Duration
GR-CON-Z04-1487 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Dec-23 02-Jan-24 6 226
GR-CON-Z04-1488 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jan-24
system 11-Jan-24 8 226
Electrical Works 18-Nov-23 30-Jun-24 179 101
GR-CON-Z04-1494 Excavation And Disposal 18-Nov-23 22-Nov-23 5 253
GR-CON-Z04-1495 Sand Bedding 23-Nov-23 27-Nov-23 4 253
GR-CON-Z04-1496 laying cables 28-Nov-23 02-Dec-23 4 253
GR-CON-Z04-1497 Backfilling (sand / Sub base) 03-Dec-23 07-Dec-23 5 253
GR-CON-Z04-1498 Control Panel / Distribution Panel Installation 09-Dec-23 12-Dec-23 4 253
GR-CON-Z04-1499 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Toilet - 03 06-Nov-23 05-Oct-24 271 19
Site Preparation 06-Nov-23 16-Nov-23 10 19
GR-CON-Z04-1500 Excavation And Disposal 06-Nov-23 11-Nov-23 5 19
GR-CON-Z04-1501 Backfilling (one layer) 12-Nov-23 16-Nov-23 5 19
Civil Works 18-Nov-23 11-May-24 140 19
GR-CON-Z04-1502 Polyethylene Under Footings, Grade Slab and Beams 18-Nov-23 20-Nov-23 3 19
GR-CON-Z04-1503 Blinding concrete 21-Nov-23 26-Nov-23 5 19
GR-CON-Z04-1504 Footings 27-Nov-23 05-Dec-23 8 19
GR-CON-Z04-1505 Waterproofing Under Footing 06-Dec-23 11-Dec-23 5 19
GR-CON-Z04-1506 Column Necks 12-Dec-23 18-Dec-23 6 19
GR-CON-Z04-1507 Waterproofing (Toilet) 25-Dec-23 03-Jan-24 9 19
GR-CON-Z04-1508 Backfilling 04-Jan-24 10-Jan-24 6 19
GR-CON-Z04-1509 Ground beams 11-Jan-24 25-Jan-24 13 19
GR-CON-Z04-1510 Slab on grade 27-Jan-24 15-Feb-24 18 19
GR-CON-Z04-1511 Columns 17-Feb-24 02-Mar-24 13 19
GR-CON-Z04-1512 Concrete, slabs Ground floor 03-Mar-24 31-Mar-24 21 19
GR-CON-Z04-1513 Roof Thermal And Moisture Protection Work 30-Apr-24 11-May-24 9 19
Architectural Works 11-May-24 05-Oct-24 121 19
GR-CON-Z04-1514 Blockwork 11-May-24 02-Jun-24 19 19
GR-CON-Z04-1515 Waterproofing 11-Jun-24 26-Jun-24 9 19
GR-CON-Z04-1516 Back Filling (sand) 26-Jun-24 02-Jul-24 5 19
GR-CON-Z04-1517 Floor finish 02-Jul-24 17-Jul-24 13 19
GR-CON-Z04-1518 Wall Finish 17-Jul-24 15-Aug-24 25 19
GR-CON-Z04-1519 Door Installation 15-Aug-24 20-Aug-24 4 19
GR-CON-Z04-1521 Celling finish 20-Aug-24 26-Aug-24 5 19
GR-CON-Z04-1522 ToiletAccessories 26-Aug-24 31-Aug-24 4 19
GR-CON-Z04-1523 Facade Finishing Works 31-Aug-24 11-Sep-24 10 19
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z07-1490 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Nov-23 18-Nov-23 6 277
GR-CON-Z07-1491 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-23
system 27-Nov-23 8 277
Electrical Works 02-Oct-23 21-May-24 189 142
GR-CON-Z07-1497 Excavation And Disposal 02-Oct-23 08-Oct-23 5 304
GR-CON-Z07-1498 Sand Bedding 08-Oct-23 12-Oct-23 4 304
GR-CON-Z07-1499 laying cables 12-Oct-23 17-Oct-23 4 304
GR-CON-Z07-1500 Backfilling (sand / Sub base) 17-Oct-23 23-Oct-23 5 304
GR-CON-Z07-1501 Control Panel / Distribution Panel Installation 23-Oct-23 28-Oct-23 4 304
GR-CON-Z07-1502 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-81 27-Sep-23 21-May-24 193 142
Site Preparation 27-Sep-23 22-Oct-23 21 314
GR-CON-Z07-1503 Demolition (Asphalt.Paving,etc.....) 27-Sep-23 02-Oct-23 4 208
GR-CON-Z07-1504 Excavation And Disposal 02-Oct-23 08-Oct-23 5 208
GR-CON-Z07-1505 Prepretion And Compaction 08-Oct-23 15-Oct-23 6 314
GR-CON-Z07-1506 Backfilling 15-Oct-23 22-Oct-23 6 314
Curbstone and Paving 08-Oct-23 30-Nov-23 46 280
GR-CON-Z07-1507 Excavation Curbstone 08-Oct-23 14-Oct-23 5 245
GR-CON-Z07-1508 Plain Concrete 14-Oct-23 21-Oct-23 6 280
GR-CON-Z07-1509 Installation Curbstone 21-Oct-23 31-Oct-23 9 280
GR-CON-Z07-1510 Casting Concrete (Mortar haunch) 31-Oct-23 05-Nov-23 4 280
GR-CON-Z07-1511 Backfilling (sand / Sub base) 05-Nov-23 15-Nov-23 9 280
GR-CON-Z07-1512 Installation of Paving 15-Nov-23 30-Nov-23 13 280
Landscape Works 14-Oct-23 28-Apr-24 159 142
GR-CON-Z07-1513 Excavation (Tree Pit ) 14-Oct-23 19-Oct-23 5 245
GR-CON-Z07-1514 Aggregate Drainage layer 19-Oct-23 26-Oct-23 6 245
