Final Bill S#4
Final Bill S#4
Final Bill S#4
Name of the Contractor : UTILITY POWER TECH LIMITED (1011806) LOA No. & Date : 4000246093 - 03.09.2020
Location : Korba Super Thermal Power Proj Name of the work : UPL Combined Biennial job
contrac
Service Entry Sheet No. : 1003188318 Period of measurement : 26.12.2022 - 05.01.2023
SES Short Text : FINAL BILL Date of Run : 12.05.2023
Generated By : SHYAM LAL MAHANAND
1. Work has been done/completed as per specification, scope of work, Drawing and Terms & Conditions of the contract.
2. Method of measurement is as mentioned in the contract
3. It is certified that the works billed in the invoice have been executed and all relevant checks/ inspection and associated tests as per approved FQP and contract technical
specification have been carried out and results are in conformity. Surveillance on all category #C# checks have been carried out and found in conformity. Documentation and
records as per approved FQP have been maintained.
4. Reconciliation Statement for owner issue materials is enclosed/ No owner's materials were issued to the agency.
5. Agency has complied with all statutory requirements including Labour Law Compliance.
6. Applicable Taxes & Duties may be deducted.
7. Retention and net payable amount as per detail below.
8. Details of deduction for Retention, Security deposit, Penalty and recovery of HRR, electricity, Hiring of equipment etc as per details given below.