CA-4079 Daily Progress Report 12-May-24
CA-4079 Daily Progress Report 12-May-24
CA-4079 Daily Progress Report 12-May-24
CA-4079
Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contract No : CA/4079 CPO(s): 341226, 350837, 364249, 345870 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-22-458 START DATE: 11-Nov-21 END DATE: 5-May-23
TANK ROOF TYPE: Floating Roof DIA (M): 43.90 HEIGHT (M): 17.70 PRODUCT: KLD
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 19-Dec-21 11924967 23-Dec-21 26-Dec-21 7
Bottom Plate Coupon Cutting 10-Apr-22 2022-18750 14-Apr-22 18-Apr-22 8
Internal/External Painting 10-Apr-22 12431553 8-May-22 22-May-22 42
Sampling Points 10-Apr-22 2022-22930 8-May-22 10-Aug-22 122
Hydro Test For TDS/TFS 10-Apr-22 2022-24840 8-May-22 21-Sep-22 164
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Hand Over To KNPC For De-Blinding Hand Over To KNPC For De-Blinding
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Floating Roof DIA (M): 5.780 HEIGHT (M): 5.350 PRODUCT: CHEMICAL
INSPECTION OFFERED DATE INSPECTION IAT ISSUE DATE DURATION IAT DESCRIPTION IAT No. REMARKS
START DATE
13-Nov-22 13-Nov-22 13-Nov-22 1 Preliminary Inspection 2022-28998
13-Nov-22 17-Nov-22 12-Dec-22 29 Inspection & Hydrotest 2022-30382
22-Dec-22 22-Dec-22 25-Dec-22 3 Hydrotest Witnessed 2022-30971
Works Executed Today : Work Plan for Next Working Day :
Handed Over to KNPC for De-Blinding
Contract No : CA/4079 CPO(s): 340896, 342651, 350830, 355796 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-22-264 START DATE: 1-Aug-21 END DATE: 29-Dec-22
TANK ROOF TYPE: Fixed Roof DIA (M):36.57 HEIGHT (M): 14.63 PRODUCT: F/WATER
INSPECTION OFFERED DATE INSPECTION IAT ISSUE DATE DURATION IAT DESCRIPTION IAT No. REMARKS
START DATE
11-Aug-21 24-Mar-22 225 Preliminary Inspection 2022-17650
16-Oct-21 17-Mar-22 152 Internal And External Painting 2022-17006
14-Dec-22 Internal & External Painting 2022-30545
Works Executed Today : Work Plan for Next Working Day :
Handed Over to KNPC for Deblinding
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE : Fixed Roof DIA (M) : 29.016 HEIGHT (M) : 15.24 PRODUCT : SEA WATER
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Contract No : CA/4079 CPO(s): 350834, 352983, 357630, 359853, 361083 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-61-464 START DATE: 24-Dec-21 END DATE: 24-Dec-22
TANK ROOF TYPE: Floating Roof DIA (M): 43.891 HEIGHT (M): 19.507 PRODUCT: MOGAS
Contract No : CA/4079 CPO(s): 327461, 328607, 363335, 364253, 345183 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-61-600 START DATE: 6-Nov-20 END DATE: 8-Jan-23
TANK ROOF TYPE: Fixed Roof DIA (M): 43.891 HEIGHT (M): 14.630 PRODUCT: HSD
Contract No : CA/4079 CPO(s): 360929, 355793, 360929, 367337 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-22-454 START DATE: 26-Jun-22 END DATE: 26-Apr-23
TANK ROOF TYPE : Cone Roof DIA (M): 18.288 HEIGHT (M): 12.192 PRODUCT: HGO/WAXY
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Contract No : CA/4079 CPO(s): 350835, 355000, 364885, 374685 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-22-253 REVISION NO: 0 START DATE: 4-Jan-22 END DATE: 19-Jun-23
TANK ROOF TYPE: FLOATING ROOF DIA (M): 46.94 HEIGHT (M): 19.51 PRODUCT: NAPTHA
Release by KNPC Operational Planning Team 4-Jan-22 4-Jan-22 1 4-Jan-22 4-Jan-22 100%
Dead-Stock Transfer 5-Jan-22 31-Jan-22 26 5-Jan-22 31-Jan-22 100%
Tank Blinding Works 1-Feb-22 4-Feb-22 3 6-Feb-22 6-Feb-22 100% 5 Days Delayed Due to Blinding activities delayed by mechanical Maintenance
Gas Freeing & Stripping 14-Feb-22 20-Feb-22 6 15-Feb-22 20-Feb-22 100%
De-Sludging Works 21-Feb-22 27-Feb-22 6 21-Feb-22 27-Feb-22 100%
Washing & Cleaning Works 28-Feb-22 3-Mar-22 3 28-Feb-22 2-Mar-22 100%
Preliminary Inspection 4-Mar-22 6-Mar-22 2 6-Mar-22 6-Mar-22 100% 2 Days Delayed due to Holiday
Electrical, Instrumentation & Rotating Activities 4-Mar-22 6-Mar-22 7 6-Mar-22 6-Mar-22 100%
Removal of Heat Detection Cable 7-Mar-22 10-Mar-22 3 11-Mar-22 20-Mar-22 100% 3 Days Delayed by electrical maintenance to remove cable
Removal of Roof Seal 10-Mar-22 18-Mar-22 8 21-Mar-22 31-Mar-22 100% 11 Days Delayed Due to the Heat detection cable not being removed as per the schedule
Internal Sweep Blasting & Cleaning 1-Apr-22 7-Apr-22 6 2-Apr-22 3-Apr-22 100%
External Scaffolding Erection 28-May-22 6-Jun-22 9 28-May-22 5-Jun-22 100%
External Shell Inspection 4-Apr-22 16-Apr-22 12 8-May-22 3-Jun-22 100% 34 Days Delayed in Inspection(Inspectors not available)
Inspection & Servicing of Roof Drain Line 4-Apr-22 16-Apr-22 12 8-May-22 3-Jun-22 100% 34 Days Delayed Due to Inspection Roof drain Line Serviced
Inspection of Tank 4-Apr-22 16-Apr-22 12 8-May-22 3-Jun-22 100% 34 Days Delayed in Inspection(NDT Crew not available)
Issuance of IAT(s) 10-Mar-22 11-Aug-22 154 10-Mar-22 10-Aug-22 100%
Re-Roofing Works 28-Jun-22 6-Jul-22 8 28-Jul-22 25-Aug-22 100% 28 Days Delayed Due to Pontoon sweep Blasting IAT received on 18-7-22,Got inspection clearance on 10-Aug-22
Existing Bottom Plates & Old Soil Removal 7-Jul-22 27-Jul-22 20 22-Jun-22 11-Aug-22 100% 29 Days Due to Reroofing work completion Delayed
C.P. System Installation 27-Oct-22 11-Dec-22 45 26-Oct-22 18-Dec-22 100% 28 Days Delayed Due to CP System Cable - Material Delivery Delayed by Vendor from 21-Nov-22 to 19-Dec-22
Re-Bottoming Works 12-Dec-22 16-Jan-23 35 25-Nov-22 6-Feb-23 100% 21 Days Delayed Due to CP System installation work Delayed
Access Door Reinstallation 17-Jan-23 21-Jan-23 4 23-Jan-23 4-Feb-23 100% 6 Days Delayed Due to CP System installation work Delayed
N.D.T. Inspection Works 22-Jan-23 24-Jan-23 2 29-Jan-23 6-Feb-23 100% 7 Days Due to CP System installation work Delayed
Installation of Roof Seal 21-Jan-23 29-Jan-23 8 22-Jan-23 28-Jan-23 100%
Tank Foundation Repair Works NA
