Work Activity Base Production Rates

Item Unit Base Rate Metric Base Rate

Grade Items

Mobilization Days 5

Clearing & Grubbing Acres 3 1

Demo. Of Buildings Each 1

Asbestos Rem.(Res./Small Commercial) Days 4

Asbestos Rem.(Large Commercial) Days 10

Demo. Of Asphalt Pave. S.Y. 1500 1254

Sawcut Pavement L.F. 800 244

Remove Curb& Gutter L.F. 600 183

Remove Exist. DI/Manhole & Assoc. Pipe Each 6

Temporary Detour Days 6

Roadway Excavation C.Y. 2000 1529

Excavation Small/Irregular Area Projects C.Y. 850 650

Excavation - Large quantity projects C.Y. 5000 3823

Drainage Corrug.Metal 18" L.F. 205 62

Drainage Concrete Pipe 15" L.F. 168 51

Drainage Conc. Pipe 18" L.F. 144 44

Drainage Conc. Pipe (24" to 54") L.F. 72 22


Drainage Conc. Pipe (60 in. & greater) L.F. 48 15

Inlets/Manholes Each 2

Minor Excavation (Drainage Structures) C.Y. 250 191

Box Culverts, Class A Conc. C.Y. 20 15

Box Culverts, Cast in Place L.F. 5 2

Box Culverts, Precast L.F. 20 6

Retaining Walls, Cast in Place L.F. 5 2

Major Retaining Walls S.F. 210 20

Sub-grade Stabilization S.Y. 8000 6689

Aggregate Base Tons 1360 1234

Aggregate Base Small/Irregular Projects Tons 680 617

Drainage Blanket Tons 1200 1089

Asphalt Base Tons 1175 1066

Asphalt Intermediate Tons 750 680

Asphalt Surface Tons 500 454

Milling/Flexible Pavement Planing (Max. 2") S.Y. 3000 2509

Curb & Gutter (Machine Placed) L.F. 800 244

Curb & Gutter (Hand Placed) L.F. 400 122

Curb& Gutter Radial (Hand Placed) L.F. 150 46

Concrete Entrance S.Y. 80 67


Sidewalk S.F. 1550 144

Concrete Driveway S.Y. 150 125

Entrance Pavement S.Y. 100 84

Barrier Walls, Slip Form L.F. 630 192

Concrete Repair S.Y. 30 25

Concrete Paving S.Y. 2500 2090

Slurry Seal S.Y. 8000 6689

Seeding Acres 2.5 1

Fencing L.F. 1000 305

Fine Grading S.Y. 2000 1672

Lime Stabilization S.Y. 6000 5017

Shoulder Construction L.F. 500 152

Slope Protection C.Y. 100 76

Underdrain L.F. 1500 457

Underdrain Outlet/Endwall Each 8

Utility 12" Ductile Iron L.F. 105 32

Utility 12" PVC L.F. 320 98

Directional Drilling L.F. 50 15

Traffic Items
Item Unit Base Rate Metric Base Rate

Initial Traffic Control Days 2

Ordering Signal Equip. Days 30

Major Traffic Signals Days/Intersec. 40

Pavement Markings L.F. 10,000 3048

Stop Bars, etc. L.F. 500 152

Arrows/Letters Each 50

Order Sign Material Days 60

Order Overhead Sign Struct. Days 80

Erecting Overhead Signs Days 10

Erecting Signs S.F. 1000 93

Ordering Lighting Material Days 60

Erecting Lighting Days/support 3

Guardrail L.F. 1500 457

Guardrail Terminals Each 2

Order Impact Attenuators Days 30

Install Impact Attenuator Each 3

Electrical Conduit L.F. 400 122

Electrical Wire L.F. 3500 1067

Precast concrete barrier L.F. 800 244