GR-CON-Z07-1515 Installation Geotextile 26-Oct-23 31-Oct-23 4 245
GR-CON-Z07-1516 Backfilling (Soil max for tree) 31-Oct-23 07-Nov-23 6 245
GR-CON-Z07-1517 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10656 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10666 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10676 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10686 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1518 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1519 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1520 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z02-1186 HDPE Pipe Installations and fittings and conduit for cable 10-Dec-23 04-Jan-24 23 85
GR-CON-Z02-1188 Test pressure 06-Jan-24 14-Jan-24 8 85
GR-CON-Z02-1187 Installation of Valves and Accessories 15-Jan-24 21-Jan-24 6 85
GR-CON-Z02-1189 Back filling (sand / Subbase ) 22-Jan-24 31-Jan-24 9 85
GR-CON-Z02-1190 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Feb-24 11-Feb-24 9 173
GR-CON-Z02-1191 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-Feb-24
system 25-Feb-24 12 173
Electrical Works 03-Dec-23 04-Jul-24 170 85
GR-CON-Z02-1197 Excavation And Disposal 03-Dec-23 11-Dec-23 8 213
GR-CON-Z02-1198 Sand Bedding 12-Dec-23 18-Dec-23 6 213
GR-CON-Z02-1199 laying cables 19-Dec-23 25-Dec-23 6 213
GR-CON-Z02-1200 Backfilling (sand / Sub base) 26-Dec-23 03-Jan-24 8 213
GR-CON-Z02-1201 Control Panel / Distribution Panel Installation 04-Jan-24 10-Jan-24 6 213
GR-CON-Z02-1202 Road Crossing Ducts 25-Jun-24 04-Jul-24 8 85
Street SS-30.1 14-Nov-23 03-Jun-24 163 108
Site Preparation 14-Nov-23 07-Dec-23 21 250
GR-CON-Z02-1203 Demolition (Asphalt.Paving,etc.....) 14-Nov-23 18-Nov-23 4 141
GR-CON-Z02-1204 Excavation And Disposal 19-Nov-23 23-Nov-23 5 145
GR-CON-Z02-1205 Prepretion And Compaction 25-Nov-23 30-Nov-23 6 250
GR-CON-Z02-1206 Backfilling 02-Dec-23 07-Dec-23 6 250
Curbstone and Paving 25-Nov-23 16-Jan-24 46 216
GR-CON-Z02-1207 Excavation Curbstone 25-Nov-23 29-Nov-23 5 181
GR-CON-Z02-1208 Plain Concrete 30-Nov-23 06-Dec-23 6 216
GR-CON-Z02-1209 Installation Curbstone 07-Dec-23 17-Dec-23 9 216
GR-CON-Z02-1210 Casting Concrete (Mortar haunch) 18-Dec-23 21-Dec-23 4 216
GR-CON-Z02-1211 Backfilling (sand / Sub base) 23-Dec-23 01-Jan-24 9 216
GR-CON-Z02-1212 Installation of Paving 02-Jan-24 16-Jan-24 13 216
Landscape Works 30-Nov-23 11-May-24 129 108
GR-CON-Z02-1213 Excavation (Tree Pit ) 30-Nov-23 05-Dec-23 5 181
GR-CON-Z02-1214 Aggregate Drainage layer 06-Dec-23 12-Dec-23 6 181
GR-CON-Z02-1215 Installation Geotextile 13-Dec-23 17-Dec-23 4 181
GR-CON-Z02-1216 Backfilling (Soil max for tree) 18-Dec-23 24-Dec-23 6 181
GR-CON-Z02-1217 Installation of Trees 20-Mar-24 25-Mar-24 3 108
GR-CON-Z02-9416 Installation of Shrubs 25-Mar-24 30-Mar-24 3 108
GR-CON-Z02-9426 Installation of Succulents 30-Mar-24 03-Apr-24 3 108
GR-CON-Z02-9436 Installation of Ground Covers 03-Apr-24 08-Apr-24 3 108
GR-CON-Z02-9446 Installation of Grass 08-Apr-24 17-Apr-24 3 108
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z10-1185 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Jan-24 24-Jan-24 6 257
GR-CON-Z10-1186 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-24
system 25-Nov-24 6 16
Mosque M-06 29-Nov-23 25-Nov-24 295 16
Site Preparation 29-Nov-23 21-Dec-23 19 270
GR-CON-Z10-1187 Demolition (Asphalt.Paving,etc.....) 29-Nov-23 04-Dec-23 4 67
GR-CON-Z10-1188 Excavation And Disposal 04-Dec-23 10-Dec-23 5 185
GR-CON-Z10-1189 Prepretion And Compaction 10-Dec-23 14-Dec-23 4 270
GR-CON-Z10-1190 Backfilling 14-Dec-23 21-Dec-23 6 270
Curbstone and Paving 21-Dec-23 16-Jan-24 22 270
GR-CON-Z10-1195 Backfilling (sand / Sub base) 21-Dec-23 01-Jan-24 9 270
GR-CON-Z10-1196 Installation of Paving 01-Jan-24 16-Jan-24 13 270
Landscape Works 10-Dec-23 25-Nov-24 286 16
