CONSTRUCTION OF 96 NO.

S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
1 PROVINCIAL HOUSING AUTHORITY 1090 days?Jan 6 '21 Jun 30 '24
2 PHA-1 MOBALIZATION & SITE SETUP 25 days Jan 6 '21 Feb 3 '21
3 DATE OF COMMENCMENT 0 days Jan 6 '21 Jan 6 '21 1/6
4 MOBSLIZATION & SITE SETUP 15 days Jan 6 '21 Jan 23 '21

5 GENERAL SURVEY & BUILDING 25 days Jan 6 '21 Feb 3 '21

6 PHA-2 CONSTRUCTION OF 96 NO,S OF FLATS 1065 days?Feb 4 '21 Jun 30 '24


7 PHA-2.1 CIVIL WORK 1065 days?Feb 4 '21 Jun 30 '24
8 PHA-2.1.1 SUBSTRUCTURE WORK 151 days Feb 4 '21 Jul 29 '21
9 EARTHWORK EXCAVATION 21 days Feb 4 '21 Feb 28 '21

10 TRANSPORTATION OF EARTHWORK 18 days Feb 10 '21 Mar 2 '21

11 PRE.& COMPACTION OF NATURAL SURFACE 95% 15 days Mar 3 '21 Mar 20 '21
TO 100%

12 TERMITE TREATMENT 12 days Mar 21 '21 Apr 3 '21

13 GRANULAR BACKFILL 27 days Apr 4 '21 May 4 '21

14 PRE.&COMP. OF BACKFILL 30 days Apr 15 '21 May 19 '21

15 PCC 1:4:8 15 days May 20 '21 Jun 6 '21

16 REINF. FOR RCC IN RAFT 26 days Jun 7 '21 Jul 6 '21

17 FORM WORK RAFT STEEL 18 days Jun 19 '21 Jul 8 '21

18 RCC IN RAFT FOUNDATION 18 days Jul 10 '21 Jul 29 '21

19 PHA-2.1.2 SUPER STRUCTURE WORK 914 days? Jul 31 '21 Jun 30 '24
20 PHA-2.1.2.1 RCC WORK AT ALL FLOOR 914 days? Jul 31 '21 Jun 30 '24
21 PHA-2.1.2.1.1 RCC WORK AT BF 520 days Jul 31 '21 Mar 28 '23
22 SAND UNDER FLOORS & TOPPING OF 30 days Nov 20 '21 Dec 23 '21
CONCRETE

23 UNDER FLOOR PCC 1:4:8 35 days Nov 23 '21 Jan 2 '22

24 STEEL WORK AT BF 80 days Jul 31 '21 Oct 31 '21

25 FORM WORK AT BF 75 days Aug 7 '21 Nov 1 '21

26 RCC WORK FOR COLUMN/RETAINING 40 days Aug 10 '21 Sep 25 '21


WALLS

27 CONCRETE WORK FOR SLAB/BEAMS 8 days Nov 1 '21 Nov 9 '21

28 DPC RATIO 1:2 12 days Mar 15 '23 Mar 28 '23

29 RCC STAIR BF 15 days Sep 23 '21 Oct 10 '21

30 PHA-2.1.2.1.2 RCC WORK AT GROUND 399 days Nov 16 '21 Feb 23 '23
FLOOR
31 UNDER FLOOR PCC 1:4:8 40 days Jan 9 '23 Feb 23 '23

32 PCC 1:2:4 25 days Jan 9 '23 Feb 6 '23

33 STEEL WORK 75 days Nov 16 '21 Feb 10 '22

34 FORM WORK 70 days Nov 22 '21 Feb 10 '22

35 RCC COLUMNS 35 days Nov 28 '21 Jan 6 '22

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK
CONSTRUCTION OF 96 NO.S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
36 CONCRETE WORK FOR SLAB/BEAMS 10 days Feb 12 '22 Feb 22 '22

