot of station capacity. Sunnynook Station
which has the shortest platforms of all the busway stations will also be experiencing over capacity
conditions affecting dwell times. Akoranga Station is also starting to experience congestion by this
time.
By 2036, performance has degraded further at the above stations, whilst Constellation and Smales
Farm are now also expected to experience over capacity conditions affecting operational performance
(i.e. dwell times).
By 2046 all of the busway stations are expected to be at or near capacity suffering from increased
dwell times and greater dwell time variability affecting operational performance.
Harbour Crossing: The assessment of 2016 conditions finds quality, capacity and performance
issues associated with the northbound link from Victoria Park (Fanshawe Street) to Akoranga Station
via SH1 Northern Motorway including the Auckland Harbour Bridge. This is due to a range of factors
including limited bus priority on the motorway itself or on the Esmonde Road off ramp. In the
The Additional Waitematā Harbour Crossing (AWHC) project is currently undergoing further design
development ahead of route protection and as such the proposed level of bus priority as part of this
project is not yet know. However, the previous plans (2010) proposed dedicated bus lanes on the AHB
itself as well as a bus only bridge linking the northbound ‘kerbside’ bus lane to the two-way busway
on the eastern side of the motorway south of Esmonde Road. These are expected to improve travel
time and reliability performance on this section of the North Shore RTN from 2026.
City Centre: The city centre extension of the busway from Victoria Park to Britomart and Learning
Quarter has been shown to be the weakest link in the North Shore RTN for every assessment period.
In the 2016 assessment year, significant issues are evident with the operational performance of all
City Centre sections of this RTN extension. However, by 2026, a significant improvement in city
centre bus infrastructure has been assumed. These interventions, while still conceptual in nature and
subject to funding commitments, could improve operational performance. However, these upgraded
bus priority corridors and new termini are still constrained by signals at intersections. As such even in
2026, soon after implementation the city centre infrastructure is likely to only just provide sufficient
capacity to meet demands.
By 2036, all City Centre corridors and termini are likely to be under sustained pressure in peak times
at between 102-108 per cent of capacity. This is likely to lead to degraded performance, with dwell
times becoming more variable, increased bunching of buses and accumulation of passengers at stops
congesting footways. It is in by this time period that the performance of the busway is likely to no
longer be to an acceptable RTN standard.
By 2046, virtually all parts of the City Centre used by buses would be operating at over 110 per cent
of theoretical capacity, and with highly degraded and unacceptable levels of performance (slow and
highly variable travel times).
Evidence on wider economic impacts of poor transport performance on the North Shore RTN
There is some evidence that future poor passenger transport outcomes on the North Shore RTN will
have negative economic impacts. Evidence for the ‘wider economic benefits’ of improved North Shore
RTN will need to developed further as part of later stages of the business case process, potentially
including some degree of quantification in the Economic Case.
Economic theory and evidence suggests that improved transport accessibility, including PT
accessibility, can lead to economic benefits over and above the benefits to transport users. This
includes higher economic productivity as a result of increased agglomeration economies. This
suggests that North Shore RTN investment that can overcome accessibility or transport capacity
constraints to the Auckland City Centre may have regionally and nationally significant benefits for
economic growth and productivity.
• Agglomeration economies, i.e. the economic benefits associated with increased scale and
density of economic activity;
• Imperfect competition benefits, i.e. the additional savings from reductions in the cost of
business travel in imperfectly competitive markets;
• Labour supply benefits, i.e. the impact of reduced commuting costs on labour market
participation and hence income tax collections; and
• Job relocation impacts, i.e. the wage and productivity increases arising when major transport
improvements allow people to move to higher-productivity locations.
Kernohan and Rognlien’s findings were subsequently incorporated into recent updates to the NZTA’s
Economic Evaluation Manual, and their proposed methodologies for quantifying these benefits have
been applied in a number of projects.