GR-CON-Z10-1197 Excavation (Tree Pit ) 10-Dec-23 16-Dec-23 5 218
GR-CON-Z10-1198 Aggregate Drainage layer 16-Dec-23 23-Dec-23 6 218
GR-CON-Z10-1199 Installation Geotextile 23-Dec-23 28-Dec-23 5 218
GR-CON-Z10-1200 Backfilling (Soil max for tree) 28-Dec-23 03-Jan-24 5 218
GR-CON-Z10-1201 Installation of Trees 11-Sep-24 16-Sep-24 4 16
GR-CON-Z10-4026 Installation of Climbers 16-Sep-24 21-Sep-24 4 16
GR-CON-Z10-4036 Installation of Shrubs 21-Sep-24 26-Sep-24 4 16
GR-CON-Z10-4046 Installation of Succulents 26-Sep-24 01-Oct-24 4 16
GR-CON-Z10-4056 Installation of Ground Covers 01-Oct-24 06-Oct-24 4 16
GR-CON-Z10-1202 Backfilling (Mulch) 06-Oct-24 23-Oct-24 15 16
GR-CON-Z10-1203 Natural Boulders Installation 23-Oct-24 07-Nov-24 13 16
GR-CON-Z10-1204 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Nov-24 25-Nov-24 15 16
Irrigation Works 10-Dec-23 25-Nov-24 286 16
GR-CON-Z10-1205 Excavation Pipe Irrigation 10-Dec-23 16-Dec-23 5 185
GR-CON-Z10-1206 Sand Bedding 16-Dec-23 19-Dec-23 3 185
GR-CON-Z10-1207 HDPE Pipe Installations and fittings and conduit for cable 19-Dec-23 06-Jan-24 15 185
GR-CON-Z10-1209 Test pressure 06-Jan-24 11-Jan-24 5 185
GR-CON-Z10-1208 Installation of Valves and Accessories 11-Jan-24 16-Jan-24 4 185
GR-CON-Z10-1210 Back filling (sand / Subbase ) 16-Jan-24 23-Jan-24 6 185
GR-CON-Z10-1211 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Jan-24 30-Jan-24 6 252
GR-CON-Z10-1212 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-24
system 25-Nov-24 6 16
Parking P-18 22-Jan-24 15-Oct-24 214 51
Site Preparation 22-Jan-24 29-Jan-24 6 246
GR-CON-Z10-1244 Backfilling 22-Jan-24 29-Jan-24 6 246
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z10-1447 HDPE Pipe Installations and fittings and conduit for cable 27-Apr-24 13-May-24 15 85
GR-CON-Z10-1449 Test pressure 14-May-24 19-May-24 5 85
GR-CON-Z10-1448 Installation of Valves and Accessories 20-May-24 23-May-24 4 85
GR-CON-Z10-1450 Back filling (sand / Subbase ) 25-May-24 30-May-24 6 85
GR-CON-Z10-1451 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jun-24 06-Jun-24 6 144
GR-CON-Z10-1452 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Jun-24
system 16-Jun-24 8 144
Electrical Works 22-Apr-24 16-Nov-24 174 24
GR-CON-Z10-1458 Excavation And Disposal 22-Apr-24 27-Apr-24 5 171
GR-CON-Z10-1459 Sand Bedding 28-Apr-24 01-May-24 4 171
GR-CON-Z10-1460 laying cables 02-May-24 06-May-24 4 171
GR-CON-Z10-1461 Backfilling (sand / Sub base) 07-May-24 12-May-24 5 171
GR-CON-Z10-1462 Control Panel / Distribution Panel Installation 13-May-24 16-May-24 4 171
GR-CON-Z10-1463 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-73 03-Apr-24 16-Nov-24 184 24
Site Preparation 03-Apr-24 04-May-24 21 187
GR-CON-Z10-1464 Demolition (Asphalt.Paving,etc.....) 03-Apr-24 09-Apr-24 4 0
GR-CON-Z10-1465 Excavation And Disposal 09-Apr-24 20-Apr-24 5 81
GR-CON-Z10-1466 Prepretion And Compaction 21-Apr-24 27-Apr-24 6 187
GR-CON-Z10-1467 Backfilling 28-Apr-24 04-May-24 6 187
Curbstone and Paving 21-Apr-24 12-Jun-24 46 153
GR-CON-Z10-1468 Excavation Curbstone 21-Apr-24 25-Apr-24 5 118
GR-CON-Z10-1469 Plain Concrete 27-Apr-24 02-May-24 6 153
GR-CON-Z10-1470 Installation Curbstone 04-May-24 13-May-24 9 153
GR-CON-Z10-1471 Casting Concrete (Mortar haunch) 14-May-24 18-May-24 4 153
GR-CON-Z10-1472 Backfilling (sand / Sub base) 19-May-24 28-May-24 9 153
GR-CON-Z10-1473 Installation of Paving 29-May-24 12-Jun-24 13 153
Landscape Works 27-Apr-24 23-Oct-24 150 24
GR-CON-Z10-1474 Excavation (Tree Pit ) 27-Apr-24 01-May-24 5 118
GR-CON-Z10-1475 Aggregate Drainage layer 02-May-24 08-May-24 6 118
GR-CON-Z10-1476 Installation Geotextile 09-May-24 13-May-24 4 118
GR-CON-Z10-1477 Backfilling (Soil max for tree) 14-May-24 20-May-24 6 118
