Project Management
Project Management
Project Management
Integrity
• Project Management
• Managing a single project
• Program Management
• Managing a group of strategically grouped projects to facilitate effective
management
• Portfolio Management
• Managing a group of related projects in a coordinated way to obtain
benefits and control
Do the activities
Act Do and document
while you do
Development Phase
• Operation Managers
• Functional Managers
• Business Partners
• Customers
• Government
Other
Stakeholders
Project Team
• Sponsor
• Project Manager
• Team Members
• Functional
• Matrix
• Weak Matrix
• Balanced Matrix
• Strong Matrix
• Projectized
Monitoring &
Controlling
Processes
Initiating Planning Executing Closing
Processes Processes Processes Processes
• Collect Requirements
• Define Scope
• Create WBS
• Verify Scope
• Control Scope
• Interviews
• Focus groups
• Facilitated workshops
• Group Creativity Techniques
• Brainstorming, Nominal group technique, The Delphi Technique,
Idea/mind mapping, Affinity diagram
• Group Decision Making Techniques
• Unanimity, majority, plurality, dictatorship
• Questionnaires/surveys
• Prototypes
• Document
• How requirements meet the business needs
• How the requirements originated
• Requirements:
• Project Charter
• Preliminary scope statement
• Stakeholder Register
• Section 10.1, page 246 (see sample)
Car
Project
1.0
2.0 Design 3.0 Build
Requirements
• Methods
• Top-Down
• Bottom-Up
• WBS Standards
• WBS Templates
• Inspection
• Measure
• Examine
• Verify (against baseline)
• Outputs
• Accepted deliverables
• Formally signed off by the customer or sponsor
• Change requests
• For deliverables not accepted
• Include reasons for non-acceptance
• Scope creep
• Incremental expansion of the project scope or delivered
product/service/result
• Gold plating
• Giving the customer or sponsor an “improved” product/service/result
(more than they asked for)
• Considered a failure
• Outputs
• Work Performance Measurements
• Planned vs. actual performance (scope, time, cost)
• Change Requests
• To request changes to the scope; can be initiated by the customer/sponsor or the
project team
• Define Activities
• Sequence Activities
• Estimate Activity Resources
• Estimate Activity Durations
• Develop Schedule
• Control Schedule
• Finish-to-finish (FF)
• Activity A must finish before Activity B can finish
• Start-to-start (SS)
• Activity A must start before Activity B can start
• Mandatory Dependency
• Contractually required or inherent in the nature of the work (hard logic –
required)
• Discretionary Dependency
• Preferred actions based on best practices or desires (soft logic – not
required)
• External Dependency
• Involve a relationship between project activities and non-project
activities and are outside the project team’s control
• Expert judgment
• Alternatives analysis
• Published estimating data
• Bottom-up estimating (requires further decomposition)
• Uses the actual time (or cost, etc.) from a previous, similar project
to estimate time required (or cost, etc.) for a future project (root
of the word analogy)
• Uses historical information and expert judgment
• Typically used early in the project
• Less costly and time consuming than other methods…but also can
be less accurate!
• Example – Rough Order of Magnitude
A
3 weeks
LS LF
• Relationships are arrows:
A B
A C G
(7) (6) (3)
H
Start Finish
(2)
B D E
(3) (3) (3)
F
(2)
0 7 7 13 13 16
A C G
(7) (6) (7)
16 18
H Finish
Start (2)
0 3 3 6 6 9
B D E
(3) (3) (3)
3 5
F
(2)
0 7 7 13 13 16
A C G
(7) (6) (7)
0 7 7 13 13 16
16 18
H Finish
Start (2)
0 3 3 6 6 9 16 18
B D E
(3) (3) (3)
7 10 10 13 13 16
3 5
F
(2)
11 13
89 Project Time Management
Example (cont’d)
7. Identify the float and critical path
0 0 0
0 7 7 13 13 16
A C G
(7) (6) (7) 0
0 7 7 13 13 16
16 18
Start 7 7 7 H
(2)
Finish
0 3 3 6 6 9 16 18
B D E
(3) (3) (3)
7 10 10 13 13 16
8
3 5
F
(2)
11 13
90 Project Time Management
Critical Chain Method
• Performance Reviews
• Earned Value Management (EVM)
• Schedule Variance (SV)
• Schedule Performance Index
• Determining if schedule variance requires corrective action
• Variance Analysis
• Project Management Software
How to determine …
• What is a requirement?
