EAC Notes
EAC Notes
MARKS
Before taking up any work, the owner should know the total volume of work and its probable
cost required to carry out the proposed project. Estimating for any construction work may be
defined as the process of calculating quantities and costs of various items required in
connection with the work. An estimate is worked out from the dimensions on the drawings.
Costing is defined as the process of finding out the probable cost of work before starting that
work. It is prepared considering the standard rates at the time of making estimate.
An estimate is prepared by calculating the quantities of items from the drawings and then
multiplying them with the unit cost of concerned item. The accuracy of an estimate depends
on careful study of various dimensions on drawings, the method of estimating, consideration
of rates, probable unforeseen expenses and also quantity of tolerance for wastages.
PURPOSE
1. To determine the necessary amount of money required by the owner to complete the
proposed work. For public works, estimate is required to obtain administrative, technical
sanction and budget provision.
2. To find out quantities of materials required for their timely procurement.
3. To calculate the number of different categories of workers to be employed for timely
completion of work.
4. To check the requirement of tools, plants and equipments required.
5. To fix the completion period from the volume of work.
6. To prepare a construction schedule and arrange for funds accordingly.
7. To justify the investment from Benefit-Cost ratio. (Ideally > 1)
8. To invite tenders.
9. To prepare bills for payment.
10. An estimate of an existing property is required for its valuation.
1
11. Alterations in specifications, drawings and estimate can be done if costing of project is
above the budget available.
For any new work, the concerned department prepares proposal report regarding the cost of
work and its necessity. After studying the proposal, the department will then proceed for
‘Administrative Approval’. The Engineering Department will then prepare detailed drawings,
designs, estimates and submit the same to higher authorities for ‘Technical Sanction’.
The competent authority studies the detailed drawings, designs, estimates carefully and verify
it according to the rules stated and then provide ‘Technical Sanction’. Then the ‘Budget
Provision’ is made for the project as per the government plan. The execution of work is then
started by that contractor whose tender is selected.
ADMINISTRATIVE APPROVAL
It is the formal acceptance of the proposal for putting money in the project, given by the
concerned administrative department. The said approval also confirms that the plan suits the
suggested needs of the project. For example, Government Polytechnic, Bandra wants to
construct boys hostel in its campus. They give the details regarding number of students and
their requirements to PWD. Then, PWD prepares estimate and drawing on preliminary basis
which is formally accepted by GPB. The administrative approval remains in force for five
years. This approval is required for new/original works only. Once the administrative
approval is obtained, the proposal goes into the second important phase known as ‘Technical
sanction’.
TECHNICAL SANCTION
2
Chief Engineer has full powers to grant Technical Sanction.
Superintending Engineer can sanction a work up to 15 lakhs.
Executive Engineer can sanction a work up to 5 lakhs.
BUDGET PROVISION
Every year the estimates are prepared in different divisional offices and then submitted to the
circle office of SE. Based on these estimates, raw materials, organisational set up, the total
cost for execution of work is calculated. The office of CE prepares the annual budget on the
basis of proposal received from SE. These budget statements are then submitted to ministerial
level for sanctioning finance. This approval of sanctioning finance is termed as ‘Budget
Provision’. The Budget Provision remains in force till 31st March of sanctioned year and
allotted amount may revise time to time.
TYPES OF ESTIMATE –
1. APPROXIMATE ESTIMATE
2. DETAILED ESTIMATE
A detailed estimate is the calculation of quantities and costs of all items and materials that
would be used in finishing the construction project. It differs from an initial approximate
estimate by the mere concern of detailing of all the items. It is usually done after finalizing
the drawings. Quantities are calculated from the dimensions of all items given in the drawing
3
and are written in a format called as Measurement sheet. These quantities are then transferred
to another format known as Abstract sheet in which, the cost of each item is calculated by
taking the product of quantity and the unit rate of that item. Expenses for miscellaneous
provisions are added to the final cost of all items. Thus, the total cost of project is determined.
This is the most accurate method. Such a detailed estimate is made for Administrative
approval, Technical sanction, Budget provision and also for the contract document.
1. REVISED ESTIMATE
It is a detailed estimate for revised quantities and rates of items originally provided in
estimate. It is accompanied with a comparative statement abstract showing variation of
quantities, rates, amount for each item of work as compared with original estimate. This
comparison also states the reason of its variation side by side. A revised estimate is prepared
and submitted for fresh Technical sanction. It is prepared:-
1. When a sanctioned estimate is likely to exceed by more than 5%
2. When expenditure of work exceeds by more than 10% of Administrative approval (for
work more than 5 lakhs)
3. When there are material deviations from original proposal (not structural in nature)
4. When it is found that sanctioned estimate is more than actual requirement.
2. SUPPLEMENTARY ESTIMATE
While a work is in progress, some changes or additional works due to material deviations of
structural nature may be necessary. An estimate is then prepared to include all such works.
4
This is known as supplementary estimate. The method of preparing supplementary estimate is
similar to detailed estimate and it should be accompanied by a full report of circumstances
stating its necessity. The abstract must show amount of original estimate and the total of
sanction required including the supplementary amount.
When a work is partially abandoned and the estimated cost of remaining work is less than
95% of original work or, when there are material deviations and changes in design which may
cause substantial saving in estimate then, the amount of original estimate is revised. A
supplementary and revised estimate is then prepared for taking fresh Technical sanction.
After completion of a work, it is necessary to maintain the same for its proper function. An
estimate is prepared for this purpose considering items which require renewal, replacement,
repair etc. Such detailed estimate is referred as Repair and Maintenance estimate. For
buildings this includes, white washing, colour washing, painting, plaster repair, minor repairs
etc. For road work it includes, patch repair, renewal, berms repair, repair of bridges and
culverts. In no case, the amount of such estimate should increase more than 1.5% to 2% of the
capital cost of building.
5. RENOVATION ESTIMATE
5
An estimate prepared to provide all the renovation items is termed as a renovation estimate. In
this estimate, not all the items from the original detailed estimate are required. Only those
items which are essentially required for uplifting the condition of building are considered.
6
ROLES AND RESPONSIBILITY OF ESTIMATOR
A building estimator is an individual who quantifies the materials, labour and equipment
needed to complete a construction project. The roles and responsibilities of an estimator are:-
Items of an estimate should be listed as per the sequence of execution so that, an estimator
may imagine the progress of construction works and can arrange the items accordingly.
7
8. Steel work
9. Plastering
10. Flooring
11. Lime terracing for roof / RCC slab
12. White washing and Colour washing
PRINCIPLE OF UNITS
MODES OF MEASUREMENT
EARTHWORK
8
Earthwork in excavation m3
Surface dressing m2
Puddling m3
Quarrying of stones m3
Blasting of rock m3
CONCRETE
Lime concrete m3
DPC m2
BRICKWORK
Brickwork masonry m3
STONEWORK
Stone masonry m3
9
Stone slab in roof, shelve, sill, stone chajja (thickness specified) m2
WOOD WORK
Sawing of timber m2
Panel work m
STEEL WORK
Threading cm
Welding, soldering cm
Railing m
10
Iron grill, collapsible gate m2
Rolling shutter m2
ROOFING
Timber roofing m2
Thatch roofing m2
Pointing m2
Distempering m2
Painting, Varnishing m2
11
Painting letters and figures numbers
Coal tarring m2
FLOORING
MISCELLANEOUS WORKS
1. Measurement shall be item wise for the finished item of work and its description shall
include materials, transport, labour, fabrication, hoisting, tools and plants, overheads,
shape, size, design and specifications.
2. While recording measurements, the order shall be in the sequence of length, breadth and
height or depth or thickness.
3. All works shall be measured net subject to following tolerances unless otherwise stated:-
a) Dimensions shall be measured to the nearest 0.01 m.
b) Areas shall be measured to the nearest 0.01 m2.
c) Cubic contents shall be measured to the nearest 0.01 m3.
d) Weights shall be measured to the nearest 0.01 Kg.
4. Same type of work under different conditions and nature shall be measured separately
under separate items.
5. The bill of quantities shall fully describe materials, proportions and workmanship.
6. In case of structural concrete, brickwork, stone masonry, the following categories shall be
considered for measuring separately with height:-
a) Foundation to Plinth level.
12
b) Plinth level to First floor level.
c) First floor level to Second floor level and so on.
d) Parapet is measured with corresponding lower floor.
1. No deductions shall be made for ends of joists, beams, posts etc. and openings less than 0.5
m2 each and no addition shall be made for reveals, jambs, soffits, sills etc. of these
openings.
2. For openings more than 0.5 m2 but less than 3 m2 each, deduction shall be made for one
face only and the other face shall be allowed for jambs, soffits and sills which shall not be
measured.
3. In case of openings of area above 3 m 2 each, deduction shall be made for both faces of
openings and the jambs, sills shall be measured and added.
4. When the two faces are plastered with different mortars or if one side is plastered and the
other is pointed then, the deduction shall be made for the outer face only.
