API Question
API Question
service the condition of the insulation system shell be observed at lease every:
A: 6 Year.
B: 1 Year.
C: 5 Year.
D 10 Year.
2- Repair of a pressure vessel that comply with ASME code section viii Division 2
required
The appropriate of a:
A: 120 F ( 49 C )
B: 125 F ( 52 C )
C: 250 F ( 121 C )
D: 300 F ( 149 C )
A: Every Turnaround
B: 3 Year
C: 5 Year
D: 10 Year
5- When should temporary repair be removed and replaced with suitable requirements.
D: when performing alteration that may affect the integrity of the repair
6- Before starting any vessel inspection and maintenance activities, Personal should
REF-API-572 (9.4.7)
8- Above which temperature would a correction adjustment typically be applied when measuring
the ultrasonically.
A: 100 F ( 38 C)
B: 150 F (65 C )
C: 212 F (100 C)
D: 300 F ( 149 C)
9- the pressure gauge installed for convenience in the hydrostatic testing of a vertical pressure
vessel the s 125 FT ( 38100 mm) in overall length. The first is the top of the vessel 45 FT
( 13716mm) from the top and read 169.5 PSIg ( 1168 MPA) The third is 100 FT ( 30480 mm )
From the top end read 193.3 PSI ( 1.334 MPA ) What is the pressure of top.
C: The change in risk that may exist by not doing the planned inspection
additional damage
11- When conducting internal inspection if the lining appear damage or corroded the following
should be performed:
B: External WFMT examination technique shell be use to inspect the condition of the
base metal
C: Remove small portion of the lining to investigate the condition of the lining and the
A. No pit depth is greater then one half of the vessel wall thickness including the corrosion
allowance
B. The total area of pit deeper then the corrosion allowance d0es not exceed 7in²
C. ( 45.2 cm²) within any 8in² (20.32 cm ) diameter circle
D. The sum of the pit diameter along any straight line with in 8in diameter (20.32 cm ) circle
does not exceed 5in (12.70 cm)
E. The vessel is remaining life more the ten year.
13- A pressure relief valve remove from service for shop overhaul has been tested to determine the
as received PoP pressure . The initial PoP pressure is higher the ( CDTP ). The next inspection
should be to:
REF-API-576-(6.2.9.2)
14- Weld and heat affected zone are often inspected for:
A: Hydrogen Blistering
B: Corrosion
C: Temper Embrittlement
D: Graphitization
REF-API-510-5.10
15- A vessel is inspected after a four year of service and the thinnest part of the shell is found to be
1.360 in (34.5 mm). if the original thickness was 1.438in (35.5 mm) and the minimum required
thickness is 1.232in (31.3 mm) what thickness of material is available for the remaining
corrosion allowance:
A: 0.064in ( 1.6 mm )
B: 0.078in ( 2.0mm )
D: 0.206in ( 5.2 mm )
REF-API-510 (7.2.1)
16- Liquid penetrate examination on both side of a furnished single v weld can detect all of the
following
A: cold shut
B: surface crack
C: surface porosity
D: underbead crack
REF-ASME V ( T-620 )
17- A pressure vessel is deeply corroded but not through its wall. A full circumferential band is
intended to serve as a temporary repair. The repair band material is not suitable for direct
contact with the contained fluid. Is this repair acceptable:
D: No, unless it is approved and documented by a pressure vessel engineer and the
REF-API-510 (8.1.6.1.4)
18- Corrective action for a welding nonconformance upon:
A: The nature of the non conformance and its impact on the properties of the weldment
REF-API-577 (4.5)
19- With carbon and low alloy steel material CUI is usually in the Form of:
A: localized corrosion
D: Galvanized corrosion
A: Material toughness
C: Tensile strength
23- A person responsible for determining if a hydrostatic test must be performed after repairing
pressure vessel is the:
B: Owner/user
B: Creep
C: Erosion
D: corrosion
A: Engineer
B: construction code
C corrosion specialist
26- POP testing as a received condition or pressure relief valve in acid, caustic, toxic service can be
accomplished by what method:
A: using the lifting leaver on the valve while under nitrogen pressure prior to removed
B: carefully removing a solid fouling material that may effect the POP pressure
C: utilizing a test stand but onsite in the area where the valve is installed
REF_API – 576
27- After being in service for 5 year a 14ft. (4.267 mm) (seam to seam) vertical vessel has a
measured thickness of 0.82in.(20.8 mm) over the entire length of the cylindrical shell. the measure
inside diameter is 38.13 in. ( 968.5 mm). the material of construction was originally 0.875in .( 22.2mm)
thick with an allowable stress of 17500 psi( 120.6 MPa) was fully radiographed and was design for a
pressure of 600psi(4.13MPa), including static head.