Roof Drain Line Installation & Inspection 22-Jan-23 1-Feb-23 10 28-Jan-23 2-Feb-23 100% 6 Days Delayed After Roof Seal Removal
Tank Hydro Test 9-Feb-23 9-Mar-23 25 6-Feb-23 4-Mar-23 100%
Internal Washing & Cleaning Works 10-Mar-23 13-Mar-23 3 4-Mar-23 7-Mar-23 100%
TDS & TFS Lines Repair & Wrapping Works 1-Mar-23 6-Mar-23 5 2-Mar-23 7-Mar-23 100%
TDS & TFS Lines Hydro Test & Service Test 7-Mar-23 9-Mar-23 2 22-Jan-23 28-Jan-23 100%
U/G Piping Repair & Testing Works 14-Mar-23 29-Mar-23 15 24-Jan-23 22-Feb-23 100%
U/G Piping Wrapping Works 30-Mar-23 5-Apr-23 6 23-Feb-23 20-Apr-23 100%
External Shell Blasting & Painting 1-Mar-23 24-Apr-23 54 23-Feb-23 23-May-23 100%
Tank Logo & Number Stencilling Works 25-Apr-23 27-Apr-23 2 28-May-23 29-May-23 100% Preparation For Final Inspection
External Scaffolding Dismantling 28-Apr-23 8-May-23 10 1-Jun-23 4-Jun-23 100%
Removal of Roof Seal for Painting Works 14-Mar-23 19-Mar-23 5 7-Mar-23 13-Mar-23 100%
Rolling Ladder Blasting & Painting Works 20-Mar-23 28-Mar-23 7 16-Mar-23 29-Mar-23 100%
Roof Top Side Blasting & Painting Works 28-Apr-23 28-May-23 30 17-Apr-23 15-May-23 100%
Roof Under Side Blasting & Painting Works 10-May-23 30-May-23 20 18-Mar-23 15-May-23 100%
Roof Leg Pad Blasting & Painting Works 25-Apr-23 13-May-23 18 7-Mar-23 20-Apr-23 100%
Tank Bottom Blasting & Painting Works 11-May-23 5-Jun-23 25 15-May-23 13-Jun-23 100%
Re-Installation of Roof Seal 6-Jun-23 14-Jun-23 8 4-Jun-23 12-Jun-23 100%
Electrical, Instrumentation & Rotating Activities 5-Jun-23 12-Jun-23 7 7-Jun-23 14-Jun-23 100%
Tank Calibration 15-Jun-23 16-Jun-23 1 11-Jun-23 11-Jun-23 100%
Final Cleaning & Housekeeping 15-Jun-23 16-Jun-23 1 12-Jun-23 14-Jun-23 100%
Tank Foundation Repair Works 16-Jun-23 17-Jun-23 1 13-Jun-23 13-Jun-23 100%
Tank Box-Up Works 16-Jun-23 17-Jun-23 1 15-Jun-23 17-Jun-23 100%
De-Blinding Works 16-Jun-23 18-Jun-23 2 Handover to KNPC for Blinding Works
Hand-Over To KNPC Operations Team 19-Jun-23 19-Jun-23 1
[SCHEDULE REVISION STATUS]
REVISION DURATION
REVISED ACTIVITY DATE NUMBER (DAYS) REASON
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION IAT DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE ISSUE DATE (DAYS) REMARKS
TANK ROOF TYPE:FLOATING ROOF DIA (M): 49.987 HEIGHT (M): 19.51 PRODUCT: NAPTHA
Release by KNPC Operational Planning Team 12-Jul-22 12-Jul-22 1 12-Jul-22 12-Jul-22 100%
Dead-Stock Transfer 14-Jul-22 19-Jul-22 6 21-Jul-22 26-Jul-22 100% 7 Days Delayed -Awaited clearance from the electrical department
Tank Blinding Works 27-Jul-22 30-Jul-22 4 1-Aug-22 3-Aug-22 100% 3 Days Delayed- Awaited Blindlist
Gas Freeing & Stripping 11-Aug-22 15-Aug-22 5 23-Aug-22 23-Aug-22 100% 12 Days Delayed-Due to delay in CTRA and non availability of Dumping facility
De-Sludging Works 16-Aug-22 22-Aug-22 7 24-Aug-22 28-Aug-22 100% 8 Dyas Delayed-Due to Non availability of Dumping facility
Washing & Cleaning Works 23-Aug-22 28-Aug-22 6 3-Sep-22 5-Sep-22 100% 12 Days Delayed-Due to delay in earlier activities
Preliminary Inspection 28-Aug-22 29-Aug-22 3 6-Sep-22 6-Sep-22 100% 9 days Delayed -Due to delay in Tank cleaning activity
Electrical, Instrumentation & Rotating Activities 28-Aug-22 4-Sep-22 7 6-Sep-22 6-Sep-22 100%
Removal of Heat Detection Cable 7-Sep-22 9-Sep-22 3 15-Sep-23 18-Sep-23 100% 7 Dyas Delayed- Delayed by electrical maintenance to remove cable
Removal of Roof Seal NA
Internal Sweep Blasting & Cleaning 20-Sep-22 5-Oct-22 16 20-Sep-22 18-Oct-22 100% 13 days Delayed- Due to High DFT of Paint
External Scaffolding Erection NA
External Shell Inspection 6-Oct-22 8-Oct-22 3 18-Oct-22 9-Nov-22 100% 12 Days Delay- Due to delay in Sweep Blasting
Inspection & Servicing of Roof Drain Line 12-Jan-23 14-Jan-23 3 13-Dec-22 17-Jan-23 100%
Inspection of Tank 21-Nov-22 24-Nov-22 1 24-Nov-22 24-Nov-22 100%
Issuance of IAT(s) 20-Nov-22 20-Nov-22 1 24-Nov-22 24-Nov-22 100%
Minor Mechanical Repair Works on Tank Bottom NA
N.D.T. Inspection Works NA
Installation of Roof Seal NA
Tank Foundation Repair Works 4-Dec-22 12-Dec-22 7 5-Dec-22 13-Dec-22 100%
Tank HydroTest 28-Nov-22 11-Jan-23 38 6-Dec-22 5-Jan-23 100% 8 Days Delay- Due to After Completion of HydroTest of TK-TK-22-264
Inspection & Servicing of Roof Drain Line 12-Jan-23 16-Jan-23 3 15-Jan-23 17-Jan-23 100%
Internal Washing & Cleaning Works 12-Jan-23 16-Jan-23 3 7-Jan-23 12-Jan-23 100%
TDS & TFS Lines Repair & Wrapping Works NA
TDS & TFS Lines HydroTest & Service Test 29-Oct-22 30-Oct-22 2 29-Oct-22 30-Oct-22 100%
U/G Piping Repair & Testing Works 12-Jan-23 16-Jan-23 5 16-Jan-23 18-Jan-23 100%
U/G Piping Wrapping Works NA
External Shell Blasting & Painting(1 ft) 27-Apr-23 4-May-23 6 19-Feb-23 8-May-23 100%
Tank Logo & Number Stenciling Works NA
External Scaffolding Dismantling NA
Removal of Roof Seal for Painting Works 12-Jan-23 22-Jan-23 8 13-Jan-23 22-Jan-23 100%
Roof Top Side Blasting & Painting Works NA
Roof Under Side Blasting & Painting Works 23-Jan-23 13-Feb-23 18 21-Jan-23 15-Mar-23 100%
Roof Leg Pad Blasting & Painting Works 14-Feb-23 2-Apr-23 40 7-Feb-23 25-Mar-23 100%
Tank Bottom Blasting & Painting Works 3-Apr-23 26-Apr-23 20 15-Apr-23 7-May-23 100%
Re-Installation of Roof Seal 27-Apr-23 6-May-23 7 29-Apr-23 6-May-23 100%
Electrical, Instrumentation & Rotating Activities 3-Apr-23 11-Apr-23 7 8-May-23 12-May-23 20%
Tank Calibration 7-May-23 8-May-23 1 2-May-23 2-May-23 100%
Final Cleaning & Housekeeping 9-May-23 11-May-23 2 7-May-23 10-May-23 100%
Tank Box-Up Works 12-May-23 14-May-23 2 12-May-23 12-May-23 100%
De-Blinding Works 15-May-23 17-May-23 2 13-May-23 13-May-23 100%
H&-Over To KNPC Operations Team 18-May-23 20-May-23 1
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Contract No : CA/4079 CPO(s): 280671, 287251, 354417, 361452, 369228 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-34-424 REVISION NO: 1 START DATE: 20-Mar-22 END DATE: 12-Jul-23