37 RCC STAIR 15 days Mar 1 '22 Mar 17 '22

38 PHA-2.1.2.1.3 RCC WORK AT 344 days Mar 1 '22 Apr 5 '23


FIRST FLOOR
39 UNDER FLOOR PCC 1:4:8 & 1:2:4 45 days Feb 13 '23 Apr 5 '23

40 STEEL WORK 78 days Mar 1 '22 May 30 '22

41 FORM WORK 75 days Mar 7 '22 Jun 1 '22

42 RCC COLUMNS 40 days Mar 13 '22 Apr 27 '22

43 CONCRETE WORK FOR SLAB/BEAMS 9 days Jun 5 '22 Jun 14 '22

44 RCC STAIR 18 days Jun 21 '22 Jul 11 '22

45 PHA-2.1.2.1.5 RCC WORK AT 2ND 284 days Jun 20 '22 May 16 '23
FLOOR
46 UNDER FLOOR PCC 50 days Mar 20 '23 May 16 '23

47 STEEL WORK 75 days Jun 20 '22 Sep 14 '22

48 FORM WORK 72 days Jun 26 '22 Sep 17 '22

49 RCC COLUMNS 38 days Jul 2 '22 Aug 14 '22

50 CONCRETE WORK FOR SLAB/BEAMS 10 days Sep 22 '22 Oct 3 '22

51 RCC STAIR 16 days Oct 10 '22 Oct 27 '22

52 PHA-2.1.2.1.6 RCC WORK AT 3RD 203 days Oct 22 '22 Jun 14 '23
FLOOR
53 UNDER FLOOR PCC 45 days Apr 24 '23 Jun 14 '23

54 STEEL WORK 76 days Oct 22 '22 Jan 17 '23

55 FORM WORK 70 days Oct 27 '22 Jan 16 '23

56 RCC COLUMNS 35 days Nov 2 '22 Dec 12 '22

57 CONCRETE WORK FOR SLAB/BEAMS 10 days Jan 24 '23 Feb 4 '23

58 RCC STAIR 18 days Feb 11 '23 Mar 2 '23

59 PHA-2.1.2.1.4 RCC WORK AT TOP 210 days Feb 22 '23 Oct 24 '23
ROOF
60 UNDER FLOOR PCC 35 days Jun 15 '23 Jul 25 '23

61 STEEL WORK 30 days Feb 22 '23 Mar 28 '23

62 FORM WORK 25 days Feb 28 '23 Mar 28 '23

63 RCC COLUMNS 25 days Mar 6 '23 Apr 3 '23

64 CONCRETE WORK FOR SLAB/BEAMS FOR 20 days Apr 4 '23 Apr 26 '23
MUMTY SLAB

65 RCC OVER HEAD WATER TANK 35 days May 9 '23 Jun 18 '23

66 ROOF INSULATION 15 days Jul 3 '23 Jul 19 '23

67 JAMBOLAN SHEET 20 days Jul 23 '23 Aug 14 '23

68 SINGLE LAYER OF TILES 40 days Aug 15 '23 Sep 30 '23

69 PARAPHET WALL / RAIN WATER PIPE 45 days Apr 27 '23 Jun 18 '23

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK
CONSTRUCTION OF 96 NO.S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
70 GREY STRUCTURE COMPLETION 20 days Oct 2 '23 Oct 24 '23

