2023.05.04 Daily Progress Report For 7.9 MW Ground-Mounted PV Power Plant
2023.05.04 Daily Progress Report For 7.9 MW Ground-Mounted PV Power Plant
2023.05.04 Daily Progress Report For 7.9 MW Ground-Mounted PV Power Plant
9 MW Ground - Mounted PV
Power Plant
Assessment:
7.9 MW Ground - Mounted PV Power Plant • Drilling of the center of the concrete blocks prior to the installation of
rebars for the pedestal.
2023.05-04
• Welding and Installation of H-Beam to the Concrete Blocks.
• Installation of Mounting structures in Lines 20 & 21.
• Installation of PV modules in Line 18.
Area 2 • Inspection of PV Modules in Line 16 & 17.
• H-Beam Inspection for Lines 8A & 9A.
• Chipping of Rocky side at Hillside portion where Line 20-22 are located.
Area 2
7.9 MW Ground - Mounted PV Power Plant
2023.05-04
Area 2
Area 2
Area 2
7.9 MW Ground - Mounted PV Power Plant Installation of Mounting Structures
2023.05.04 for Area 3: line 1
Assessment:
• Drilling of the center of the concrete blocks prior to
the installation of rebars for the pedestal.
• Welding and Installation of H-Beam to the Concrete
Blocks.
• H-Beam inspection for Area 3: Line 5
• Installation of Mounting structures in Line 3 ( with no
railings yet).
Area 3
7.9 MW Ground - Mounted PV Power Plant
2023.05.04
Area 3
7.9 MW Ground - Mounted PV Power Plant
Assessment:
2023.05.04
• Drilling on the center of the concrete blocks in
preparation for the installation of H-Beams.
• Disassembling of formworks in Inverter House 1.
Inspection of H-Beam’s distances • Inspection of H-Beam distances and Plumbness
and plumbness in Line 8. in Line 8.
• Installation of H-Beams in area 4.
Area 4
END