GR-CON-Z10-1478 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11536 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11546 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11556 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11566 Installation of Grass 26-Sep-24 30-Sep-24 3 24
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z14-1056 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 21-Feb-24 14 205
MUGA 31-Aug-23 27-Feb-24 153 209
GR-CON-Z14-1057 Excavation And Disposal 31-Aug-23 06-Sep-23 6 276
GR-CON-Z14-1058 Prepretion And Compaction 07-Sep-23 14-Sep-23 7 276
GR-CON-Z14-1059 polyethylene under footings ( fence and gates) 16-Sep-23 21-Sep-23 6 276
GR-CON-Z14-1060 Blinding concrete (flooring) 24-Sep-23 30-Sep-23 6 276
GR-CON-Z14-1061 Concrete Footings ( fence and gates) 01-Oct-23 16-Oct-23 14 276
GR-CON-Z14-1062 Tools Play Installation ( basketball / football ..) 02-Jan-24 22-Jan-24 17 209
GR-CON-Z14-1063 PaintAcrylic Play Surface 22-Jan-24 07-Feb-24 14 209
GR-CON-Z14-1064 Fence (high / low) / gates Installation 07-Feb-24 27-Feb-24 17 209
Irrigation Works 17-Aug-23 03-Mar-24 169 205
GR-CON-Z14-1065 Excavation Pipe Irrigation 17-Aug-23 23-Aug-23 6 271
GR-CON-Z14-1066 Sand Bedding 24-Aug-23 27-Aug-23 3 271
GR-CON-Z14-1067 HDPE Pipe Installations and fittings and conduit for cable 02-Sep-23 21-Sep-23 17 266
GR-CON-Z14-1069 Test pressure 21-Sep-23 30-Sep-23 6 266
GR-CON-Z14-1068 Installation of Valves and Accessories 30-Sep-23 05-Oct-23 5 266
GR-CON-Z14-1070 Back filling (sand / Subbase ) 05-Oct-23 14-Oct-23 7 266
GR-CON-Z14-1071 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Oct-23 22-Oct-23 7 310
GR-CON-Z14-1072 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Feb-24
system 03-Mar-24 9 205
Mosque M-23 10-Aug-23 27-Mar-24 193 206
Site Preparation 10-Aug-23 31-Aug-23 19 359
GR-CON-Z14-1107 Demolition (Asphalt.Paving,etc.....) 10-Aug-23 14-Aug-23 4 40
GR-CON-Z14-1108 Excavation And Disposal 15-Aug-23 20-Aug-23 5 274
GR-CON-Z14-1109 Prepretion And Compaction 21-Aug-23 24-Aug-23 4 359
GR-CON-Z14-1110 Backfilling 26-Aug-23 31-Aug-23 6 359
Curbstone and Paving 02-Sep-23 27-Sep-23 22 359
GR-CON-Z14-1115 Backfilling (sand / Sub base) 02-Sep-23 11-Sep-23 9 359
GR-CON-Z14-1116 Installation of Paving 12-Sep-23 27-Sep-23 13 359
Landscape Works 21-Aug-23 27-Mar-24 184 206
GR-CON-Z14-1117 Excavation (Tree Pit ) 21-Aug-23 26-Aug-23 5 307
GR-CON-Z14-1118 Aggregate Drainage layer 27-Aug-23 02-Sep-23 6 307
GR-CON-Z14-1119 Installation Geotextile 03-Sep-23 07-Sep-23 5 307
GR-CON-Z14-1120 Backfilling (Soil max for tree) 09-Sep-23 13-Sep-23 5 307
GR-CON-Z14-1121 Installation of Trees 10-Jan-24 15-Jan-24 4 206
GR-CON-Z14-4346 Installation of Climbers 15-Jan-24 20-Jan-24 4 206
GR-CON-Z14-4356 Installation of Shrubs 20-Jan-24 24-Jan-24 4 206
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z13-1190 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Apr-24 02-May-24 6 156
GR-CON-Z13-1191 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 156
Electrical Works 05-Mar-24 22-Aug-24 132 78
GR-CON-Z13-1197 Excavation And Disposal 05-Mar-24 11-Mar-24 5 183
GR-CON-Z13-1198 Sand Bedding 11-Mar-24 16-Mar-24 4 183
GR-CON-Z13-1199 laying cables 17-Mar-24 23-Mar-24 4 183
GR-CON-Z13-1200 Backfilling (sand / Sub base) 23-Mar-24 30-Mar-24 5 183
GR-CON-Z13-1201 Control Panel / Distribution Panel Installation 31-Mar-24 06-Apr-24 4 183
GR-CON-Z13-1202 Road Crossing Ducts 17-Aug-24 22-Aug-24 5 78
Street SS-19 24-Feb-24 19-Sep-24 165 54
Site Preparation 24-Feb-24 07-Apr-24 32 187
GR-CON-Z13-1203 Demolition (Asphalt.Paving,etc.....) 24-Feb-24 02-Mar-24 6 54
GR-CON-Z13-1204 Excavation And Disposal 02-Mar-24 11-Mar-24 8 66
GR-CON-Z13-1205 Prepretion And Compaction 11-Mar-24 24-Mar-24 9 187
GR-CON-Z13-1206 Backfilling 24-Mar-24 07-Apr-24 9 187
Curbstone and Paving 11-Mar-24 13-Jun-24 71 134
GR-CON-Z13-1207 Excavation Curbstone 11-Mar-24 23-Mar-24 8 86
GR-CON-Z13-1208 Plain Concrete 23-Mar-24 06-Apr-24 9 134
