Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
Download as pdf or txt
Download as pdf or txt
You are on page 1of 33

Image: BOWL Image: BOWL

Foundation Design for the Beatrice Offshore Wind Farm

R. McLean – SUPERGEN Wind Hub General Assembly, 08th November 2018


Contents

Introduction to Beatrice
Foundation Design Challenges
• Site characterisation
• Pile design
• Jacket design
• Fabrication approach
• Installation considerations
• Other challenges
Conclusions

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Introduction
Overview

588MW offshore wind farm in the Moray


Firth
Clean electricity for 450,000 homes
Overall project £2.6bn Image: BOWL

Site:
Circa 13km offshore
132km2
Water depths 35-55m LAT

Scotland’s largest offshore wind farm!


Image: BOWL

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Overview

Offshore structures
84no. 7MW wind turbine generators (WTGs)
2no. offshore transformer modules (OTMs)

Image: BOWL

Foundations = jackets on driven piles


86 jackets; 85,000 tonnes
344 piles; >14km total length; 44,000 tonnes

Deepest offshore wind fixed structures in


the world

Image: Siemens UK

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
WTG

~110
154

Jacket
Image: Hufton + Crow
Gherkin, 180

~55
Image: Wikimedia

Heron Tower, Piles

~45
230

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
EPCI 91 inter-array
SIEM
cables

Jackets: Bladt,
Smulders,
BiFab
Fabrication:
SHL
Piles: EEW,
SIF
EPCI 84 WTG
foundations Installation: SHL

T&I 2 OTM and


foundations Design: Atkins

EPC 2 OTM and


Design: Atkins
BOWL foundations

STDL

SSE Offshore Wind Alliance EPCI export cables

Framework of key suppliers designed to


address the key challenges of Round 3 SWP EPCI 84 WTG
offshore wind and drive efficiencies in SSE's
offshore wind programme. GI, soil
Atkins parameters for
Collaborative work through Concept and design
FEED between Developer, WTG and OSP
Supplier, Installation contractor, Fabricator
and Designer.

Feb 2011 2012 2013 2014 2015 2016 2017 2018 2019
2009 - Lease Consent Cables Piling First Full
CfD Piling Jackets Start Com- Turbines gene- Gene-
STW agree- Appli- Qualified Financial
Grant ment cation CfD Consent SG2 FID Close Start Start plete Start ration ration

CONCEPT FEED DETAILED DESIGN INSTALLATION OPERATION

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Foundation Design
Challenges
Site Characterisation
Vast site

Image: Google

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Available data - onshore

Image: BGS

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Available data - offshore

Image: BGS

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Phased investigation
Geophys, 5 BH Desk study
Prelim GM Review GM Interim GI Update GM Completion GI 6466000
Beatrice Farm Layout with Clusters & Water Depth
Final GM
6465000

(BE-G14, -54.9)
6464000 (BE-J13, -54.2)
(BE-H13, -53.4)
(BE-G13, -53.4) (BE-K12, -53.1)
6463000
(BE-F13, -54.2) (BE-J12, -52.2)
(BE-H12, -51.8) (BE-L11, -52.4) Cluster1
6462000 (BE-G12, -50.5) (BE-K11, -52.0)
(BE-M10, -49.9)
Cluster2
(BE-F12, -48.6) (BE-J11, -50.8)
(BE-E12, -52.9) (BE-H11, -50.2) (BE-L10, -49.6) Cluster3
6461000 (BE-K10, -51.5)
(BE-G11, -51.1)
(BE-M9, -49.0)
Cluster4
(BE-F11, -48.8) (BE-J10, -49.5)

6460000 (BE-E11, -46.6) (BE-H10, -49.6) (BE-L9, -49.4) Cluster5


(BE-D11, -50.1) (BE-G10, -49.4) (BE-K9, -48.6)
Spare
(BE-F10, -48.2) (BE-J9, -47.8)
6459000 (BE-E10, -46.6) (BE-H9, -47.8) (BE-L8, -47.8)
(BE-K8, -47.6)
OTM Location
(BE-D10, -45.3) (BE-G9, -49.9)
(BE-F9, -49.0) (BE-J8, -45.5)
6458000
(BE-E9, -46.0) (BE-H8, -44.2) (BE-L7, -44.5)

NORTHING
(BE-D9, -44.4) (BE-G8, -45.2) (BE-K7, -44.3)
6457000 (BE-C9, -45.5) (BE-F8, -45.7) (BE-J7, -42.7) NOTES:
(BE-E8, -46.0) (BE-H7, -42.5)
(BE-D8, -43.8) (BE-G7, -41.2) (BE-K6, -44.6) 1. All Water depths are relative to (mLAT)
6456000
(BE-C8, -43.3) (BE-F7, -42.5) (BE-J6, -41.5) 2. Names and locations taken from
(BE-E7, -43.7) (BE-H6, -40.0) LF000005-MAP-091
6455000 (BE-D7, -44.0) (BE-G6, -40.2)
(BE-C7, -42.3) (BE-F6, -41.6) (BE-J5, -41.4) Locations in each Cluster:
(BE-B7, -46.4) (BE-E6, -40.7) (BE-H5, -41.9)
6454000 (BE-D6, -42.2) (BE-G5, -39.7) Cluster 1 = 27 WTGs + 1 OTM
(BE-C6, -41.4) (BE-F5, -39.7) Cluster 2 = 21 WTGs + 1 OTM
(BE-B6, -44.0) (BE-E5, -40.4) (BE-H4, -41.1) Cluster 3 = 20 WTGs
6453000
(BE-D5, -41.9) (BE-G4, -38.6) Cluster 4 = 10 WTGs
(BE-C5, -40.4) (BE-F4, -40.4) Cluster 5 = 6 WTGs
6452000 (BE-B5, -39.7) (BE-E4, -40.7)
(BE-A5, -47.7) (BE-D4, -39.4)
(BE-G3, -40.5) Total = 84 WTGs + 2 OTMs
(BE-C4, -38.1) (BE-F3, -38.7)
6451000 Spares = 2 locations not used
(BE-E3, -38.6)
(BE-D3, -38.2)

6450000 (BE-F2, -40.2)


(BE-E2, -38.2) Date: 19/04/2016

6449000
(BE-E1, -38.9)

6448000
499000 500000 501000 502000 503000 504000 505000 506000 507000 508000 509000 510000 511000 512000 513000 514000
EASTING

2011 2012 2013 2014 2015 2016


CONCEPT FEED DETAILED DESIGN

CPT
Sampling
Lab tests
Images: BOWL/ Fugro/ Atkins Routine Advanced

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Pile Design Process
Loading

Relatively small vertical load


Wind
Large horizontal loads from wind, waves
and currents WTG

High overturning moment at mudline


Resisted by piles in ‘push / pull’
Jacket
Piles work in compression & tension
Cyclic Wave &
current
Small self
weight

Large
moment

Push-pull
Piles
(compression-
tension in piles)

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Pile axial capacity

Need efficiency & reliability Which method?

Optimised Pile Tensile Capacity (MN)


pile length 0 2 4 6 8 10 12 14 16 18 20 22 24
0
Reliable
Reduced
level of
noise
safety 5 ICP-05
UWA-05
10
NGI-05

Pile penetraion (m bml)


Optimised
Reliable 15 DNV / API
axial
safety
Efficient & response Load
reliable pile 20
design
25

Reduced 30
Optimised
fatigue
CAPEX 6m difference between
damage
35
ICP-05 and DNV / API

Reduced Reduced 40
install. risk install. time

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Jacket Design Process
- Clustering approach

- Structural analyses
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process

Coupled Uncoupled
AFC Design
Analysis Analysis

Bookending Variances in- Inclusive of all


Site Cluster contributors

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: Coupled Analysis

Pre-processing:
› ~1,000 wave loading simulations

SWP Analysis:
› Up to 20,000 combined wave + turbine simulations

Post-processing (Retrieval):
› ~300 critical ULS simulations
› 232 FLS simulations
› Code checking

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: Uncoupled Analysis
ULS: FLS:

Enveloping Factors
Enveloping Factors
Baseline: Baseline:
As per CA As per CA

Deep Water: Deep Water:


5% WTG contingency 5% WTG contingency
Water depth uncertainty ± Water depth uncertainty

Shallow Water: Shallow Water:


Short stickup Short stickup
Stiff soil Stiff soil
5% WTG contingency 5% WTG contingency
Water depth uncertainty ± Water depth uncertainty

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design Process: AFC Design
TP & Joint
FEM
Attachments
T&I & VIV
[sympathetic
Damage
loading]

Uncoupled
Joint Axial
Analysis
Stress
Factors

Primary
Weld Root Factor for all
Assessment Steel FLS cases
AFC

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Fabrication
Beatrice Foundation Fabricators

Image: Google

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Design for Serial Fabrication
Common TP & Upper Jacket

Image: Smulders

Image: Smulders

Cluster Specific Lower Jacket

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Installation
~1km

Major geological fault Stratum III

Pile Installation risks


Seabed
Stratum I

Stratum
II

Stratum IV

Boulders Stratum IV

Stratum
IV

Bedrock horizons Horizons within Horizons within


Stratum IV Stratum IV

Strong and laterally traceable seismic


reflectors
Identified in intact Lower Cretaceous
Variable in lateral extent
Some have corresponding evidence in the
borehole data
Some relate to sandstone beds

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Mitigation

Remediation = drive-drill-drive
Derive method to assess
Reduction of capacity from drilling
Shaft friction increase from ageing that can be relied upon
Capacity gain from concrete plug

Analyse impact of drilling at varying depths


with and without concrete plug
Installation contractor has clear pre-defined
scenarios to know instantly whether:
Pile must be abandoned,
Pile can be saved with a concrete plug
Pile does not require a concrete plug

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Jacket Installation

• Transportation fatigue
• Upending vs vertical towing
• Installation vessel limits
• Early age cycling
• Safe access
• Walk to work systems
• Evacuation procedures

Image: SHL Image: Ian Greenwood

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Conclusions
Conclusions

› Multi-disciplinary approach required to manage risk and optimise


standardisation
› Good design should consider:
› Variable site conditions
› Fabrication approach
› Installation approach
› Project programme
› Through life user safety
› Innovation, collaboration and adaptability are key to future success of
industry.

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Successes to date

› Design AFC and certification to


programme
› Pile installation completed
December 2017
› Jacket installation completed July
2018
› First power generation July 2018
Image: BOWL

› Fully operational in 2019

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Thank you

All images © Atkins unless otherwise stated.

Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018

You might also like