• What is not a requirement?
Types of requirements:
• Functional requirements
• Non-functional requirements
• Hidden and generated requirements
Graphical Textual
Engineering
Marketing
WBS
PMO
# WBS Item Who is … Description
1.0 Plan C C RA R Responsible Assigned work
2.0 Execute RA C I A Accountable Owns the work
2.1.1
Design
1.0
2.2 2.3.1
Plan
Phase 2 Upgrade
2.1.2
Focus
Group
• Is data rounded?
Level of accuracy
• Are there contingencies in the estimates?
Cash flow • Estimated costs and benefits with resulting cash flow
analysis • i.e. CASH IN and CASH OUT
Profit
Fee
Rate
Fee is based on Profit Rate is
COST based on PRICE
Direct Indirect
Costs Costs clearly Costs Costs only
traceable indirectly related
(associated) with to performing
project the project
• Labour • Overhead
• Material • Taxes
• Equipment • Risk
• Fees • Office Rent
• Administrative staff
• Benefits
Fixed Variable
Costs Occur at regular Costs Occur in
intervals at a proportion to
relatively fixed some usage
rate factor
Tangible Intangible
Costs Costs
Easy to measure Difficult to
in monetary measure in
terms monetary terms
Capital Operating
Costs Costs
Capital Operating
expenditures or expenditures or
Cap. Ex. Op. Ex.
Reserve Funds
• Money set aside to allow for difficult to predict situations
• Contingency reserves allow for future situations that may be
partially planned for (sometimes called known unknowns) and
are included in project cost baseline
• Management reserves allow for future situations that are
unpredictable (sometimes called unknown unknowns) but are
not included in project cost baseline
Estimate Costs
Determine Budget
Control Costs
119 Project Management
Estimate Costs
Objectives:
• Make a project “go/no go” decision (feasibility analysis)
• Project evaluation
• Provide a basis for cost control
Good budgets start with good estimates:
• To complete projects within budget limits
• Budgets only as good as estimates
• Estimates built upon assumptions
Project managers must know:
• Types of cost estimates
• How to prepare cost estimates
• Typical problems associated with cost estimates
125%
115%
±50%
Variance
105%
95% ±5%
85%
75%
65%
Time
121 Project Management
Estimate Costs
Problem Consequence
Each bid is “new”
Lack of historical cost information
Do not learn from failure/success
Technical staff write proposals,
Techies are not cost accountants
as additional duty
Obsolete estimating databases Inaccurate cost estimates
Guesstimates Ballpark guesses often too low
Arbitrary changes by senior Why cost estimate?
management Unreasonable budgets
Complex accounting systems Useful functionality under-utilized
Management secrecy Estimator must assume numbers,
– labour, indirect costs not shared though they are available
James Taylor, Project Scheduling and Cost Control: Planning, Monitoring and Controlling the Baseline (2007) J Ross
Publishing, P.85
Estimate Costs
Determine Budget
Control Costs
131 Project Management
Cost Baseline – Example
Cost Baseline Cost (QAR) / Day Total
WBS Items 1 2 3 4 5 6 7 (QAR)
1. Initiate & Plan 1600 3200 200 5,000
2. Execute
2.1 Phase I
2.1.1 Design 2400 600 3,000
2.1.2 Focus Group 1000 1,000
2.2 Phase II 600 1200 1800 3,600
2.3 Phase III
2.3.1 Upgrade 2800 700 3,500
2.3.2 Integration 1000 1,000
3. Monitor & Control 600 600 600 600 600 3,000
4. Close 1500 1,500
5. Reserves (20%) 4,320
TOTALS 1600 5600 3000 1800 5200 2300 2100 25,920
132 Project Management
Tools and Techniques
Reserve Analysis
• Contingency Reserve (Include known risks)
• Management Reserve (Exclude unknown risks)
Expert Judgment
Historical Relationships
• E.g. Building type has cost per square meter
Expenditures
Time
• Due to Inflation, QAR 100 today is worth more than QAR 100 in
one year
• Discount Rate is annual investment return
• Always DISCOUNT future amounts to a given time (today) so comparisons
are meaningful
• i.e. Opportunity Cost of investing money today
• Present Value PV is value of Riyal today.