TANK ROOF TYPE: INTERNAL ROOF/DOME ROOF DIA (M): 67.056 HEIGHT (M): 22.250 PRODUCT: GASOLINE
Blasting & Painting Works 20-Jun-23 Rev.1 39 Dust Settlement Issues due to Closed Internal Floating Roof-Exceeded Planned Blasting Duration
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 7-Aug-22 12706029 8-Aug-22 10-Aug-22 2
Partial Replacement - F/W Line 2022-29490 2-Nov-22 24-Nov-22 22
Sump Pit Drain Line Replace 2022-29612 2-Nov-22 27-Nov-22 25
External & Internal Painting 3-Nov-22 2022-29941 3-Nov-22 8-Dec-22 35
FRP lining required Roof Leg Pad 2022-29941 3-Nov-22 15-Dec-22 42 Revised IAT
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Handover to KNPC for Tank Box-up, Electrical, Instrumentation & Rotating Activities in Progress Tank Box-Up Works
Electrical, Instrumentation & Rotating Activities
TANK ROOF TYPE: Floating Roof DIA (M): 50.596 HEIGHT (M): 18.288 PRODUCT: GASOIL
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 17-Jul-22 2022-23111 10-Aug-22 17-Aug-22 31
TDS/TFS Line Replacement 8-Sep-22 2022-30383 4-Dec-22 12-Dec-22 95
Internal and External Painting 8-Sep-22 2022-31380 12-Dec-23 18-Jan-23 132
Hydro test Witnessed 26-Jan-23 2023-00911 26-Jan-23 26-Jan-23 1 Fill the Gap with Epoxy filler
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Hand Over For Tank Boxup to KNPC Electrical, Instrumentation & Rotating Activities
Electrical, Instrumentation & Rotating Activities
Contract No : CA/4079 CPO(s): 361450, 364097, 370844, 372044 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-61-534 REVISION NO: 1 START DATE: 11-Aug-22 END DATE: 24-Sep-23
TANK ROOF TYPE: FLOATING ROOF DIA (M): 49.900 HEIGHT (M): 19.507 PRODUCT: ATK
Release by KNPC Operational Planning Team 10-Aug-22 10-Aug-22 1 10-Aug-22 10-Aug-22 100%
Dead-Stock Transfer 10-Aug-22 20-Aug-22 11 13-Aug-22 18-Aug-22 100%
Tank Blinding Works 24-Aug-22 29-Aug-22 6 26-Aug-22 29-Aug-22 100%
Gas Freeing & Stripping 1-Sep-22 8-Sep-22 8 5-Sep-22 11-Sep-22 100%
De-Sludging Works 9-Sep-22 13-Sep-22 5 5-Sep-22 11-Sep-22 100%
Washing & Cleaning Works 14-Sep-22 20-Sep-22 7 12-Sep-22 15-Sep-22 100%
Preliminary Inspection 18-Sep-22 18-Sep-22 2 18-Sep-22 18-Sep-22 100%
Electrical, Instrumentation & Rotating Activities 18-Sep-22 25-Sep-22 7 18-Sep-22 18-Sep-22 100%
Removal of Heat Detection Cable 20-Sep-22 22-Sep-22 3 29-Dec-22 29-Dec-22 100% 9 Days Delay - Removal of Cable by Electrical Maintenance
Removal of Roof Seal 20-Sep-22 22-Sep-22 3 N/A
Internal Sweep Blasting & Cleaning 20-Oct-22 7-Nov-22 19 22-Oct-22 10-Nov-22 100% 3 Days - Due to Bad Weather
External Scaffolding Erection 20-Oct-22 7-Nov-22 5 22-Oct-22 10-Nov-22 100%
External Shell Inspection 13-Nov-22 14-Nov-22 2 18-Dec-22 2-Jan-23 100% 35 Days Delayed by Inspection
Inspection & Servicing of Roof Drain Line 13-Nov-22 14-Nov-22 2 18-Dec-22 2-Jan-23 100%
Inspection of Tank 13-Nov-22 14-Nov-22 2 18-Dec-22 2-Jan-23 100% 56 Days Delayed - Tank Inspection Crews not Available
Issuance of IAT(s) 15-Nov-22 16-Nov-22 1 3-Jan-23 8-Jan-23 100% 49 Days Delayed - For Issuance of IAT
Existing Tank Bottom Sketch Plates Removal 21-Dec-22 14-Jan-23 20 15-Jan-23 19-Feb-23 100%
Access Door Removal 15-Jan-23 18-Jan-23 3 11-Feb-23 12-Feb-23 100% Delay in Access Door Drawing Approval from KNPC from 19-Jan-23 to 11-Feb-23
Re-Bottoming Works 19-Jan-23 23-Feb-23 30 16-Feb-23 1-May-23 100%
Access Door Reinstallation 24-Feb-23 28-Feb-23 4 9-Apr-23 21-Apr-23 100%
N.D.T. Inspection Works 1-Mar-23 5-Mar-23 3 22-Apr-23 8-May-23 100%
Installation of Roof Seal 6-Mar-23 9-Mar-23 3 N/A
Tank Foundation Repair Works 24-Feb-23 4-Mar-23 7 1-Mar-23 11-Mar-23 100%
Inspection & Servicing of Roof Drain Line 6-Mar-23 9-Mar-23 3 26-Apr-23 7-May-23 100%
Tank HydroTest 10-Mar-23 13-Apr-23 30 9-May-23 8-Jun-23 100% 13 Days Delayed - Awaiting HydroTest Completion of Tanks TK-61-226
Internal Washing & Cleaning Works 14-Apr-23 17-Apr-23 3 8-Jun-23 14-Jun-23 100%
TDS & TFS Lines Repair & Wrapping Works 18-Apr-23 22-Apr-23 3 N/A
TDS & TFS Lines Hydro Test & Service Test 18-Apr-23 22-Apr-23 3 15-Feb-23 27-Mar-23 100%
U/G Piping Repair & Testing Works 15-Mar-23 2-Apr-23 15 14-Mar-23 27-Mar-23 100%
U/G Piping Wrapping Works 3-Apr-23 9-Apr-23 5 28-Mar-23 11-Apr-23 100%
Tank Logo & Number Stencilling Works 31-Aug-23 14-Sep-23 2 N/A
External Scaffolding Dismantling 31-Aug-23 14-Sep-23 5 28-Aug-23 28-Aug-23 100%
Removal of Roof Seal for Painting Works 27-Jun-23 4-Jul-23 8 14-Jun-23 20-Jun-23 100%
Roof Under Side Blasting & Painting Works 7-Aug-23 31-Aug-23 25 3-Jul-23 22-Aug-23 100%
Roof Leg Pad Blasting & Painting Works 17-Jun-23 31-Aug-23 40 22-Jun-23 19-Aug-23 100%
Tank Bottom Blasting & Painting Works 31-Aug-23 15-Sep-23 16 20-Aug-23 14-Sep-23 100%
External Shell Blasting & Painting(1 ft.) 12-Sep-23 21-Sep-23 9 29-Aug-23 20-Sep-23 100%
Re-Installation of Roof Seal 12-Sep-23 21-Sep-23 10 7-Sep-23 21-Sep-23 100%
Electrical, Instrumentation & Rotating Activities 12-Sep-23 21-Sep-23 7 21-Sep-23 24-Sep-23 100%
Tank Calibration 22-Sep-23 22-Sep-23 1 6-Sep-23 6-Sep-23 100%
Final Cleaning & Housekeeping Works 23-Sep-23 24-Sep-23 2 21-Sep-23 24-Sep-23 100%
Tank Box-Up Works 24-Sep-23 24-Sep-23 1 24-Sep-23 24-Sep-23 100%
De-Blinding Works 24-Sep-23 24-Sep-23 1 30-Sep-23 30-Sep-23 100% Handover to KNPC for De-Blinding Work
Hand-Over To KNPC Operations Team 24-Sep-23 24-Sep-23 1 1-Oct-23 1-Oct-23 Previous ETC :10-Oct-23
[SCHEDULE REVISION STATUS]
REVISION DURATION
REVISED ACTIVITY DATE NUMBER (DAYS) REASON
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
TANK ROOF TYPE: Cone Roof DIA (M): 10.668 HEIGHT (M): 10.973 PRODUCT: MOGAS
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DURATION REMARKS
OFFER DATE START DATE DATE (DAYS)
Preliminary Inspection 5-Oct-22 2022-26711 6-Oct-22 12-Oct-22 7
Inspection & Sump Repair 10-Nov-22 2022-30467 12-Nov-22 14-Dec-22 34
