SECTION 26 05 41 Underground Electrical Construction
SECTION 26 05 41 Underground Electrical Construction
SECTION 26 05 41 Underground Electrical Construction
SECTION 26 05 41
UNDERGROUND ELECTRICAL CONSTRUCTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of
underground ducts and raceways, and precast manholes and pullboxes to
form a complete underground electrical raceway system.
B. The terms “duct” and “conduit” are used interchangeably in this section.
1.2 RELATED WORK
A. Section 07 92 00, JOINT SEALANTS: Sealing of conduit penetrations.
B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:
Requirements that apply to all sections of Division 26.
C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS:
Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents.
D. //Section 31 20 00, EARTH MOVING// //Section 31 20 11, EARTH MOVING
(SHORT FORM)//: Trenching, backfill, and compaction.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS.
B. Coordinate layout and installation of ducts, manholes, and pullboxes
with final arrangement of other utilities, site grading, and surface
features.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11,
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following
requirements:
26 05 41 - 1
11-01-22
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with
drawings and specifications.
b. Submit information on manholes, pullboxes, ducts, and hardware.
Submit manhole plan and elevation drawings, showing openings,
pulling irons, cable supports, cover, ladder, sump, and other
accessories.
c. Proposed deviations from the drawings shall be clearly marked on
the submittals. If it is necessary to locate manholes, pullboxes,
or duct banks at locations other than shown on the drawings, show
the proposed locations accurately on scaled site drawings, and
submit to the //Resident Engineer// //COR// for approval prior to
construction.
2. Certifications: Two weeks prior to the final inspection, submit the
following.
a. Certification by the manufacturer that the materials conform to
the requirements of the drawings and specifications.
b. Certification by the Contractor that the materials have been
properly installed, connected, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions,
supplements, and errata) form a part of this specification to the extent
referenced. Publications are referenced in the text by designation only.
B. American Concrete Institute (ACI):
Building Code Requirements for Structural Concrete
318-19/318M-19..........Building Code Requirements for Structural
Concrete & Commentary
MNL-66-20...............ACI Detailing Manual
C. American National Standards Institute (ANSI):
77-17...................Underground Enclosure Integrity
D. American Society for Testing and Materials (ASTM):
C478/C478M-20...........Standard Specification for Precast Reinforced
Concrete Manhole Sections
C858-19.................Underground Precast Concrete Utility Structures
C990/C990M-09...........Joints for Concrete Pipe, Manholes and Precast
Box Sections Using Preformed Flexible Joint
Sealants.
E. National Electrical Manufacturers Association (NEMA):
26 05 41 - 2
11-01-22
26 05 41 - 3
11-01-22
26 05 41 - 4
11-01-22
2. Rigid metal conduit: UL 6 and NEMA RN1 galvanized rigid metal, half-
lap wrapped with 10 mil PVC tape.
2.4 GROUNDING
A. Ground Rods and Ground Wire: Per Section 26 05 26, GROUNDING AND BONDING
FOR ELECTRICAL SYSTEMS.
2.5 WARNING TAPE
A. 4-mil polyethylene 75 mm (3 inches) wide detectable tape, red with black
letters, imprinted with “CAUTION - BURIED ELECTRIC CABLE BELOW” or
similar.
2.6 PULL ROPE FOR SPARE DUCTS
A. Plastic with 890 N (200 lb) minimum tensile strength.
PART 3 - EXECUTION
3.1 MANHOLE AND PULLBOX INSTALLATION
A. Assembly and installation shall be per the requirements of the
manufacturer.
1. Install manholes and pullboxes level and plumb.
2. Units shall be installed on a 300 mm (12 inches) thick level bed of
90% compacted granular fill, well-graded from the 25 mm (1 inch)
sieve to the No. 4 sieve. Granular fill shall be compacted with a
minimum of four passes with a plate compactor.
B. Access: Ensure the top of frames and covers are flush with finished
grade.
C. Grounding in Manholes:
1. Ground Rods in Manholes: Drive a ground rod into the earth, through
the floor sleeve, after the manhole is set in place. Fill the sleeve
with sealant to make a watertight seal. Rods shall protrude
approximately 100 mm (4 inches) above the manhole floor.
2. Install a No. 3/0 AWG bare copper ring grounding conductor around the
inside perimeter of the manhole and anchor to the walls with metallic
cable clips.
3. Connect the ring grounding conductor to the ground rod by an
exothermic welding process.
4. Bond the ring grounding conductor to the duct bank equipment
grounding conductors, the exposed non-current carrying metal parts of
racks, sump covers, and like items in the manholes with a minimum No.