Assuming a corrosion rate of 0.018 in/yr.(0.4572 mm/yr) and a required thickness of 0.545in.
(13.8 mm), what is the interval for the next internal inspection.
B: 9.1 YEAR
C: 10 YEAR
28- A new replacement vessels maximum allowable working pressure is 150 psig
( 1.03 MPa ) at 300F ( 149 C ) the allowable stress is the same at this temperature as the hydrostatic test
Temperature . the operating pressure is 140psig ( 0.96MPa).the minimum design metal temperature is
20F (-6.6C ).the appropriate post fabrication hydrostatic test pressure is:
30- what is the remaining life of a vessel corroding at a rate of 0.017in (0.432 mm ) a year
When the next inspection measurement was 0.638in ( 16.205 mm ) and the minimum required
thickness is 0.513 in( 13.030mm).
A: 3.67 year
B: 7.35 year
C: 10 year
D: 14.7 year
31- The installation of a fillet weld patch on the exterior of a pressure vessel shell in most
cases require that the
C: now fillet weld patch plate not be installed on top of existing fillet welded patch.
A: the maximum temperature expected during the lifetime of the pressure vessel
B: A person who design and oversees fabrication of pressure vessel before they are placed
in service
D: A person who , through consultation with other is a composite of all entities needed to
asses technical requirements for pressure vessel.
A ductile-to-brittle transition
B plasticity
C Tensile strength
D Toughness
REF-API-577 (10.4.5)
A API 510
B ASME SA516
REF-API-510 ( 7.3)
36 The inspector needs to replace a nozzle on a vessel that is in-service. The design of the
replacement nozzle shall employ what strength factor?
A The same allowable stress criteria as used for the vessel design
D One quarter of the maximum tensile strength specified in the ASME Code
REF-API-510(8.1.4)
37 Important information for probability of failure assessment for risk-based inspection(RBI)
will chek the
38 As a minimum an, ultrasonic instrument should be checked with a calibration standard at all
of the following time except
REF-API-510 (5.3.5)
40 what is one advantage of internal rotary UT over electromagnetic inspection method for
tube inspection of heat exchanger bundles?
C electromagnetic method are slower than rotary UT method and thereby cost more
D Rotary UTs generally do not need as through bundle cleaning as electromagnetic methods
REF-API-572(9.1)
41 the two most important alloying elements for prevention of high-temperature hydrogen
attack at
REF-API-571 (5.1.3.1.6)
42 what is the term used to describe ac condition that will designate reject ability of a weld
A Defect
B Blemish
C Flaw
D Discontinuity
REF-API-510 (3.1.1.5)
43 during repairs of alteration of pressure vessel, the inspector shall verify that all new
materials are
44 all of the followings are suitable for determining the thickness of a part except
B profile radiography
C ultrasonic beam wave NOTE:STRAIGHT BEAM TECH, ARE USED FOR THICKNESS ,SHEAR
OR ANGLE BEAM TECH, ARE USED FOR WELD DISCOUNTINITY.
45 the next inspection interval for vessels in corrosive service should be determine by
calculating the remaining life of
C all nozzles
REF-API-510 (5.6.2)
46 According to API 510 how many thickness measurement should be taken on a pressure
vessel during internal or on stream inspection
B at least one on each nozzle and two on each head and shell section
D four point on the shell, one on each head and one on all major nozzle
REF-API-510 (5.6.2.1)
B ASME, Section IX
C ASME, Section V
UG-27-ASMEVIII-DIV.1
C identifying and clarifying missing weld sizes, dimensions, tests, and any additional
requirements
REF-API-577 ( 4.2.1)
REF-API-510 (4.4)
51 API 510 allows a statistical analysis of ultrasonic thickness data to assess
A. Creep damage
B. Vessel with random but significant localized corrosion
C. The number of condition monitoring locations (CMLs) required
D. Corrosion rates and remaining life
REF-API-510 (5.6.2.1)
52 while performing a magnetic particle examination, the best result are achieved when the
lines of flux
A. At 45 to the discontinuity
B. Parallel to the discontinuity
C. Created around the discontinuity
D. Perpendicular to the discontinuity
53 weld buildup for purpose of the restoring base metal thickness involves the use of weld
metal having
REF-API ?
54 when performing a weld repair on a section of stainless steel weld overlay on is carbon steel
vessel the hydrogen service, which of the following is most important
REF-API-510 (8.1.6.4.3)A
55 accessible flange face should be inspected to determine
A. Metal specification
B. Correct dimensions
C. Environmental cracking
D. Gasket seating surface condition
REF-API-510 ( 5.11.2)
57 A new pressure vessel corrosion rates to be based of the following measurement taken from a
similar vessel after 6 years of the same service:
The controlling corrosion rate that will determine the inspection interval is.
