Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
84 views

QC Program

The document outlines quality control procedures for construction projects, including: 1. Progress inspection reports that are conducted regularly to document weather, work activity, compliance with specifications, and any non-conformities. 2. Responsibilities of field quality control engineers to carry out inspections, record quality issues, and ensure any deviations are addressed. 3. Procedures for recording inspection findings, discussing potential non-conformances with management, and issuing work suspension or non-conformance reports if needed. 4. Requirements for inspecting, testing and approving all construction works to confirm compliance with contract and specification requirements.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views

QC Program

The document outlines quality control procedures for construction projects, including: 1. Progress inspection reports that are conducted regularly to document weather, work activity, compliance with specifications, and any non-conformities. 2. Responsibilities of field quality control engineers to carry out inspections, record quality issues, and ensure any deviations are addressed. 3. Procedures for recording inspection findings, discussing potential non-conformances with management, and issuing work suspension or non-conformance reports if needed. 4. Requirements for inspecting, testing and approving all construction works to confirm compliance with contract and specification requirements.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

QUALITY CONTROL PROGRAM

PROGRESS INSPECTION REPORT

The purpose of this procedure is to define Progress Inspection Report carried out by the Project Engineer
In charge.

The procedure shall apply to all works for the construction of all permanent works (and major temporary
works if deemed necessary) irrespective of the location being at site, or in the fabrication yard.

RECORDS ARE AS FOLLOWS:


• Weather
• Work Activity
• Work Description
• Person Responsible
• Compliance with specifications
• Discussions held
• Non-conformities
• Photographs appended
And any data deemed required
IT shall be numbered by the date of inspection being formatted as (Year-Month-Date) – Sequence number.
i.e. 2023-001

Furthermore, Work Suspension Notice shall be served to prevent possible Non-Conformity or observed
deviation on ongoing activity.

Non-conformance Report shall be issued based on the deviation and severity of onsite infraction.

1 RESPONSIBILITIES

3.1 Field QC Engineers


• Carry out and oversee activities that needs improvement and corrections throughout the
duration of the works.
• Records quality issues
• Ensures any deviations or potential non-compliances
• Conducts daily, or as deemed necessary, to identify and to resolve quality issues
2 PROCEDURE

5.1 Recording of Information and Review


Field Engineer shall document in progress inspection call out especially non-conforming items
that require immediate attentions.

The findings/observations (potential non-conformances) that require immediate attention will be


discussed with the Project Management Team.

6. QUALITY RECORDS

The following documents generated under this procedure are quality records:
(1) Progress Inspection Report
(2) Progress Inspection Report Registry
(3) Work Suspension Notice
(4) Non-Conformance Report

INSPECTIONS, TESTING & APPROVAL OF WORK

This procedure describes the management for inspection, testing and approval of the works, in compliance
with the Project and Contract Agreements.

The procedure shall apply to all works for the construction of permanent works (and major temporary works
if deemed necessary).

Works shall be inspected and tested to confirm compliance with contract requirements, and records kept
in accordance with the contract requirements.

The objective is to set up the sequence of activities within a work operation (pre-construction, construction,
post-construction and approval of works), and associate against each activity the inspection and testing
regime in accordance with the acceptance criteria defined in the Project Agreements specifications,
Designer’s Construction Specifications and Drawings. These will also define Hold-Points and Witness
Point which require a Quality Control or Quality Assurance inspection before proceeding with follow-on
works.
1 RESPONSIBILITIES

3.1 Project Manager/ Project Engineer (Construction)


• Implement and ensure the continuing suitability and effectiveness of this procedure.
• Identify any non-conforming construction activities and dispose of according with the Quality
Procedure
• Ensures sampling and testing are carried out, with records submitted, reviewed and approved
where required.
• Ensures checklists and test records are submitted and filed in a systematic order, and in the
appropriate record files (records become as-builts).
• Inspection of Hold-Points and Witness-Points,
• Ensure Inspection checklists and the “Work Request” form are completed for works.
• Responsibility for preparing Inspection and Test Plan
• Responsibility of party undertaking the works to fulfill 100% of the inspection and testing
requirements undertaken by the subcontractors or suppliers.
• Testing by an independent party.
• Issues “Work Request” form and Inspection Checklist

2 PROCEDURE

Inspection and test plan are prepared by the Site Engineer and reviewed by the Project In-
Charge or QA Supervisor and approved by the Project Manager and Designer by means of
Request for Approval.

Inspection & test plan are developed to assist with inspections and testing requirements. It
specify the QC inspection and testing frequencies carried out by the responsible party
undertaking the works, eg. subcontractor, supplier and testing laboratory. The Quality
Assurance process are secondary checks to ensure that the Quality Control inspection and
testing has been carried out satisfactorily.

Inspection checklists shall be completed by the QC Team to provide evidence that the specified
inspections have been undertaken. Records of testing undertaken by the testing laboratory will
be generated to confirm compliance.

