Method Statement For Fixing of Slab Formwork
Method Statement For Fixing of Slab Formwork
13
METHOD Rev: 0 Working status :
STATEMENT
FOR FIXING OF SLAB
Page 1 / 5 Date : 02.11.2023
FORMWORK WORK
Page | 1
TPHL/QMS Document No. 13
METHOD Rev: 0 Working status :
STATEMENT
FOR FIXING OF SLAB
Page 2 / 5 Date : 02.11.2023
FORMWORK WORK
CONTENTS
3. Materials required
4. Engineering works
5. Responsibility
6.1 Hazards
7. Sequence of work
7.3 Miscellaneous
8. Documentation
Page | 2
TPHL/QMS Document No. 13
METHOD Rev: 0 Working status :
STATEMENT
FOR FIXING OF SLAB
Page 3 / 5 Date : 02.11.2023
FORMWORK WORK
3. Materials required:
3.1 Iron Nails
3.2 Marker pen
3.3 Timber Log
3.4 Film faced Plywood sheets
3.5 Scaffolding standard and Ledger
3.6 Scaffolding Joint Pin
3.7 Adjustable base jack
3.8 Wooden Runner
3.9 Scaffolding Coupler
3.10 Scaffolding Clamp
3.11 Scaffolding Prop jack
3.12 Scaffolding Pipe
3.13 U shape jack
3.14 Wing nut
3.15 Tie rods
3.16 Steel decking
4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.
5. Responsibility:
5.1 The Engineer-in-charge will be responsible for implementing everything in this method
statement.
Prepared by : Karambir Singh Reviewed by: Approved by :
Page | 3
TPHL/QMS Document No. 13
METHOD Rev: 0 Working status :
STATEMENT
FOR FIXING OF SLAB
Page 4 / 5 Date : 02.11.2023
FORMWORK WORK
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to
the type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out
in the Quality Management Plan.
Page | 4
TPHL/QMS Document No. 13
METHOD Rev: 0 Working status :
STATEMENT
FOR FIXING OF SLAB
Page 5 / 5 Date : 02.11.2023
FORMWORK WORK
such a way as to reduce the severity of human injury or damages and to regain control within the
least possible time.
6.3.2 In incidents of major nature such as those resulting in fatalities, severe human injuries, fire and
explosion and natural calamities like rain, wind, sand storm etc.
6.3.3 Work will be stopped immediately and appropriate emergency response procedures adopted as
per procedures of company.
6.3.4 The matter will be communicated to key personnel by the easiest available means, seeking
assistance and advice.
6.3.5 Further work will be started only on getting clearance from senior management.
6.3.6 Tool box meeting will be conducted of all employees to explain the HSE part of the incident, the
immediate and the corrective/control measures that are essential to prevent further occurrences of
similar incidents.
6.3.7 Detailed investigation will be made into the incident, other than natural calamities, and the
learning points disseminated to the work force.
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.
7. Sequence of work:
8.1 Preparation of Slab formwork:
8.1.1 The Engineer-in-charge will ensure layout work shall be completed as per drawings and to be
checked by him.
8.1.2 Carpenter shall make formwork of plywood (12mm thickness) shape & dimensions as per
drawing and according to design load.
8.1.3 Site Engineer shall check the formwork made by carpenter before fixing as per drawings.
8.3 Miscellaneous:
The completed works shall be inspected and any left out items, minor defects if any, will be rectified
immediately.
8. Documentation: RFI and checklist shall be maintained by the site Engineer for the work.
Page | 5