6 AWG bare copper jumper using an exothermic welding process.
SPEC WRITER NOTE: Remove paragraphs below
if not required by project scope. Include
sump pump circuit in manholes subject to
26 05 41 - 5
11-01-22
//D. Manhole Lighting: Provide NEMA 3R lighting switch mounted no more than
600 mm (2 feet) from top of ladder and a 13 W LED wet-listed luminaire
in manhole. Provide dedicated 20 mm (0.75 inch) direct-buried conduit
and conductors to nearest electrical panelboard.//
//E. Sump Pump: Provide 120V cord and plug connected sump pump complete with
float switch, thermal overload protection, and GFCI receptacle mounted
in NEMA 3R boxes in manhole. Provide dedicated 20 mm (0.75 inch) direct-
buried conduit and conductors to nearest electrical panelboard.//
3.2 TRENCHING
A. Refer to //Section 31 20 00, EARTH MOVING// //Section 31 20 11 EARTH
MOVING (SHORT FORM)// for trenching, backfilling, and compaction.
B. Before performing trenching work at existing facilities, a Ground
Penetrating Radar Survey shall be carefully performed by a certified
technician to reveal all existing underground ducts, conduits, cables,
and other utility systems.
C. Work with extreme care near existing ducts, conduits, and other
utilities to avoid damaging them.
D. Cut the trenches neatly and uniformly.
E. For Concrete-Encased Ducts:
1. After excavation of the trench, stakes shall be driven in the bottom
of the trench at 1.2 M (4 feet) intervals to establish the grade and
route of the duct bank.
2. Pitch the trenches uniformly toward manholes or both ways from high
points between manholes for the required duct line drainage. Avoid
pitching the ducts toward buildings wherever possible.
3. The walls of the trench may be used to form the side walls of the
duct bank, provided that the soil is self-supporting and that the
concrete envelope can be poured without soil inclusions. Forms are
required where the soil is not self-supporting.
4. After the concrete-encased duct has sufficiently cured, the trench
shall be backfilled to grade with earth, and appropriate warning tape
installed.
F. Individual conduits to be installed under existing paved areas and roads
that cannot be disturbed shall be jacked into place using rigid metal
conduit, or bored using plastic utilities duct or PVC conduit, as
approved by the //Resident Engineer// //COR//.
26 05 41 - 6
11-01-22
26 05 41 - 7
11-01-22
13. Keep ducts clean of earth, sand, or gravel, and seal with tapered
plugs upon completion of each portion of the work.
14. Spare Ducts: Where spare ducts are shown, they shall have a nylon
pull rope installed. They shall be capped at each end and labeled as
to location of the other end.
15. Duct Identification: Place continuous strip of warning tape
approximately 300 mm (12 inches) above ducts before backfilling
trenches. Warning tape shall be preprinted with proper
identification.
16. Duct Sealing: Seal ducts, including spare ducts, at building
entrances and at outdoor terminations for equipment, with a suitable
non-hardening compound to prevent the entrance of foreign objects and
material, moisture, and gases.
17. Use plastic ties to secure cables to insulators on cable arms. Use
minimum two ties per cable per insulator.
B. Concrete-Encased Ducts:
1. Install concrete-encased ducts for medium-voltage systems, low-
voltage systems, and signal systems, unless otherwise shown on the
drawings.
2. Duct banks shall be single or multiple duct assemblies encased in
concrete. Ducts shall be uniform in size and material throughout the
installation.
3. Tops of concrete-encased ducts shall be:
a. Not less than 600 mm (24 inches) and not less than shown on the
drawings, below finished grade.
b. Not less than 750 mm (30 inches) and not less than shown on the
drawings, below roads and other paved surfaces.
c. Additional burial depth shall be required in order to accomplish
NEC-required minimum bend radius of ducts.
d. Conduits crossing under grade slab construction joints shall be
installed a minimum of 1.2 M (4 feet) below slab.
4. Extend the concrete envelope encasing the ducts not less than 75 mm
(3 inches) beyond the outside walls of the outer ducts.
5. Within 3 M (10 feet} of building and manhole wall penetrations,
install reinforcing steel bars at the top and bottom of each concrete
envelope to provide protection against vertical shearing.
6. Install reinforcing steel bars at the top and bottom of each concrete
envelope of all ducts underneath roadways and parking areas.
26 05 41 - 8
11-01-22
26 05 41 - 9
11-01-22
26 05 41 - 10
11-01-22
---END---
26 05 41 - 11