Painting of doors and windows should be measured closed and flat in m 2 including edges,
frames, cleats etc. Different types of doors and windows shall be grouped under one item and
areas of uneven surfaces shall be covered into equivalent area by multiplying the flat
measured area with a multiplying factor (on each side) as given below:-
13
Partly panelled and partly glazed 1
Flush door 1
Guard bars, balustrades, grating, railing, grills 1 (for painting all over)
General or Brief specification forms a general idea for the project. It describes the nature and
class of work along with names of materials that are to be used.
1. FOUNDATION AND PLINTH – Foundation and plinth shall be of first class brickwork
in lime mortar or 1:6 cement mortar over lime concrete or 1:4:8 cement concrete.
2. DAMP PROOF COURSE – DPC shall be of 2.5 cm thick cement concrete in 1:1.5:3
proportion, mixed with 1 Kg of water proofing compound per bag of cement and painted
with two coats of bitumen.
4. ROOFING – Roof shall be of RCC slab with an insulation layer and lime concrete
terracing above, supported over RS joists or RCC beams as required. Height of rooms shall
be more than 3.7 m (12 feet).
5. FLOORING – Drawing room and dining room floors shall be of mosaic (terrazo).
Bathroom and WC floors and dado work shall be of ceramic tiles. Floors of bedroom shall be
coloured and polished of 2.5 cm cement concrete over 7.5 cm lime concrete.
6. FINISHING – Inside and outside walls shall be of 12 mm cement lime plastered 1:1:6
proportion. Drawing room, dining room and bedroom shall be distempered inside and other
14
rooms white washed inside with 3 coats. Outside shall be snowcem coloured with 2 coats
over 1 coat of white wash.
7. DOORS AND WINDOWS – Frames shall be of seasoned teak wood. Shutters shall be of
teak wood 4.3 cm thick panelled. All fittings shall be of brass. Doors and windows shall be
painted 2 coats with high class enamel paint over 1 coat of priming. Windows shall be
provided with iron grills.
The rates are variable from place to place and time to time even within the same state. To
facilitate preparation of estimates and to serve as a guide in deciding the rates of various
items, a schedule of rates is maintained in Engineering departments. These rates are in the
form of printed booklet and are called as DSR. This booklet is revised every year due to
changes in cost of labour and material. Refer www.mahapwd.com for downloading it. DSR
provides following two types of rates for works:-
COMPLETED RATES – This is the rate of an item which includes charges for materials,
transportation, storage, labours, tools, machineries, water charges and contractor’s profit.
LABOUR RATES – It is the labour component of an item which includes charges to be paid
to different categories of labours like head mason, mason, mazdoor, coolie, bhisti etc.
15
MEASUREMENT SHEET
ABSTRACT SHEET
FACE SHEET
Sr.
Particulars Amount
No
2. Rs _______________________
Estimated cost of abstracted items (first floor)
3. Rs _______________________
Total cost for ground and first floor
+
4. Rs _______________________
Water supply & sanitary charges @___ % (4-
8%) +
5. Rs _______________________
6. Rs _______________________
16
Total cost of all items
8. Rs _______________________
Add 5% contingencies +
9. Rs _______________________
10. Rs _______________________
17
18
19
CHAPTER 2 – APPROXIMATE ESTIMATES – 6 MARKS
In this method, all costs of a unit quantity such as per kilometre for highway, per meter of
span for bridge, per classroom for school building, per bed for hospital, per litre for water
tank etc. are considered first and the estimate is prepared by multiplying the rate per
corresponding unit by with the number of units in the structure.
This estimate can be prepared quickly but, it requires records of current unit rates of similar
designed structures having similar specifications in that particular locality. Government
works are executed through different engineering departments. Each department is entrusted
to undertake particular categories of work and it also maintains the unit cost for those works.
This method is adopted to prepare preliminary estimates mainly for public works. Following
considerations are made for the preparation of an estimate by this method:-
a) Variation of price level
b) Change in specification and location of site
c) Number of units provided in the structures (more the units, less is the rate and vice versa)
d) Soil conditions etc.
20
Approximate cost of a new structure = (Number of service units in the new structure x Rate
per service unit of an existing structure)
Rate per service unit of an existing structure = (Total construction cost of existing
structure / Number of service units in the existing structure)
Service units for:-
Road / Highway – per kilometre
Bridge – per meter of span
School – per classroom / per student
Hospital – per bed
Water tank – per litre
Cinema theatre – per seat
Stadium – per seat
Reservoir – per litre
Dam – per meter length
Prison – per cell
Office / Commercial complex – per cubical / per room / per office unit
Hotel – per room
Hostel – per student / per room
Stable – per animal
Mall / Shopping complex – per gala / per shop / per showroom / per store
Apartment – per flat / per tenement
Godown / Factory / Railway platform – per bay
Parking stand – per vehicle
This estimate is prepared on the basis of plinth area of building and the rate is derived from
the cost of a similar building in same locality having similar specifications, heights and
construction. Plinth area estimate is calculated by finding plinth area of new building and
multiplying it with the plinth area rate. The plinth area should be calculated for covered area
by considering external dimensions of the building at floor level. Courtyard and other open
areas should not be included in the plinth area. This estimate is only approximate / rough and
is a preliminary estimate to know the approximate cost of structure in advance. For a multi-
storeyed building, plinth area estimate is prepared for each storey (floor) separately.
21
To calculate plinth area of a building from given floor area or carpet area, add extra 20% to
40% to the same floor area or carpet area for walls, circulation, waste etc.
Approximate cost of a new building = (Plinth area of new building x Plinth area rate of an
existing building)
Plinth area rate of an existing building = (Total construction cost of the existing building /
Plinth area of that existing building)
Cube rate estimate is a preliminary or an approximate estimate and is prepared on the basis of
cubical contents (volume) of a building. The cube rate is derived from the cost of similar
building in the locality having similar specifications and construction.
The approximate cost of a new building is calculated by finding volume (length x width x
height) of that building and then multiplying it with the cube rate of an existing building in
the same locality with similar specifications. The length and width should be taken as external
dimensions of building at floor level and height should be taken from top of floor level to top
of roof level. This height should be taken half-way for the sloped roof. For multi-storeyed
building, the height is considered from top of one floor level to the top of upper floor level.
Foundation, plinth and parapet above the roof are not taken into account for finding the
cubical content.
Cube rate estimate is the most accurate method as compared to Plinth area rate estimate
because, the height of building is also considered in this method.
Approximate cost of a new building = (Volume of new building x Cube rate of an existing
building)
Cube rate of an existing building = (Total construction cost of the existing building /
Volume of that existing building)
In this method,
Approximate cost of new structure = (Number of bays in proposed structure x Rate of one
such bay)
22
Bays are compartments or similar portions of a structure. When the area of a structure
consists of similar cabins or parts such as godown, factory shades, railway platform etc.
which have been built up with intermediate columns or with roof trusses on walls, placed at
equal distances with the same roofing on top of those supporting members then, the area may
be divided from centre to centre of supports. Each such division may be treated as a bay.
Consider a godown 6 m wide and 15 m long with roof trusses provided at 3 m centre to centre
will have (15/3) = 5 portions / parts / compartments or bays of equal dimensions – 6 m x 3 m.
For its extension with 2 more bays,
Here, Rate of one bay = (Total cost of construction / Number of bays) which can be
determined from previous estimate.
This is the most reliable approximate estimate that can be made. Following points should be
considered for using this method:-
a) End bay should be considered separately due to its end wall (gable wall).
b) Current rate per bay should be worked out from previous recorded rate.
c) The location, specifications and drawings should be the same.
In this method, approximate total length of walls is found out in running meters and this total
length multiplied by the rate per running meter of wall gives a fairly accurate cost. For this
method, the structure may be divided in two parts:-
a) Foundation including plinth and
b) Superstructure
The running meter rate for foundation and superstructure should be calculated first and these
rates should be multiplied with the total length of walls. To find the running meter rate for
foundation, the approximate quantities of items such as excavation, foundation, brickwork
upto plinth and damp proof course are calculated per running meter and by multiplying with
the rates of these items, the rate per running meter is determined. Similarly for superstructure,
the rate per running meter is determined from the approximate quantities of brickwork, wood
works, roof, floor finishing etc. For using this method, plan of structure should be available.
23
APPROXIMATE ESTIMATE FOR:-
From the above survey reports, maps and data, approximate estimate is prepared per ‘km’
basis by adding following heads:-
i) Cost of earthwork in excavation, embankment, hauling etc. is worked out by using contour
map.
ii) Cost of bridges and culverts is calculated by multiplying its span by cost per meter span of
similar existing structure.
iii) Cost of sub-base consisting of soling and edging according to nature of soil selected is
worked out for road width per ‘km’.
iv) Cost of base-course including premix carpet is worked out per ‘km’ basis.
v) Cost of boundary stones / pillars is taken as lumpsum per ‘km’.
vi) Total cost of heads i) to v) is calculated.
vii) Contingencies - 15% & work charged establishment - 5% are added to above total cost.
viii) Cost of permanent land is added finally to work out the approximate total estimated cost
of the road project.
