Item Description Qty Uni T Rate Amount GH : Proposed Fence Wall 31 Meters Long 7/1/2023

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Item Description Qty Uni Rate Amount GH¢

t
PROPOSED FENCE WALL 31 METERS LONG
7/1/2023
Excavation
A Excavate foundation trench not exceeding
1.5m deep commencing at formation level.
10 m3 40.00 400.00
B
Excavate pit to receive column bases not exceeding
1.5m deep commencing at formation level.
6 m3 45.00 270.00
C
Backfill selected excavated material around
foundation.
8 m3 15.00 123.15
D Remove surplus excavated material from site. 8 m3 15.00 116.85

CONCRETE WORK.
Plain in-situ concrete (21N/mm2 20mm aggregate)
as described in:

E Foundation 3 m3 250.00 750.00

m2
F 50mm thick blinding 7 8.50 59.50
-
REINFORCED IN-SITU CONCRETE. -
Reinforced in-situ vibrated concrete -
2
(25N/mm -20mm aggregate )as described in: -
G Column bases. 2 m3 250.00 500.00
-
H Columns. 2 m3 250.00 500.00
-
J Tie beams 2 m3 250.00 500.00
-
K Coping m3 250.00 -
-
REINFORCEMENT. -
Mild steel reinforcement round bar to BS 4449 -
L 12mm Diameter bars in column bases. 83 kg 1 .10 91.30
-
M 12mm Diameter bars in columns. 123 kg 1 .10 135.30
-
N 12mm Diameter in tie beams 110 kg 1 .10 121.00
-
P 10mm Diameter bars as links and stirrups in columns. 49 kg 1 .10 53.90
-
Q Ditto in tie beams 87 kg 1 .10 95.70
-
R Ditto in coping kg 1 .10
-
-

CFWD 3,716.70

Item Description Qty Uni Rate Amount GH¢


t
FORMWORK. BFWD 3,716.70

Formwork to:

A Vertical sides of columns. 30 m2 28.00 840.00


-
B Ditto to sides of tie beams 19 m2 28.00 532.00
-
C Ditto to sides of coping m2 2 8.00
-
BLOCKWORK. -
-
Solid sandcrete block in cement and sand -
(1:3) mortar as described in: -
D 150mm Wall. 83 m2 28.88 2,397.04
-
E Include the provisional sum of GHC 1200 for the demolishing of 1,200.00
the existing security post and foundation concrete. -
-
-
-

8,685.74
PROPOSED FENCE WALL 31 METERS LONG

Item Description Qty Uni Rate Amount GH¢


t
SUPERSTRUCTURE PENTHOUSE WORKS ORK AND CONCR TE WORK)
(BLOCKW E
7/1/2023
CONCRETE WORK
REINFORCED IN-SITU CONCRETE.
Reinforced in-situ vibrated concrete
(25N/mm2 -20mm aggregate )as described in:
A Columns 7 m3 250.00 1,750.00

B Beams 5 m3 250.00 1,250.00

C 150mm suspended roof slab 12 m3 250.00 3,000.00

D Coping 3 m3 250.00 750.00

REINFORCEMENT
Mild steel round bar reinforcement to
B. S. 4449.

E 16mm Diameter bars in columns 846 Kg 1 .10 930.60

F 16mm Diameter bars in beams 1862 Kg 1 .10 2,048.20


G 12mm Diameter bars in suspended roof slab 1887 Kg 1 .10 2,075.70

H 10mm Diameter bars as links and stirrups in columns 199 Kg 1 .10 218.90
10mm Diameter bars as links and stirrups in beams
J 498 Kg 1 .10 547.80

K Ditto in coping 163 Kg 1 .10 179.30

FORMWORK.
Sawn Formwork to:

L Vertical sides of columns. 81 m2 28.00 2,268.00

M Sides and soffits of beams 85 m2 28.00 2,380.00

N Soffit of suspended roof slab 82 m2 28.00 2,296.00

P Edges of suspended roof slab 150mm high 68 m 4 .20 285.60


Q Ditto in coping 25 m2 2 8.00 700.00

CONCRETE WORK
Carried to Summary. GH¢
20,680.10

Item Description Qty Uni Rate Amount GH¢


t
BRICKWORK AND BLOCKWORK
Solid sandcrete blockwork in cement and
sand (1:4) mortar as described in:

m2
A 125mm hollow block Wall 231 38.00 8,778.00
-
B Ditto to parapet wall 183 m2 38.00 6,954.00

BRICKWORK AND BLOCKWORK


Carried to Summary. GH¢ 15,732.00

-
SUPERSTRUCTURE PENTHOUSE WORKS (BLOCKWORK AND CONCRETE R 36,412.10
WO

Item Description Qty Uni Rate Amount GH¢


t
SUMMARY
A PROPOSED FENCE WALL 31 METERS LONG 8,685.74
B SUPERSTRUCTURE PENTHOUSE WORKS (BLOCKWORK AND CONCRETE 36,412.10
WOR

45,097.84
PENTHOUSE AND FENCE WALL