TFS/TDS Pipe Replacement 10-Nov-22 2022-30468 12-Nov-22 14-Dec-22 34
External and Internal Painting 12-Dec-22 2022-31382 20-Dec-22 18-Jan-23 37
Partial Replacement of TDS Line sections 5-Feb-23 2023-01728 5-Feb-23 7-Feb-23 2
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Hand-Over To KNPC for Box-up Tank Box-Up Works
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Fixed Roof DIA (M) : 5.791 HEIGHT (M): 7.315 PRODUCT: DM Water
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 18-Dec-22 CHECK LIST: TANK LIST
TANK NO.: TK-34-406 REVISION NO: 1 START DATE: 15/May/22 END DATE: 11-Nov-23
TANK ROOF TYPE: DOME ROOF DIA (M): 54.800 HEIGHT (M) : 32.000 PRODUCT: PROPANE
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 6-Oct-22 12947954 7-Oct-22 12-Oct-22 6
Hole& Pitting Observed on Internal Roof Annular Plates 27-May-23 2023-07186 29-May-23 29-May-23 2
External Painting 6-Jun-23 2023-07863 20-May-23 15-Jun-23 9
External Painting Under Insulation 6-Jun-23 2023-07975 20-May-23 16-Jun-23 10
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Handover To KNPC For Tank Box Up since 04-Dec-23 Tank Box-Up Works
Contract No : CA/4079 CPO(s): 355445, 359849, 360930, 363332, 374688, 387093, 391048 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 15-May-23 CHECK LIST: TANK LIST
TANK NO.: TK-61-703 REVISION NO: 6 START DATE: 11/Apr/22 END DATE: 31-Dec-23
TANK ROOF TYPE: FIXED ROOF DIA (M): 51.21 HEIGHT (M) : 16.46 PRODUCT: LFO
Tank Hydrotest 22-Jul-23 Rev.2 20 As per Tank Hydrotest Priorities (Communicated by Mail )
Tank Hydrotest-Water Filling 13-Sep-23 Rev.3 7 Delay Due to low rate of flow in Hydrotest- Water Filling
Tank Hydrotest-Water Draining 26-Sep-23 Rev.4 8 Delay Due to low rate of flow in Hydrotest- Water Draining
Tank Bottom Blasting & Painting Works 13-Nov-23 Rev.5 18 Delayed Due to Paint Material Shipment Delay
Tank Bottom Blasting & Painting Works 22-Nov-23 Rev.6 -7 Reassess of Duration as per KNPC Priority
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply : Paint Material Shipment Delay From 08-11-2023 to 15-11-2023
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 17-Jul-22 2022-22269 17-Jul-22 18-Jul-22 1
Patch Plate for Shell at Pitting location 2-Feb-23 2023-01874 2-Feb-23 9-Feb-23 7
Internal and External Painting Requirement 2-Feb-23 2023-02257 2-Feb-23 20-Feb-23 18
Contract No : CA/4079 CPO(s) : 357548, 362414, 369763, 369763, 387091, 387702 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 18-Dec-22 CHECK LIST: TANK LIST
TANK NO.: TK-22-651 REVISION NO: 4 START DATE: 23/May/22 END DATE: 18-Jan-24
TANK ROOF TYPE: DOME ROOF DIA (M): 36.576 HEIGHT (M) : 14.63 PRODUCT: DIESEL OIL
Tank Hydrotest 16-Aug-23 Rev.2 19 Hydrotest Sequence Changed as per Tank Hydrotest Priorities
Tank Hydrotest 10-Sep-23 Rev.3 32 Hydrotest Sequence Revised as per Tank Hydrotest Priorities (Second Revision)/Tank Hydrotest to be Planned after Completion of Tanks TK-61-703, TK-61-834 & TK-61-452(As per mail Confirmation)
External Shell Blasting & Painting Works 29-Nov-23 Rev.4 5 Inclement Weather - Rain & Humidity
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 19-Aug-22 2022-23300 20-Aug-22 22-Aug-22 3
Bottom Sump & TDS/TFS Repair 8-Nov-22 2022-30946 12-Dec-22 22-Dec-22 44
Tank Bottom Plate Partial Replacement 28-Dec-22 2022-31239 28-Dec-22 28-Dec-22 1
External and Internal Painting 29-Dec-22 2023-00950 22-Dec-22 24-Jan-23 27
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Hand Over to KNPC for De-Blinding Works Hand Over to KNPC for De-Blinding Works
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 18-Dec-22 CHECK LIST: TANK LIST
TANK NO.: TK-63-705B REVISION NO: 2 START DATE: 24/Feb/23 END DATE: 19-Feb-24
TANK ROOF TYPE: DOME ROOF DIA (M) : 20.000 HEIGHT (M) : 14.500 PRODUCT: OILY WATER
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 23-Mar-23 2023-02953 23-Mar-23 25-Mar-23 2
Inspection points 23-Mar-23 2023-04011 23-Mar-23 25-Mar-23 2
Bottom Repair 18-Apr-23 2023-05354 18-Apr-23 23-Apr-23 5
External & Internal coating 18-Apr-23 2023-05795 19-Apr-23 1-May-23 13
Shell and Roof Repair Works 30-May-23 2023-08237 11-Jun-23 22-Jun-23 23
SHELL COURSE MEASUREMENTS 21-Feb-24 2024-02927 21-Feb-24 22-Feb-24 1
[WORK PLAN STATUS]
Works Executed Today : Work Plan for Next Working Day :
Deblinding of Tank completed
TANK ROOF TYPE: Fixed Roof DIA (M): 4.9 HEIGHT (M): 6.09 PRODUCT: BITUMEN
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Internal Roof/Dome Roof DIA (M): 67.056 HEIGHT (M): 22.250 PRODUCT: GASOLINE
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE : Floating Roof DIA (M) :15.24 HEIGHT (M): 13.4112 PRODUCT: ATK
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Fixed Roof DIA (M): 25.207 HEIGHT (M): 16.459 PRODUCT: SOUR WATER
INSPECTION OFFERED DATE INSPECTION IAT ISSUE DATE DURATION IAT DESCRIPTION IAT No. REMARKS
START DATE
15-Jun-22 22-Jun-22 Preliminary Inspection 12528606
21-Sep-22 Internal Coating 2022-24833
24-Nov-22 Dimension Measurement 2022-29336
Works Executed Today : Work Plan for Next Working Day :
Tank Shell Dimensional Check Completed Shell Dimension Measurement
Scaffolding Erection
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Contract No : CA/4079 CPO(s) : 356125, 357540, 360597, 361453, 369762 Date of Report: 12-May-2024
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities TANK LIST
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO.: TK-14-101 (North Pier) START DATE: 20-May-22 END DATE: 19-Feb-23
TANK ROOF TYPE: Floating Roof DIA (M): 17.983 HEIGHT (M): 10.973 PRODUCT : DM Water
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Fixed Roof DIA (M): 22.500 HEIGHT (M): 17.200 PRODUCT: Fuel Oil
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Remarks:
Supervisor: Rajukumar Site Engineer: Sukesh Shetty Planning Engineer: Dhruvil Vaniyawala