Agglomeration economies tend to account for the majority of wider economic impacts of major
transport projects. These arise from fixed costs in production or increasing returns to scale at the
firm level (Fujita, Krugman and Venables, 2001) or knowledge spillovers or improved potential for
specialisation between firms and workers (Glaeser, 2008). This enables businesses located in larger
or denser areas to be more productive. Following Alfred Marshall, there are three main “micro-
foundations” for agglomeration:
• Geographically concentrated industries can support a wider and more specialised range of
local providers of inputs and better supply-chain linkages
• Increased accessibility between firms and workers can support labour market pooling, which
increases productivity by better matching workers to jobs and enabling firms to better adjust
their labour input in response to demand shocks
• Geographic proximity facilitates knowledge spill-overs between firms and between workers.
A number of empirical studies have confirmed a relationship between locations’ ‘effective density’, or
their accessibility to a larger number of other firms or workers, and higher productivity levels. There
is evidence of bidirectional causality at work – i.e. higher density/accessibility leads to higher
productivity, and vice versa (Graham et al, 2010). In New Zealand, Maré and Graham (2009) have
studied agglomeration economies in different industries, finding a positive (causal) relationship
between the effective density of employment and productivity. This relationship tends to be strongest
in service sectors that tend to locate in major centres, including financial services, professional
services, and retail trade.
Maré (2008) provides further evidence on the “Auckland productivity premium”. As shown in Table 4,
the Auckland urban area is 29 per cent more productive than the rest of New Zealand even after
adjusting for industry composition. He finds an even higher productivity premium of 72 per cent in
the Auckland City Centre, which is the city’s most accessible and dense employment centre. The
North Shore as a whole also enjoys a productivity premium relative to the rest of the country, albeit
not as large a premium.
18
Kernohan, D. and Rognlien, L. 2011. Wider economic impacts of transport investments in New Zealand. NZTA Research
Report 448.
If observed relationships between transport accessibility, effective density, and productivity continue
to hold true, then it is reasonable to expect reductions in the performance of North Shore PT will
reduce agglomeration economies in Auckland. Longer or less reliable commuting for some North
Shore residents and constraints to peak-period capacity of the overall passenger transport system
(both road and public transport) will constrain the growth of employment and limit labour market
pooling.
However, further analysis, potentially including modelling of the agglomeration benefits of alternative
transport and land use arrangements using procedures set out in the NZTA’s Economic Evaluation
Manual, is likely to be useful in establishing the degree to which constraints on PT capacity and
reliability will affect economic outcomes. This is likely to be a focus for economic cases, particularly
at the Indicative Business Case level.
Further work is needed to provide specific quantitative evidence around problem 2. This should
include, but is not necessarily limited to:
• A review of the available engineering feasibility and costing studies to identify costs for
different project components or alternative designs, and identify cases where non-integrated
designs may physically constrain options for corridor or station development;
• A review of costs associated with planning, investigation, and consenting, e.g. to obtain
multiple Notices of Requirement for separate projects on the same corridor;
• A review of the link between road and PT outcomes, particularly focused on the relationship
between provision of PT services or rapid transit corridors and road congestion; 19 and
• A more in-depth discussion of the value of preserving future investment opportunities, e.g. to
enable the longer-term development of the city’s rapid transit and road networks to enable
economic and urban growth.
19
There are a number of empirical studies of the impact of disruptions to PT networks on road congestion. These generally
find that unmet public transport demand worsens congestion. See e.g. Ministry of Transport (2014), The transport impacts of
the 20 June 2013 storm in Wellington; Adler and van Ommeren (2015), Does Public Transport Reduce Car Travel Externalities?
• A land transport system that addresses current and future demand for access to economic
and social opportunities
• A land transport system that provides appropriate transport choices
• A land transport system that is resilient
• A land transport system that delivers the right infrastructure and services to the right level at
the best cost
Given the uncertainties associated with timeframes in staging and delivering future improvements to
RTN and the likelihood of North Shore RTN requiring very significant investment, the Government is
likely to be involved in future stages.
The Auckland Council, through the Auckland Plan, has a vision to “make Auckland the world’s most
liveable city”. Further explanation of the Plan’s view to achieving this through delivering transport
outcomes are included below in section 4.1.
The Auckland Plan also refers to planning for an Additional Waitematā Harbour Crossing, see
Appendix 6. Of note are the recognition of long-term urban density possibilities, references to
further studies (which are yet to be done) and the recognition that any North Shore RTN rail solution
will require significant investment beyond that which can be delivered by traditional funding
methods, requiring new revenue tools.