71 PHA-2.1.2.5 BRICK MASONERY 486 days Nov 28 '21 Jun 17 '23


72 BRICK MASONERY WALL BF 38 days Nov 28 '21 Jan 10 '22

73 BRICK MASONERY WALL GF 38 days Mar 16 '22 Apr 28 '22

74 BRICK MASONERY FACING GF 30 days Mar 26 '22 Apr 28 '22

75 BRICK MASONERY WALL FF 38 days Jul 9 '22 Aug 21 '22

76 BRICK MASONERY FACING FF 30 days Jul 20 '22 Aug 23 '22

77 BRICK MASONERY WALL SF 39 days Oct 22 '22 Dec 5 '22

78 BRICK MASONERY FACING SF 29 days Nov 5 '22 Dec 7 '22

79 BRICK MASONERY WALLS 3RD F 38 days Feb 21 '23 Apr 5 '23

80 BRICK MASONERY FACING 3F 30 days Mar 4 '23 Apr 6 '23

81 BEICK MASONERY WALLS TOP ROOF 34 days May 9 '23 Jun 17 '23

82 PHA-2.1.2.2 INTERNAL PLASTER 478 days Feb 3 '22 Aug 14 '23


83 INTERNAL PLASTER WORK BF 34 days Feb 3 '22 Mar 14 '22

84 INTERNAL PLASTER WORK GF 60 days Sep 17 '22 Nov 24 '22

85 INTERNAL PLASTER WORK FF 58 days Nov 26 '22 Jan 31 '23

86 INTERNAL PLASTER WORK SF 62 days Feb 1 '23 Apr 13 '23

87 INTERNAL PLASTER WORK 3F 60 days Apr 15 '23 Jun 22 '23

88 INTERNAL PLASTER WORK 4F 30 days Jul 11 '23 Aug 14 '23

89 PHA-2.1.2.3 FINISHING WORK AT 516 days Oct 27 '22 Jun 19 '24


ALL FLOORS
90 PHA-2.1.2.3.1 FINISHING WORK 210 days Apr 16 '23 Dec 16 '23
AT BF
91 SAMPLE APPROVEL FOR STAIR MARBEL 15 days Oct 2 '23 Oct 18 '23

92 STAIR MARBLE BF 15 days Oct 19 '23 Nov 5 '23

93 MOASIC FLOORING & SKIRTING BF 35 days Aug 22 '23 Oct 1 '23

94 RAILING FOR STAIR BF 14 days Nov 18 '23 Dec 3 '23

95 SAMPLE APPROVEL FOR PAINT 29 days May 21 '23 Jun 22 '23

96 WALL PUTTY ,COATING AND PAINTING 40 days Oct 4 '23 Nov 19 '23
AT BF

97 SAMPLE APPROVEL FOR DOORS 20 days Jun 13 '23 Jul 5 '23

98 INSTALLATION OF DOORS IN BF 20 days Nov 23 '23 Dec 16 '23

99 SAMPLE APPROVEL FOR WINDOWS 35 days Apr 16 '23 May 25 '23

100 INSTALLATION OF WINDOWS 15 days Nov 23 '23 Dec 10 '23

101 PHA-2.1.2.3.5 FINISHING WORK 396 days Oct 27 '22 Jan 31 '24
AT GF
102 STAIR MARBLE GF 5 days Nov 6 '23 Nov 11 '23

103 FLOOR MARBEL APPROVEL 20 days Oct 27 '22 Nov 19 '22

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK
CONSTRUCTION OF 96 NO.S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
104 FLOOR MARBLE & SKIRTING GF 120 days Dec 7 '22 Apr 25 '23

105 CLAD STONE 70 days Jul 20 '23 Oct 9 '23

106 RAILING FOR STAIR 10 days Nov 18 '23 Nov 28 '23

107 SAMPLE APPROVEL FOR TILE 45 days May 2 '23 Jun 22 '23

108 TILE WORK IN BATH 25 days Jul 11 '23 Aug 8 '23

109 WALL PUTTY ,COATING AND PAINTING 40 days Nov 20 '23 Jan 4 '24
AT GF

110 INSTALLATION OF DOORS 40 days Dec 17 '23 Jan 31 '24

111 INSTALLATION OF WINDOWS 45 days Dec 11 '23 Jan 31 '24

112 PHA-2.1.2.3.3 FINISHING WORK 288 days Apr 26 '23 Mar 26 '24
AT FIRST FLOOR
113 STAIR MARBLE 10 days Nov 12 '23 Nov 22 '23

114 FLOOR MARBLE & SKIRTING 55 days Apr 26 '23 Jun 28 '23

115 RAILING FOR STAIR 17 days Nov 29 '23 Dec 18 '23

116 TILE WORK IN BATH 40 days Aug 9 '23 Sep 24 '23

117 WALL PUTTY ,COATING AND PAINTING 40 days Jan 6 '24 Feb 20 '24
WORK

118 INSTALLATION OF DOORS 40 days Feb 1 '24 Mar 18 '24

119 INSTALLATION OF WINDOWS 45 days Feb 1 '24 Mar 24 '24

120 PHA-2.1.2.3.3 FINISHING WORK 266 days Jun 29 '23 May 4 '24
AT SECOND FLOOR
121 STAIR MARBLE 9 days Nov 23 '23 Dec 3 '23