GR-CON-Z13-1209 Installation Curbstone 06-Apr-24 28-Apr-24 14 134
GR-CON-Z13-1210 Casting Concrete (Mortar haunch) 28-Apr-24 05-May-24 6 134
GR-CON-Z13-1211 Backfilling (sand / Sub base) 05-May-24 21-May-24 14 134
GR-CON-Z13-1212 Installation of Paving 21-May-24 13-Jun-24 20 134
Landscape Works 23-Mar-24 13-Aug-24 111 54
GR-CON-Z13-1213 Excavation (Tree Pit ) 23-Mar-24 03-Apr-24 8 86
GR-CON-Z13-1214 Aggregate Drainage layer 04-Apr-24 21-Apr-24 9 86
GR-CON-Z13-1215 Installation Geotextile 21-Apr-24 28-Apr-24 6 86
GR-CON-Z13-1216 Backfilling (Soil max for tree) 28-Apr-24 08-May-24 9 86
GR-CON-Z13-1217 Installation of Trees 15-Jun-24 24-Jun-24 4 54
GR-CON-Z13-12176 Installation of Shrubs 24-Jun-24 27-Jun-24 3 54
GR-CON-Z13-12186 Installation of Succulents 27-Jun-24 01-Jul-24 3 54
GR-CON-Z13-12196 Installation of Ground Covers 01-Jul-24 04-Jul-24 3 54
GR-CON-Z13-12206 Installation of Grass 04-Jul-24 08-Jul-24 3 54
GR-CON-Z13-1218 Backfilling (Mulch) 08-Jul-24 14-Jul-24 5 54
GR-CON-Z13-1219 Natural Boulders Installation 14-Jul-24 21-Jul-24 6 54
GR-CON-Z13-1220 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 13-Aug-24 20 54
Site Furnishing 13-Aug-24 19-Sep-24 32 54
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z20-1530 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 30-Dec-23 23-Oct-24 242 38
GR-CON-Z20-1531 Excavation Pipe Irrigation 30-Dec-23 03-Jan-24 5 141
GR-CON-Z20-1532 Sand Bedding 04-Jan-24 07-Jan-24 3 141
GR-CON-Z20-1533 HDPE Pipe Installations and fittings and conduit for cable 08-Jan-24 24-Jan-24 15 141
GR-CON-Z20-1535 Test pressure 25-Jan-24 30-Jan-24 5 141
GR-CON-Z20-1534 Installation of Valves and Accessories 31-Jan-24 04-Feb-24 4 141
GR-CON-Z20-1536 Back filling (sand / Subbase ) 05-Feb-24 11-Feb-24 6 141
GR-CON-Z20-1537 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 12-Feb-24 18-Feb-24 6 230
GR-CON-Z20-1538 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-28 24-Dec-23 23-Oct-24 247 38
Site Preparation 24-Dec-23 14-Jan-24 19 244
GR-CON-Z20-1539 Demolition (Asphalt.Paving,etc.....) 24-Dec-23 27-Dec-23 4 137
GR-CON-Z20-1540 Excavation And Disposal 28-Dec-23 02-Jan-24 5 137
GR-CON-Z20-1541 Prepretion And Compaction 03-Jan-24 07-Jan-24 4 244
GR-CON-Z20-1542 Backfilling 08-Jan-24 14-Jan-24 6 244
Curbstone and Paving 15-Jan-24 08-Feb-24 22 244
GR-CON-Z20-1547 Backfilling (sand / Sub base) 15-Jan-24 24-Jan-24 9 244
GR-CON-Z20-1548 Installation of Paving 25-Jan-24 08-Feb-24 13 244
Landscape Works 03-Jan-24 23-Oct-24 238 38
GR-CON-Z20-1549 Excavation (Tree Pit ) 03-Jan-24 08-Jan-24 5 192
GR-CON-Z20-1550 Aggregate Drainage layer 09-Jan-24 15-Jan-24 6 192
GR-CON-Z20-1551 Installation Geotextile 16-Jan-24 21-Jan-24 5 192
GR-CON-Z20-1552 Backfilling (Soil max for tree) 22-Jan-24 27-Jan-24 5 192
GR-CON-Z20-1553 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-5026 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-5036 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-5046 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-5056 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1554 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1555 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1556 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 03-Jan-24 23-Oct-24 238 38
GR-CON-Z20-1557 Excavation Pipe Irrigation 03-Jan-24 08-Jan-24 5 137
GR-CON-Z20-1558 Sand Bedding 09-Jan-24 11-Jan-24 3 137
GR-CON-Z20-1559 HDPE Pipe Installations and fittings and conduit for cable 13-Jan-24 29-Jan-24 15 137
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z20-1057 HDPE Pipe Installations and fittings and conduit for cable 28-Jan-24 14-Feb-24 15 123
GR-CON-Z20-1059 Test pressure 14-Feb-24 20-Feb-24 5 123
GR-CON-Z20-1058 Installation of Valves and Accessories 20-Feb-24 25-Feb-24 4 123
GR-CON-Z20-1060 Back filling (sand / Subbase ) 25-Feb-24 03-Mar-24 6 123