24
RAILWAY PROJECT
Main items of work are foundation, gauge, sleeper, ballast, cutting and filling, bridges,
crossings, gradient etc. Railway estimates are prepared by knowing the cost ‘per km’ of
recently constructed similar railway line.
BRIDGES / CULVERTS
Approximate estimate of bridges are prepared on the basis of ‘per m’ span. It depends on
roadway, nature of bridge, depth and type of foundation etc. For the calculation of
approximate cost, ‘per m’ rate of a similar bridge is considered. For culverts, approximate
cost may be determined ‘per m’ span or by per number of culverts having different span.
Alternatively, cost of bridge and culvert can also be worked out according to sub-structure
and superstructure.
IRRIGATION PROJECTS
There are different systems of irrigation. But in general the method of preparing approximate
estimates involves the following steps:-
1) Statements of objects – It should be ascertained whether the project is for single purpose
i.e. to serve only one purpose or multiple purpose project i.e. serve more purposes. (Like
Irrigation, Hydroelectric power, water supply etc.)
2) Collection of data – To arrive at reasonable decision from the preliminary estimate
reliable data (like physical, hydrologic, geological, agricultural etc.) to serve the objects are
collected and furnished to prepare the approximate estimate.
3) Projections of planning - The future needs should be evaluated. The true economical
demand in future period is estimated.
4) Project Formulation – Comprehensive list of all the possible alternative units should be
prepared and defined the boundary conditions which restrict the project. In the Catalogue all
the possible project units along with the alternative plans for each project unit is indicated.
25
5) Project Evaluation –
∙ Preliminary estimate for each of the catalogued project units are prepared by comparison of
cost method.
∙ The approximate cost of the proposed units is found by modifying the known cost of similar
units constructed previously in accordance with one particular cost index figure.
∙ Approximate estimated cost of units of irrigational canals may be prepared per kilometre
basis depending on the capacity of canal or multiplying the commanded area in hectares of
canal by approximate average cost per hectare.
∙ From alternative units the most efficient unit whose benefit cost ratio is more than one, may
be recommended for construction.
∙ An amount for contingency (normally 10%) is added to the cost of project.
∙ For overheads as percentage (usually 10%) cost of the approximate estimate is included in
the estimate.
∙ At last the cost for land acquisition (normally 12%) is added to frame the total approximate
estimated cost of a project.
The approximate cost may be evaluated on the basis of project area or on the basis of
population of project area. For the first case, project area in ‘km 2’ is multiplied by existing
rate of a similar project. For the second case, total projected population is worked out and is
multiplied by existing average cost per capita for similar type of project.
i) Area served by the project: In this case, the total area covered by the project is worked
out in hectares or in sq. km. Then to prepare approximate estimate, the project area in
hectares or sq. km is multiplied by the existing rate of similar project per hectares or sq. km.
ii) Population served by the project: In this case, the total population to be served by the
project is worked out. Then to prepare approximate estimate total projected population is
multiplied by the existing cost per capita for similar type of project.
26
To serve any other loads for industries or institutions, their individual load is worked out and
converted to equivalent area or population. The per capita cost is widely variable according to
density of population, location of different zones, demand of water per capita and existing
facilities in case of water supply project.
2. Prepare an estimate for 3 span bridge of 40 m each, the cost of existing bridge is Rs.
40,000/- per meter. (Answer – Rs. 4800000/-)
1m Rs. 40000
120 m ?
3. The plinth area of a proposed building is 390 sq. m. The known cost of construction for
similar structure is Rs. 1935000 having plinth area 215 sq. m. Calculate approximate cost
of proposed building. (Answer – Rs. 3510000/-)
27
390 m2 ?
4. The cost of construction of Govt. Polytechnic Nanded Building is 2 crores for a capacity of
500 students and area of construction about 2000 m2. Prepare approximate estimate of a
newly proposed Govt. Polytechnic Building for 1200 students with the area 5000 m2.
(Answer – Rs. 5 crore Plinth area rate method)
(Answer – 4.8 crore Service unit method)
5. The cost of construction of school building is 2.50 crores for a capacity of 600 students and
area of construction is 1600 m2. Prepare approximate estimate of a newly proposed school
building for 1500 students with the area 5000 m2. Use plinth area method. (Answer
– Rs. 78125000/-)
28
5000 m2 ?
Area calculation
Proposed building
No. of classroom = 12
Area of one classroom = 50 m2
Area of all 12 classrooms 12 x 50 600 m2
Area of classrooms + Area of other = 600 + 1500
Total area
facilities = 2100 m2
29
= 1500 m2 x Rs. 4000 per m2
= Rs. 60,00,000/-
Water supply & sanitary installation
= 5% of Construction cost
= (5/100) x 6000000
= Rs. 3,00,000/-
Electric installation = 10% of Construction cost
= (10/100) x 6000000
= Rs. 6,00,000/-
Other services = 5% of Construction cost
= (5/100) x 6000000
= Rs. 3,00,000/-
Overall cost of building = Construction cost + Water supply & sanitary installation +
Electric installation + Other services
= 6000000 + 300000 + 600000 + 300000
= Rs. 72,00,000/-
Contingencies = 3% of Overall cost of building
= (3/100) x 7200000
= Rs. 2,16,000/-
Supervision charges = 8% of Overall cost of building
= (8/100) x 7200000
= Rs. 5,76,000/-
Total cost of building
= Overall cost of building + Contingencies + Supervision charges
= 7200000 + 216000 + 576000
= Rs. 79,92,000/-
8. Prepare approximate estimate of a public building having plinth area equal to 1800 sq.m.
i) Plinth area rate as Rs. 3,500/sq.m.
ii) Special architectural treatment = 3% of cost of building.
iii) Water supply and sanitary installation = 5% of cost of building.
iv) Electric installation = 14% of cost of building.
v) Other services = 5% of cost of building.
vi) Contingencies = 3% of overall cost of building.
vii) Supervision charges = 8% of overall cost of building. (Answer – Rs. 88,81,110/-)
30
9. Prepare approximate estimate for high school building from following data:
(i) Proposed plinth area = 2500 sqm.
(ii) Plinth area rate = 4000 / sqm.
(iii) Water supply charges = 3% of cost of building
(iv) Electric installation charges = 10% of cost of building
(v) Contingencies = 3% of overall cost of building
(Answer – Rs. 1,16,39,000/-)
10. Prepare approximate estimate for public building from given data:
(i) Plinth area = 2200 sqm
(ii) Plinth area rate = 3500/sqm
(iii) Electric installation charges = 8% of cost of building.
(iv) Water supply charges = 3% of cost of building
(v) Contingencies = 2% of overall cost of building
(vi) Engineer supervision charges = 4% of overall cost of building
(Answer – Rs. 90,59,820/-)
A detailed estimate is the calculation of quantities and costs of all items and materials that
would be used in finishing the construction project. It differs from an initial approximate
estimate by the mere concern of detailing of all the items. It is usually done after finalizing
the drawings. Quantities are calculated from the dimensions of all items given in the drawing
31
and are written in a format called as Measurement sheet. These quantities are then transferred
to another format known as Abstract sheet in which, the cost of each item is calculated by
taking the product of quantity and the unit rate of that item. Expenses for miscellaneous
provisions are added to the final cost of all items. Thus, the total cost of project is determined.
This is the most accurate method. Such a detailed estimate is made for Administrative
approval, Technical sanction, Budget provision and also for the contract document.
1. DRAWINGS – Drawings like plan, elevation, sections, site plan etc. are required for
preparing detailed estimate. Plans provide the horizontal dimensions (length and width or
thickness) of a structure whereas sections provide all the necessary heights or depths. These
all dimensions are used to enter in the Measurement sheet for calculating quantities of various
items.
2. SPECIFICATIONS – They specify quality, quantity, proportion of materials,
workmanship, method of execution, mode of measurement and payment for all items of work.
It is a guide for supervising the work as per the owner’s satisfaction. The rates of items
depend on specifications. Higher grade specifications cost more than the medium or low
grade specifications.
3. RATES – The rates per unit of various items of work, rates of different materials and
wages of all categories of labour are required for making a detailed estimate. These may be
taken from PWD Schedule of rates (DSR) or may be worked out by Rate analysis method.
4. UPDATED MODE OF MEASUREMENT – Modes or units of measurement of all items
of work are necessary for calculation of quantities and also for standard deductions or
additions to maintain the accuracy while preparing a detailed estimate.
5. STANDING CIRCULARS – Standard notices or circulars which specify the rules of tax
and insurance are required to find the prevailing rates if not given in the DSR.