Auckland Transport delivers on the Council’s transport outcomes via its Statement of Intent (SOI).
Further explanation of the 2015-2018 SOI is included in section 4.1 below.
The Auckland Transport Alignment Project (ATAP) is a joint project including Auckland Transport,
Auckland Council, the NZ Transport Agency, Ministry of Transport, the Treasury and the State
Services Commission. ATAP is underway to identify and agree on Auckland’s strategic transport
requirements. It acknowledges the significant travel demand pressures that Auckland faces. ATAP
recognises that route protection for a new Waitematā Harbour crossing needs to progress, as well as
integrating public transport and road and investigation into costs and benefits. Further to the ATAP
recommendations noted in section 3.4.2:
The existing Auckland Harbour Bridge has limits on its ability to cater for heavy traffic
growth, and increased private vehicle and public transport demand. A new crossing has very
high opportunity costs meaning it is very important to understand key drivers, alternatives,
costs and benefits before any investment decisions are made. Route protection for a new
crossing needs to progress in a way that integrates further roading and public transport
requirements.
The NZ Transport Agency notes that Connecting New Zealand and the National Infrastructure Plan
give policy direction to the GPS around improving transport network efficiency improving the use of
existing networks, and appropriately allocating new investment. These are fundamental to the NZ
Transport Agency’s investment principles, in particular the investment hierarchy and basis of the
NZTA Business Case Approach.
Auckland Council - Auckland Council is responsible for the Auckland Plan 2012, which guides
Auckland’s future over the next 30 years and is intended to tackle Auckland’s challenges, including
reducing transport and housing shortages. It outlines overall transport objectives, for Auckland
Transport to give effect to it.
NZ Transport Agency - The NZ Transport Agency is the Crown entity with responsibilities to invest in
land transport activities, manage the state highway network and provide access to and regulation for
land transport. The NZ Transport Agency’s primary function is to promote an affordable, integrated,
safe, responsive and sustainable land transport system.
Auckland Council
Auckland Council is responsible for the Auckland Plan 2012. The Auckland Plan’s strategic direction
for transport (Strategic Direction 13 – Auckland’s Transport) is:
“Auckland expects significant improvements in it’s transport system so that it works well for
business, residents and visitors and supports Auckland’s development and contributes to the health
and safety of it’s people and the character of it’s places.”
The Auckland Plan states that the vision of becoming the world’s most liveable city will not be
achieved by incremental change. It submits that transformational change is required and puts
forward six “Transformational Shifts”. Of particular relevance to the rapid transit network are:
- Move to outstanding public transport with one system - The congestion on Auckland’s
transport network will increase as the population grows. Unchecked, this will have a negative
impact on our economic performance and our quality of life. Addressing this congestion requires
a transformational shift towards far greater use of public transport and a stronger focus on
planning, developing, and operating the entire transport network as an integrated system.
- Radically improve the quality of urban living
- “Double public transport from 70 million trips in 2012 to 140 million trips by 2022”
- “Increase the proportion of trips made by public transport into the city centre during the morning
peak, from 47s of all vehicular trips in 2011 to 70% by 2040.”
- “Increase the proportion of people living within walking distance of frequent public transport from
14% (2011) to 32% by 2040.”
AT’s responsibility in relation to rapid transit planning and implementation is explained in two key
statutory documents:
1) Regional Land Transport Plan (RLTP) - this identifies AT’s approach to investment and lists all
future transport investments in the Auckland region over a ten year period, including local
roads, public transport services and infrastructure, maintenance and renewals, walking and
cycling and investment management activities as well as (NZTA) state highway activities.
2) Regional Passenger Transport Plan (RPTP) - which outlines AT’s approach to public transport
over a three year period. This includes policies that relate to fare box recovery and
concessions
The Auckland Transport Board has adopted the following set of strategic themes in it’s 2015-2018
Statement of Intent which relate to the Auckland Plan directions:
• Prioritise rapid, high frequency public transport
• Transform and elevate customer focus and experience
• Build network optimisation and resilience
• Ensure a sustainable funding model
• Implement accelerated, adaptive, innovative solutions
Though these are more easily applied to an operational situation than planning for a RTN, these
strategic themes are directly related to the transport benefits that a RTN delivers.
