Universiti Teknologi Mara Uitm (Perak) BQS663 Earthworks

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

AP224 6D

UNIVERSITI TEKNOLOGI MARA


UiTM (PERAK)

BQS663

EARTHWORKS

COURSE : MEASUREMENT OF CIVIL ENGINEERING WORKS

COURSE CODE : BQS 663

DATE OF ISSUE : WEEK 5

DATE OF SUBMISSION : WEEK 7

PREPARED FOR : ENCIK MOHD NAZRI BT ABDULLAH

PREPARED BY:

NAME MATRIC NO

NUR SYAMIMI AMIRAH BT AZMAN 2019608016


TAKING OFF LIST Pages : 1

Project : Proposed construction and completeion of flexible road pavement and other related
works at KM87 route 8 Telemin Jaya-Berembang road.
Date : 20/5/2021
Taker-off : SYAMIMI AMIRAH

Item Code Description Unit


Class F-Earthwork
F121 Excavation, cut to fill excavated material erath M3

F311.1 Filling, general, excavated material M3

F332.1 Filling, replacement, imported material M3


Pages : 1
QUERY LIST

Project EARTHWORK
Date : 20/5/2021 From :
Attention : Send by :
Fax no./email : Fax no./email :

Item Question Assumption Answer

1 What is the type imported material for filling ? Earth To be confirmed by


the engineer

2 Where is the topsoil diposed ? Contractor own To be confirmed by


dumpsite the engineer
BILL OF QUANTITIES PAPER
JABATAN UKUR BAHAN,
FAKULTI SENIBINA, PERANCANGAN DAN UKUR, UiTM PERAK, KAMPUS SERI ISKANDAR

PROJECT : Proposed construction and completion of flexible road pavement and other related PAGE : 1
works at KM87 route 8 Telemin Jaya-Berembang road.
DRWG. NO : PPUB/QSM663/QSB651/JAN 2018/2 DATE : 20/5

Code Description Unit Quantity Rate (RM) Amount (RM)


ELEMENT: EARTHWORKS

Cut to Fill
F121 Excavation, cut to fill, earth material from original
ground level M3 93

General
F311.1 Filling, general, excavated material; earth M3 1036

Replacement
F332.1 Filling,replacement, imported material, earth M3 944
DIRECT BILLING PAPER
JABATAN UKUR BAHAN,
FAKULTI SENIBINA, PERANCANGAN DAN UKUR, UiTM PERAK, KAMPUS SERI ISKANDAR

PROJECT : EARTHWORK PAGE : 1


DRWG. NO : PPUB/QSM663/QSB651/JAN 2018/2 DATE : 20/5/2021

DESCRIPTION UNIT QUANTITY RATE $ cts.


ELEMENT: EARTHWORKS

Cut to fill
F121 Excavation, cut to fill, earth M3 93

Chainage Total Area


CH0.00 16.15
CH10.00 11.68

Volume1
Simpson
Rule

=1 V=L (A1+A2) 1/3

0.00 x (16.15 + 11.68) x

92.77 1/2

=10.00 x 27.83 x 1/3

=92.77
92.77
F311.1
General
Filling; general, excavated material, earth M3 1036

Chainage Total Area


CH10.00 13.64
CH20.00 45.80
CH30.00 120.60
CH40.00 69.64
CH50.00 37.56
CH60.00 23.65
TOTAL 310.89

Volume 1

V=1/3 x distance btwn cross section x sum of


all cross section

1036.3 =1/3 x 10.00m x 310.89

=1036.30
1,036.30

1.036.30
DIRECT BILLING PAPER
JABATAN UKUR BAHAN,
FAKULTI SENIBINA, PERANCANGAN DAN UKUR, UiTM PERAK, KAMPUS SERI ISKANDAR

PROJECT : EARTHWORK PAGE : 2


DRWG. NO : PPUB/QSM663/QSB651/JAN 2018/2 DATE : 20/5/2021

DESCRIPTION UNIT QUANTITY RATE $ cts.


ELEMENT: EARTHWORKS

Replacement
F332.1 Filling; general, imported materials, earth M3 944

Total Fill
= 1036.30

Total Cut
= 92.77

Fill - Cut
1,036.30
less 92.77
943.53 943.53
943.53
EARTHWORK JAN 2018 – NUR SYAMIMI AMIRAH BT AZMAN

SCHEDULE OF EARTHWORK

Cross Section Area (m2) Weightage Weightage Area

CUT (Area x weightage)


CH0.00 16.15 1 16.15
CH10.0 2.92 4 11.68
CH20.0 0 2 0
CH30.0 0 4 0
CH40.0 0 2 0
CH50.0 0 4 0
CH60.0 0 1 0
TOTAL 27.83

Cross Section Area (m2) Weightage Weightage Area

FILL (Area x weightage)


CH0.00 0 1 0
CH10.0 3.41 4 13.64
CH20.0 22.9 2 45.8
CH30.0 30.15 4 120.6
CH40.0 34.82 2 69.64
CH50.0 9.39 4 37.56
CH60.0 23.65 1 23.65
TOTAL 310.89

1 x Distance between cross sections x Sum of all cross sections


3

1 x 10.00m x 27.83
3
= 92. 77m

FILL

1 x Distance between cross sections x Sum of all cross sections


3

1 x 10.00m x 310.89
3
= 1036.3m