Supervisor: Rajukumar Site Engineer: Sukesh Shetty Planning Engineer: Dhruvil Vaniyawala
TANK ROOF TYPE : FIXED ROOF DIA (M):13.411 HEIGHT (M): 12.802 PRODUCT: DESAL. WATER
Release by KNPC Operational Planning Team 4-Mar-23 4-Mar-23 1 4-Mar-23 4-Mar-23 100%
Tank Blinding Works 4-Mar-23 5-Mar-23 2 4-Mar-23 4-Mar-23 100%
Gas Freeing & Stripping 6-Mar-23 6-Mar-23 1 6-Mar-23 6-Mar-23 100%
De-Sludging Works 7-Mar-23 7-Mar-23 1 6-Mar-23 6-Mar-23 100%
Washing and Cleaning Works 7-Mar-23 7-Mar-23 1 6-Mar-23 7-Mar-23 100%
Preliminary Inspection 8-Mar-23 8-Mar-23 1 7-Mar-23 7-Mar-23 100%
Electrical, Instrumentation & Rotating Activities 8-Mar-23 14-Mar-23 7 7-Mar-23 7-Mar-23 100%
External Scaffolding Erection 9-Mar-23 10-Mar-23 2 25-Mar-23 25-Mar-23 100%
External Shell Inspection 11-Mar-23 11-Mar-23 1 10-Mar-23 11-Mar-23 100%
Insulation Pocket Opening for Thickness Survey 12-Mar-23 12-Mar-23 1 21-Mar-23 21-Mar-23 100%
Internal Bottom Sweep Blasting 13-Mar-23 15-Mar-23 3 7-Mar-23 9-Mar-23 100%
Inspection of Tank Bottom 16-Mar-23 17-Mar-23 2 10-Mar-23 11-Mar-23 100%
Issuance of IAT(s) 18-Mar-23 18-Mar-23 1 20-Mar-23 20-Mar-23 100%
Internal Scaffolding Erection 19-Mar-23 20-Mar-23 2 15-Mar-23 18-Mar-23 100%
Internal Tank Roof & Shell Sweep Blasting 21-Mar-23 24-Mar-23 4 23-Mar-23 29-Mar-23 100% In Blasting Consume more Time Due to a late in Daily Work Permit issuing
Inspection of Tank Roof & Shell 25-Mar-23 25-Mar-23 1 18-Mar-23 1-Apr-23 100% Due to Shell Sweep Blasting completion delay
Issuance of IAT(s) 26-Mar-23 26-Mar-23 1 1-Apr-23 4-Apr-23 100%
Internal Roof, Structure & Shell Blasting Works 27-Mar-23 1-Apr-23 6 5-Apr-23 9-Apr-23 100% Due to Previous Activity Completion Delayed
Internal Roof, Structure & Shell Painting Works 2-Apr-23 9-Apr-23 8 6-Apr-23 13-Apr-23 100%
Internal Scaffolding Dismantling 10-Apr-23 10-Apr-23 1 13-Apr-23 14-Apr-23 100% Due to Internal Structure Blasting & Painting Completion Delays
Minor Mechanical Repair Works (Bottom Weld build up) 11-Apr-23 11-Apr-23 1 15-Apr-23 16-Apr-23 100%
N.D.T. Inspection Works(Vacuum Box Test) 11-Apr-23 11-Apr-23 1 16-Apr-23 17-Apr-23 100%
Tank Foundation Repair Works 6-Apr-23 12-Apr-23 7 22-Mar-23 27-Mar-23 100%
Tank Hydro Test 12-Apr-23 19-Apr-23 8 17-Apr-23 28-Apr-23 100% Due to Hydro Feeling Flow Rate Getting Less
Internal Washing and Cleaning Works 20-Apr-23 20-Apr-23 1 28-Apr-23 29-Apr-23 100%
Internal Bottom Blasting and Painting Works 21-Apr-23 28-Apr-23 8 29-Apr-23 3-May-23 100%
External Scaffolding Dismantling 21-Apr-23 21-Apr-23 1 3-May-23 4-May-23 100%
Electrical, Instrumentation & Rotating Activities 28-Apr-23 28-Apr-23 1 3-May-23 4-May-23 100%
Final Cleaning & Housekeeping 28-Apr-23 28-Apr-23 1 3-May-23 4-May-23 100%
Tank Box-Up Works 28-Apr-23 28-Apr-23 1 4-May-23 8-May-23 100%
De-Blinding Works 29-Apr-23 29-Apr-23 1 8-May-23 9-May-23 100%
Hand-Over To KNPC Operations Team 30-Apr-23 30-Apr-23 1
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Fixed Roof DIA (M):6.4 HEIGHT (M): 7 PRODUCT : SULFURIC ACID
Release by KNPC Operational Planning Team 1-Dec-22 1-Dec-22 1 1-Dec-22 1-Dec-22 100%
Dead-Stock Transfer NA
Tank Blinding Works 2-Dec-22 4-Dec-22 3 2-Dec-22 5-Dec-22 100%
Gas Freeing & Stripping 5-Dec-22 12-Dec-22 8 8-Dec-22 18-Dec-22 100% 3 Days Delayed-Due to a decrease the saturation of H 2So4 and for getting Low LEL
De-Sludging Works 13-Dec-22 17-Dec-22 5 21-Dec-22 27-Dec-22 100% 8 Days Delayed-Due to the decrease the saturation of H 2So4 add sand, Authorization from KNPC
Washing and Cleaning Works 18-Dec-22 22-Dec-22 5 27-Dec-22 27-Dec-22 100% 9 Days Delayed in Authorization for Man entry from KNPC
Preliminary Inspection 23-Dec-22 23-Dec-22 1 28-Dec-22 28-Dec-22 100% 5 Days Delayed Due to delay in Tank cleaning
Internal Bottom Sweep Blasting 24-Dec-22 4-Jan-23 12 10-Jan-23 12-Jan-23 100% 17 Days Delayed- Due to Priority Change in Sweep Blasting for Tank TK-61-703
Inspection of Tank Bottom 5-Jan-23 5-Jan-23 1 14-Jan-23 17-Jan-23 100% 9 Days Delayed-Due to Bottom Sweep Blasting Work completion late
Issuance of IAT(s) 6-Jan-23 6-Jan-23 1 28-Dec-22 29-Dec-22 100%
External Scaffolding Erection 7-Jan-23 16-Jan-23 10 5-Jan-23 8-Jan-23 100%
External Shell Inspection 17-Jan-23 20-Jan-23 4 14-Jan-23 17-Jan-23 100%
Internal Scaffolding Erection 21-Jan-23 3-Feb-23 14 16-Jan-23 19-Jan-23 100%
Internal Tank Roof & Shell Sweep Blasting and Cleaning 4-Feb-23 18-Feb-23 15 19-Jan-23 23-Jan-23 100%
Inspection of Tank Roof & Shell 19-Feb-23 21-Feb-23 3 24-Jan-23 24-Jan-23 100%
Issuance of IAT(s) 22-Feb-23 22-Feb-23 1 24-Jan-23 5-Feb-23 100%
Minor Mechanical Repair Works on Roof & Shell 23-Feb-23 4-Mar-23 10 6-Feb-23 8-Feb-23 100%
N.D.T. Inspection Works 5-Mar-23 7-Mar-23 3 8-Feb-23 8-Feb-23 100%
Tank Foundation Repair Works NA
Internal Scaffolding Dismantling 8-Mar-23 17-Mar-23 10 11-Feb-23 12-Feb-23 100%
Tank HydroTest 18-Mar-23 1-Apr-23 15 2-Mar-23 11-Mar-23 100%
Internal Washing and Cleaning Works 2-Apr-23 4-Apr-23 3 11-Mar-23 12-Mar-23 100%
TDS & TFS Lines Repair & Wrapping Works NA
TDS & TFS Lines HydroTest & Service Test NA
U/G Piping Repair & Testing Works NA
U/G Piping Wrapping Works NA
External Roof Blasting & Painting Works NA
External Shell Blasting & Painting Works 5-Apr-23 14-Apr-23 10 16-Mar-23 27-Mar-23 100%
Tank Logo and Number Stenciling Works NA
External Scaffolding Dismantling 15-Apr-23 20-Apr-23 6 30-Mar-23 1-Apr-23 100%
Internal Scaffolding Erection NA
Internal Roof and Shell Blasting and Painting Works NA
Internal Scaffolding Dismantling NA
Tank Bottom Blasting & Painting Works NA
Tank Calibration NA
Final Cleaning & Housekeeping 21-Apr-23 22-Apr-23 2 1-Apr-23 3-Apr-23 100%
Tank Box-Up Works 23-Apr-23 24-Apr-23 2 3-Apr-23 3-Apr-23 100%
De-Blinding Works 25-Apr-23 26-Apr-23 2 4-Apr-23 4-Apr-23 100%
Hand-Over To KNPC Operations Team 27-Apr-23 27-Apr-23 1 5-Apr-23 5-Apr-23 100%