NZ Transport Agency
The NZ Transport Agency states its mandate on delivering on the National Land Transport Fund by
way of a 2015 Statement of Performance Expectations. The 2015 Statement of Performance
Expectations for the Transport Agency gives its overall function as Planning and Investing in the Land
Transport Network. Its Services and Investment are defined as:
• Investment management
• Public transport
• Road safety promotion
• Local road improvements
• Walking and cycling
It has two objectives that are particularly relevant to the North Shore RTN:
• Integrate land uses and transport networks to shape demand at national, regional and local
levels
• Integrate national and local transport networks to support strategic connections and travel
choice
The NZ Transport Agency’s planning programme for an AWHC is accelerated and ahead of Auckland
Transport’s RTN investigation planning. There is some risk that planning for an AWHC may be
established, ahead of determining the optimal outcome for integrated RTN and an AWHC.
Given the uncertainties associated with timeframes in staging and delivering future improvements to
RTN and the likelihood of North Shore RTN requiring very significant investment, funding for delivery
is not included in any strategic plan. As noted above, the Auckland Transport Alignment Project
recognises these transport funding shortfalls and is investigating delivery mechanisms.
The North Shore RTN provides around 23 per cent of the regional morning peak period PT trips into
the city centre. Aside from ferry, it provides the only viable PT access to the city centre. The North
Shore RTN is a core component of the regional rapid transit network and it is strategically important
to ensure RTN provision into the future.
Section 4 explains the context of the AWHC in terms of the Auckland Plan. Other considerations
include the fact that the North Shore RTN has potential to include access to the metropolitan centres
of Albany and Takapuna, the fact that it links people to the city centre and onwards across the
region.
The relevant expected long term results from the GPS objectives are:
• Support economic growth and productivity through the provision of better access to markets,
employment and business areas
• Support economic growth of regional New Zealand through provision of better access to
markets
• Provide appropriate travel choices, particularly for people with limited access to a private
vehicle
• Improved network resilience at the most critical points
• Delivery of the right infrastructure and services to the right level
• Improved returns from road maintenance
• Improved returns from public transport
Relevant investment performance measures for investigation into future improvements to North
Shore RTN are included in Section 3.3, Table 2.
The NZ Transport Agency is currently planning for route protection for an AWHC. An AWHC could
enable future improvements to North Shore RTN. Integrated planning for the North Shore RTN and
an AWHC is crucial to achieving cost-effective regional road and public transport outcomes.
Auckland Transport needs to continue to work with the NZ Transport Agency to understand future
transport network requirements and to protect for future improvements to North Shore RTN as part
of an integrated approach to an AWHC.
7. SCOPE
7.1 Purpose
The purpose of the Programme Business Case (PBC) for planning for future improvements to the
North Shore Rapid Transit Network is to investigate and develop a preferred programme of activities
for integration with the AWHC project, for further investigation as part of an Indicative Business Case,
which will best achieve the benefits and outcomes defined in this strategic case.
A Programme Business Case for future improvements to the North Shore RTN is currently being
scoped, using the existing evidence base, outlined in Section 3. The PBC is scheduled to be complete
by October/November 2016. This will then be considered along with future AWHC business case
processes to develop programmes to take forward for assessment.
Along with Figure 2 (which contains more detail), the diagram in Figure 8 explains how AT and the NZ
Transport Agency are working together through the Business Case Approach. It is anticipated that
once the North Shore RTN Programme Business Case is complete, that this work, along with the NZTA
AWHC preliminary business case, be subject to a Programme Review and a Financial Review 20. These
will help to identify any gaps and to scope a joined-up approach to an Indicative Business Case, which
still enables AT and the NZ Transport Agency to carry out work within their statutory scope.
20
Note that in light of ATAP work which suggests that an AWHC is not required as soon as the project had proposed, a hold
has been put on the planned Programme Review and Financial Review. The NOR will go ahead as planned but further business
case work related to the AWHC is on hold.
Benefit 3: A high-quality PT service benefits users and increases PT mode-share, improving the
efficiency of Auckland’s wider multi-modal transport network.
