Me8793 Ppce Unit IV
Me8793 Ppce Unit IV
Me8793 Ppce Unit IV
PROUCTION COST
ESTIMATION
1 PREPARED BY
J. SRINIVAS. M.E.,
ASSISTANT PROFESSOR,
MECHANICAL ENGINEERING.
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
SYLLABUS
Estimation of Different Types of Jobs
Estimation of Forging Shop
Estimation of Welding Shop
Estimation of Foundry Shop
2
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
ESTIMATION OF DIFFERENT TYPES OF JOBS
There are many types of jobs done by using fabrication in which different
operations are performed to get desired jobs. The different types of operations
done are:
Sheet metal works
Forging
Welding
Foundry
Turning up – for making sharp bends to sheets for seaming, hemming etc.,
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
ESTIMATION OF DIFFERENT TYPES OF JOBS
Hollowing – process of beating the metal for giving it concave shape
Allowance for Hollowing = ½ (base)2 + (height)2
Raising – process of beating the metal over the spherical head to give a convex
shape.
Allowance for Raising = ½ (base)2 + (height)2
Planishing – gives the final finish to the hollow or raised surfaces by removing
minor bends by beating the sheet with the help of Planishing hammer.
Edge Stiffening – to give a product with finished appearance.
Wiring – Allowance = 2.5 x D + 4 x t
7
of weld
SHEET METAL PROBLEM
Machine Forging
Smith forging
Drop Forging
Press Forging
Forging Operations
Drawing Down
Up Setting
Bending
9
Punching and Drafting
Swaging
ESTIMATION OF FORGING SHOP
the hole.
ESTIMATION OF FORGING SHOP
weight.
ESTIMATION OF FORGING SHOP
29
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
FORGING SHOP PROBLEMS
Volume of the Component = 5.06582 x 10-5 m3
Scale Loss = 3.0396x 10-5 m3, Shear Loss = 2.533 x 10-5 m3
Flash Loss = 3.57 x 10-5 m3, Tong Loss = 6.283 x 10-6 m3
Sprue Loss = 3.5462x 10-5 m3, Total Loss = 1.33171x 10-4 m3
Gross Volume = 1.8383 x 10-4 m3 /Piece,
For 150 pieces Total Volume = 0.027575 m3
Length of Bar = 87.77 m,
Cost of Material = ₹ 4564
Surface Area = 0.012959 m2
Forging Charge/Piece = ₹ 3.24,
Total Forging Charges = ₹ 486 Overheads = ₹ 486
Total Cost Incurred = ₹ 5536 30
ESTIMATION OF WELDING SHOP
For estimating the cost of arc welding, following costs are included:
Material cost – includes the cost of electrodes
Labour cost
Power charges
On – cost
32
ESTIMATION OF WELDING SHOP
Plate Power
Electrode Length of electrode Welding time in
Thickness consumption per
no. required in m of welding min/m
in mm m length in KWh
3 10 0.50 – 0.60 6–7 1.2
5 8 0.70 – 0.80 10 – 12 2.0
10 6 1.00 – 1.20 20 – 25 3.0
33
15 6 1.75 – 2.00 35 – 40 3.7
20 4 2.00 – 2.60 40 – 45 4.8
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
34
Assume for 6 mm thickness, Power Consumption = 2.2 KWh/m and Power Charges as ₹ 5/KWh
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
WELDING SHOP PROBLEMS
Volume of Container = 50 x 50 x 100 = 250000 cm3
Weight of Container = 250000 x 8 = 2000000 g or 2000 Kg
Actual weight of sheet metal plate = 2000 + 0.05 x 2000 = 2100 Kg
Length of the welding area = 11’+12+1’2’+22’+14+23+2’3’+1’4’
Length of the welding area = 0.5+0.5+0.5+0.5+1+1+1+1 = 6 m
Cost of welding material = 6 x 20 = ₹ 120
Cost of sheet metal plate = 2100 x 10 = ₹ 21000
Cost of Labour = 10% of sheet metal cost = 0.1 x 21000 = ₹ 2100
Power Consumption = 2.2 x 6 = 13.2 KWh
Power Charges = 13.2 x 5 = ₹ 66
Total Cost of the container = Cost of welding material + Cost of sheet metal
plate + Cost of Labour + Power Charges = 120 + 21000 + 2100 + 66 35
Cost of Electrodes:
Length of electrode required @1.8m/m of welding = 1.8 x 2 x 9.283 = 33.42 m
37
For 6% discarded electrodes, Electrodes assumed = 33.42 x 1.06 = 35.425 m
Cost of Electrodes @ ₹12/m = 32.425 x 12 = ₹ 425.10
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
WELDING SHOP PROBLEMS
Power Charges:
Power P = VA = 40 x 325 = 13000 VA = 13 KVA, Power factor = 0.85
Power P = 13 x 0.85 = 11.05 KWh or 11.05 Unit
Power Charges @₹7/ unit = 11.05 x 7 = ₹ 77.35
41
GAS WELDING
Machining allowance
48
Draft allowance
Estimate the power cost for melting Aluminium of 150 kg at 6500 C from
room temperature of 350 C. Specific heat and latent heat of aluminium
are 0.91 KJ/kg and 398 KJ/kg respectively. Unit cost of power is ₹7.
