RM - Beatrice
RM - Beatrice
Introduction to Beatrice
Foundation Design Challenges
• Site characterisation
• Pile design
• Jacket design
• Fabrication approach
• Installation considerations
• Other challenges
Conclusions
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Introduction
Overview
Site:
Circa 13km offshore
132km2
Water depths 35-55m LAT
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Overview
Offshore structures
84no. 7MW wind turbine generators (WTGs)
2no. offshore transformer modules (OTMs)
Image: BOWL
Image: Siemens UK
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
WTG
~110
154
Jacket
Image: Hufton + Crow
Gherkin, 180
~55
Image: Wikimedia
~45
230
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
EPCI 91 inter-array
SIEM
cables
Jackets: Bladt,
Smulders,
BiFab
Fabrication:
SHL
Piles: EEW,
SIF
EPCI 84 WTG
foundations Installation: SHL
STDL
Feb 2011 2012 2013 2014 2015 2016 2017 2018 2019
2009 - Lease Consent Cables Piling First Full
CfD Piling Jackets Start Com- Turbines gene- Gene-
STW agree- Appli- Qualified Financial
Grant ment cation CfD Consent SG2 FID Close Start Start plete Start ration ration
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Foundation Design
Challenges
Site Characterisation
Vast site
Image: Google
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Available data - onshore
Image: BGS
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Available data - offshore
Image: BGS
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Phased investigation
Geophys, 5 BH Desk study
Prelim GM Review GM Interim GI Update GM Completion GI 6466000
Beatrice Farm Layout with Clusters & Water Depth
Final GM
6465000
(BE-G14, -54.9)
6464000 (BE-J13, -54.2)
(BE-H13, -53.4)
(BE-G13, -53.4) (BE-K12, -53.1)
6463000
(BE-F13, -54.2) (BE-J12, -52.2)
(BE-H12, -51.8) (BE-L11, -52.4) Cluster1
6462000 (BE-G12, -50.5) (BE-K11, -52.0)
(BE-M10, -49.9)
Cluster2
(BE-F12, -48.6) (BE-J11, -50.8)
(BE-E12, -52.9) (BE-H11, -50.2) (BE-L10, -49.6) Cluster3
6461000 (BE-K10, -51.5)
(BE-G11, -51.1)
(BE-M9, -49.0)
Cluster4
(BE-F11, -48.8) (BE-J10, -49.5)
NORTHING
(BE-D9, -44.4) (BE-G8, -45.2) (BE-K7, -44.3)
6457000 (BE-C9, -45.5) (BE-F8, -45.7) (BE-J7, -42.7) NOTES:
(BE-E8, -46.0) (BE-H7, -42.5)
(BE-D8, -43.8) (BE-G7, -41.2) (BE-K6, -44.6) 1. All Water depths are relative to (mLAT)
6456000
(BE-C8, -43.3) (BE-F7, -42.5) (BE-J6, -41.5) 2. Names and locations taken from
(BE-E7, -43.7) (BE-H6, -40.0) LF000005-MAP-091
6455000 (BE-D7, -44.0) (BE-G6, -40.2)
(BE-C7, -42.3) (BE-F6, -41.6) (BE-J5, -41.4) Locations in each Cluster:
(BE-B7, -46.4) (BE-E6, -40.7) (BE-H5, -41.9)
6454000 (BE-D6, -42.2) (BE-G5, -39.7) Cluster 1 = 27 WTGs + 1 OTM
(BE-C6, -41.4) (BE-F5, -39.7) Cluster 2 = 21 WTGs + 1 OTM
(BE-B6, -44.0) (BE-E5, -40.4) (BE-H4, -41.1) Cluster 3 = 20 WTGs
6453000
(BE-D5, -41.9) (BE-G4, -38.6) Cluster 4 = 10 WTGs
(BE-C5, -40.4) (BE-F4, -40.4) Cluster 5 = 6 WTGs
6452000 (BE-B5, -39.7) (BE-E4, -40.7)
(BE-A5, -47.7) (BE-D4, -39.4)
(BE-G3, -40.5) Total = 84 WTGs + 2 OTMs
(BE-C4, -38.1) (BE-F3, -38.7)
6451000 Spares = 2 locations not used
(BE-E3, -38.6)
(BE-D3, -38.2)
6449000
(BE-E1, -38.9)
6448000
499000 500000 501000 502000 503000 504000 505000 506000 507000 508000 509000 510000 511000 512000 513000 514000
EASTING
CPT
Sampling
Lab tests
Images: BOWL/ Fugro/ Atkins Routine Advanced
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Pile Design Process
Loading
Large
moment
Push-pull
Piles
(compression-
tension in piles)
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Pile axial capacity
Reduced 30
Optimised
fatigue
CAPEX 6m difference between
damage
35
ICP-05 and DNV / API
Reduced Reduced 40
install. risk install. time
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Jacket Design Process
- Clustering approach
- Structural analyses
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process
Coupled Uncoupled
AFC Design
Analysis Analysis
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: Coupled Analysis
Pre-processing:
› ~1,000 wave loading simulations
SWP Analysis:
› Up to 20,000 combined wave + turbine simulations
Post-processing (Retrieval):
› ~300 critical ULS simulations
› 232 FLS simulations
› Code checking
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: Uncoupled Analysis
ULS: FLS:
Enveloping Factors
Enveloping Factors
Baseline: Baseline:
As per CA As per CA
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: AFC Design
TP & Joint
FEM
Attachments
T&I & VIV
[sympathetic
Damage
loading]
Uncoupled
Joint Axial
Analysis
Stress
Factors
Primary
Weld Root Factor for all
Assessment Steel FLS cases
AFC
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Fabrication
Beatrice Foundation Fabricators
Image: Google
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design for Serial Fabrication
Common TP & Upper Jacket
Image: Smulders
Image: Smulders
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Installation
~1km
Stratum
II
Stratum IV
Boulders Stratum IV
Stratum
IV
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Mitigation
Remediation = drive-drill-drive
Derive method to assess
Reduction of capacity from drilling
Shaft friction increase from ageing that can be relied upon
Capacity gain from concrete plug
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Jacket Installation
• Transportation fatigue
• Upending vs vertical towing
• Installation vessel limits
• Early age cycling
• Safe access
• Walk to work systems
• Evacuation procedures
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Conclusions
Conclusions
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Successes to date
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Thank you
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018