Upon completion of a structure or work activity, Work Requests (WR), all inspection checklists
and test reports shall be filed in a systematic order.
TESTING

Site tests will be carried out in accordance with the Works Procedure, or as otherwise defined in
the Designer’s Construction Specifications.

Test records shall be reviewed for adequacy and approved by the QA Engineer and maintained
in the appropriate files, along with the inspection checklists.

Quality Control Testing: The Project In-Charge shall ensure all testings are carried out by
testing agencies (laboratories) approved in accordance with
Project Specifications and contract requirements.

Quality Assurance Validation: The Project In-Charge and QA Engineer shall decide if third-party
testing is necessary to substantiate compliance. Considering that
QC testing is undertaken at the 100% regime, it is important to
recognise that any QA testing may be undertaken at a frequency
of 0% to 10% of the Quality Control testing.

Additional testing may be requested by the QA Engineer in the event of questionable test results
or failed test results

MOCK UP
The purpose of this procedure is to establish guidelines on how Mock-ups are conducted on site. This
Procedure will ensure products or processes will conform to specified requirements based on plans,
details, specifications, functionality, testing and acceptance criteria and other requirements that need to
be addressed before the actual construction or production of mock-up units and or products/services. The
procedure shall apply to all work activities to be done by the Contractor or its subcontractors based on the
project scope of work.

1 RESPONSIBILITES

The QA Engineer and Project In-Charge shall be responsible for implementing this procedure. The Project
In-Charge shall ensure that project mock-ups for the following items such as, but not limited to:
a. Tiles
b. Paints
c. Ceiling System
d. Wall and cladding
e. Doors and Windows
f. Railings
g. Lighting fixtures and devices

2 PROCEDURE

2.1 Initiating Mock-up Works

All items subject for mock-up will be discussed during Design Coordination Meeting.

The Project In-Charge shall arrange a meeting and discuss to the project team the preparation of
mock-ups on site. The meeting will discuss but not be limited to the following:

• Mock-up Milestone requirements


• Assignment of Subcontractors
• Approved Submittal Requirements
• Resolution of Design Issues that will affect Mock-up
• Mock-up Schedule per Activity
• Acceptance Criteria and level of workmanship
• Approval of Mock-up

All conducted mock-ups will be presented during the Design Coordination meeting, for comments
and approval.

2.2 Monitoring of Mock-up Schedule and Implementation

Proper coordination must be implemented between Project Engineer and Project Manager to ensure
that reports are prepared for monitoring of mock-up from the start to actual completion of the activity.

2.3 Approval of Mock-ups

Mock-ups have to be approved as early as possible to avoid repair or reworks on the succeeding
works. Workmanship acceptance criteria have to be agreed by all parties to prevent
misunderstanding later during handing over of the works. Acceptance has to be documented showing
the names and signatures of all parties involved.
QUALITY MANAGEMENT BY WALKTHROUGH
This procedure is to provide a guideline for the process of conducting “Quality Management by through.
Line management at all levels need to process knowledge of how to manage Quality on a day to day basis
throughout their areas of responsibility in order to control and eliminate quality issues on working progress

1 RESPONSIBILITES

3.1 Project In Charge


Responsible to ensure;
§ The requirements of this procedure are implemented on the project.
§ Monitoring is done to ensure compliance
§ This document is available to all involved personnel

3.2 Project Engineers/ Supervisors


§ Responsible to ensure that Quality Management is done and all observations and findings are resolve
according to Quality Procedures.

2 DEFINITIONS

2.1 Quality Management by Walking through – A process that takes the management team from all
levels into the work areas where they have responsibility and is meant to be both an inspection on the
implementation of QUALITY rules and procedures and learning how the workers have integrated Quality
into their daily work activities through the use of Site Workmanship Awareness Training (SWAT).

2.2 Progress Inspection Report, (PIR) – is the report generated during walk through activities

3 PROCEDURE

Quality Management by Walk Through aims to promote Quality work practices and eliminate the
number of defects or noncompliance that occur in the workplace. This proactive approach will lead to
improve Quality and lower operating costs and improve productivity for the project.

Verification of delivered material in warehouse, on-site stockyard and installed materials should be
included in the walk through inspection parameters.
The management people performing the walk around need to know that the Quality procedures are:
• Should be conducted by small groups of management representative’s ideally in groups of 3
– 4. Large groups can intimidate workers and often leads to the workers stopping work
activities.
• The group decides on what area to go to, identifies what work activities to focus on and
review previous concerns that may have been identified.
• The process can be under taken by all members of management from the project and
members of management or head offices when they are visiting projects.

The Project in charge shall be required to undertake a walk through at a minimum of twice a week (Monday
identification and Friday close out). The Sub-Contractor representative shall be expected also to undertake
walk through daily through their contract area.

Checklist during a walk through:


§ Work Request (WR)
§ Inspection Checklist
§ Validated Method Statement and Inspection & Test Plan
§ QA Bulletin Compliance
§ Correct implementation, sequence of work
§ Proper supervision
§ Proper tools used per trade
§ Measurement tools (meter tape, spirit level...)
§ Proper implementation as per survey layout

You might also like