GR-CON-Z20-1061 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Mar-24 10-Mar-24 6 204
GR-CON-Z20-1062 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Mar-24
system 20-Mar-24 8 204
Electrical Works 23-Jan-24 14-Oct-24 212 46
GR-CON-Z20-1068 Excavation And Disposal 23-Jan-24 29-Jan-24 5 231
GR-CON-Z20-1069 Sand Bedding 29-Jan-24 03-Feb-24 4 231
GR-CON-Z20-1070 laying cables 03-Feb-24 07-Feb-24 4 231
GR-CON-Z20-1071 Backfilling (sand / Sub base) 07-Feb-24 13-Feb-24 5 231
GR-CON-Z20-1072 Control Panel / Distribution Panel Installation 13-Feb-24 18-Feb-24 4 231
GR-CON-Z20-1073 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-19 13-Jan-24 14-Oct-24 221 46
Site Preparation 13-Jan-24 06-Feb-24 21 246
GR-CON-Z20-1074 Demolition (Asphalt.Paving,etc.....) 13-Jan-24 17-Jan-24 4 118
GR-CON-Z20-1075 Excavation And Disposal 17-Jan-24 23-Jan-24 5 118
GR-CON-Z20-1076 Prepretion And Compaction 23-Jan-24 30-Jan-24 6 246
GR-CON-Z20-1077 Backfilling 30-Jan-24 06-Feb-24 6 246
Curbstone and Paving 23-Jan-24 18-Mar-24 46 212
GR-CON-Z20-1078 Excavation Curbstone 23-Jan-24 29-Jan-24 5 177
GR-CON-Z20-1079 Plain Concrete 29-Jan-24 05-Feb-24 6 212
GR-CON-Z20-1080 Installation Curbstone 05-Feb-24 15-Feb-24 9 212
GR-CON-Z20-1081 Casting Concrete (Mortar haunch) 15-Feb-24 20-Feb-24 4 212
GR-CON-Z20-1082 Backfilling (sand / Sub base) 20-Feb-24 02-Mar-24 9 212
GR-CON-Z20-1083 Installation of Paving 02-Mar-24 18-Mar-24 13 212
Landscape Works 29-Jan-24 19-Sep-24 187 46
GR-CON-Z20-1084 Excavation (Tree Pit ) 29-Jan-24 04-Feb-24 5 177
GR-CON-Z20-1085 Aggregate Drainage layer 04-Feb-24 11-Feb-24 6 177
GR-CON-Z20-1086 Installation Geotextile 11-Feb-24 15-Feb-24 4 177
GR-CON-Z20-1087 Backfilling (Soil max for tree) 15-Feb-24 22-Feb-24 6 177
GR-CON-Z20-1088 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14136 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14146 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14156 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14166 Installation of Grass 25-Aug-24 27-Aug-24 3 46
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z20-1320 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Jul-24 25-Jul-24 6 100
GR-CON-Z20-1321 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Jul-24
system 04-Aug-24 8 100
Electrical Works 05-Jun-24 14-Oct-24 108 46
GR-CON-Z20-1327 Excavation And Disposal 05-Jun-24 10-Jun-24 5 127
GR-CON-Z20-1328 Sand Bedding 11-Jun-24 15-Jun-24 4 127
GR-CON-Z20-1329 laying cables 16-Jun-24 24-Jun-24 4 127
GR-CON-Z20-1330 Backfilling (sand / Sub base) 25-Jun-24 30-Jun-24 5 127
GR-CON-Z20-1331 Control Panel / Distribution Panel Installation 01-Jul-24 04-Jul-24 4 127
GR-CON-Z20-1332 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Zone 16 03-Dec-23 17-Nov-24 285 11
Future Neighborhood Park FNP-24 03-Dec-23 25-Sep-24 240 56
Site Preparation 03-Dec-23 26-Dec-23 20 276
GR-CON-Z16-1157 Demolition (Asphalt.Paving,etc.....) 03-Dec-23 07-Dec-23 4 16
GR-CON-Z16-1158 Excavation And Disposal 07-Dec-23 14-Dec-23 6 169
GR-CON-Z16-1159 Prepretion And Compaction 14-Dec-23 19-Dec-23 4 276
GR-CON-Z16-1160 Backfilling 19-Dec-23 26-Dec-23 6 276
Curbstone and Paving 14-Dec-23 06-Feb-24 46 240
GR-CON-Z16-1161 Excavation Curbstone 14-Dec-23 20-Dec-23 5 226
GR-CON-Z16-1162 Plain Concrete 20-Dec-23 27-Dec-23 6 240
GR-CON-Z16-1163 Installation Curbstone 27-Dec-23 07-Jan-24 9 240
GR-CON-Z16-1164 Casting Concrete (Mortar haunch) 07-Jan-24 11-Jan-24 4 240
GR-CON-Z16-1165 Backfilling (sand / Sub base) 11-Jan-24 22-Jan-24 9 240
GR-CON-Z16-1166 Installation of Paving 22-Jan-24 06-Feb-24 13 240
Landscape Works 20-Dec-23 25-Sep-24 225 56
GR-CON-Z16-1167 Excavation (Tree Pit ) 20-Dec-23 26-Dec-23 5 226
GR-CON-Z16-1168 Aggregate Drainage layer 26-Dec-23 02-Jan-24 6 226
GR-CON-Z16-1169 Installation Geotextile 02-Jan-24 07-Jan-24 4 226
GR-CON-Z16-1170 Backfilling (Soil max for tree) 07-Jan-24 14-Jan-24 6 226
