Project Shedule 2
Project Shedule 2
Project Shedule 2
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
1 PROVINCIAL HOUSING AUTHORITY 1090 days?Jan 6 '21 Jun 30 '24
2 PHA-1 MOBALIZATION & SITE SETUP 25 days Jan 6 '21 Feb 3 '21
3 DATE OF COMMENCMENT 0 days Jan 6 '21 Jan 6 '21 1/6
4 MOBSLIZATION & SITE SETUP 15 days Jan 6 '21 Jan 23 '21
11 PRE.& COMPACTION OF NATURAL SURFACE 95% 15 days Mar 3 '21 Mar 20 '21
TO 100%
19 PHA-2.1.2 SUPER STRUCTURE WORK 914 days? Jul 31 '21 Jun 30 '24
20 PHA-2.1.2.1 RCC WORK AT ALL FLOOR 914 days? Jul 31 '21 Jun 30 '24
21 PHA-2.1.2.1.1 RCC WORK AT BF 520 days Jul 31 '21 Mar 28 '23
22 SAND UNDER FLOORS & TOPPING OF 30 days Nov 20 '21 Dec 23 '21
CONCRETE
30 PHA-2.1.2.1.2 RCC WORK AT GROUND 399 days Nov 16 '21 Feb 23 '23
FLOOR
31 UNDER FLOOR PCC 1:4:8 40 days Jan 9 '23 Feb 23 '23
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
36 CONCRETE WORK FOR SLAB/BEAMS 10 days Feb 12 '22 Feb 22 '22
45 PHA-2.1.2.1.5 RCC WORK AT 2ND 284 days Jun 20 '22 May 16 '23
FLOOR
46 UNDER FLOOR PCC 50 days Mar 20 '23 May 16 '23
52 PHA-2.1.2.1.6 RCC WORK AT 3RD 203 days Oct 22 '22 Jun 14 '23
FLOOR
53 UNDER FLOOR PCC 45 days Apr 24 '23 Jun 14 '23
59 PHA-2.1.2.1.4 RCC WORK AT TOP 210 days Feb 22 '23 Oct 24 '23
ROOF
60 UNDER FLOOR PCC 35 days Jun 15 '23 Jul 25 '23
64 CONCRETE WORK FOR SLAB/BEAMS FOR 20 days Apr 4 '23 Apr 26 '23
MUMTY SLAB
65 RCC OVER HEAD WATER TANK 35 days May 9 '23 Jun 18 '23
69 PARAPHET WALL / RAIN WATER PIPE 45 days Apr 27 '23 Jun 18 '23
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
70 GREY STRUCTURE COMPLETION 20 days Oct 2 '23 Oct 24 '23
81 BEICK MASONERY WALLS TOP ROOF 34 days May 9 '23 Jun 17 '23
96 WALL PUTTY ,COATING AND PAINTING 40 days Oct 4 '23 Nov 19 '23
AT BF
101 PHA-2.1.2.3.5 FINISHING WORK 396 days Oct 27 '22 Jan 31 '24
AT GF
102 STAIR MARBLE GF 5 days Nov 6 '23 Nov 11 '23
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
104 FLOOR MARBLE & SKIRTING GF 120 days Dec 7 '22 Apr 25 '23
107 SAMPLE APPROVEL FOR TILE 45 days May 2 '23 Jun 22 '23
109 WALL PUTTY ,COATING AND PAINTING 40 days Nov 20 '23 Jan 4 '24
AT GF
112 PHA-2.1.2.3.3 FINISHING WORK 288 days Apr 26 '23 Mar 26 '24
AT FIRST FLOOR
113 STAIR MARBLE 10 days Nov 12 '23 Nov 22 '23
114 FLOOR MARBLE & SKIRTING 55 days Apr 26 '23 Jun 28 '23
117 WALL PUTTY ,COATING AND PAINTING 40 days Jan 6 '24 Feb 20 '24