PVn = FVn
i = discount rate
(1+i )n
n = number of years
• Payback Analysis
• The time it takes for Benefits to equal Costs
• Net Present Value
NPV = Σ Discounted Benefits – Σ Discounted Costs
• Return on Investment (ROI)
Lifetime Benefits – Lifetime Costs
Lifetime ROI =
Lifetime Costs
$80,000
$60,000
$40,000
$20,000
$0
1 2 3 4 5 6
Year
Estimate Costs
Determine Budget
Control Costs
139 Project Management
What is Cost Control?
• Direct progress
• Direct actions
• Control results
• Conserve resources
USA
UK/France
Canada
• Sydney • A planned • Chunnel • F35 Joint
Opera $2 million • 80% for Strike
House gun registry construction Fighter
• 1,400% ended up costs project at
costing • 140% for $388
over $1 financing billion
billion. costs • 50% over
initial
estimated
budget
CPI = EV / AC
SPI = EV / PV
EV = Earned Value
Time
Identify EV curve first, then compare to PV
(schedule) and AC (cost) variances
145 Project Management
Earned Value Management
Ahead of
75 100 100 Schedule
On Budget
Ahead of
75 100 150 Schedule
Over Budget
Ahead of
100 150 100 Schedule
Under Budget
Behind
150 100 75 Schedule
Under Budget
Behind
100 75 100 Schedule
Over Budget
Behind
150 100 100 Schedule
On Budget
1/3
1/3 Chance Chance
200 People that 600 400
that no
will be saved, People
saved 2/3 that
one dies,
will die
none saved 2/3 that
600 die
Food
Flying Driving Terrorism
Poisoning
• Evolution:
• Brain reaction: Amygdala vs. Neocortex
• Evolution has bias towards “lucky”
• People often poor judges of risk
• Bad at dealing with large numbers
• 1:2 1:4 1:1,000,000 1:1,000,000,000
Over-
Novelty Dread
reaction
Severity of risks
Probability of risks
Magnitude of risks
effects = impact
Known risk
• Identified & analyzed
with planned response
Unknown risk
• Cannot be proactively
managed
• Need a contingency
plan
Negative risk
• Threat
• Project problems
• Aim to minimize
Open communication
Organizational support
Perform Qualitative
• Prioritize risks for further analysis
Risk Analysis
Perform Quantitative
• Numerical models of risk analysis
Risk Analysis
I. Methodology
II. Roles and Responsibilities
III. Budget and Schedule
IV. Risk Categories
V. Define Probability and Impact terms
VI. Risk Documentation
VII.Risk Tracking Mechanism
Documentation Reviews
Brainstorming
Interviewing
SWOT analysis
Diagramming Techniques
O T
• Helps identify the broad negative and positive risks that apply to a
project
Risks + –
Market Risk
Financial Risk
Technology Risk
People Risk
Structure / Process Risk
181 Project Management
Risk Breakdown by Knowledge Area
Integration Scope Time
• Inadequate planning • Poor definition of scope or work • Errors in estimating time or
• Poor resource allocation packages resource availability
• Poor integration management • Incomplete definition of quality • Poor allocation and
• Lack of post-project review requirements management of float
• Inadequate scope control • Early release of competitive
products
Project
Technical External Organizational
Management
IT Project
Project
Business Technical Organizational
Management
Executive
Competitors Hardware Estimates
support
Risk Name
Risk Description
Risk Category
Risk Register Contents
Root Cause
Triggers / Symptoms
Project Risk Management
Potential Responses
Owner
Probability (High/Medium/Low)
Impact (High/Medium/Low)
Status (Open/Closed/Issue)
Risk Register Contents
Identify Risks
Project 1
Project 1
P=0.80 EMV=
EMV=
O=$-40,000 $-32,000
$28,000
Decision P=0.10 EMV=
O=$-20,000 $-2,000
P=0.20 EMV=
O=$-50,000 $-10,000
Project 2
Project 2
P=0.70 EMV=
EMV=
O=$60,000 $42,000
$30,000
EMV
Probability Outcome Expect
(P) (O) Monetary
Value
Cost-effective
Timely
Contingency Plans
• Predefined actions that project team will take if an
identified risk event occurs
Fallback Plans
• When primary response proves inadequate
Contingency Reserves
• Provisions held by project sponsor or organization to
reduce risk of cost or schedule overruns to an acceptable
level
Identify Stakeholders
Plan Communications
Distribute Information
Manage Stakeholder Expectations
Report Performance
207 Project Communication
Role of Communication in PM
Oral
• Presentation
• Audience Awareness
• Body Language
• Paralingual
Non-Verbal Written
• Academic Writing
• Critical Listening
• Revision & Editing
• Empathy
• Critical Reading
• Emotion
• Data Presentation
Monitor
Visualize
Non-verbals
Effective
Listening
Encourage
Paraphrase
the Other to
& Repeat
Talk
Make No
Assumptions
Project charter
Procedural Documents
High
Keep Manage
Satisfied Closely
Power
Keep
Monitor
Informed
Low High
218 Influence
Project Communication Management
Expert Judgment
• Senior management
• Other departments
• Key stakeholders
• Experienced PM on similar projects
• Subject matter experts (SMEs)
• Industry groups and consultants
• Professional and technical associations
225
Project Quality Management
Plan Quality Management
• Quality must be planned into project
• Identify relevant quality standards
• Determine how to satisfy them
• Pareto Principle
or 80/20 rule
• No Gold Plating!