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE DURATION (DAYS) REMARKS
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Floating Roof DIA (M): 67.06 HEIGHT (M): 22.25 PRODUCT: KNG/PCNA
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: CONE ROOF DIA (M) :28.96 HEIGHT (M) :15.24 PRODUCT : LSRN/HCLN
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: CONE ROOF DIA (M) :28.96 HEIGHT (M) :15.24 PRODUCT : LSRN/HCLN/MTBE
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 31.800 HEIGHT (M) : 19.507 PRODUCT: HGO
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION IAT No. IAT ISSUE DATE REMARKS
OFFER DATE START DATE (DAYS)
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: FLOATING ROOF DIA (M) :49.987 HEIGHT (M) : 19.507 PRODUCT : REFRA
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION (DAYS) REMARKS
OFFER DATE START DATE
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: FIXED ROOF DIA (M): 7.35 HEIGHT (M): 7.35 PRODUCT: CARBONATE SOLUTION
Release by KNPC Operational Planning Team 11-Mar-23 11-Mar-23 1 11-Mar-23 11-Mar-23 100%
Dead-Stock Transfer NA
Tank Blinding Works 12-Mar-23 12-Mar-23 1 12-Mar-23 12-Mar-23 100%
Gas Freeing & Stripping 13-Mar-23 16-Mar-23 4 14-Mar-23 15-Mar-23 100%
De-Sludging Works 17-Mar-23 23-Mar-23 7 15-Mar-23 16-Mar-23 100%
Washing & Cleaning Works 24-Mar-23 28-Mar-23 5 16-Mar-23 16-Mar-23 100%
Preliminary Inspection 29-Mar-23 30-Mar-23 2 16-Mar-23 19-Mar-23 100%
Electrical, Instrumentation & Rotating Activities NA
Internal Bottom Sweep Blasting 31-Mar-23 2-Apr-23 3 21-Mar-23 22-Mar-23 100%
Inspection of Tank Bottom 3-Apr-23 3-Apr-23 1 19-Mar-23 3-Apr-23 100%
Issuance of IAT(s) 4-Apr-23 4-Apr-23 1 3-Apr-23 3-Apr-23 100%
External Shell Scaffolding Erection 5-Apr-23 9-Apr-23 5 27-Mar-23 28-Mar-23 100%
External Shell Inspection 10-Apr-23 13-Apr-23 4 28-Mar-23 3-Apr-23 100%
Internal Scaffolding Erection 14-Apr-23 18-Apr-23 5 28-Mar-23 28-Mar-23 100%
Tank Roof & Shell Sweep Blasting & Painting (located area) 19-Apr-23 21-Apr-23 3 8-Apr-23 12-Apr-23 100%
Inspection of Tank Roof & Shell 22-Apr-23 24-Apr-23 3 19-Mar-23 3-Apr-23 100%
Issuance of IAT(s) 25-Apr-23 25-Apr-23 1 3-Apr-23 3-Apr-23 100%
Minor Mechanical (Coil HydroTest) 26-Apr-23 30-Apr-23 5 15-Apr-23 16-Apr-23 100%
N.D.T. Inspection Works(Bottom Plate Vacuum Box Test) 1-May-23 2-May-23 2 16-Apr-23 18-Apr-23 100%
Tank Foundation Repair Works 25-Apr-23 1-May-23 7 16-Apr-23 16-Apr-23 100%
Internal Scaffolding Dismantling NA
Tank Hydro Test NA
Internal Washing & Cleaning Works NA
TDS & TFS Lines Repair & Wrapping Works NA
TDS & TFS Lines Hydro Test & Service Test NA
U/G Piping Repair & Testing Works NA
U/G Piping Wrapping Works NA
External Roof Blasting & Painting Works NA
External Shell Blasting & Painting Works (Damaged Location only) 3-May-23 5-May-23 3 12-Apr-23 15-Apr-23 100%
Tank Logo & Number Stencilling Works NA
External Scaffolding Dismantling 6-May-23 8-May-23 3 19-Apr-23 21-Apr-23 100%
Internal Scaffolding Erection NA
Internal Roof & Shell Blasting & Painting Works NA
Internal Scaffolding Dismantling NA
Tank Bottom Blasting & Painting Works NA
Electrical, Instrumentation & Rotating Activities NA
Tank Calibration NA
Final Cleaning & Housekeeping Works 9-May-23 9-May-23 1 22-Apr-23 25-Apr-23 100%
Tank Box-Up Works 10-May-23 10-May-23 1 25-Apr-23 25-Apr-23 100%
De-Blinding Works 11-May-23 11-May-23 1 25-Apr-23 25-Apr-23 100%
Hand-Over To KNPC Operations Team 12-May-23 12-May-23 1 26-Apr-23 26-Apr-23 100%
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Dome Roof DIA (M):54.8 HEIGHT (M): 24.3 PRODUCT: PROPANE
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 07-Nov-23 CHECK LIST: TANK LIST
TANK NO. : TK-12-866 REVISION NO: 3 START DATE: 10/Oct/23 END DATE: 30-Jun-24
TANK ROOF TYPE : FIXED ROOF DIA (M) : 25.000 HEIGHT (M) : 14.630 PRODUCT: BITUMEN
Major Mechanical Work 8-Jan-24 Rev.1 16 As Per IAT Revised with Major Mechanical Work
Partial Re-bottoming 17-Apr-24 Rev.2 45 Due to non availability of A 537 Grade Plate in KNPC & Local Vendor, also Awaiting Approval from KNPC to Proceed A 283 Grade Plates
Overall Schedule 24-Apr-24 Rev.3 -27 Work Schedule changed on 24 Hrs basis
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 07-Nov-23 CHECK LIST: 08/Oct/23 TANK LIST
TANK NO. : TK-22-512 REVISION NO: 0 START DATE: 08/Oct/23 END DATE: 5-Jul-24
TANK ROOF TYPE : FIXED ROOF DIA (M) : 24.348 HEIGHT (M) : 12.192 PRODUCT: KEROSENE
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-22-996 REVISION NO: 2 START DATE: 05/Feb/24 END DATE: 11-Jul-24
TANK ROOF TYPE : FIXED ROOF DIA (M) : 16.789 HEIGHT (M) : 15.000 PRODUCT: WET SLOP
Blasting and Painting Works 13-Apr-24 Rev.1 -35 Based on the IAT issued by Corrosion
Blasting and Painting Works 25-Apr-24 Rev.2 10 Increase the Painting Scope of Works (Internal Shell full Blasting and Painting)
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 07-Nov-23 CHECK LIST: 08/Oct/23 TANK LIST
TANK NO. : TK-22-503 REVISION NO: 1 START DATE: 28/Oct/23 END DATE: 29-Jul-24
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 24.380 HEIGHT (M) : 12.192 PRODUCT: KEROSENE
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection IAT 9-Nov-23 2023-14244 9-Nov-23 21-Nov-23 12
Cutting of Sample Coupons 5-Jan-24 2024-00453 6-Jan-23 10-Jan-24 5
Detailed Inspection & Recommendation 21-Jan-24 2024-00950 21-Jan-24 22-Jan-24 1
Painting IAT (Internal & external) 29-Jan-24 2024-01453 29-Jan-24 30-Jan-24 1
[WORK PLAN STATUS]
WORK EXECUTED TODAY: WORK PLAN FOR NEXT WORKING DAY:
Tank Hydrotest Water Filling Completed (Level 10.900/ 10.900 Mtr) - Water Holding for Inspection
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST 10/Dec/23 TANK LIST
TANK NO. : TK-22-725 REVISION NO: 1 START DATE: 28/Dec/23 END DATE: 9-Aug-24
TANK ROOF TYPE : CONE ROOF DIA (M) : 15.24 HEIGHT (M) : 12.19 PRODUCT: ATK L.M.