Preparation of detailed estimate consists of working out quantities of different items of work
and then working out the cost in two stages:-
32
items in a structure are obtained after studying the drawings of that structure in detail. These
quantities are recorded in a format known as Measurement sheet. The whole work is divided
into different items of work as earthwork, concrete, brickwork etc. Details of measurement of
each item are seen from drawing and tabulated in Measurement sheet. Then calculation of
quantities like length, area, volume or numbers is done as per relevant units. This process of
working out the areas, volumes etc. is termed as squaring out.
a) Quantity of materials
b) Availability of materials
c) Transportation of materials
d) Location of site
e) Local labour charges
33
METHODS OF DETAILED ESTIMATE
In the unit quantity method, the work is divided into as many operations or items as are
required. A unit of measurement is decided. The total quantity of work under each item is
taken out in the proper unit of measurement. The total cost per unit quantity of each item is
analyzed and worked out. Then the total cost for the item is found by multiplying the cost per
unit quantity by the number of units. For example, while estimating the cost of a building
work, the quantity of brickwork in the building would be measured in cubic meters. The total
cost (which includes cost of materials, labour, plant, overheads and profit) per cubic meter of
brickwork would be found and then, this unit cost multiplied by the number of cubic meters
of brickwork in the building would give the estimated cost of brickwork.
This method has the advantage that the unit costs on various jobs can be readily compared
and that the total estimate can easily be corrected for variations in quantities.
In the total quantity method, an item of work is divided into the following five subdivisions:
a) Materials
b) Labour
c) Plant
d) Overheads
e) Profit.
The total quantities of each kind or class of material or labour are found and multiplied by
their individual unit cost. Similarly, the cost of plant, overhead expenses and profit are
determined. The costs of all the five sub-heads are summed up to give the estimated cost of
the item of work. For example, the cost of brickwork in a building would be determined as
below:
SR.
COST OF COMPONENT COST
NO.
34
Bricks Rupees
Sand Rupees
Cement Rupees
Water Rupees
4 Overheads Rupees
5 Profit Rupees
UNIT QUANTITY
TOTAL QUANTITY METHOD
METHOD
The work is divided into An item of work is divided in five categories – Material,
various items Labour, Plant, Overheads, Profit
Quantity of work for each Quantity of each type of material and labour are found and
item is calculated as per multiplied with their individual rate per unit to calculate its
proper unit of measurement individual cost
Rate per unit for each item is Cost of Plant, Overheads and Profit are determined
analysed and worked out
Quantity of an item Cost of all above five categories are added to give the
multiplied by rate per unit of estimated cost of that item
that item gives the cost of
that item
35
LONG WALL AND SHORT WALL METHOD (OUT TO OUT AND IN TO IN
METHOD OR PWD METHOD OR GENERAL METHOD OR INDIVIDUAL /
SEPARATE WALL METHOD)
In this method, measure external length of walls running in longitudinal direction generally
the long walls out to out and the internal lengths of walls running in transverse direction in to
in i.e. short walls. Calculate the quantities by multiplying the length, width, height of wall.
The same rule applies to the excavation in foundation, concrete in foundation and masonry
work. Care should be taken to note the difference in dimensions at different height due to
offset. Simply take long wall and short wall separately to measure centre to centre length of
walls from the plan. For symmetrical footings on either sides, the centre line remains same for
superstructure, plinth and foundation. This method is simple, accurate and has less chance of
mistakes.
Length of Long wall = centre to centre length of longitudinal wall + one width
Length of Short wall = centre to centre length of transverse wall – one width
36
CENTRE LINE METHOD
In this method, sum total length of centre line of walls has to be found out first for long and
short walls having same type of foundation and then quantities of an item are found out by
multiplying total centre line length with respective width and height. This length remains
same for excavation in foundation, concreting and superstructure with slight difference when
there are cross walls or number of junctions. This method is quick but requires attention and
consideration at junctions (meeting points of partition or cross walls).
For circular, rectangular, hexagonal, octagonal buildings having no inter / cross walls, this
method is quite simple. For building with junctions, deduct half width of respective item
(wall / footing) from total centre line length. If two walls come from opposite directions and
meet a wall at the same point then, there will be two junctions.
For buildings having different types of walls, each set of wall has to be dealt separately. Find
total centre line length of walls of one type and proceed in the same manner as described
above. Similarly, find the total centre line length of walls of second type and deal with this
separately and so on. It may be noted that at corners of the building where two walls are
meeting, no deduction or addition is required.
Total Centre line Length (TCL) = Addition of centre line lengths of all walls
No deduction for L shaped junctions but TCL – (0.5 x n x b) for T shaped junction
37
BAR BENDING SCHEDULE
This is a list of reinforcement bars in a tabular format showing all its details. This format
helps to calculate quantity of bars as per size, details of bending and cutting accurately at the
work site. Also, it helps to avoid confusion and facilitates checking of reinforcement works
along with fast preparation of estimates. In working drawings for RCC structures, bar bending
schedule is mentioned.
Total Total
Bar Diameter Length Weight
Shape Numbers length weight
mark (mm) (m) (Kg)
(m) (Kg)
RCC work is usually estimated under two items. The concrete work including centring,
shuttering and binding of steel bars in position is taken under one item in cubic meters and the
steel reinforcement with its bending is taken under separate item in quintal. The quantity of
steel being small, no deduction is made for steel from the volume of concrete. Binding wire is
not taken separately but included in item of RCC work. If detailed drawings are not available,
steel reinforcement is calculated approximately on the basis of percentage of concrete. The
density of steel is taken as 78.5 quintal per cubic meters or 7850 Kg per cubic meters.
38
where, D = effective depth of beam or slab = Overall depth – 2 covers
L = length of beam or slab
1 tonne = 1000 Kg and 1 quintal = 100 Kg Diameter = ϕ
39
PROVISIONS IN DETAILED ESTIMATE
CONTINGENCIES
The term contingencies indicate incidental expenses of miscellaneous character which cannot
be classified under any item. 3 to 5% of estimated cost is provided to allow for the
miscellaneous items which do not fall under any sub-heads of items of work. Such incidental
expenses are met from the amount provided for contingencies. If there is any saving against
40
the amount provided for contingencies, this amount may be utilised with sanction of
competent authority to meet the expenses of extra items.
Example – Estimate mentions Kotah flooring for staircase covering only length and width of
tread. During construction, it is desired to have nosing at the end of steps. As there is no
allocation of funds for nosing, its cost can be met from the contingencies.
Work charged establishment is the staff charged directly to works. During construction of a
building project, a certain number of supervisors, watchmen, accountants etc. are required to
be employed. Their salaries are paid from the amount of work charged establishment
provided in the estimate. 1.5 to 2% of estimated cost is considered for this purpose. The work
charged employees are temporary staff and their appointment is sanctioned by the competent
authority for a specific period. Their services are terminated at the end of sanctioned period.
Fresh sanction is taken if they are further required. However, they can be terminated at any
time but, usually one month’s notice is given.
When the engineering department takes up the work of another government department, a
percentage amount of 10 to 15% of the estimated cost is charged to meet the expenses of
establishment, designing, planning, supervision, audit etc. These percentage charges are
known as centage charges. It is also made on contributory and deposit works of local bodies,
41
private persons and others. The centage charge is provided in the estimate of work of Central
government undertaken for execution, also referred as supervision charges.
In a building work for internal electrification, sanitary and water supply arrangements, a
percentage of about 20% of estimated cost of building is provided –
Internal electrification includes electric wiring for lights, fans and plug points, brackets,
shades, holders, bulbs, switch boards etc. Excluding fans, 8% of estimated cost may be
sufficient for electrification.
Internal water supply works include water pipeline, taps, valves, fittings, fixtures, overhead
tanks etc. Whereas, sanitary works include sewer pipeline, water closets, flushing cisterns,
fittings, traps and other fixtures etc.
Cost of water supply and sanitary works, electrification may vary from 5 to 8% of building
cost. In unsewered area, an additional amount of about 3 to 4% of building cost may be
required for the provision of septic tank, soak pit etc.
For large projects, 1 to 1.5% of estimated cost is provided for purchase of tools and plants
required for execution of work. Usually, contractor has to use his own tools and plants.
PRIME COST
Prime cost is the actual cost of articles at shop and refers to the supply of articles only and not
to the carrying out of work. It is not always possible at the time of preparing estimate, to
specify the types of articles required. For example, water supply fittings, sanitary fittings,
42
door and window fittings etc. are to be decided at the time of actual fitting according to the
choice of owner / client / Engineer incharge.
For the execution of such items, a reasonable amount is kept in the estimate as Prime cost and
the same is also provided in bill of quantities of the contract.
The supply of articles will be made by contractor on receiving instructions from client’s side
regarding quality and price. The price to be paid to the contractor for prime cost articles will
be the actual price paid by him to the merchants. Contractor is not allowed any profit on
prime cost articles. While tendering, contractor should not alter the amount of prime cost, if
he does, such alteration will be ignored. Prime cost articles may be purchased directly or
through some agency. This amount is provided as lumpsum. Builder’s hardware which is not
an ordinary pattern may be taken as prime cost item.