WORK
120 PHA-2.1.2.3.3 FINISHING WORK 266 days Jun 29 '23 May 4 '24
AT SECOND FLOOR
121 STAIR MARBLE 9 days Nov 23 '23 Dec 3 '23
122 FLOOR MARBLE & SKIRTING 50 days Jun 29 '23 Aug 26 '23
125 WALL PUTTY ,COATING AND PAINTING 35 days Feb 21 '24 Apr 1 '24
WORK
128 PHA-2.1.2.3.6 FINISHING WORK 241 days Aug 27 '23 Jun 2 '24
AT THIRD FLOOR
129 STAIR MARBLE 9 days Dec 4 '23 Dec 13 '23
130 FLOOR MARBLE & SKIRTING 45 days Aug 27 '23 Oct 17 '23
133 WALL PUTTY ,COATING AND PAINTING 30 days Apr 2 '24 May 6 '24
WORK
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
136 PHA-2.1.2.3.7 FINISHING WORK 211 days Oct 18 '23 Jun 19 '24
COMPLETION
137 STAIR MARBLE 6 days Dec 14 '23 Dec 20 '23
138 FLOOR MARBLE & SKIRTING 20 days Oct 18 '23 Nov 9 '23
141 WALL PUTTY ,COATING AND PAINTING 30 days May 7 '24 Jun 10 '24
WORK
146 EXTERNAL PLASTER WORK LEFT SIDE 10 days Mar 27 '23 Apr 6 '23
JOINT -1
147 EXTERNAL PLASTER WORK BACK SIDE 15 days Apr 8 '23 Apr 24 '23
JOINT -1
148 EXTERNAL PLASTER WORK MID SIDE 12 days Apr 25 '23 May 8 '23
JOINT-1
149 EXTERNAL PLASTER WORK RIGHT SIDE 10 days May 9 '23 May 20 '23
JOINT -2
150 EXTERNAL PLASTER WORK LEFT SIDE 10 days May 21 '23 May 31 '23
JOINT -2
151 EXTERNAL PLASTER WORK MID SIDE 15 days Jun 1 '23 Jun 18 '23
JOINT -2
152 EXTERNAL PLASTR WORK FRONT SIDE 15 days Jun 19 '23 Jul 5 '23
JOINT -2
155 PHA-2.1.2.6 PLUMBING WORKS 175 days Jun 25 '23 Jan 14 '24
ID Task Name Duration Start Finish Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
N J M M J S N J M M J S N J M M J S N J M M J
164 PHA-2.1.2.7 ELECTRICAL WORK 577 days Aug 17 '22 Jun 19 '24
165 DATA NETWORK SYSTEM 50 days Jun 5 '23 Aug 1 '23
166 PVC CONDUITS IN WALLS AND SLAB 122 days Aug 17 '22 Jan 5 '23
167 SAMPLE APPROVEL FOR LT SWITCH BOARD 15 days Jun 19 '23 Jul 5 '23
169 SAMPLE APPROVEL FOR TELEPHONE 25 days Jun 19 '23 Jul 17 '23
SYSTEM
171 SAMPLE APPROVEL FOR CCTV CAMERA 25 days Sep 9 '23 Oct 7 '23
SYSTEM
173 FIRE ALARM & FIRE EXTANGUISHER SYSTEM 29 days Nov 20 '23 Dec 23 '23
174 SAMPLE APPROVEL FOR WIRING 15 days Feb 7 '24 Feb 24 '24
ACCESSORRIES
179 WIRNG IN WALL AND SLAB 150 days Jul 1 '23 Dec 21 '23
180 UNDER FLOOR & WALL BOXES 120 days Oct 3 '22 Feb 19 '23
181 LT MAIN / SUB DISTRIBUTION BOARDS 60 days Feb 29 '24 May 8 '24
182 LIGHT FIXTURES AND LIGHTS 55 days Jan 15 '24 Mar 18 '24