The northern boundary for the project includes consideration of the northern reaches of the Auckland
region, focussing on the need to service areas of population growth, notably Warkworth, Wainui and
Dairy Flat. Further intensification is expected within the urban limits too. The southern reaches of
the project are connections into and integration with RTN in the city centre. State Highway 1 is a key
consideration as it is also the route of the current North Shore RTN. Other considerations include
access from the west via SH18 and any future SH18 RTN alignment. The maps below show the
geographic extent with Figure 9 showing the Unitary Plan map 21 of zoning with areas of future growth
highlighted in yellow. Figure 10 shows the state highways and existing North Shore RTN.
21
Recommendations zoning maps,
http://www.aucklandcouncil.govt.nz/EN/planspoliciesprojects/plansstrategies/unitaryplan/Documents/ihprecommendations/a
upzoningmaplegendmap.pdf, accessed 17/08/16.
Orewa
Wainui
Silverdale
Dairy Flat
Albany
City
Centre
Albany
Metro
Centre
Constellation Station
Sunnynook Station
SH18
SH1
Akoranga Station
AHB/SH1
City
Centre
The Northern Busway includes a station at Albany and runs
from Constellation Station, until just south of Onewa Rd
Gaps in the evidence base for the North Shore RTN strategic case will either be filled or highlighted
for further work. In particular, problem 2 relates to the potential efficiencies in AT and the NZ
Transport Agency working together. This may still be hard to quantify at the PBC stage, and will be
addresses through NZTA’s Financial Review of both the AWHC and the North Shore RTN planning.
During the North Shore RTN PBC, further work will be undertaken to define the investment objectives,
refine the key performance indicators and determine baselines and targets.
Further transport modelling will be required, including modelling the packages/programmes put
forward as part of the PBC. An updated land use scenario will also be required to better-understand
the likely impacts of the growth enabled by the Unitary Plan. However, this will not be available until
after the PBC stage (this is a challenge currently facing all transport projects, given the recent Unitary
Plan decisions, and the approach will be to continue with existing modelling until such time as newer
material is available).
Further work is required to understand potential for staging and (if required) integrating/introducing
any future “step-change” in mode.
Further developments and directions from ATAP will also clearly need to be taken into consideration
in the planning and programming of any future investment.
The NZ Transport Agency had planned a parallel exercise in undertaking a Programme Review and a
Financial Review of both the AWHC and the NS RTN planning, expected to run from September 2016
through to 2017 (outlined in Figure 2). The Programme Review proposes a bespoke ILM process to
consolidate the problems and benefits relating to the Waitematā Harbour Crossing. The Programme
Review will involve a strategic assessment to reframe the problem, refine the benefits and KPIs and
identify gaps in the IBC scope. In light of ATAP work which suggests that an AWHC is not required as
soon as the project had proposed, a hold has been put on the planned Programme Review and
Financial Review. The AWHC NOR will go ahead as planned (lodgement planned for April 2017) but
further business case work related to the AWHC is on hold.
The programme business case will be completed within the existing North Shore RTN Study contract
(via variation). Section 10 explains project financial management.
Work already undertaken suggests that the current Northern Busway alignment provides the most
likely alignment for future improvements to RTN. The Northern Busway runs directly alongside State
Highway 1, together these crucial spines of infrastructure both access and sever the surrounding
areas. The PBC will consider and test other alignment options.
A key assumption is the form and alignment of the AWHC. The Notice of Requirement for the AWHC
is anticipated to be notified in April 2017. While the designation sought is compatible with rail
options, at the NOR stage, it will not obligate Auckland Transport to provide for rail.
7.5 Interfaces
There are two projects that are likely to be of the most consequence to planning for future
improvements to North Shore RTN. These are the Additional Waitematā Crossing and decisions made
on rapid transit networks in the city centre, namely the Central Access Programme (City to Airport
Mass Rapid Transit).
Existing access between the city centre and the North Shore is via State Highway 1, on the Auckland
Harbour Bridge (AHB). The Northern Busway is the core of the current North Shore RTN. In assessing
the need for an improved North Shore RTN, options including but not restricted to the AHB and AWHC
will need to be considered.