GR-CON-Z16-1171 Installation of Trees 15-Aug-24 18-Aug-24 2 56
GR-CON-Z16-2706 Installation of Shrubs 18-Aug-24 20-Aug-24 2 56
GR-CON-Z16-2716 Installation of Succulents 20-Aug-24 22-Aug-24 2 56
GR-CON-Z16-2726 Installation of Ground Covers 22-Aug-24 25-Aug-24 2 56
GR-CON-Z16-2736 Installation of Climbers 25-Aug-24 27-Aug-24 2 56
GR-CON-Z16-2746 Installation of Grass 27-Aug-24 29-Aug-24 2 56
GR-CON-Z16-2756 Installation of Lawns 29-Aug-24 01-Sep-24 2 56
GR-CON-Z16-1172 Backfilling (Mulch) 01-Sep-24 04-Sep-24 3 56
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z16-1203 HDPE Pipe Installations and fittings and conduit for cable 27-Dec-23 14-Jan-24 15 166
GR-CON-Z16-1205 Test pressure 14-Jan-24 20-Jan-24 5 166
GR-CON-Z16-1204 Installation of Valves and Accessories 20-Jan-24 24-Jan-24 4 166
GR-CON-Z16-1206 Back filling (sand / Subbase ) 24-Jan-24 31-Jan-24 6 166
GR-CON-Z16-1207 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 31-Jan-24 07-Feb-24 6 233
GR-CON-Z16-1208 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Oct-24
system 29-Oct-24 6 27
Mosque M-26 12-Dec-23 29-Oct-24 261 27
Site Preparation 12-Dec-23 03-Jan-24 19 247
GR-CON-Z16-1209 Demolition (Asphalt.Paving,etc.....) 12-Dec-23 17-Dec-23 4 63
GR-CON-Z16-1210 Excavation And Disposal 17-Dec-23 23-Dec-23 5 162
GR-CON-Z16-1211 Prepretion And Compaction 23-Dec-23 27-Dec-23 4 247
GR-CON-Z16-1212 Backfilling 27-Dec-23 03-Jan-24 6 247
Curbstone and Paving 03-Jan-24 29-Jan-24 22 247
GR-CON-Z16-1217 Backfilling (sand / Sub base) 03-Jan-24 14-Jan-24 9 247
GR-CON-Z16-1218 Installation of Paving 14-Jan-24 29-Jan-24 13 247
Landscape Works 23-Dec-23 29-Oct-24 252 27
GR-CON-Z16-1219 Excavation (Tree Pit ) 23-Dec-23 28-Dec-23 5 195
GR-CON-Z16-1220 Aggregate Drainage layer 28-Dec-23 04-Jan-24 6 195
GR-CON-Z16-1221 Installation Geotextile 04-Jan-24 10-Jan-24 5 195
GR-CON-Z16-1222 Backfilling (Soil max for tree) 10-Jan-24 16-Jan-24 5 195
GR-CON-Z16-1223 Installation of Trees 15-Aug-24 20-Aug-24 4 27
GR-CON-Z16-4666 Installation of Climbers 20-Aug-24 25-Aug-24 4 27
GR-CON-Z16-4676 Installation of Shrubs 25-Aug-24 29-Aug-24 4 27
GR-CON-Z16-4686 Installation of Succulents 29-Aug-24 03-Sep-24 4 27
GR-CON-Z16-4696 Installation of Ground Covers 03-Sep-24 08-Sep-24 4 27
GR-CON-Z16-1224 Backfilling (Mulch) 08-Sep-24 26-Sep-24 15 27
GR-CON-Z16-1225 Natural Boulders Installation 26-Sep-24 12-Oct-24 13 27
GR-CON-Z16-1226 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Oct-24 29-Oct-24 15 27
Irrigation Works 23-Dec-23 29-Oct-24 252 27
GR-CON-Z16-1227 Excavation Pipe Irrigation 23-Dec-23 28-Dec-23 5 162
GR-CON-Z16-1228 Sand Bedding 28-Dec-23 01-Jan-24 3 162
GR-CON-Z16-1229 HDPE Pipe Installations and fittings and conduit for cable 01-Jan-24 18-Jan-24 15 162
GR-CON-Z16-1231 Test pressure 18-Jan-24 24-Jan-24 5 162
GR-CON-Z16-1230 Installation of Valves and Accessories 24-Jan-24 29-Jan-24 4 162
GR-CON-Z16-1232 Back filling (sand / Subbase ) 29-Jan-24 05-Feb-24 6 162
GR-CON-Z16-1233 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Feb-24 12-Feb-24 6 229
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z16-1481 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-May-24 03-Jun-24 9 128
GR-CON-Z16-1482 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jun-24
system 17-Jun-24 12 128
Electrical Works 12-Mar-24 17-Nov-24 199 11
GR-CON-Z16-1488 Excavation And Disposal 12-Mar-24 24-Mar-24 8 168
GR-CON-Z16-1489 Sand Bedding 24-Mar-24 02-Apr-24 6 168
GR-CON-Z16-1490 laying cables 02-Apr-24 11-Apr-24 6 168
GR-CON-Z16-1491 Backfilling (sand / Sub base) 11-Apr-24 25-Apr-24 8 168
GR-CON-Z16-1492 Control Panel / Distribution Panel Installation 25-Apr-24 02-May-24 6 168
GR-CON-Z16-1493 Road Crossing Ducts 07-Nov-24 17-Nov-24 8 11
Street SS-28 22-Feb-24 20-Oct-24 191 35
Site Preparation 22-Feb-24 19-Mar-24 21 205