PROVISIONAL SUM
Provisional sum is the amount provided in estimate and bill of quantities for some specialised
work to be done by a specialist firm, whose details are not known at the time of preparing
estimate. For example, installation of drinking water fountain, display fountain, lift, air-
conditioners etc. for which details may not be known while tendering and are to be done
through some specialist firm only. An amount provided in estimate and bill of quantities of
contract for such works is referred as provisional sum.
The amount paid to contractor will not be the exact amount of provisional sum but, will
depend on the arrangement made during execution as per its full information. The contractor
should not alter the amount of provisional sum while tendering, if he does, such alteration
will not be valid. The provisional sum item may be installed directly by some specialist firm.
This amount is provided as lumpsum. Some works of such nature which cannot be accurately
considered or which requires site measurement shall be described as provisional. Like
excavation, whose quantity cannot be ascertained before hand or electric service connection
as its charges by Electricity board may not be known.
PROVISIONAL QUANTITIES
When the quantities of a particular item are not certain, provisional quantities are provided
separately for such items. For this purpose, the quantities are calculated from measurements
43
on drawings with certain assumption of probable increase and are kept separately in bill of
quantities marked as provisional. For a building, if the nature of soil is uncertain and if it is
thought that extra depth of foundation will be required then, normal quantities of earthwork,
foundation concrete and brickwork will be calculated from dimensions in the drawing
whereas, their additional quantities due to probable extra depth are worked out separately,
marked as provisional quantities.
In a tender, contractor quotes rate for provisional quantities but, the payment of such
quantities is made on the completion of these items of work as actually done and measured. If
unnecessary extra depth is provided then, it will not be paid as provisional quantity. When
there is possibility of certain concrete piles required to be lengthened in position, provisional
quantities shall be provided separately for additional quantities.
BILL OF QUANTITIES
Bill of quantities or BOQ is the document made for specifying quantities of items and their
costs. It has five main components – Description of item, quantity, unit, rate per unit and cost.
This document is prepared by an estimator and it provides project specific measured
quantities of the items of work identified by the drawings and specifications in the tender
documentation. The bill of quantities is issued to tenderers for them to prepare a price for
carrying out the works. The bill of quantities assists tenderers in the calculation of
construction costs for their tender and as it means all tendering contractors will be pricing the
same quantities (rather than taking off quantities from the drawings and specifications
themselves), it also provides a fair and accurate system for tendering. The contractor tenders
against the bill of quantities, stating their price for each item. This priced bill of quantities
constitutes the tenderer's offer. As the offer is built up of prescribed items, it is possible to
compare both the overall price and individual items directly with other tenderers' offers,
allowing a detailed assessment of which aspects of a tender may offer good or poor value.
This information can assist with tender negotiations.
The term ‘spot items’ refers to the items of existing buildings that require alteration and
repair. In order for quantity surveyors to be able to price spot items, they need to be inspected
44
on site to gain an understanding of the extent of work that will be involved. A good working
knowledge of the construction technology and methodology is required to be able to write
spot items, making it easy to visualise and price accurately. In a bill of quantities, the
measurement unit will be stated as ‘Item’, although quantities may be given if they are
considered more appropriate. Items that have quantities are generally much easier for an
estimator to price. Typically, spot items will be set out in progression from location to
location in the building, as this makes monitoring and estimating easier and clearer.
The term ‘day work’ is used to denote a procedure of costing or valuing an item of work on
the basis of actual labours and materials required. Certain items of work which cannot be
measured like - a design in plaster work, plastered statue work on elevation, under water
concreting, architectural finish of a building etc. are valued and paid by day work. In such
cases, the schedule of rates of materials and different classes of labours likely to be engaged
in the work should be included in the tender. For the purpose of day work payment, the
contractor has to maintain day work records where details of various materials actually used
and details of labour working hours are kept. This day work record should be frequently
verified by Engineer incharge.
The day work prices usually include material, labour, transport, contractor’s profit, overhead
charges, tools and plants etc. Day work method of payment is usually confined to small items
of works and may be on hourly basis so that, payment may be made for actual period of work
done by labours.
NUMERICALS
1. Calculate quantities of following items for a load bearing structure as shown in figures:-
Earthwork, Plain cement concrete bed in 1:4:8 proportion (PCC),
45
Un Coursed Rubble Masonry work (UCRM) in cement mortar 1:6 proportion,
Damp Proof Course (DPC) in 1:3:6 proportion,
Brickwork in superstructure in cement mortar 1:6 proportion,
Internal plastering 12 mm thick in cement mortar 1:4 proportion,
Mosaic tiled flooring, Skirting and Reinforced cement concrete (RCC) slab.
46
3. Taking out quantities of 9 items as mentioned in question number 1 above.
47
LENGTH OF LONG WALLS
TCL = 2 ((0.3/2) + 4 + 0.3 + 4.5 + (0.3/2)) + 1 ((0.3/2) + 3.9 + (0.3/2)) + 5 ((0.3/2) + 3.3 +
(0.3/2)) = 40.4 m
48
Item Length Widt Height
Description Nos. Quantity
no. (m) h (m) (m)
1 Excavation in foundation
Second step
49
LW1 = 9.1 + 0.7 = 9.8 m 2 9.8 0.7 0.6 8.232
LW2 = 4.2 + 0.7 = 4.9 m 1 4.9 0.7 0.6 2.058
SW1 = 3.6 – 0.7 = 2.9 m 5 2.9 0.7 0.6 6.09
Third step
LW1 = 9.1 + 0.5 = 9.6 m 2 9.6 0.5 0.75 7.2
LW2 = 4.2 + 0.5 = 4.7 m 1 4.7 0.5 0.75 1.7625
SW1 = 3.6 – 0.5 = 3.1 m 5 3.1 0.5 0.75 5.8125
48.52 m3
First step
Second step
Third step
50
Length = 40.4 – (0.5 x 4 x 0.5) 1 39.4 0.5 19.70 m2
5 Brickwork in superstructure
in cement mortar 1:6 proportion
Deductions
51
For walls of Room 2 2 3.3 3.2 21.12
Item Length Widt Height
Description Nos. Quantity
no. (m) h (m) (m)
Deductions
52
42.00 m2
Deductions
53
5. Taking out quantities of 9 items as mentioned in question number 1 above.
54
6. Taking out quantities of 9 items as mentioned in question number 1 above.
55
56
8.
57
9. Work out the quantity of concrete and steel in footing for a RCC column as shown in
figure.
A1 = 1.0 x 1.2 = 1.2 m2 and A2 = 0.5 x 0.5 = 0.25 m2 (as 50 mm offset from column)
= 1316 mm = 1.316 m
= 1116 mm = 1.116 m
58
BAR BENDING SCHEDULE
10.
59
11. Work out the quantity of steel and concrete for a circular RCC column with following
data:-
Diameter of column = 600 mm, Height of column = 4500 mm, Main steel = 8 bars of
TOR steel with 12 mm diameter, Links = 6 mm diameter MS bars @ 125 mm c/c.
= 1777.63 mm = 1.77763 m
1 Main bars 8 – 12 mm ϕ @
8 4.5 36 0.89 32.04
0.89 Kg/m
12.
60
13. Prepare bar bending schedule for slab of size 6300 x 3000 mm with 150 mm thickness.
Main bars 12 mm ϕ bent up alternately are provided along short span at 150 mm c/c.
Distribution steel 6 mm ϕ is provided in long span at 200 mm c/c. All round cover is 20
mm.
Main steel length = width of slab – 2 end covers + 2 hooks + one bent i.e. (0.42 x D)
= 3222.2 mm = 3.2222 m
= 6300 – (2 x 20) + (2 x 9 x 6)
= 6368 mm = 6.3680 m
Add total four distribution bars at the top for tying with bent up bars i.e. two on each side.
14.
61
15. A RCC beam 330 mm wide, 450 mm deep and 5100 mm long is reinforced with 5 – 16
mm ϕ placed in one row. Out of 5, 3 bars are straight and two are bent up. In addition to
this 3 – 12 mm ϕ are provided at top as anchor bars. 6 mm ϕ stirrups are provided at 150
mm C/C. Overall cover provided to the beam is 25 mm. Calculate total quantity of steel
and prepare bar bending schedule.
= 5338 mm = 5.338 m
Main bent up bars length = Length of beam – 2 covers + 2 hooks + 2 bents i.e. (2 x 0.42 x D)
= 5100 – (2 x 25) + (2 x 9 x 16) + (2 x 0.42 x 400) here (450 – 2 covers = 400 mm)
= 5674 mm = 5.674 m
= 5266 mm = 5.266 m
4 Stirrups 6 mm ϕ stirrups @
35 1.504 52.64 0.22 11.58
150 mm c/c, 0.22 Kg/m
62
16.