122 FLOOR MARBLE & SKIRTING 50 days Jun 29 '23 Aug 26 '23

123 RAILING FOR STAIR 14 days Dec 19 '23 Jan 3 '24

124 TILE WORK IN BATH 38 days Sep 25 '23 Nov 7 '23

125 WALL PUTTY ,COATING AND PAINTING 35 days Feb 21 '24 Apr 1 '24
WORK

126 INSTALLATION OF DOORS 35 days Mar 19 '24 Apr 28 '24

127 INSTALLATION OF WINDOWS 35 days Mar 25 '24 May 4 '24

128 PHA-2.1.2.3.6 FINISHING WORK 241 days Aug 27 '23 Jun 2 '24
AT THIRD FLOOR
129 STAIR MARBLE 9 days Dec 4 '23 Dec 13 '23

130 FLOOR MARBLE & SKIRTING 45 days Aug 27 '23 Oct 17 '23

131 RAILING FOR STAIR 13 days Jan 4 '24 Jan 18 '24

132 TILE WORK IN BATH 35 days Nov 8 '23 Dec 18 '23

133 WALL PUTTY ,COATING AND PAINTING 30 days Apr 2 '24 May 6 '24
WORK

134 INSTALLATION OF DOORS 30 days Apr 29 '24 Jun 2 '24

135 INSTALLATION OF WINDOWS 25 days May 5 '24 Jun 2 '24

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK
CONSTRUCTION OF 96 NO.S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
136 PHA-2.1.2.3.7 FINISHING WORK 211 days Oct 18 '23 Jun 19 '24
COMPLETION
137 STAIR MARBLE 6 days Dec 14 '23 Dec 20 '23