A. 2.5 years
B. 5 years
C. 6 years
D. 12 years
REF-API-510 ( 7.2)
59 Pressure-relief valves are considered stuck if they fail to pop at the inlet pressure of what
pressure of the CDTP?
A. 103%
B. 110%
C. 125%
D. 150%
60 which of the following may be used as permanent repair for damage other than cracks?
A. Non-penetrating nozzles
B. Lap band repairs
C. Fillet welded patch
D. Fiberglass reinforced patch
REF-API-510 ( 8.16.1.4)
61 in conducting a risk base (RBI) identifying and evaluating potential damage mechanism
REF-API-510 ( 5.2.2)
62 when performing local post weld heat treatment (PWHT) in lieu of a 360 bending PWHT when
maintain ptre heat temperature must be maintain during welding
A. 150F(66C)
B. 200F(93C)
C. 250F(121C)
D. 300F(150C)
REF-API-510 (8.1.7.4.2)E
63 Which of the following best describes how to establish the inspection interval for pressure vessel
describe?
REF-API-510 ( 6.1)
64 preheat temperature use in making welding repair shall be in accordance with the
REF-API-510 ( 8.1.7.3)
65 in conducting a risk base inspection (RBI) identifying and evaluating potential damage mechanism
REF-API-510 (5.2.1)
66 according to API standard 510 flush (insert) patches must
REF-API-510 (8.1.6.1.2.2)
67 when evaluating existing equipment with minimal document what is the maximum joint efficiency
that can be used for seamless shell head or nozzle when the extent of radiography performed is
unknown
A. 0.55
B. 0.65
C. 0.70
D. 0.85
68 API 510 code who is responsible for weld quality of welder and welding procedure
REF-API-510 (8.1.7.2.1)
69 unless justified by risk base inspection (RBI) assessment an external inspection on an above ground
vessel shall be performed
A. At every turnaround
B. When operational change occur
C. At the lesser of either 5 years or at the same interval as the required internal/onstream
inspection
D. At the lesser of either 5 years or at the quarter corrosion rate life
REF-API-510 (6.5)
70 a vessel has a measured head thickness of 0.875 in (2202mm) and a required thickness of 0.563 in
(14.3 mm). if the corrosion rate is 0.019 in/yr (0.4826 mm/yr) what is the interval for the next internal
inspection of the vessel
A. 4.1 years
B. 8.2 years
C. 10.0 years
D. 16.4 years
71 a risk base inspection (RBI) assessment for the internal are on-stream inspection shall be invested
and approved at intervals not to exceed a maximum of
A. 3 years
B. 5 years
C. 10 years
D. 15 years
REF-API-510 (6.5.1.1)
72 when performing vessel repair which of the following does not qualify as an API 510 repirs
A. Owner/user shop
B. Contractor chosen by the owner/user
C. ASME U stamp holder
D. ASME VR stamp holder
REF-API-510 ( 3.1.62)
73 what is the main reason pressure vessel should be inspected at the time of installation
REF-API-510 (6.2.1)
74 if the remaining life of the vessel estimated at 3 years an external inspection shell be performed
when:
A. 1.5 years
B. 2 years
C. 3years
D. 5 years
REF-API-510 (6.5.1.2)
75 the inspector in consultation with whom should determine when it is necessary to remove deposit
or lining to perform adequate inspection
A. A corrosion specialist
B. The inspection supervisor
C. A pressure vessel engineer
D. A NACE coating inspector
REF-API-510 (5.5.2.3)
76 external inspection of a vessel reveals that the anchor bolts are corroding which of the following
test would best determine the overall condition of the bolting
A. Radiography
B. Hammer testing
C. Scrapping rust from a nut
D. Visual inspection
77 Which of the following non destructive examination (NDE ) method is most likely to detect a sub
surface lamination in a pressure vessel
REF-API-510 (8.1.6.1.1)
A. Consequence assessment
B. Repair and replacement
C. Management of change
D. Inspection activities
80 a pneumatic test
Option
82 …….. provide the controls that are necessary when contract inspector used to supply inspection ….