63
17. Calculate the quantity of steel and concrete for a RCC lintel and chajja as shown in figure.
Consider all round cover as 20 mm, stirrups as 6 mm ϕ @ 100 mm c/c, chajja
reinforcement as 8 mm ϕ main steel @ 150 mm c/c and 6 mm ϕ distribution steel @ 200
mm c/c.
Concrete in lintel = 1.5 x 0.3 x 0.15 = 0.0675 m3 here (1.2 m width + 2 bearings of 0.15 m)
here (300 – 2 covers = 260 mm) and (150 – 2 covers = 110 mm)
64
= 1500 – (2 x 20) + (2 x 9 x 6) = 1568 mm = 1.568 m
65
CHAPTER 4 – RATE ANALYSIS – 12 MARKS
RATE ANALYSIS
Determination of rate per unit of a particular item from cost of material, labour and other
miscellaneous petty expenses required for its completion is known as the Analysis of rate.
PURPOSE
3. To calculate the quantity of materials and labour required for project planning.
IMPORTANCE
In rate analysis of any item, usually 10 % contractor’s profit is added. Rates of materials are
usually taken as the rates delivered at the site of work and include the cost at origin (first
cost), cost of transport, railway freight, taxes etc. If the materials are to be carried out from a
distant place (more than 8 Km) then, cost of transport is also added. As the rates of material
and labour vary from place to place therefore, the rates of different items of work also vary
from place to place. It is useful in preparing abstract as it gives rate per unit.
66
FACTORS AFFECTING RATE ANALYSIS
1. Specifications of the item which indicates the quality and proportion of materials,
methods of construction and protection of work.
2. The present material rates for the items of work upto the work site.
3. Daily wages of different categories of labours in the locality with their respective
outputs.
4. The range of lead and lift required for material deposition to carry out the item of
work.
5. Percentage charge for overheads which include insurance and the possibility of theft or
loss.
6. The range of profit and availability of water in connection with the construction work.
(Contractor’s profit, water charges, Tools & Plants, sundries, scaffolding)
7. Besides these the site condition, site organization and cost control during execution etc.
should be considered as these factors affect the cost per unit of work done at site.
8. Major factors are Material and Labour whereas Minor factors are Special equipment,
Place of work, Magnitude of work, Conditions of contract, Profit of contractor,
Miscellaneous items etc.
Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth.
This distance of 30 m and height of 1.5 m are known as normal lead and lift. Normal rate for
earthwork is for 30 m lead and 1.5 m lift. For greater (extra) lead and lift, the rates will be
higher for every unit of 30 m lead and for every unit of 1.5 m lift. The earthwork is therefore
estimated separately for every 30 m lead and for every 1.5 m lift.
Standard lead is the horizontal distance upto which the contractor will haul the excavated
material and is included in the rates of excavation. Lift is the vertical distance for the
excavated material during construction work. It is the height upto which the excavated
material is lifted.
67
OVERHEAD CHARGES
It includes general office expenses, rents, taxes, supervision and other costs which are indirect
expenses and not productive expenses on the job. The miscellaneous expenses on overheads
may be under following heads –
Overhead charges are usually 2.5 % of net cost of a unit rate and may rise upto 5 %.
Overhead charges may increase if the progress of work is delayed.
WATER CHARGES
For drinking purpose of the workers and for the work execution, arrangement of water either
by sinking tube well or by taking temporary water connection from the Municipal
Corporation becomes necessary. In order to meet these expenses, an amount of 1 % to 1.5 %
of total cost of materials and labour has been provided in the analysis of rates as water charge.
CONTRACTOR’S PROFIT
The contractor may be allowed a net profit of 6 to 8 % and the miscellaneous overhead
expenses may come to about 5 to 10 %. For overhead expenses and contractor’s profit, 15 %
of the actual cost may be reasonable amount but, it is usual practice to add 10 % for all these
under the head of profit. For small works, overhead cost may be very little.
68
PROCEDURE OF RATE ANALYSIS
To fix the rate per unit of an item like rate of 1 cubic meter of brickwork or 1 cubic meter of
concrete work etc. following sub-heads are estimated and a summation of these is the rate per
unit of an item –
Rate analysis is usually worked out for the unit of payment of particular item of work under
above mentioned heads. The cost of materials are taken as delivered at site inclusive of the
transport, local taxes and other charges. For tools and plants and miscellaneous petty items
(sundries) which cannot be accounted in details, lumpsum provision is made. A provision for
water charges about 1.5 % of total cost is made in the rate. Adding 10 % to this cost as
Contractor’s profit, the rate per unit of item of work is obtained. 10 % profit may be added
over the whole cost of labour and materials including cement and steel, if it is not specified
that these will be supplied by the department (PWD).
69
TASK WORK AND FACTORS AFFECTING TASK WORK
The capacity of doing work by an artisan or skilled labour in the form of quantity of
work per day is known as the task work or out turn of the labour.
The out turn of work per artisan varies to some extent according to size, nature, height,
situation, location of work etc.
In bigger cities where specialized & experienced labour is available, the out turn is
more than small towns and country sides.
70
Sand filling in plinth 4 m3 / mazdoor
Excavation in ordinary soil 3 m3 / beldar
Excavation in hard soil 2 m3 / beldar
Mangalore tiling 6 m2 / tile layer
Terrazo flooring 5 m2 / mason
To obtain labour cost, the number and wages of different categories of labours - Skilled,
Semi-skilled and Unskilled, namely mason or carpenter, mazdoor etc. required for each unit
of work should be known and this number is to be multiplied by the respective wage per day.
Cost of labour = Number of labours x Rate of one labour per day. Depending upon the nature
of construction work of an item, different categories of labours may be appointed and paid
according to their skills. To complete the work early, number of labours required is more. But
the rate of labour per job remains same and is independent of time of activity. To appoint
number of labours for a job depends on the experience of Engineer.
Mason 800
Mazdoor 700
Coolie 600
Bhisti 500
Painter 700
Carpenter 2000
Blacksmith 1200
71
Stone cutter 2000
Supervisor 1000
Foreman 1500
Woodwork 0.18 m3 5 15
A bullock cart can carry one tonne load. The average speed of bullock cart may be taken as
3.2 Km / hour. Around 45 minutes may be allowed for loading and unloading. Taking 8 hours
working per day, the number of trips per day can be calculated.
72
Aggregates 0.7 m3 1 m3
Sand 0.85 m3 1 m3
The estimator calculates the quantities of various materials required per unit quantity of an
item following the detailed specification and also determines its cost from local market rates.
Quantities of materials are those required per unit rate of work delivered at site and its cost
include first cost, freight, transportation, sales tax and insurance charges as arises in question.
In case when materials like cement, steel, stone chips and bitumen are supplied
departmentally then, profit on the cost of materials is not allowed but, cost of carriage from
godown to work site shall be added.
If the site is within 8 Km radius from the place of transporting materials then, transportation
charges are included in the rates of material. Transportation charges is the amount paid to
contractor, if the materials are to be carried from a distance more than 8 Km from the work
site. Rates of materials vary from place to place and the transportation charges also vary. If
the transportation charges are to be paid by the department then, these charges shall be
considered while preparing the rate analysis of item.
MATERIALS REQUIRED
Particulars Quantity
73
Standard bricks in brickwork 500 numbers / m3
Timber for partly paneled and glazed door shutter 4 cm thick 3 m3 / 100 m2
MATERIAL RATES
74
Binding wire 70 / Kg
Steel 40 / Kg
Sand 1000 / m3
Aggregates 1500 / m3
Bricks 7 / number
Cement paint 80 / Kg
Bitumen emulsion 35 / Kg
Unit 1 m3 Take 10 m3
75
Sand = 2.17 x 2 = 4.34 m3
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 62 bags 300 18600
Fine aggregate 4.34 m3 1400 6076
Coarse aggregate 8.68 m3 800 6944
Labour etc.
Mistry (Head mason) (1/3) number 700 235
Mason 2 numbers 600 1200
Mazdoor 12 numbers 500 6000
Boy or Woman coolie 20 numbers 400 8000
Bhisti (including curing) 6 numbers 400 2400
Formwork Lumpsum 1500 1500
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 51155
Add 1.5 % Water charges 511.55
Add 10 % Contractor's Profit 5115.5
Grand Total - 56782.05
Rate per cubic metre = (Grand Total / 10) = 5678.205
Unit 1 m3 Take 10 m3
76
Binding wire = 2 Kg
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 79 bags 350 27650
Sand 4.14 m3 1000 4140
Metal / Aggregates 8.28 m3 1200 9936
Steel @ 2% of concrete @ 7850 Kg per cubic metre 1570 Kg 40 62800
Binding wire 2 Kg 70 140
Labour etc.