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 7-Jan-24 2024-00434 8-Jan-24 10-Jan-24 2
Replacement of 3" drain line spool for the tank 4-Feb-24 2024-01779 6-Feb-24 13-Feb-24 7
Detailed IAT for TDS & TFS replacement work 21-Jan-24 2024-03192 7-Feb-24 28-Feb-24 21
Bottom plates repair IAT 21-Jan-24 2024-03520 7-Feb-24 28-Feb-24 21
External and Internal painting IAT 2024-03609 10-Mar-24
[WORK PLAN STATUS]
WORK EXECUTED TODAY: WORK PLAN FOR NEXT WORKING DAY:
Preparation for Internal Washing & Cleaning in Progress after Hydrotest
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery BAR CHART SUBMISSION DATE: 25-Dec-23 CHECK LIST: 19/Nov/23 TANK LIST
TANK NO. : TK-34-413 REVISION NO: 0 START DATE: 19/Nov/23 END DATE: 15-Aug-24
TANK ROOF TYPE : FIXED ROOF DIA(M): 43.891 HEIGHT(M): 30.480 PRODUCT: BUTANE
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: 25-Dec-23 CHECK LIST 07/Dec/23 TANK LIST
TANK NO. : TK-22-451 REVISION NO: 0 START DATE: 08/Dec/23 END DATE: 3-Sep-24
TANK ROOF TYPE : CONE ROOF DIA (M) : 13.72 HEIGHT (M) : 14.63 PRODUCT: MOGAS
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary inspection 15-Jan-24 2024-00750 16-Jan-24 20-Jan-24 5
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST 21/Dec/23 TANK LIST
TANK NO. : TK-61-469 REVISION NO: 0 START DATE: 21/Dec/23 END DATE: 16-Sep-24
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 49.866 HEIGHT (M) : 19.508 PRODUCT: KNG/PCNA
Release by KNPC Operational Planning Team 20-Dec-23 20-Dec-23 0 Product Level: 2.094 Mtr (Product Transfer to TK-61-468)
Preparation for Dead Stock Transfer 21-Dec-23 24-Dec-23 4 21-Dec-23 26-Dec-23 100% 2 Days Delayed- due to Electrical Clearance From KNPC from 24-Dec-23 to 26-Dec-23
Dead-Stock Transfer 25-Dec-23 5-Jan-24 12 27-Dec-23 3-Jan-24 100%
Tank Blinding Works 6-Jan-24 6-Jan-24 1 4-Jan-24 4-Jan-24 100%
Gas Freeing & Stripping 7-Jan-24 14-Jan-24 8 7-Jan-24 12-Feb-24 100% 20 Days Delayed - Awaited Clearance for Dumping from KNPC From 10-Jan-24 to 24-Jan-24 and 27-Jan-24 to 02-Feb-24 (Stripped Product:0.180 Mtr)
De-Sludging Works 15-Jan-24 20-Jan-24 6 12-Feb-24 13-Feb-24 100%
Washing & Cleaning Works 21-Jan-24 24-Jan-24 4 13-Feb-24 17-Feb-24 100%
Preliminary Inspection 25-Jan-24 25-Jan-24 1 18-Feb-24 18-Feb-24 100%
Issuance of IAT(s) 26-Jan-24 27-Jan-24 2 19-Feb-24 19-Feb-24 100%
Electrical, Instrumentation & Rotating Activities 26-Jan-24 1-Feb-24 7 19-Feb-24 19-Feb-24 100%
Removal of Heat Detection Cable 20-Feb-24 21-Feb-24 2 21-Mar-24 21-Mar-24 100%
Tank Bottom & 1Mtr Shell Sweep Blasting 21-Feb-24 6-Mar-24 15 29-Feb-24 21-Mar-24 100%
Tank External Shell Sweep Blasting (1ft) 7-Mar-24 12-Mar-24 6 23-Mar-24 23-Mar-24 100% (Blasting work delayed from 20-Feb-24 to 28-feb-24 due to Manpower Transfered for Shutdown Works of Unit-29)
Removal of Garnet from Tank & Cleaning Works 13-Mar-24 16-Mar-24 4 22-Mar-24 27-Mar-24 100%
External Scaffolding Erection for Inspection 13-Mar-24 20-Mar-24 8
Inspection of Tank 17-Mar-24 31-Mar-24 15 8-May-24 Tank Inspection (Thickness Survey) in Progress (42 Days Delayed - Offered for Tank Inspection on 30-Mar-24 and Started Inspection: 08-May-24)
Issuance of IAT(s) 1-Apr-24 7-Apr-24 7
Collection of Material from KNPC 8-Apr-24 10-Apr-24 3
Minor Mechanical Repair Works on Tank Bottom 11-Apr-24 20-Apr-24 10
N.D.T. Inspection Works 21-Apr-24 23-Apr-24 3
Installation of Roof Seal 24-Apr-24 30-Apr-24 7
Inspection & Servicing of Roof Drain Line 1-May-24 2-May-24 2
Tank Hydrotest 3-May-24 27-May-24 25
Tank Foundation Repair Works 1-May-24 7-May-24 7
Internal Washing & Cleaning Works 28-May-24 30-May-24 3
TDS & TFS Lines Repair & Coating Works 3-May-24 12-May-24 10
TDS & TFS Lines Hydro Test & Service Test 13-May-24 16-May-24 4
U/G Piping Repair & Testing Works 17-May-24 31-May-24 15
U/G Piping Coating Works 1-Jun-24 3-Jun-24 3
Removal of Roof Seal for Painting Works 31-May-24 7-Jun-24 8
External Shell & Accessories Blasting & Painting 7-Jun-24 2-Jul-24 26
Tank Logo & Number Sentencing Works 3-Jul-24 5-Jul-24 3
Painting Touch Up and Inspection on External Shell 6-Jul-24 11-Jul-24 6
External Scaffolding Dismantling 12-Jul-24 19-Jul-24 8
Roof Top Side Blasting & Painting 2-Jul-24 16-Jul-24 15
Roof Top Side Paint Touch Up & Inspection 17-Jul-24 20-Jul-24 4
Roof Leg Pad Blasting & Painting Works 10-Jun-24 9-Jul-24 30
Roof Under Side Blasting & Painting Works 21-Jul-24 7-Aug-24 18
Paint Touch Up and Inspection on Roof Underside 8-Aug-24 11-Aug-24 4
Tank Bottom Blasting & Painting Works 12-Aug-24 31-Aug-24 20
Paint Touch Up, Holiday & Inspection on Bottom 1-Sep-24 4-Sep-24 4
Re-Installation of Roof Seal 5-Sep-24 12-Sep-24 8
Electrical, Instrumentation & Rotating Activities 5-Sep-24 11-Sep-24 7
Tank Calibration 5-Sep-24 5-Sep-24 1
Final Cleaning & Housekeeping Works 13-Sep-24 14-Sep-24 2
Tank Box-Up Works 15-Sep-24 15-Sep-24 1
De-Blinding Works 16-Sep-24 16-Sep-24 1
Hand-Over To KNPC Operations Team 16-Sep-24 16-Sep-24 1
[SCHEDULE REVISION STATUS]
REVISION DURATION
REVISED ACTIVITY DATE NUMBER (DAYS) REASON
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION OFFER DATE IAT No. START DATE IAT ISSUE DATE (DAYS) REMARKS
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: 25-Dec-23 CHECK LIST 23/Jan/24 TANK LIST
TANK NO. : TK-61-661 REVISION NO: 0 START DATE: 07/Jan/24 END DATE: 3-Oct-24
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 49.866 HEIGHT (M) : 19.508 PRODUCT: TGO
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION IAT No. IAT ISSUE DATE REMARKS
OFFER DATE START DATE (DAYS)
Preliminary IAT 25-Jan-24 2024-01292 25-Jan-24 28-Jan-24 3
29-Feb-24 2024-07278 14-Apr-24 8-May-24 69
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-61-833 REVISION NO: 0 START DATE: 15/Jan/24 END DATE: 8-Oct-24
TANK ROOF TYPE : FIXED ROOF DIA (M) : 38.100 HEIGHT (M) : 19.508 PRODUCT: VGO