the site
REF-API-510 ( 4.4)
83 for vessel whose remaining safe operating life is estimated to be only 5 years the next external
inspection shall be before
A. 2 years
B. 2.5 years
C. 4 years
D. The vessels full life has expired
REF-API-510 (6.4.1)
84 if corrosion under insulation damage is found the inspector
B. Shall remove half of all damage insulation for inspecting the vessel wall condition
B. Should remove the damage insulation plus a minimum one foot around all nozzles
C. Should use acoustic emission testing to locate damage areas
REF-API-510 (5.5.6.2)
85 inspection for corrosion under insulation shall be consider for externally insulated austonatic
stainless steel vessel operating between
86 unless justified by RBI an on stream inspection cannot be substituted for an internal inspection for
vessel
A. Where the corrosion character of the content has been established by at least 5 years of the
same service
B. Operating at temperatures below the creep rapture range
C. That have a non integrally bonded liner
D. Where the size or configuration makes vessel entry impossible
REF-API-510 (5.6.2.1)
87 prior to using preheat or controlled deposition welding as alternatives to post weld heat treatment
(PWHT) a metallurgical review shall be conducted by a/an
REF-API-510 (8.1.7.4.3.1.2)
88 according to ASME code section ix essential welding procedure variable are those in which a change
in a variable
REF-API-510 (8.2.1.7)
A. All nondestructive examination (NDE) activities apply to a pressure vessel during fabrication
and/or repair
B. All planned and preventative action required to determine if a pressure will meet requirements
C. All nondestructive examination (NDE) activities applied to a pressure vessel during required
inspection activities
D. A list of all the quality control and nondestructive examination (NDE) procedure that are
required for an in service inspection.
REF-API-510 (3.1.59)
90 brittle fracture usually occurs only at:
REF-API-571 ( 4.5.1.6)
REF-API-510 (8.2.1)
A. Can only used if the cap has a thickness corresponding to XXS or greater
B. May be used as permanent repairs for other than crack when the design and method of
attachment comply with the applicable construction code
C. May be used only as temporary repair until permanent repair can be effected at the next
available maintenance opportunity
D. Are prohibited as a means of temporary or permanent repair
REF-API-510 (8.1.6.1.4)
94 a plant engineer would like to increase a vessel operating temperature by 100F(38C ) the vessels
name plate state a maximum allowable working pressure of 250 psig( 1.7 MPa) at 650F (343C ) and the
current operating temperature is 600F ( 315 C ) what is the first step in increasing the operating
temperature ?
REF-API-510 ( CHAP 7)
95 if a pressure vessel component should fail because an incorrect material was investigated suitable
for the specified material the inspector shall:
REF-API-510 ( 5.9.2)
96 on in service vessel if there is a conflict between requirement of the ASME code and the API 510
code, which should take precedence ?
A. ASME Code
B. API 510 Code
C. Most stringent code
D. Applicable code as determined by authorized pressure vessel inspector
REF-API-510 (1.1.1)
97 Fillet-welded patches may be used as
A. The thickness at which it is unsafe for continued service without risk assessment
B. The thickness at which the component must be replaced
C. The minimum thickness based on the design code calculation including required corrosion
allowance
D. The minimum thickness based on the design code calculation not including required corrosion
allowance
REF-API-510 (3.1.63)
100 for localized corrosion , it is important that examinations are conducted using
A. Scanning methods
B. Digital thickness measurements
C. Electromagnetic techniques
D. Ultrasonic shear wave techniques
RER-API-571 (3.14.7)
101 an inspector finds a thin area in the shell of pressure vessel. The corroded areas is a groove above
the demister pad. The groove crosses a longitudinal butt weld seam. When evaluating the required
thickness of shell more than 1 in. (25.4 mm) away from the longitudinal butt weld the joint efficiency to
use is.
A. 0.70
B. 0.85
C. 0.90
D. 1.00
REF-API-510 (7.4.5)
102 a written material verification programmed indicating the extent and type of PMI is to be as
outlined the API document?
A. 510
B. 572
C. 577
D. 578
REF-API-510 (5.9.1)
A. Alteration has design implications beyond the scope of the existing data reports
B. Alteration are defined by the requirements of jurisdictional authorities
C. Adding a reinforced nozzle to either head of the vessel is always an alteration
D. Major repairs are always considered alteration, while routine repairs are not considered
alterations.
REF-API-510 (3.1.1)
104 which of the following may be used to establish the maximum allowable worksing pressure for
continued use of a pressure vessel without rerating?
REF-API-510 (7.3.1)
REF-API-510 (5.1.3)
106 what is the remaining life of a vessel corroding at rate of 0.021 in/yr (0.533 mm/yr) whwn the
inspection measurement is 0.638 in (16.2 mm/yr) and the minimum required thickness is 0.4375 in (11.3
mm) ?
A. 2.39 years
B. 4.78 years
C. 9.55 years
D. 10 years REF-API-510 ( 7.2.1)
A. A records of two consecutive CML measurements shall be used to justify the change
B. A vessel engineer should be consulted
C. A corrosion specialist should be consulted
D. Approval of authorized inspector is required
REF-API-510 (5.6.3)
108 the pressure vessel record need not contain which of the following?
REF-API-510 (5.3.5)
REF-API-510 ( 5.5.4.1.1)
110 the pressure vessel is in noncontinuous service. While out of service vessel is isolated and
protected from internal corrosion. If a risk base inspection(RBI)is not considered, the maximum internal
or on stream inspection interval shall be
REF-API-510 (6.5.1.2)