Mistry (Head mason) (1/2) number 1000 500
Mason 3 numbers 800 2400
Mazdoor 12 numbers 700 8400
Boy or Woman coolie 20 numbers 600 12000
Bhisti (including curing) 6 numbers 500 3000
Formwork Lumpsum 1500 1500
Sundries, Tools and Plants Lumpsum 200 200
Bending, Binding, Cranking bars -
Blacksmith (II class) 12 numbers 800 9600
Mazdoor 12 numbers 500 6000
Centering and Shuttering (erect and dismantle)
Timber planks Lumpsum 1500 1500
Carpenter (II class) 10 numbers 800 8000
Mazdoor 10 numbers 500 5000
Nails - Tools and Plants Lumpsum 200 200
Total of Material and Labour - 162966
Add 1.5 % Water charges 2444.49
Add 10 % Contractor's Profit 16296.6
Grand Total - 181707.09
Rate per cubic metre = (Grand Total / 10) = 18170.709
77
BRICK MASONRY
Unit 1 m3 Take 10 m3
Add for wastage, breakage, frog filling, bonding = (0.23 x 1.15) = 0.26 m3
Add 25 % for Dry to wet volume = (0.26 x 1.25) = 0.32 m 3 = around 0.3 m3 = 30 % mortar =
3 m3 for 10 m3
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 13 bags 350 4550
Sand 2.58 m 3
1000 2580
Bricks I class 5000 numbers 8 40000
Labour etc.
Mistry (Head mason) (1/2) number 1000 500
Mason 10 numbers 800 8000
Mazdoor 7 numbers 700 4900
Boy or Woman coolie 10 numbers 600 6000
Bhisti (including curing) 2 numbers 500 1000
Scaffolding Lumpsum 1500 1500
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 69230
Add 1.5 % Water charges 1038.45
Add 10 % Contractor's Profit 6923
Grand Total - 77191.45
Rate per cubic metre = (Grand Total / 10) = 7719.145
78
STONE MASONRY
Unit 1 m3 Take 10 m3
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 18 bags 350 6300
Sand 3.6 m3 1500 5400
Stones 125 % 12.5 m3 1000 12500
Labour etc.
Mistry (Head mason) (1/2) number 800 400
Mason 16 numbers 700 11200
Mazdoor 16 numbers 500 8000
Boy or Woman coolie 8 numbers 400 3200
Bhisti (including curing) 1.5 numbers 400 600
Scaffolding Lumpsum 500 500
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 48300
Add 1.5 % Water charges 724.5
Add 10 % Contractor's Profit 4830
Grand Total - 53854.5
Rate per cubic metre = (Grand Total / 10) = 5385.45
79
VITRIFIED TILE FLOORING
Cement for paste for laying tiles and for joints = 0.2 m3 = 6 bags
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 11 bags 330 3630
Sand 2.16 m3 1400 3024
Vitrified Tiles (0.59 m x 0.605m) 100 m2 601 60100
Cement for grout in laying tiles and for joint
6 bags 330 1980
filling 0.2 m3
Labour etc.
Mistry (Head mason) 1 number 600 600
Mason 15 numbers 500 7500
Mazdoor including raking 15 numbers 400 6000
Bhisti 1.5 numbers 400 600
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 83634
Add 1.5 % Water charges 836.34
Add 10 % Contractor's Profit 8363.4
Grand Total - 92833.74
Rate per square metre = (Grand Total / 100) = 928.3374
80
PLASTERING
Add 30 % for filling joints and uneven surfaces = (1.2 x 1.3) = 1.56 m3
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Materials
Cement 9 bags 330 2970
Sand 1.74 m3 1400 2436
Labour etc.
Mistry (Head mason) (1/3) number 600 200
Mason 10 numbers 500 5000
Mazdoor including raking 15 numbers 400 6000
Bhisti (including curing) 0.75 number 400 300
Scaffolding Lumpsum 500 500
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 17606
Add 1.5 % Water charges 264.09
Add 10 % Contractor's Profit 1760.6
Grand Total - 19630.69
Rate per square metre = (Grand Total / 100) = 196.3069
81
WOODWORK FOR DOOR AND WINDOW
Take a frame of 1.2 m x 2 m door without sill and with 8 cm x 12 cm section made of Ghana
teak wood. Window of size 100 cm x 150 cm.
Rate Cost
Particulars Quantity
(Rupees) (Rupees)
Door Materials
Timber 5.48 x 0.08 x 0.12 m 0.05 m3 78252 3912.6
L = (2 x 2.14) + (1 x 1.2) = 5.48 m
Add Wastage 5 % 0.0025 m 3
78252 195.63
Shutter = (1.2 – 0.06 – 0.06) x (2.1 – 0.06) x 0.04 0.0881 m3 78252 6894.0
0.06 from 0.08 to allow for 2 cm insertion & fitting
Labour etc.
Mistry (Carpenter I class) (1/16) number 700 45
Carpenter II class (3/4) number 500 375
Coolie (helper) (1/2) number 400 200
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 4928.23
Add 10 % Contractor's Profit 492.823
Grand Total - 5421.053
Rate per cubic metre = (Grand Total / 0.05) = 108421.06
Window Materials
Timber - styles - 4 x 1.5 x 0.075 x 0.04 0.018 m 3
78252 1408.53
Top and Bottom rails - 2 x 1 x 0.075 x 0.04 0.006 m3 78252 469.51
Sash bars vertical - (2 x 1.38 x 0.04 x 0.04) 0.004 m 3
78252 313.00
insert 1.5 cm L=150 - (2 x 7.5) + (2 x 1.5) = 138 cm
Sash bars horizontal - (6 x 0.38 x 0.04 x 0.04) 0.003 m 3
78252 234.75
insert 1.5 cm L=50 - (2 x 7.5) + (2 x 1.5) = 38 cm
Add Wastage 5 % 0.002 m 3
78252 156.50
Fixtures and fittings Lumpsum 1000 1000
Labour etc.
Mistry (Carpenter I class) (1/15) number 700 47
Carpenter II class 2 number 500 1000
Coolie (helper) 1 number 400 400
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 5229.3
Add 10 % Contractor's Profit 522.93
Grand Total - 5752.24
Rate per square metre = (Grand Total / 1.5) = 3834.83
82
DAMP PROOF COURSE
Rate Cost
Particulars Quantity (Rupees) (Rupees)
Materials
Cement 22 bags 300 6600
Fine aggregate 1.125 m3 1400 1575
Coarse aggregate 2.25 m3 800 1800
Cem-seal (1 Kilogram per cement bag) 22 Kg 50 1100
Labour etc.
Mistry (Head mason) (1/3) number 700 235
Mason 8 numbers 600 4800
Mazdoor 8 numbers 500 4000
Bhisti (including curing) 1 number 400 400
Formwork Lumpsum 1500 1500
Sundries, Tools and Plants Lumpsum 200 200
Total of Material and Labour - 22210
Add 1.5 % Water charges 222.1
Add 10 % Contractor's Profit 2221
Grand Total - 24653.1
Rate per square metre = (Grand Total / 100) = 246.531
83
EARTHWORK IN EXCAVATION IN FOUNDATION INCLUDING FILLING IN
TRENCHES UPTO 30 m LEAD and 1.5 m LIFT.
84
CHAPTER 5 – ESTIMATE FOR CIVIL ENGINEERING WORKS – 12 MARKS
Cross-section of earthwork for roads, bund and canals in banking or in cutting is usually in
the form of trapezium and the quantity of earthwork may be calculated by the formula –
Cross-sectional area = Area of central rectangular portion + Area of two triangular portions
= Bd + 2 (0.5 x Sd x d)
= Bd + Sd2
S:1 is the ratio of side slopes as horizontal : vertical (H:V). For 1 vertical, horizontal
component is S so, for d vertical, horizontal component is Sd.
For calculation of earthwork, longitudinal section and cross section of ground are taken and
the formation level of the road is fixed. If the road is in cutting for some length and in
banking for some other length then, the excavated earth from cutting portion should be
utilized for banking portion with economical limits during the execution of work. Not to
consider this during estimation of earthwork quantities so as to avoid complicacy.
From L-section and formation line, the height of bank and depth of cutting are calculated. The
difference of RL of ground and RL of formation gives the height or depth.
85
Cross sectional figures for banking if inverted, gives cross sections for cutting. To distinguish
between cutting and filling, cutting is indicated by negative sign.
When the ground is in a longitudinal slope, the height of bank or depth of cutting will be
different at the two ends of section. Here, mean height or depth may be taken for ‘d’ and
sectional area at mid-section is taken out from mean height or depth. This sectional area at
mid-section multiplied by length gives the quantity of earthwork. Different types of soils as
sandy, clayee, rock etc. are estimated separately as their rates vary.
L = Length of section
B = Formation width
Volume Volume
RL of RL of d
Distance dm Bdm Sdm2 Bdm+Sdm2 Length of of
Formation Ground
(m) (m) (m ) (m )
2 2
(m )
2
(m) Filling Cutting
(m) (m) (m)
(m3) (m3)
86
MEAN SECTIONAL AREA METHOD
Sectional area at the two ends may be calculated and the mean of two sectional areas is taken
out. Sectional area at the mid-section or the mean sectional area multiplied by length gives the
quantity of earthwork.