Key to understanding how the North Shore RTN will fit with the wider regional network will be
opportunities and limitations to integrating in the city centre. This will involve consideration of the
findings to date of the Central Access Programme.
Other projects which interface with the North Shore RTN include:
AT has budgeted $350,000 for the Indicative Business Case work in the 2016/17 year, WBS
E.700701.02.02.
Funding conditions
This strategic case is to confirm the NZ Transport Agency’s agreement to part-fund or co-invest in the
North Shore RTN Programme Business Case. It is understood that this would be by way of a CSA (or
other) to The NZ Transport Agency’s HNO AWHC work, at a rate of 51 per cent.
Document management
All key electronic documents will be stored within Auckland Transport’s SharePoint system under Key
Strategic Initiatives/Rapid Transit Network/North Shore RTN.
Quality assurance
The programme business case phase will be delivered in accordance with NZTA’s business case
approach and signed-off through Auckland Transport’s delegation requirements.
Top project risks relate to not finding the best outcome to address the problem statements identified
in the NS RTN ILM (and for providing an AWHC). As the project(s) progress, key issues such as RTN
function, form, network integration, feasibility, constructability, affordability, staging and political
support will need to be addressed. In terms of project approach, the business case approach
inherently seeks to reduce project risk as the project progresses through stages.
Having two organisations (AT and NZTA) involved in the project, with differing statutory obligations
and guiding policies introduces risk. A “One Network Approach” and reframing during the
Programme Review stage will help to mitigate this risk.
North Shore RTN management and organisational risks are included in a North Shore RTN Risk
Register (SharePoint/KSI/RTN/SNRTN/Project_Risk_Register_NS RTN).
Change control
Any changes to the approach outlined in Figure 8 will be consulted on and agreed as appropriate.
Completion of the PBC will be undertaken by AT Strategy Division with the assistance from specialist
consultants. Development of the PBC will be in consultation with the NZ Transport Agency and AT
internal stakeholders and will be reported through AT management and the AT Board.
Key stakeholders
The area of influence for the North Shore RTN strategic case is large and is highly connected to a
wide range of parallel or related workstreams. RTN investment can also be strategically influential in
city-shaping. These factors generate a wide range of stakeholders that may have in interest in or may
be able to inform and shape the project outcomes.
Table 6 below includes identified stakeholders. Note that stakeholder involvement is also contingent
on the level of detailed feedback sought. For instance, Local Boards would be interested in the whole
of life of the project, whereas individuals may be interested in more immediate land impacts.
Transport interest groups Needs and aspirations of users of all transport modes
The project partners will continue to work together to understand the interactions between land use,
public transport and road components of the studies.
Along with the project partners, Auckland Council and internal stakeholders will be invited to attend a
workshop on option development and assessment. The majority of these stakeholders were involved
during development of the North Shore RTN study so have existing knowledge of the project.
External stakeholders will be informed of Auckland Transport’s position on the project, as the AT
Board are briefed and agree to information becoming publically available
Procurement strategy
The North Shore RTN Study was procured via an open tender, using a Purchaser Nominated Price
procedure, in line with Auckland Transport’s Procurement Policy and Procurement Strategy. The
value of the contract was $350,000. Aurecon were awarded the contract (#342-16-261-PS). The
North Shore RTN Study will form the basis of the PBC. However, as outlined in the scope, further
work is required to refine and articulate the PBC. This is being managed as a variation to the Aurecon
contract, to the order of $60,000.
Auckland Transport is committed to providing a healthy and safe working environment for all those
involved with its activities including employees, contractors, volunteers and all other persons working
in or visiting our workplaces.
We will achieve this through an effective partnership between management, our employees, and all
those working for us that will promote a culture of zero harm and by taking all reasonably practicable
steps to ensure the health and safety of all people associated with our operations.
In 1959, the Auckland Harbour Bridge opened. While originally tolled, it improved access and
spurred development in the North Shore suburbs of Northcote, Wairau Valley, Glenfield, Sunnynook
and Forrest Hill. Extensions of State Highway 1 led to a proliferation of inland growth with expansion
of suburbs such as Northcote, Glenfield, Wairau Valley, Forrest Hill and further north around the East
Coast Bays.