226
Project Quality Management
Plan Quality Management
• Quality policy
• Organization directives on quality
• Who is responsible?
Quality • Both process and product responsibilities
Management
Plan • Where are we going?
• Depends on specific performance targets
• How are we going to get there?
• Processes, resources, and standards
• Process boundaries
• Process configuration
Process • Process metrics
Improvement
Plan • What is measured?
• What are thresholds and tolerances
• Targets for improvement
227
Project Quality Management
Quality Assurance vs. Control
• Prevent – Do right things in right • Detect – Keep mistakes out of
way deliverables
• Prevent mistakes from entering • Inspect – What’s done vs. What
project was expected
• Work is done properly the first • Ensure results conform to
time specifications
• Select relevant standards or • Provide basis for corrective action
specifications • Assess performance
• Collect data and compare results
• Recommend necessary changes
to plan
• Develop and apply metrics
228
Project Quality Management
Basic Quality Tools
TECHNICAL ORGANIZATIONAL
Requirements Politics
Technology Resources
Quality Funding
Vendors Estimating
Subcontractors Planning
Market Communications
Environment PROJECT Checklists
EXTERNAL MANAGEMENT Item
Cause and effect diagram A ✓
(Fishbone or Ishikawa diagram)
B ✓
C
…
Start Do … ? Stop
Benchmarking
Compare to similar project
Design of Experiments (DoE)
Determine optimal (best) conditions for process
Statistical Sampling
Establish sample frequency and size
A/B Testing
• Brainstorming
• Force field analysis
• Nominal group technique (NGT)
230
Project Quality Management
Quality Metrics
• On-time performance
• Cost of Quality (CoQ)
• Fault frequency
• Failure rate
• Availability
• Reliability
• Test coverage
231
Project Quality Management
Earned Value Management
232
Project Quality Management
Project Stakeholders
Project Team
• Sponsor
• Project Manager
• Team Members
Other Stakeholders
• Functional Managers
• Business Partners
• Customers
• Government
233
Project Quality Management
Closing Processes
Monitoring
and
Controlling
Processes
Executing
Processes
234
Project Quality Management
Closing Processes
237
Project Quality Management
Suggested Skills for Project Managers
238
Project Quality Management
Suggested Skills for Project Managers
Success
239
Project Quality Management
Task Time Predecessor
Name (Days) (Dependencies)
Proje 240
Task Time Predecessor
Task Time Name (Days) (Dependencies)
A 12 –
Early Early
Start Finish B 3 –
Late Late
Slack=0
FINISH is Critical
= START + TIME –1
Path C 14 –
Start Finish G 6 D 4 A, B
Slack= 17 22 E 17 B
20 25 F 3 C
A 12 D 4
Slack=3 G 6 D
1 12 13 16 H 2 D
4 15 16 19 I 5 E, F
H 2
Slack=3 Slack=3 J 1 F
17 18
24 25
B 3 E 17
Slack=7
START 1 3 4 20 END
0 1 3 4 20 25
I 5
Slack=0 Slack=0
21 25
21 25
C 14 F 3 Slack=0
1 14 15 17
4 17 18 20
J 1
Slack=3 Slack=3
18 18
25 25
Slack=7
Proje 241
Shortening Schedules