Q1 = m Cp (T2 – T1) = 150 x 0.91 x (650 – 35) = 83947.5 KJ
Q2 = m (LH) = 150 x 398 = 59700 KJ
Q = Q1 + Q2 = 83947.5 + 59700
Q = 143647.5 KJ
(1 Joule = 2.8 x 10– 7 KWh) 143647.5 x 103 J = 143647500 x 2.8 x 10– 7
Power = 39.93 KWh
Power Cost = 39.93 x 7
49
Power Cost = ₹ 280 (Approx)
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
50
APRIL/MAY 2018, 14 (a)
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
FOUNDRY SHOP PROBLEMS
{Q = m (LH) = 1000 x 272 = 272000 KJ – Additional Data Given}
Materials Cost = ₹ 38/kg x 1000 kg = ₹ 38000
Total working hours of furnace = 24 x 300 = 72000 hours
Labour cost = ₹ 20000/month = ₹240000/year
Power = 750 KVA, Power factor = 0.95
Power = 750 x 0.95 = 712.5 KWh = 712.5 Units
Power Cost = 712.5 x 6 = ₹4275.45/month = ₹4275.45 x 12 = ₹ 51305.48 /Year
Total Cost for Melting CI/kg = (Furnace cost + labour cost+ Miscellaneous Exp +
Materials Cost + Maintenance Cost+ Power Cost)/ m
Total Cost for Melting CI/kg = (6000000 + 240000+ 70000 + 38000 + 200000 +
51305.48)/ 1000 = 6599305.48 / 1000
Total Cost for Melting CI/kg = ₹ 6599.305 51
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
52
NOV/DEC 2018
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
FOUNDRY SHOP PROBLEMS
Volume of the component = 2 x volume of the leg + volume of the arc
Volume of the component = 2 x (6x2x6) + x (7.52 – 62) x 6/2 = 335 cm3
Net weight of the casting = 335 x 7.2 = 2412 g = 2.412 kg
Process scrap = 2.412 x 0.17 = 0.4 kg
Total Material / piece = 2.4 + 0.4 = 2.8 kg
Material cost/ piece = 2.8 x 30 = ₹ 84
Process return = 0.4 x 5 = ₹ 2
Net Material Cost per Piece = 84 – 2 = ₹ 82
Labour charges / piece = Moulding & Pouring + Casting removal, Gate cutting
etc + Fettling & Inspection = 10 x 30/60 + 4 x 10/60 + 6 x 10/60
Labour charges / piece = 5 + 0.67 + 1 = ₹ 6.67/piece
Shop overheads/piece = 10 x 30/60 + 4 x 30/60 + 6 x 30/60 = 5+2+3 = ₹ 10/piece53
Administrative Overheads = 2 x 2.8 = ₹ 5.6
ME8793_PPCE_Prepared By J. SRINIVAS., ME., Assistant Professor/Mechanical Engineering
FOUNDRY SHOP PROBLEMS
Total Cost per Piece = Net Material Cost + Labour Charges + Shop Overheads +
Administrative Overheads
Total Cost per Piece = 82 + 6.67 + 10 + 5.6
Total Cost per Piece = ₹ 104.27
54