Further development of the SH1 during the 1990s stimulated development around Albany, supported
around a decade later by improved access from SH18 from the west. By the mid-2000s, bus mode
share was just over a third of morning peak demand into the city centre, with ferries playing a more
minor support role. The Northern Busway became fully operational in 2008, providing more reliable
public transport access to/from the city centre and establishing a strong growth pattern towards the
urban limits. By 2016, the Northern Busway is well-established as the basis of the North Shore Rapid
Transit Network (RTN).
• Continued growth in public transport ridership will put pressure on key bus corridors into the
central area. Efficiency improvements to the bus network (completing currently planned bus
infrastructure improvements, rerouting services and fully utilising benefits of the City Rail Link
project) will help to address these challenges. However, substantial further capacity increases will
be required to avoid severe overcrowding in the future.
• The existing Auckland Harbour Bridge has limits on its ability to cater for heavy traffic growth,
and increased private vehicle and public transport demand. A new crossing has very high
opportunity costs meaning it is very important to understand key drivers, alternatives, costs and
benefits before any investment decisions are made. Route protection for a new crossing needs to
progress in a way that integrates further roading and public transport requirements.
• Enabling growth in newly developing areas requires early investment in route protection and land
acquisition, and an early start is needed on key connections in the north-west and south,
including investment to support Special Housing Area development.
• Northern Motorway: future enhancements will be strongly tied to timing of Additional Waitemata
Harbour Crossing (AWHC) and greenfield growth in the longer term, leading to demand growth
north of Albany.
• AWHC: protect route for a new crossing, but further analysis of drivers and timing, and better
integration with public transport options is needed before investment decisions are made.
Provide new infrastructure and services: Ensure that transport enables and supports growth:
• New urban growth areas in the north, north-west and south will need investment in transport
infrastructure before significant growth can occur.
• Without investment, a lack of transport infrastructure will constrain development in these areas.
Early growth areas in the north-west and south require new internal and external connections
within the next decade to enable their development.
• An early investment focus on route protection and land acquisition is required to ensure
investment is able to proceed when required and in a cost-effective way. Route protection helps
avoid incompatible development and reduces the cost of land purchase for key projects.
• Early investment will also be needed to support Special Housing Areas, address current
deficiencies and enable a faster rate of development, particularly in the north-west and parts of
the south.
• Transport investment within the existing urban area can also unlock growth by providing
improved accessibility and making redevelopment more market attractive. Projects like AMETI,
which improves access and connections in east Auckland, are important catalysts for growth,
especially in the town centres they serve. Similarly, ensuring that planning documents enable
growth in areas with good accessibility and spare capacity is an important way to minimise future
investment requirements.
• The extent to which a transport investment enables growth should be an important consideration
in its prioritisation for funding.
• Further work required for final report: understand which potential investments enable the
greatest level of growth, particularly in the next decade.
Auckland is likely to need an additional harbour crossing by approximately 2030 to move increasing volumes of freight and a
growing population. The capacity of the transport network will need to increase, to respond to the pressure on the state
highway network and remove constraints on economic growth. While this Plan foresees significant business and
employment growth in the north, large numbers of future employees will still travel from the North Shore around the
Auckland isthmus and further south. The additional crossing must make provision for road and public transport (rail), and will
require significant investment beyond that which can be delivered by traditional funding methods, requiring new revenue
tools.
An additional harbour crossing would improve the resilience of Auckland’s transport infrastructure and provide new and
better connectivity into and through the central city. Several feasibility study reports on the next crossing have been
completed, including a 2010 study comparing a bridge with a tunnel, without recommending either option. Submissions to
the Auckland Unleashed discussion document show that Aucklanders prefer a tunnel to a bridge.
The tunnel option aligns the west of the city centre from Esmonde/Onewa Roads to the Wynyard Quarter, emerging around
Wellington Street. It has provision for rail, and is estimated to cost $5.8 billion. This alignment would future-proof suburban
rail for a Gaunt Street station and involve the removal of the Victoria Park viaduct completely when the additional crossing
opens. With the western alignment, there will be complementary improvements for rail and road access to the port
undertaken in the second decade (see Figure 13.2). Auckland Council acknowledges that there are different views on the
alignment of the new crossing, particularly around a possible eastern alignment.