GR-CON-Z16-1494 Demolition (Asphalt.Paving,etc.....) 22-Feb-24 27-Feb-24 4 39
GR-CON-Z16-1495 Excavation And Disposal 27-Feb-24 04-Mar-24 5 99
GR-CON-Z16-1496 Prepretion And Compaction 04-Mar-24 11-Mar-24 6 205
GR-CON-Z16-1497 Backfilling 11-Mar-24 19-Mar-24 6 205
Curbstone and Paving 04-Mar-24 08-May-24 46 171
GR-CON-Z16-1498 Excavation Curbstone 04-Mar-24 10-Mar-24 5 136
GR-CON-Z16-1499 Plain Concrete 10-Mar-24 18-Mar-24 6 171
GR-CON-Z16-1500 Installation Curbstone 18-Mar-24 01-Apr-24 9 171
GR-CON-Z16-1501 Casting Concrete (Mortar haunch) 01-Apr-24 07-Apr-24 4 171
GR-CON-Z16-1502 Backfilling (sand / Sub base) 07-Apr-24 23-Apr-24 9 171
GR-CON-Z16-1503 Installation of Paving 23-Apr-24 08-May-24 13 171
Landscape Works 10-Mar-24 26-Sep-24 157 35
GR-CON-Z16-1504 Excavation (Tree Pit ) 10-Mar-24 16-Mar-24 5 136
GR-CON-Z16-1505 Aggregate Drainage layer 17-Mar-24 25-Mar-24 6 136
GR-CON-Z16-1506 Installation Geotextile 26-Mar-24 01-Apr-24 4 136
GR-CON-Z16-1507 Backfilling (Soil max for tree) 01-Apr-24 10-Apr-24 6 136
GR-CON-Z16-1508 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13096 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13106 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13116 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13126 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1509 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1510 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1511 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
Activity ID Activity Name Start Finish Original Total Float
Duration
GR-CON-Z15-1588 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Apr-24 07-May-24 6 170
GR-CON-Z15-1589 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-May-24
system 16-May-24 8 170
Electrical Works 10-Mar-24 05-Aug-24 113 111
GR-CON-Z15-1595 Excavation And Disposal 10-Mar-24 16-Mar-24 5 197
GR-CON-Z15-1596 Sand Bedding 17-Mar-24 23-Mar-24 4 197
GR-CON-Z15-1597 laying cables 23-Mar-24 28-Mar-24 4 197
GR-CON-Z15-1598 Backfilling (sand / Sub base) 28-Mar-24 06-Apr-24 5 197
GR-CON-Z15-1599 Control Panel / Distribution Panel Installation 06-Apr-24 11-Apr-24 4 197
GR-CON-Z15-1600 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-57 27-Feb-24 05-Aug-24 123 111
Site Preparation 27-Feb-24 25-Mar-24 21 213
GR-CON-Z15-1601 Demolition (Asphalt.Paving,etc.....) 27-Feb-24 03-Mar-24 4 75
GR-CON-Z15-1602 Excavation And Disposal 03-Mar-24 09-Mar-24 5 95
GR-CON-Z15-1603 Prepretion And Compaction 09-Mar-24 16-Mar-24 6 213
GR-CON-Z15-1604 Backfilling 17-Mar-24 25-Mar-24 6 213
Curbstone and Paving 09-Mar-24 13-May-24 46 179
GR-CON-Z15-1605 Excavation Curbstone 09-Mar-24 14-Mar-24 5 144
GR-CON-Z15-1606 Plain Concrete 14-Mar-24 24-Mar-24 6 179
GR-CON-Z15-1607 Installation Curbstone 24-Mar-24 07-Apr-24 9 179
GR-CON-Z15-1608 Casting Concrete (Mortar haunch) 07-Apr-24 17-Apr-24 4 179
GR-CON-Z15-1609 Backfilling (sand / Sub base) 17-Apr-24 28-Apr-24 9 179
GR-CON-Z15-1610 Installation of Paving 28-Apr-24 13-May-24 13 179
Landscape Works 14-Mar-24 13-Jul-24 89 111
GR-CON-Z15-1611 Excavation (Tree Pit ) 14-Mar-24 23-Mar-24 5 144
GR-CON-Z15-1612 Aggregate Drainage layer 23-Mar-24 01-Apr-24 6 144
GR-CON-Z15-1613 Installation Geotextile 01-Apr-24 07-Apr-24 4 144
GR-CON-Z15-1614 Backfilling (Soil max for tree) 07-Apr-24 20-Apr-24 6 144
GR-CON-Z15-1615 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12816 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12826 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12836 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12846 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1616 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1617 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1618 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
Activity ID Activity Name Start Finish Original Total Float
Duration