2023.05.04 Daily Progress Report For 7.9 MW Ground-Mounted PV Power Plant

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

2023.05.04 Site Updates for 7.

9 MW Ground - Mounted PV
Power Plant
Assessment:
7.9 MW Ground - Mounted PV Power Plant • Drilling of the center of the concrete blocks prior to the installation of
rebars for the pedestal.
2023.05-04
• Welding and Installation of H-Beam to the Concrete Blocks.
• Installation of Mounting structures in Lines 20 & 21.
• Installation of PV modules in Line 18.
Area 2 • Inspection of PV Modules in Line 16 & 17.
• H-Beam Inspection for Lines 8A & 9A.
• Chipping of Rocky side at Hillside portion where Line 20-22 are located.

Installation and Alignment of PV


Modules at Line 18 ( Afternoon
Time ).
Inspection of Mounting Structures
7.9 MW Ground - Mounted PV Power Plant
In Line 18: Torqueing ( 70 Nm ) and
2023.05.04 checking the angle of inclination.
Morning time

Area 2
7.9 MW Ground - Mounted PV Power Plant
2023.05-04

Area 2

Inspection of PV Modules at Line


16 & 17.
7.9 MW Ground - Mounted PV Power Plant
2023.05.04

Area 2

Starting Chipping of the rocky side


at the hillside portion.
7.9 MW Ground - Mounted PV Power Plant Checking of H-Beam distances
2023.05.04 from center to center and its
plumbness.

Area 2
7.9 MW Ground - Mounted PV Power Plant Installation of Mounting Structures
2023.05.04 for Area 3: line 1
Assessment:
• Drilling of the center of the concrete blocks prior to
the installation of rebars for the pedestal.
• Welding and Installation of H-Beam to the Concrete
Blocks.
• H-Beam inspection for Area 3: Line 5
• Installation of Mounting structures in Line 3 ( with no
railings yet).

Area 3
7.9 MW Ground - Mounted PV Power Plant
2023.05.04

Installation of Mounting Structure


with Rails yet in line 3.

Area 3
7.9 MW Ground - Mounted PV Power Plant
Assessment:
2023.05.04
• Drilling on the center of the concrete blocks in
preparation for the installation of H-Beams.
• Disassembling of formworks in Inverter House 1.
Inspection of H-Beam’s distances • Inspection of H-Beam distances and Plumbness
and plumbness in Line 8. in Line 8.
• Installation of H-Beams in area 4.

Area 4
END