The additional Waitematā Harbour Crossing will make provision for rail, because of the anticipated population and business
growth north of the bridge. It will also form a key component of the single system approach to Auckland’s transport. Rail to
the North Shore will impact on future growth opportunities in northern Auckland, and initial rail route options are being
investigated. Long-term urban density possibilities, and the demand for travel by rapid transit, will be taken into account
when considering these route options. Further detailed studies will look at the economic, social and environmental benefits
and costs associated with the various options. Regardless of the option decided on in the future, rail to the north will be a
substantial investment. It is unlikely that any physical work on rail north of the crossing will commence within the period of
this Plan.
This problem / opportunity identified in the Strategic Case involves journeys for employment, access
to economic opportunities and freight, where strategic travel demand modelling shows that there will
be a shortfall in PT supply/capacity in future years. This will impact on levels of service for journey
time reliability, resilience and mismatched capacity and demand that results in severe congestion.
The North Shore rapid transit network would connect residents living in the North to employment
opportunities in the City Centre. It would also improve access to employment opportunities in the
metropolitan centres at Takapuna and Albany and tertiary education centres in Albany.
Significant brownfield and greenfield growth is anticipated in the North Shore over the next three
decades. Access to and from development is an important factor to its uptake and viability.
Investment in North Shore RTN will support public transport mode share, providing faster, more
reliable journey times for public transport passengers and road users (including freight).
The North Shore rapid transit network would also increase resilience of the transport network by
improving connectivity and providing an alternative mode of travel that is separated from congestion
in general traffic lanes, particularly over the Auckland Harbour Bridge (AHB) which is currently the
critical link for journeys to/from the City Centre and the North Shore.
EFFECTIVENESS (Medium)
Outcomes Focussed (H) – This activity provides a tangible change relative to the strategic fit
outcomes identified in a number of strategic documents including the Auckland Plan and the
Regional Public Transport Plan. Investment in the North Shore RTN is expected to alleviate the
problems arising from the anticipated brownfield and greenfield growth by providing regional access
to employment and education, provide resilience on a critical connection from the City Centre to the
North Shore and links with the proposed changes to the AHB.
Integrated (H) - The activity is well-aligned with current network and future transport plans (both
regional and national) and land use. It takes into account the continued development of the North as
well as growth as a result of intensification. It will also consider the linkages with other activities also
in progress within the North growth areas and the Additional Waitematā Harbour Crossing project
being developed by NZTA HNO. The project is supported by the two project partners (the NZ
Transport Agency and Auckland Transport). The activity will support the wider state highway network
and will improve connectivity with public transport services on ancillary corridors.
Correctly Scoped (M) - The planning phase of this activity has been identified in the RLTP and a
strategic case is being finalised. For the purpose of developing a PBC, this activity is correctly scoped
and is of an appropriate scale in relation to the issue. Work to date shows that at some point during
the 2030s, peak travel demand is expected to overtake the practical capacity of the busway, even
taking into account planned improvements. Some form of higher-capacity solution is therefore likely
to be required for future improvements to North Shore RTN.
Affordable (M) - The development of the PBC is affordable and is considered to be value for money,
however no funding has been identified for North Shore RTN within the Long Term Plan or the RLTP.
Timely (M) - The development of the PBC is timely. Growth in the North is occurring faster than
previously anticipated and there is an opportunity to align the delivery of planning outcomes in
conjunction with other key activities being undertaken (e.g. AWHC, SH1 Northern Corridor
Improvements and TFUG). While the capital funding has not been identified, the planning of major
projects is required in advance to ensure that opportunities can be identified for land acquisition
early and undertake notice of requirement / route protection. Ongoing benefits are expected to arise
from increased rapid transit capacity along the corridor, similar to those observed with the existing
Northern Busway.
Confidence (H) - Risks have been identified and are acknowledged. These will be considered further
during the development of the PBC, particularly around interdependencies with other activities within
the North Shore. The AWHC/NS RTN Programme Review and Financial Review will further consider
these interdependencies as well as possible cost impacts.