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION IAT No. IAT ISSUE DATE REMARKS
OFFER DATE START DATE (DAYS)
Preliminary inspection 10-Feb-24 2024-02246 11-Feb-24 13-Feb-24 2
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: 25-Dec-23 CHECK LIST 25/Nov/23 TANK LIST
TANK NO. : TK-22-762 REVISION NO: 1 START DATE: 25/Nov/23 END DATE: 31-Oct-24
TANK ROOF TYPE : CONE ROOF DIA (M) : 64.618 HEIGHT (M) : 19.507 PRODUCT: FUEL OIL
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: 25-Dec-23 CHECK LIST 22/Nov/23 TANK LIST
TANK NO. : TK-61-272 REVISION NO: 1 START DATE: 30/Nov/23 END DATE: 30-Nov-24
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 38.100 HEIGHT (M) : 17.068 PRODUCT: HCLN
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Preliminary Inspection 2024-00125
Detailed Inspection & Recommendation 28-Jan-24 2024-04963 27-Mar-24 16-Apr-24 79
Tank Bottom Plate Partial Replacement 23-Apr-24 2024-05417
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-09-951 REVISION NO: 0 START DATE: 11/Dec/23 END DATE: 20-Dec-23
TANK ROOF TYPE : CONE ROOF DIA (M) : 3.734 HEIGHT (M) : 3.658 PRODUCT: CAUSTIC SODA
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
INSPECTION INSPECTION DURATION
IAT DESCRIPTION IAT No. IAT ISSUE DATE REMARKS
OFFER DATE START DATE (DAYS)
Preliminary inspection 11-Dec-23 2023-16324 10-Dec-23 11-Dec-23 1
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-09-952 REVISION NO: 0 START DATE: 11/Dec/23 END DATE: 20-Dec-23
TANK ROOF TYPE : CONE ROOF DIA (M) : 4.343 HEIGHT (M) : 4.877 PRODUCT: CAUSTIC SODA
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-61-901 REVISION NO: 0 START DATE: 24/Dec/23 END DATE: 29-Dec-23
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 23.25 HEIGHT (M) : 13.41 PRODUCT: DRY SLOP
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
DAILY PROGRESS REPORT
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
DAILY PROGRESS REPORT
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
DAILY PROGRESS REPORT
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
DAILY PROGRESS REPORT
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
LOCATION : MAA REFINERY BAR CHART SUBMISSION DATE: CHECK LIST TANK LIST
TANK NO. : TK-14-204(NP) REVISION NO: 0 START DATE: 12/Jan/24 END DATE: 30-Dec-99
TANK ROOF TYPE : FLOATING ROOF DIA (M) : 30.480 HEIGHT (M) : 11.064 PRODUCT: CRUDE OIL
Schedule shall be updated after the Completion of the Tank Inspection Works
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT DESCRIPTION INSPECTION IAT No. INSPECTION IAT ISSUE DATE DURATION REMARKS
OFFER DATE START DATE (DAYS)
TANK NO. : Impervious TK-22-514,515,454,455 REVISION NO: 0 START DATE: 28-Jan-24 END DATE: 30-Apr-24
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
Sr. No Tank No Tank Roof type Nozzle size Inch Tag No Fixing Flanges Flange with TX DCSCR
1 TK-22-454 Fixed 4 22-LSHH-1454 SA105 GR. B 4", 300# ,SS 316L WCR
2 TK-22-608 Fixed 4 22-LSHH-1608 SA105 GR. B 4", 300# ,ss 316L WCR
3 TK-22-510 Fixed 6 22-LSHH-1510 SA105 GR. B 6", 300 #, SS 316L WCR
4 TK-22-600 Filled 6 61-LSHH-1600 SA105 GR. B 6", 300 #, SS 316L WCR
5 TK-22-601 Fixed 6 61-LSHH-1601 SA105 GR. B 6", 300 #, SS 316L WCR
6 TK-22-634 Fixed 6 22-LSHH-1634 SA105 GR. B 6", 300 #, SS 316L WCR
7 TK-22-651 Fixed 6 22-LSHH-1651 SA105 GR. B 6·, 300 #, SS 316L WCR
8 TK-22-751 Fixed 6 22-LSHH-1751 SA105 GR. B 6", 300#, SS 316L WCR
9 TK-22-752 Fixed 6 22-LSHH-1752 SA105 GR. B 5", 300#, SS 316L WCR
10 TK-22-757 Fixed 6 61-LSHH-17S7 SA105 GR. B 6", 300 #, SS 316L WCR
11 TK-22-256 Float 22-LSHH-1256 WCR
12 TK-22-503 Float 22-LSHH-1503 WCR
13 TK-22-504 Float 22-LSHH-1504 WCR
14 TK-22-508 Float 22-LSHH-1508 WCR
15 TK-22-514 Float 22-LSHH-1514 WCR
16 TK-22-515 Float 22-lSHH-151S WCR
17 TK-22-253 Float 22-LSHH-12S3 PBCR
18 TK-22-458 Float 22-LSHH-1458 WCR
19 TK-22-226 Float 22-lSHH-1226 WCR
20 TK-22-509 Float 22-LSHH-1509 WCR
21 TK-22-703 Fixed 6 61-LSHH-1703 6", 300#, SS 316L WCR
22 TK-22-511 Float 22-LSHH-1S11 WCR
23 TK-22-452 Float 22-l.SHH-1452 WCR
24 TK-61-605 Fixed 3 61-LSHH-1605 3", 300#, SS 316L WCR
25 TK-61-755 Fixed 6 61-LSHH-1755 6", 300 #, SS 316L WCR
26 TK-22-512 Fixed 22-lSHH-1512 WCR
27 TK-22-451 Fixed 4 22-LSHH-1451 4", 300#,SS 316L WCR
28 TK-22-760 Fixed 6 22-LSHH-1760 6", 300 #, SS 316L PBCR
29 TK-22-762 Fixed 6 22-lSHH-1762 6", 300 #, SS 316L PBCR
30 TK-22-761 Fixed 6 22-lSHH-1761 6", 300 #, SS 316L PBCR
31 TK-22-603 Fixed 8 22-LSHH-1603 8",300#, SS 316L WCR
32 TK-22-652 Fixed 6 22-l.SHH-1652 5", 300 #, SS 316L WCR
33 TK-22-506 Fixed 4 22-LSHH-1506 4", 300# ,SS 316L WCR
34 TK-22-455 Fixed 6 22-LSHH-1455 6", 300 #, SS 316L WCR
35 TK-22-507 Fixed 6 22-LSHH-1507 6", 300 #, SS 316L WCR
36 TK-22-633 Fixed 6 22-LSHH-1633 6", 300 #, SS 316L WCR
37 TK-22-702 Fixed 6 61-LSHH-1702 5", 300 #, SS 316L WCR
38 TK-22-725 Fixed 6 22-lSHH-1725 6", 300#, SS 316L WCR
39 TK-22-753 Fixed 6 22-LSHH-1753 6", 300 #, SS 316L WCR
40 TK-22-754 Fixed 6 61-LSHH-1754 6", 300 #, SS 316L WCR
41 TK-22-756 Fixed 6 61-LSHH-1756 6", 300 #, SS 316L WCR
42 TK-22-758 Fixed 6 22-LSHH-1758 6", 300 #, SS 316L PBCR
43 TK-22-759 Fixed 6 22-LSHH-1759 6", 300 #, SS 316L PBCR
44 TK-22-602 Fixed 2 61-LSHH-1602 2", 300 #, SS 316L WCR
45 TK-22-225 Float 22-LSHH-1225 WCR
46 TK-22-254 Float 22-lSHH-1254 PBCR
47 TK-22-255 Float 22-LSHH-1255 WCR
48 TK-22-456 Float 22-LSHH-1456 WCR
49 TK-22-457 Float 22·LSHH-14S7 WCR
50 TK-22-459 Roat 22-LSHH-1459 WCR
Remarks:
Supervisor: Avinash
Manpower & Equipment Details
TANK LIST
TANK ROOF TYPE: Floating Roof DIA (M) : HEIGHT (M): PRODUCT:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting
Inspection of Tank
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE: Fixed Roof DIA (M) : HEIGHT (M): PRODUCT:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks: