METHOD STATEMENT FOR

REINFORCED CEMENT CONCRETE WORKS

1. INTRODUCTION
As per the contract, it is proposed to Construct the Rajasthan house new Delhi By contractor M/S
PANJITANI BUILDWELL PVT LTD

2. PROPOSED SCOPE OF WORKS COVERED UNDER THIS METHOD STATEMENT


Casting of Foundation, column, Tie beam, Grade Slab, Columns, Core & shear walls, Beams &
Suspended Slab according to specified drawings and quality standards.

3. RESPONSIBILITIES
3.1- The contractor’s approved shop drawing for RCC structural elements shall be available for
inspection by the Engineer.

3.2 -All shuttering and reinforcement is to be checked and approved by the Engineer.

3.3 The site engineer shall check that levels are as indicated on the drawings and are correct. Should
there appear to be any discrepancies, the contractor shall correct levels in consultation with the
Engineer.

3.4 The site engineer shall be deemed to have satisfied himself as to the shuttering and
reinforcement works.

3.5 The Project Manager shall be responsible for ensuring that all works are carried out strictly in
accordance with this Method Statement, the requirements of the client and the overall contract
documents.
3.6 The site safety in-charge to ensure that all the works are carried out strictly in accordance with
safety norms.

3.7 The Project Manager shall ensure the preparation and testing of concrete cubes for compressive
strength as specified.

3.8 The Project Manager shall ensure curing as specified and utmost quality shall be maintained
through the works.

4. EQUIPMENT TO BE USED ON SITE


The equipment to be used on site will include the following:

4.1- Concrete Pump

4.2- Vibrators

4.3- Masonry Tools

4.4- Cube Moulds

4.5- Slump Cone

5. PROCEDURE
5.1 Well before proposed start date for RCC works, Mix Design for all grades of concrete to be used
in works shall be conducted in Field Laboratory as per approved Technical Specifications. The Mix
Design shall be conducted in the presence of Engineer.

5.2 The RCC footing shall be done throughout the length and width of structure to be constructed
and shall conform to specified shape, levels and grade providing firm foundation, level bed and
strong structure. Concrete shall not be freely dropped into place from a height exceeding 1.5m to
avoid segregation of material.

5.3 Casting of structures shall be done by placement of shuttering in line and level followed by
placing of reinforcement and subsequent concreting. All these works shall be executed as per the
procedures and norms already laid down herein above.

5.4 After completion of excavation & surface preparation, 10cm thick PCC shall be laid as per the
approved drawings.

5.5 Location of Footing and column shall be marked according to the approved coordination
drawings.

5.6 Vertical and horizontal steel reinforcement shall be cut and bent according to the drawings and
tied by strips in steel yard and shall be fixed in position.
5.7 Corner bars in column and Tie beams shall be cranked for the entire length of the lap. The
concrete cover to reinforcements shall be as specified in the drawings.

5.8 Cover block for steel reinforcement will be provided according to specifications.

5.9 Shuttering sides shall be checked for vertical position and right angles with the help of plumb bob

5.10 Inspection of Civil Engineers will be requested 24 Hrs before the time of casting.

5.11 Concrete as per the approved mix design shall be pumped carefully, vibrated and finished. After
setting, the concrete shall be covered with polythene sheet and wet Hessian clothes as per
specifications.

5.12 Curing of Concrete - The exposed surface of fresh concrete will be covered with polythene
sheets after finishing work are completed. After final setting of concrete (8 to 12 hours after casting)
the polythene will be removed and the concrete surfaces will be covered with wet hessian cloth and
cover by polythene sheet. Wetting of Hessian cloth will be continued for a period of seven days.
Once the side shutters are removed, the sides of concrete structure will also be cured in a similar
manner.

5.13 Shutter form work will be removed according to specified time.

Tests required will be conducted

Cube compressive strength of concrete

Slump test for workability of concrete

Temperature control test.

5.4 Form work Shall be of such quality and strength that shall ensure rigidity throughout placing,
ramming, vibration and setting of concrete without visible deflection.

5.5 Joints in form work shall be closed properly and tightly secured against previously cast concrete
to prevent bleeding of concrete paste.

6. SAFETY MEASURES
6.1 Prior to concrete pouring request will be raised for Engineer’s approval.

6.2 Safety Officer, Site Engineer & Foreman will observe the works.

6.3 Safety measures will be as per safety manual.