L = Length of section
B = Formation width
Volume Volume
RL of RL of d
Distance Bd Sd2 Bd+Sd2 (Am) Length of of
Formation Ground
(m) (m 2
) (m 2
) (m 2
) (m 2
) (m) Filling Cutting
(m) (m) (m)
(m3) (m3)
87
PRISMOIDAL FORMULA METHOD
L = Length of section
B = Formation width
Quantity = L / 3 (First area + Last area + 4 (Sum of even areas) + 2 (Sum of odd areas))
First area = A1, Last area = An, Even area = A2, A4, A6 whereas, Odd area = A3, A5, A7 so on.
In case of Simpson’s rule, it is necessary to have an odd number of sectional areas and even
number of divisions. If there is an even number of sections then, the end strip should be
treated separately and volume of remaining strips should be calculated by the Simpson’s rule.
Simpson’s rule gives more accurate result as compared to Trapezoidal formula.
88
TRAPEZOIDAL FORMULA METHOD
When a series of cross-sectional areas are calculated at equidistant points then, considering
L = Length of section, the volume may be worked out by the Trapezoidal formula –
First area = A1, Last area = An, Remaining areas = A2, A3, A4, A5, A6, A7 and so on.
Trapezoidal formula gives an approximate result when compared to the Simpson’s rule. To
use Simpson’s rule or Trapezoidal formula, calculate the cross-sectional areas by the regular
procedure – Bd + Sd2.
In rural areas, in factories and in unsewered urban and semi urban areas where adequate water
supply is available from pipe, well or any other source, a septic tank is suitable for disposal of
night soil. Water is required for the flow of night soil from laterine to septic tank and for the
functioning of tank. Septic tank is so designed that the sewage is retained in the tank for 24
hours during which period certain biological decomposition by the action of anaerobic
bacteria takes place which breaks and liquifies the night soil leaving small quantity of solid
which settles down in the form of sludge at the bottom of tank and clear water flows out of
the septic tank. The effluent from domestic septic tank is usually disposed by absorption in
soil through soak pit or subsoil drains. Earthwork in excavation, PCC floor and foundation,
Brickwork of walls, Plastering with water proofing compound on floor and walls, RCC slab,
Ventilation pipe, Cowl, Manhole, Inlet and outlet pipe, Iron foot steps, Baffle wall, Sloping
floor, Tee, Bend are some of the items to be estimated for a Septic tank.
89
DETAILED ESTIMATE FOR COMMUNITY WELL
Wells are extremely important to all societies. In many places wells provide a reliable and
ample supply of water for home uses, irrigation, and industries. Where surface water is
scarce, such as in deserts, people couldn't survive and thrive without groundwater, and people
use wells to get at underground water. A bored well is constructed using an earth auger,
which bores a hole into the earth. The bore hole is then lined or cased with masonry, concrete
curbing, or casing. A dug well is constructed by excavating or digging a hole, generally
several feet in diameter, down to the water table. Earthwork in excavation in soft soil, hard
murum, hard rock is calculated separately for each standard lift, RCC ring beam, Brickwork
or Stonework in circular wall usually done is steps with decreasing thickness upwards, PCC
safety barrier at top, Flooring on sides of well, Sinking of well, Plastering, CI steps, Manhole,
RCC slab are some of the items usually estimated for a Community well.
90
USE OF COMPUTER / SOFTWARES / PROGRAMS FOR PREPARING DETAILED
ESTIMATES OF CIVIL ENGINEERING WORKS
Computer is most effective in reducing time and labour when a number of repetitive
calculations are required to be done. Such a situation is often encountered in estimating and a
computerised approach to such a problem can save time, not sacrificing accuracy at the same
time. Engineers use the FORTRAN code to develop their many programs and the knowledge
of above language is a pre-requisite of computerised estimation.
A programmer accesses a digital computer to solve a particular problem with the help of
programming language which is translated by computer to machine language. A computer
program is basically a series of statements meaning certain instructions.
1. Estimator 2.0
2. QE Pro
3. 2001 CD Estimator
4. ACEIT
5. AEST 1 Auto Estimator
6. Chief Estimator
7. DENEB Construction accounting and estimating
8. Directlink estimating
9. Esti-Mate
10. Pro-Est
11. Win-Est
12. TECS
13. BIDDAY
14. BIDFAX 2000
15. Bid-Builder
16. Bid Master
17. CONAK Trackpoint
18. CORECON Application Suite 3.0
19. Cost works
20. Estimating Advantage
91
21. Heavy Bid
22. ICE 2000
23. Job/Power Estimating
24. Paydirt
25. Precision collection
26. QSM System
NUMERICALS
50 mm ϕ CI vent pipe
MH
BM 300 mm thick
1.8 m x 5.4 m x 2 m 2m
100
mm
100 mm 5.4 m
200 mm
PCC 1:3:6
92
Item Length Width Height
Description Nos. Quantity
no. (m) (m) (m)
28.8 m2
93
9 50 mm diameter cast iron cowl at
10 Manhole 1 1 number
20 x 20 cm opening
0.712 m3
2.
94
3. Prepare detailed estimate for a community well as shown in figure.
95
Item Length Width Height
Description Nos. Quantity
no. (m) (m) (m)
1 Earthwork in excavation
Soft soil
161.77 m3
Hard murum
166.67 m3
Hard rock
181.37 m3
96
First step 1 (π/4) x (7.92 – 6.62) x 3.7 54.78 m3
117.92 m3
Section OR
Section OR
4. Calculate earthwork volume by mid sectional area method using following details:-
Width of formation = 10 m, Formation level at starting chainage = 52.00 m
Side slope = 1:1.5 for cutting and 1:2 for filling, Falling Gradient = 1 in 200
97
Chainage
36
(m) 0 40 80 120 160 200 240 280 320 400 440 480 520
0
RL of
ground 5 50. 50. 51. 51.
50.9 50.8 50.7 51.2 51.3 51 50.6 50.7 50.9
(m) 1 5 6 4 2
98
RL of formation of first chainage is 52.00 m and falling gradient is 1 m vertical for 200 m
horizontal so, for 40 m chainage it will be a falling slope of (40 x 1) / 200 = 0.2 m fall in
successive chainages. Like –
40 0.2 51.8
80 0.2 51.6
99
280 50.6 51.4 -0.8 8 0.96 8.96 6.6 40 264
320 50.4 51.3 -0.9 9 1.215 10.215 9.5875 40 383.5
360 50.2 51 -0.8 8 0.96 8.96 9.5875 40 383.5
400 50.0 50.6 -0.6 6 0.54 6.54 7.75 40 310
440 49.8 51.2 -1.4 14 2.94 16.94 11.74 40 469.6
480 49.6 50.7 -1.1 11 1.815 12.815 14.8775 40 595.1
520 49.4 50.9 -1.5 15 3.375 18.375 15.595 40 623.8
1830.05 3077.96
Chainage
0 30 60 90 120 150 180
(m)
RL of
112.00 111.80 111.70 111.60 111.50 111.30 111.40
ground (m)
This numerical is solved here first by mean sectional area method to find the areas of all cross
sections and then these areas will be used to substitute in the Prismoidal formula –
100
= (10) (21.60 + 150.6 + 48.08)
= (10) (220.30)
= 2203 m3
Same numerical is solved here by Trapezoidal formula,
7. Calculate the quantities of items – Excavation and PCC for the Community well as shown
in figure.
101
8. Calculate quantities of items – Excavation, PCC, Burnt brick masonry for the Septic
tank as shown in figure.
9. Calculate quantities of items – Excavation, PCC, Burnt brick masonry and RCC slab
for the Septic tank as shown in figure.
102
10. Calculate earthwork volume by using the following details:-
Width of formation = 10 m
Formation level at starting chainage = 52.00 m
Side slope = 1:1.5 for cutting and 1:2 for filling
Falling Gradient = 1 in 200
Chainage
0 60 120 180 240 300 360 420 480 540
(m)
RL of
ground 73.12 72.44 71.86 72.08 71.3 70.8 70.54 70.82 70.96 71.5
(m)
RL of
Formation 72.42 71.94 71.46 70.98 70.5 70.8 71.1 71.4 71.7 72
(m)
103
Mid-sectional area method
104
Filling Volume by Prismoidal formula
= L / 3 (First area + Last area + 4 (Sum of even areas) + 2 (Sum of odd areas) )
= (60 / 3) (0 + 5.5 + 4 (6.2272 + 8.4952) + 2 (6.4728) )
= 1546.7 m3
Cutting Volume by Trapezoidal formula
= L / 2 (First area + Last area + 2 (Sum of all remaning areas) )
= (60 / 2) (7.735 + 0 + 2 (5.375 + 4.24 + 12.815 + 8.96) )
= 2115.45 m3
Filling Volume by Trapezoidal formula
= (60 / 2) (0 + 5.5 + 2 (6.2272 + 6.4728 + 8.4952) )
= 1436.71 m3
105