138 FLOOR MARBLE & SKIRTING 20 days Oct 18 '23 Nov 9 '23

139 RAILING FOR STAIR 9 days Jan 20 '24 Jan 29 '24

140 TILE WORK IN BATH 16 days Dec 19 '23 Jan 6 '24

141 WALL PUTTY ,COATING AND PAINTING 30 days May 7 '24 Jun 10 '24
WORK

142 INSTALLATION OF DOORS 15 days Jun 3 '24 Jun 19 '24

143 INSTALLATION OF WINDOWS 15 days Jun 3 '24 Jun 19 '24

144 PHA-2.1.2.4 EXTERNAL 397 days Mar 15 '23 Jun 19 '24


FINISHING
145 EXTERNAL PLASTER WORK RIGHT SIDE 10 days Mar 15 '23 Mar 26 '23
JOINT -1

146 EXTERNAL PLASTER WORK LEFT SIDE 10 days Mar 27 '23 Apr 6 '23
JOINT -1

147 EXTERNAL PLASTER WORK BACK SIDE 15 days Apr 8 '23 Apr 24 '23
JOINT -1

148 EXTERNAL PLASTER WORK MID SIDE 12 days Apr 25 '23 May 8 '23
JOINT-1

149 EXTERNAL PLASTER WORK RIGHT SIDE 10 days May 9 '23 May 20 '23
JOINT -2

150 EXTERNAL PLASTER WORK LEFT SIDE 10 days May 21 '23 May 31 '23
JOINT -2

151 EXTERNAL PLASTER WORK MID SIDE 15 days Jun 1 '23 Jun 18 '23
JOINT -2

152 EXTERNAL PLASTR WORK FRONT SIDE 15 days Jun 19 '23 Jul 5 '23
JOINT -2

153 PAINTING & VARNISHING 60 days Jul 24 '23 Oct 1 '23

154 CIVIL WORK COMPLETED 12 days Jun 6 '24 Jun 19 '24

155 PHA-2.1.2.6 PLUMBING WORKS 175 days Jun 25 '23 Jan 14 '24

156 APPROVEL FOR PW SAMPLES 30 days Jun 25 '23 Jul 29 '23

157 WATER SUPPLY SYSTEM 45 days Aug 10 '23 Oct 1 '23

158 SEWERAGE SYSTEM 50 days Sep 26 '23 Nov 22 '23

159 GAS FITTING /APPLIANCES 49 days Jul 25 '23 Sep 19 '23

160 CONSTRUCTION OF MANHOLES 30 days Sep 3 '23 Oct 7 '23

161 CONSTRUCTION OF SEPTIC TANK 25 days Oct 2 '23 Oct 30 '23

162 SANITORY FITTING /FIXTURES 80 days Sep 20 '23 Dec 21 '23

163 PW COMPLETED 20 days Dec 23 '23 Jan 14 '24

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK
CONSTRUCTION OF 96 NO.S FLATS AT CIVIL QUARTERS PESHAWAR(PHASE#II) {6 DAYS CALENDER IN WEEK}

ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
164 PHA-2.1.2.7 ELECTRICAL WORK 577 days Aug 17 '22 Jun 19 '24
165 DATA NETWORK SYSTEM 50 days Jun 5 '23 Aug 1 '23

166 PVC CONDUITS IN WALLS AND SLAB 122 days Aug 17 '22 Jan 5 '23

167 SAMPLE APPROVEL FOR LT SWITCH BOARD 15 days Jun 19 '23 Jul 5 '23

168 MAIN LT SWITCH BOARDS 49 days Jul 24 '23 Sep 18 '23

169 SAMPLE APPROVEL FOR TELEPHONE 25 days Jun 19 '23 Jul 17 '23
SYSTEM

170 TELEPHONE NETWORK SYSTEM 55 days Jul 30 '23 Oct 1 '23

171 SAMPLE APPROVEL FOR CCTV CAMERA 25 days Sep 9 '23 Oct 7 '23
SYSTEM

172 CCTV CAMERA SYSTEMS 84 days Oct 22 '23 Jan 27 '24

173 FIRE ALARM & FIRE EXTANGUISHER SYSTEM 29 days Nov 20 '23 Dec 23 '23

174 SAMPLE APPROVEL FOR WIRING 15 days Feb 7 '24 Feb 24 '24
ACCESSORRIES

175 WIRING ACCESSORRIES 65 days Mar 13 '24 May 27 '24

176 APPROVEL FOR LT LINE 35 days Feb 18 '24 Mar 28 '24

177 LT CABLE 60 days Mar 31 '24 Jun 8 '24

178 CABLE TRAY 25 days Jan 15 '24 Feb 12 '24

179 WIRNG IN WALL AND SLAB 150 days Jul 1 '23 Dec 21 '23

180 UNDER FLOOR & WALL BOXES 120 days Oct 3 '22 Feb 19 '23

181 LT MAIN / SUB DISTRIBUTION BOARDS 60 days Feb 29 '24 May 8 '24

182 LIGHT FIXTURES AND LIGHTS 55 days Jan 15 '24 Mar 18 '24

183 LIGHT PROTECTION SYSTEM 18 days Jan 27 '24 Feb 15 '24

184 FAN ALL TYPES 13 days Mar 31 '24 Apr 14 '24

185 EARTHING SYSTEMS 18 days May 21 '24 Jun 10 '24

186 DISTRIBUTION TRANSFORMER 19 days May 12 '24 Jun 2 '24

187 ELECTRICAL WORK COMPLETE 15 days Jun 3 '24 Jun 19 '24

188 PHA-2.1.2.8 HVAC SYSTEMS 27 days Apr 15 '24 May 15 '24

189 EXHAUST AIR FANS 27 days Apr 15 '24 May 15 '24

190 PROJECT COMPLETION 10 days Jun 19 '24 Jun 30 '24


191 HANDING TAKING OF PROJECT 10 days Jun 19 '24 Jun 30 '24

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Jun 20 '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PROJECT MANAGER ARE


MYB NESPAK